مشروع التخرج underbalanced drilling - copy

448

Upload: hamada-amer

Post on 08-Nov-2015

144 views

Category:

Documents


12 download

DESCRIPTION

نمةنمنن

TRANSCRIPT

  • Underbalanced Drill ing Senior Project

    Underbalanced Drilling Of Horizontal

    Gas Well

    Obaiyed field case study

    Under supervision of/

    Eng. Abd El Fatah Sharf

    Team members/

    1. Abdallah Magdy Darwish

    2. EL Sayed Amer Hassan ([email protected])

    3. Mossad Mossad Dawood

    4. Sandy Mohamed Sherif

    5. Mina Naguib

    6. Magdy Hamaza Ahmed

    Cost - Depth Curve OBA D2 UBD

    4160

    4210

    4260

    4310

    4360

    4410

    4460

    4510

    4560

    4610

    4660

    $0 $500,000 $1,000,000 $1,500,000 $2,000,000 $2,500,000 $3,000,000 $3,500,000 $4,000,000 $4,500,000

    Cost in $

    Dep

    th in

    m

    Plan Actual

  • El Sayed Amer Hassan

    Team Work

    Mina Naguib Magdy Hamza

    Abdallah Magdy Darwish

    Mossad Mossad Dawood Sandy Mohamed Sherif

    Under supervision of/ Eng. Abd-Elfatah Sharaf

  • We dedicate this book to all the

    Egyptians who pay their life for the rise of

    this country. These people will be-

    forever- in our hearts where no one can

    erase them.

    I

  • Acknowledgement

    Although we didn't study UBD; But we

    challenged the process

    We would like to express our deepest gratitude to our advisor

    Eng. Abd- El Fatah Sharaf

    For supervising this work and for his valuable guidance and

    genuine interest in completing this study. We would like to thank our family for their ultimate help and efforts without Allah's blessing and their prayers we would not

    be able to finish this work.

    We also like to acknowledge our

    Prof. Attia M. Attia,

    Eng. Sayed RIzek,

    Eng. Ahmed El Rayan

    Eng. Mohamed Salah

    Project Team Work

    2012

    II

  • ABSTRACT

    Much UBD technology is still considered relatively new, and probably just leaving the Early Adopters stage. The key to success in moving underbalanced drilling up the growth curve lies in a good understanding of the technology, careful planning (including full consideration of the risks), disciplined execution, and effective dissemination of technological information. Otherwise, early adopters can pay dearly for taking up the flag of new technology. Several papers have been published discussing the UBD processes as well as the benefits achieved from this technology. However, few papers have examined the criticality of planning for UBD operations.

    We provide a detailed study in how to plan for UBD operations to achieve success in drilling the well. Our case study was brought from BAPETCO Egyptian Company, obaiyed concession, western desert. The study emphasizes formation stability, appropriate technique, well control, minimum formation damage, hydraulic analysis, and guaranteed economic incentives.

    Project Team Work

    2012

  • HISTORY OF UNDERBALANCED DRILLING ............................................................................................... 3

    WHAT IS UNDERBALANCED DRILLING? ................................................................................................... 4

    UNDERBALANCED VERSUS OVERBALANCED .......................................................................................... 6

    BENEFITS OF UNDERBALANCED DRILLING .............................................................................................. 8

    DISADVANTAGES OF UNDER BALANCED DRILLING: ............................................................................. 13

    IMPORTANT LIMITATION FOR UNDERBALANCED DRILLING................................................................. 15

    HOW TO DRILL UNDERBALANCE- TYPE OF UNITS? ............................................................................... 16

    REFERENCES .......................................................................................................................................... 20

    UNDERBALANCED DRILLING TECHNIQUES

    GASEOUS DRILLING FLUIDS ................................................................................................................... 23

    MIST DRILLING ...................................................................................................................................... 34

    FOAM DRILLING .................................................................................................................................... 37

    GASIFIED OR AERATED SYSTEMS .......................................................................................................... 43

    FLOW DRILLING ..................................................................................................................................... 49

    MUD CAP DRILLING ............................................................................................................................... 49

    SNUB DRILLING ..................................................................................................................................... 50

    CLOSED SYSTEM .................................................................................................................................... 50

    REFERENCES .......................................................................................................................................... 51

    RESERVOIR CANDIDATES AND OPTUMIM SELECTION

    GOOD CANDIDATE INDICATORS FOR UBD ............................................................................................ 54

    BAD CANDIDATE INDICATORS FOR UBD ............................................................................................... 55

    OPTIMUM SELECTION OF UNDERBALANCED TECHNIQUES.................................................................. 56

    GENERAL CONSIDERATION TO SELECT DRILLING FLUID ....................................................................... 59

    ECONOMIC STUDY MODEL ................................................................................................................... 74

    REFERENCES .......................................................................................................................................... 89

  • SURFACE EQUIPMENT OF UNDERBALANCED DRILLING

    INTRODUCTION ......................................................................................................................... 92

    GAS SUPPLY ............................................................................................................................... 92

    AIR COMPRESSION SYSTEM ........................................................................................................ 94

    IN-LINES FACILITIES .................................................................................................................... 98

    SEPARATION SYSTEM ............................................................................................................... 101

    PITS & TANKS........................................................................................................................... 104

    FLARE SYSTEM ......................................................................................................................... 105

    SURFACE MEASUREMENTS ....................................................................................................... 106

    FOAM DRILLING ACCESSORIES .................................................................................................. 107

    SURFACE EQUIPMENT LAYOUT FOR DIFFERENT UBD TECHNIQUES ............................................. 111

    IADC UNDERBALANCED OPERATION COMMITTEE ..................................................................... 114

    OBAYED FIELD SITE DRAWINGS & EQUIPMENTS ........................................................................ 116

    REFERENCES ............................................................................................................................ 119

    DOWNHOLE EQUIPMENT FOR UNDERBALANCED

    DRILLING ROTARY DRILL STRING......................................................................................................................... 122

    DRILLING BITS ...................................................................................................................................... 125

    DRILLING JARS ..................................................................................................................................... 133

    STABILIZERS ......................................................................................................................................... 134

    REAMERS ............................................................................................................................................. 134

    SHOCK SUB .......................................................................................................................................... 135

    BOTTOM HOLE ASSEMBLY .................................................................................................................. 135

    DOWN HOLE MOTOR .......................................................................................................................... 136

    MEASURMENT WHILE DRILLING (MWD) ............................................................................................ 137

    ELECTROMAGNETIC MWD .................................................................................................................. 137

    ELECTROMAGNETIC MWD .................................................................................................................. 138

    PRESSURE WHILE DRILLING (PWD) ..................................................................................................... 139

    HEAVY WEIGHT DRILL PIPE ................................................................................................................. 139

    FLOAT VALVES ..................................................................................................................................... 140

    DOWN HOLE ISOLATION VALVES ........................................................................................................ 143

  • DRILL PIPE............................................................................................................................................ 144

    REFERENCES ........................................................................................................................................ 145

    COILED TUBING

    INTRODUCTION: .................................................................................................................................. 148

    WHAT IS COILED TUBING? .................................................................................................................. 149

    FEATURES OF CT TECHNOLOGY: ......................................................................................................... 149

    USES OF COILED TUBING IN OIL INDUSTRY:........................................................................................ 150

    ADVANTAGES OF COILED TUBING: ..................................................................................................... