项目管理工具与流程-project management tools & processes

Upload: missz0e

Post on 05-Apr-2018

231 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 -Project management tools & processes

    1/23

    Project management tools & processes

    Section 1 Project Management: Basics and Tools ................................................................................2

    1.1 Project Management ...................................................................................................................21.2Project Structure and Frameworks ..............................................................................................5

    1.3 Project Stakeholders ...................................................................................................................8

    1.4 Project Management Tools .........................................................................................................9

    1.4.1 Project initiation document ..................................................................................................9

    1.4.2 Feasibility ............................................................................................................................9

    1.4.3 SWOT analysis ..................................................................................................................10

    1.4.4 Work Breakdown Structure (WBS) ...................................................................................10

    1.4.5 Costing and Budgeting ......................................................................................................10

    1.4.6 Gantt Chart ........................................................................................................................10

    1.4.7 Histogram ..........................................................................................................................10

    1.4.8 Network analysis/critical path analysis .............................................................................111.4.9 PERT (project evaluation and review technique) ..............................................................11

    1.4.10 Project Management Software .........................................................................................11

    Section 2 Project Management: Methodologies and Managing the Team .........................................12

    2.1 Project Management Methodologies and System ....................................................................12

    2.2 The Key Stages of Project Management ..................................................................................14

    2.3 The Project Initiation Stage ......................................................................................................15

    2.4 Strategy and Scope for a Project ..............................................................................................15

    2.5 Management of Configuration, Change & Risk .......................................................................16

    2.6 The Project Planning Stage .......................................................................................................18

    Section 3 Project Control ...................................................................................................................19

    3.1 Project Control Systems ...........................................................................................................19

    3.2 Control of Time, Cost and Quality ...........................................................................................20

    3.3 Quality in the Project Environment ..........................................................................................21

    3.4 Project Completion ...................................................................................................................22

  • 8/2/2019 -Project management tools & processes

    2/23

    Section 1 Project Management: Basics and Tools

    Project Management

    Project Structures and Frameworks

    Project Stakeholders

    Project management tools

    1.1 Project Management

    A project is a temporary process, which has a clearly defined start and end time, a set of tasks and a

    budget, that is developed to solve a well defined goal or objective.

    Examples of projects include implementing a new business process, producing a new product,

    organising a wedding, or decorating the dinning room.

    Characteristics of a projector (Trevor Young, The Handbook of Project Management):

    has specific purpose

    is unique

    customer focused

    a series of activities

    has time constraints

    is complex

    has cost constraints

  • 8/2/2019 -Project management tools & processes

    3/23

    The project life cycle

    Stage Description

    The defining or initiation

    phase

    Identification of a need, opportunity or problem. Establish

    requirements and achievability.

    The planning phase Submission of proposals to the customer.

    A feasibility study and cost benefit analysis is generally

    used to help evaluate the best choice and the contract is

    then agreed.

    The implementing phase The actual performance, resulting in the accomplishment of

    the project objective.

    The controlling phase Monitoring and controlling the project, through budget

    milestones

    The completing phase Deliverables provided, appraised, accepted and paid for.

  • 8/2/2019 -Project management tools & processes

    4/23

    Project management is the application of knowledge, skills, tools and techniques to project

    activities in order to meet or exceed stakeholder needs and expectations from a project.

    Objective of project management

    Define the project

    Produce manageable tasks

    Obtain resources

    Build a team or teams

    Plan the work and allocate responsibilities

    Monitor and control the work

    Report progress to senior management and/or the project sponsor

    Close down the project when completed

    Review to ensure lessons are learnt

    Process of Project Management

    ProjectStages

    Initiation Fact finding Design &

    development

    Review Completion

    Formation Position analysis Implementation

    Objective setting Options generation

    Task planning Options evaluation

    FeasibilityManag

    erialStagesAnd

    1. Initiation stage

    a. Project initiation

    document

    b. Work breakdownstructure

    c. Budget schedule

    d. Task list

    e. Network diagram

    f. List of resources

    g. Feasibility study-

    cost/benefit analysis

    2. Planning stage

    a. SWOT analysis

    b. Scenario building

    c. NPVd. Working breakdown

    structure

    e. Gantt charts

    f. Critical path analysis

    g. PERT

    h. Resource histogram

    3. Implementing

    stage

    Budget report

    Progress report

    4.Controlling

    stage

    Cost analysis

    5.Completing stage

    Completion report

    Post completion

    audit

  • 8/2/2019 -Project management tools & processes

    5/23

    1.2Project Structure and Frameworks

    Mckinseys 2S model

    The 2S model can be used in to identify:

    Strengths and weakness

    How a change made in any one of the S factors will have an impact on all of the others

  • 8/2/2019 -Project management tools & processes

    6/23

    Appreciative Inquiry (AI)

    A traditional Appreciative Inquiry is based on four steps (the AI 4-D Cycle)

    Assumptions of AI include the following:

    Something works

    What we focus on becomes our reality

    Asking questions of an organisation or group influences the group in some way.

    People have more confidence and comfort to journey to the future ( the unknown) when theycarry forward the best parts of the past (the known).

    It is important to value differences.

    the language we use creates our reality.

    Note: The AI framework can be applied a variety of interventions such as: strategic planning,

    instructional system design, diversity, organisational redesign, mergers and evaluations.

  • 8/2/2019 -Project management tools & processes

    7/23

    The Project Management Body of Knowledge (PMBOK)

    The Project Management Body of Knowledge (PMBOK) is a collection of processes and

    knowledge areas accepted as best practice within the project management discipline.

    The PMBOK

    The PMBOK describes nine Project Management Knowledge Areas:

    1) Project Integration Management

    2) Project Scope Management

    3) Project Time management

    4) Project Cost Management

    5) Project Quality Management

    6) Project Human Resource Management7) Project Communication Management

    8) Project Risk Management

    9) Project Procurement Management

  • 8/2/2019 -Project management tools & processes

    8/23

    1.3 Project Stakeholders

    Outcome and process stakeholders

    Outcome stakeholders have an interest in seeing that the projects objectives are achieved.

    Process stakeholders have an interest in the way in which the project is conducted.

    Based on the principles of one person- one boss and a decision-making authority, the hierarchy

    shown below is adapted from the one shown in Successful Project Management, Gido Jand

    Clements J, 1999.

    Note: Other stakeholders that we can include are the organisation, customers, steering committee,

    vendors, specialists and users.

    Project champions and agents of change

    A project champion- someone who grasps the benefits of and is enthusiastic about the project can

    be one of the most critical elements of any project team. Change agents are those people in the

    business that have the expertise that the project team requires to successfully delver the project and

    will ensure that all of the requirements of the business are met.

  • 8/2/2019 -Project management tools & processes

    9/23

    1.4 Project Management Tools

    1.4.1 Project initiation document

    The project initiation document ( PID) is a formal document listing the goals, constraints and

    success criteria for the project- the rules of the game.

    Note: The PID is sometimes called a statement of work or project charter.

    A PID should contain at least the following sections:

    Purpose statement

    Scope statement

    Deliverables

    Cost and time estimates Objectives

    Stakeholders

    Chain of command

    1.4.2 Feasibility

    The feasibility study should be undertaken during the early stages of project planning, once the

    requirements and specifications of the project have been identified.

    The purpose of project feasibility is to establish if the proposed project can achieve its objective in a

    cost effective manner. It enables the organisation to filter out proposed projects that would either

    cost too much disruption, make excessive demand on resources or have side effects that are

    undesirable and outweigh the advantages.

    Feasibility can be considered in a number of areas for example technical, social, environmental,

    financial and business feasibility.

    Technical feasibility will vary depending of the type of project being undertaken. The idea is

    to assess the nature of the technology required to build and run the new system/venture.

    Social feasibility is all about ensuring the project fits with the business and its social

    environment. Environmental or ecological feasibility which could include complying with heath and

    safety legislation and also making sure the system/venture is ecologically sound and not

    harmful to the surrounding environment.

    Financial feasibility is undertaken to explore whether the project provides benefits to the

    organisation and is usually assessed through cost benefit analysis.

    Business feasibility should be considered in terms of whether the project fits with the

    business goals of the company.

  • 8/2/2019 -Project management tools & processes

    10/23

    1.4.3 SWOT analysis

    trengths Weaknesses

    The things that are going well (or have gone well) in the

    projects

    The skills that are prized

    Major successes

    Parts of the project that are well received by the users or

    were completed early

    The things that are going badly (or have

    gone badly) in the projects

    The skills that area is lacking

    Major failures

    Parts of the project that are poorly

    received by the users or were completed

    late

    pportunities Threats

    Events or changes outside the project (elsewhere in the

    organisation or its business environment) that can be

    exploited to the advantage of the project

    Things likely to go well in the future

    Events or changes outside the project

    (elsewhere in the organisation or its

    business environment) that should be

    defended against

    Things likely to go badly in the future

    1.4.4 Work Breakdown Structure (WBS)

    This technique is a critical part of project planning involving an analysis of the work required to

    complete the project. The activities in the project are broken down into manageable components,

    referred to as work packages. The process defines the activities that must be carried out for each

    work package. Each work package will have defined responsibilities and deliverables.

    1.4.5 Costing and Budgeting

    The WBS can be used to produce a cost breakdown structure.

    Detailing labour, subcontractors, material, overheads, etc

    1.4.6 Gantt Chart

    This provides a visual way of illustrating the sequence of activities in a project. Complex project

    activities are converted into constituent tasks and a graphical and understandable picture is

    provided. Although it does not show dependencies internal relationship, it will show the time taken

    for each activity, resources required and responsibilities.

    1.4.7 Histogram

    This technique shows the resource requirement usage and availability against a timescale. (stacked

    bar chart)

  • 8/2/2019 -Project management tools & processes

    11/23

    1.4.8 Network analysis/critical path analysis

    Construction of a diagram showing the sequence and dependencies between activities or

    deliverables on a project. Using a work breakdown structure, network analysis arranges each work

    package/task into a logical sequence and estimates the time to complete each. The outputs from the

    work breakdown structure analysis will help the identification of which tasks are dependent on

    others. Dependencies are critical to project planning. Having identified dependencies it is thenpossible to calculate the critical path, which is the longest sequence of consecutive activities. It

    identifies those activities which, if delayed beyond the allotted time, would delay the completion of

    the project. How much certain activities could slip before there is an impact on the expected item

    completion for project. This then enables the minimum possible time to be determined.

    1.4.9 PERT (project evaluation and review technique)

    Development on network analysis, the technique is designed to account for uncertainty in the

    project life cycle. Each activity in the project PERT uses three times estimates:

    1) the optimistic time based on the duration the Shopping Centre project would take if

    conditions were ideal;

    2) the most likely/probable duration if conditions were normal or as expected;

    3) the pessimistic estimate which is the duration it would take if a number of things went

    wrong.

    These estimates are then converted into a mean time and standard deviation which means it is then

    possible to establish the duration of the project using the expected times, but also to calculate a

    contingency time allowance.

    1.4.10 Project Management Software

    Software can be used for:

    planning- network diagrams and gannt charts can be produced automatically once data is

    entered

    monitoring- actual data can be used to facilitate monitoring, with regular updates to

    diagrams

    estimating- actual data from one project can be used to estimate the next project

    reporting- they allow standard and tailored reports to be produced

  • 8/2/2019 -Project management tools & processes

    12/23

    Section 2 Project Management: Methodologies and

    Managing the Team

    Project management, methodologies and systems

    The key stages of project management

    The project initiation stage

    Strategy and scope for a project

    Management of configuration, change and risk

    The project planning stage

    2.1 Project Management Methodologies and System

    Prince is a project management system developed by the UK Central Computer and

    Telecommunications Agency.

    The acronym PRINCE stands for Projects IN Controlled Environments. The latest version of

    PRINCE is PRINCE 2.

    Prince Structure

    The basic PRINCE prefect organisational structure

    The PRINCE structure defines the roles of:

    project committee

  • 8/2/2019 -Project management tools & processes

    13/23

    project manager

    team leader

    project assurance

    project support

    PRICE 2

    PRINCE2 (Projects IN Controlled Environments, version 2) is a process-based approach for

    project management providing an easily tailored, and scaleable method for the management of all

    types of projects.

  • 8/2/2019 -Project management tools & processes

    14/23

    2.2 The Key Stages of Project Management

    PRINCE2 Process

    Directing a project the higher aspects of control and decision making

    Starting up a project- a pre-project process, selecting the team and setting aims

    Initiation- akin to a feasibility study, is it justified?

    Planning- analysis into technical, quality and management. Establishment of targets of time,

    cost and quality.

    Controlling a stage- monitoring and control activities are carried out by the project manager

    at each stage of the project.

    Managing stage boundaries- the primary objective at this stage is to ensure that all planned

    deliverables are completed as required. One stage is completed before next begins.

    Managing product delivery- this includes effective allocation of Work packages and

    ensuring that the work is carried out to the required quality standard. (specialist and

    contractors) Project closure- bringing the project to a formal and controlled close approved by the

    Project Board, it establishes the extend to which the objectives have been met.

    The JISC infoNet method

    The JISC infoNet method pares down PRINCE2 to the bare bones of a framework suitable for

    managing any project.

  • 8/2/2019 -Project management tools & processes

    15/23

    2.3 The Project Initiation Stage

    Project initiation

    The PID lists the goals, constraints and success criteria for the project.

    Project definition

    The main elements of a project definition include:

    purpose

    goals

    beneficial gains

    2.4 Strategy and Scope for a Project

    To ensure the strategic fit of the project the organisation needs to be clear about the following:

    description of the business need and its contribution to the organisations business strategyobjectives

    why it is needed now

    key benefits to be realised

    critical success factors and how they will be measured.

    Project strategy

    Project scope- agreement between customer and supplier, series of tasks or activities to be

    performed in reaching the project solution

    Project objectives and basic plans for time, cost and quality

    time constraint and budget

    an expected quality level associated with each task

    budget available for project completion, which the project manager should not exceed

    without authorisation

    Trade offs between key project objectives

    Every project has constraints. The primary ones are the trade off between time, cost and scope

    which also impact on quality.

  • 8/2/2019 -Project management tools & processes

    16/23

    2.5 Management of Configuration, Change & Risk

    Risk management

    Five stages of risk management

    1) Identify and record the risk in a risk register2) Access the risks and record the assessment

    3) Plan and record risk strategies

    4) Carry out risk strategies

    5) Review and monitor the success of the risk management approach

    Dealing with risk involves four basic approaches

    Avoidance removes the factors bringing about the risk

    Reduction- identify ways to reduce the risk

    Transference pass the risk to someone else (insurer)

    Absorption accept the risk and cope with the consequences

    Common causes of problems

    Poor project management

    Conflicting requirements

    Unrealistic deadline

    User requirements not established correctly

  • 8/2/2019 -Project management tools & processes

    17/23

    Management of change

    Change management activities:

    identify need for change

    make recommendation

    check feasibility to change

    get steering committee approval get project sponsor approval

    amend plan

    make change

    Elements of the change management plan:

    initiating a change request

    logging and tracking change requests

    assigning change requests for analysis and recommendation

    implementing change request resolution actions ( acceptance, delayed acceptance or

    rejection of change request) how accepted changes will be integrated into the project control documents ( schedule and

    task plan, risk management plan, acquisition plan, etc)

    roles and responsibilities in the change management process

    Change management

    Causes of change to the project plan What to consider when changing the plan

    Slippage

    New technology

    New legislation

    Business environment changes

    Poorly defined user requirements

    Staff changes

    What happens if the change is not

    implemented?

    Costs and benefits of the change

    Impact on time, cot and quality

    Change control procedure

    Impact on stakeholders

    Communication to all those affected

  • 8/2/2019 -Project management tools & processes

    18/23

    2.6 The Project Planning Stage

    Advantages:

    communicate what has to be done, when and by whom

    encourage forward thinking

    provide the measures of success for the project

    make clear the commitment of time, resources ( people and equipment), and money required

    for the project

    determine if targets are achievable

    identify the activities the resources need to undertake

    Three main types of planning are required within PRINCE projects:

    Project planning

    Stage planning

    Exception planning

    Detailed planning

    Resources for a detailed plan:

    The plan can be discussed with the project sponsor and users, to gain their agreement for the

    project to proceed.

    The plan will give a clear view to the project team of what is expected form them. This will

    improve their motivation level.

    The plan can be used as a basis for performance review.

    Evaluation of plans for projects

    Methods of evaluation include: examining existing records

    structured observation

    individual interviews

    group interviews

    expert opinion

    Note: For more details about methodology please refer to the study text Section on project

    methodologies and planning.

  • 8/2/2019 -Project management tools & processes

    19/23

    Section 3 Project Control

    Project control systems

    Control of time, cost and quality

    Quality in the project environment

    Project completion

    3.1 Project Control Systems

    Project control

    Project control is the continuous monitoring of the project for deviations from plan (time, cost and

    quality) and the execution of corrective action.

    Components of a basic control system:

    A plan- a statement of what is to happen

    Observations- measurements of what is happening

    Comparisons- between expectations and actual

    Corrections- actions designed to re-direct what is happening back to what should happen.

    Updates- of forecasts and or plan as appropriate.

    This involves scheduling, monitoring and controlling.

    Project control system

    The purpose of a project control system is to develop a plan of the work that is to be accomplished

    and to develop a system that monitors that plan and the performance of the work.

    The decision to introduce a formal control system and the selection of a specific system should be

    based largely on two aspects of the project:

    The risk involved

    The cost of the control system and its expected benefits

  • 8/2/2019 -Project management tools & processes

    20/23

    3.2 Control of Time, Cost and Quality

    Time, cost and quality performance measurement

    Time and money, budgets and schedules are the most basic resources within which every project

    must operate.

    Measurements can include:

    Expenditure (cost) measures- start with the establishment of budgets

    Schedule (time) performance measures- refer to the timely completion of project

    deliverables.

    Scope performance measures- are primarily concerned with product scope (the set of

    functions and features that characterise the product or service).

    Functional quality- refers to the quality or correctness

    Technical quality performance refers to the technical infrastructure that provides the

    foundation for product and service delivery. Client satisfaction measures- include client perceptions on various aspects.

    Earned value analysis (EVA)

    EVA involves calculation of three measurements:

    Budgeted cost of work scheduled (BCWS)

    Actual cost of work performance (ACWP)

    Budgeted cost of work performed (BCWP)

  • 8/2/2019 -Project management tools & processes

    21/23

    3.3 Quality in the Project Environment

    Quality is:

    Totality of features and characteristics of a product or service which bear on its ability to

    satisfy stated and implied needs. (ISO)

    Fitness for use (Juran)

    Conformance to requirements (Crosby)

    Dimensions of quality:

    Conformance quality depends upon compliance with technical specifications.

    Perceived quality relates to the customers expectations and experiences with the product.

    Quality management

    Quality management is a systematic way of ensuring that the activities necessary to design,

    develop and deliver products and services which are more likely to be fit for their intended purpose,

    take place a planned and are carried out efficiently and effectively.

    Conformance management systems

    Conformance management systems focus on:

    inspection

    quality control

    quality assurance

    Total Quality Management (TQM)

    TQM is managing the entire organisation so that it excels on all dimensions of products and

    services that are important to the customer.

    TQM deals with:

    quality standards and specifications

    cost of quality

    continuous improvement

  • 8/2/2019 -Project management tools & processes

    22/23

    3.4 Project Completion

    Closing a successfully completed project

    Elements in project finalisation:

    acceptance by client

    review outputs against goals

    disbanding the team

    post-completion review

    closure by steering committee

    Closing an unsuccessful project

    Signs of an unsuccessful project that may need to be closed before being completed include:

    The project team is unable to meet major project milestones.

    The activities do not match with the stated objectives of the project. It is clear the clients will not accept the outputs and/or outcomes of the project.

    Key project team members leave the project.

    Completion report

    Contents:

    The project objectives and the outcomes achieved

    The extend to which the required quality has been achieved

    System efficiency during live operation compared with the agreed levels of performance

    The cost of the system in comparison with budgeted cot, and explanations for variances

    Comparison of actual time taken to complete the project with the budgeted time anticipated The effectiveness of the management process

    The significance of the problems encountered, and the effectiveness of the solutions

    generated to overcome them.

    Post-completion audit

    Main purposes of post-completion audit:

    checks whether benefits have been achieved

    reduces the tendency towards over-optimism

    Post-implementation review(PIR)

    Post-implementation review (PIR) is a formal review of a programme or project. It is used toanswer the question: Did we achieve what we set out to do in business terms and if not, what

    should be done?

  • 8/2/2019 -Project management tools & processes

    23/23

    Elements of the PIR

    Project history description- provides an executive overview of the solution selected to

    satisfy the project objectives.

    Cost history- provides a set of accounts for the actual costs of the development of the project

    using the cost schedule formats as prepared for the project plan.

    Project management and systems development methodology- describe the methodology

    used to develop the system. Performance measures provide a list of the performance measures initially used to justify

    the project.

    Lessons learned- describe the lessons learned during this project

    Impact of the system-briefly describe the general impact of the system on the mangers, users

    and customers.

    The PIR process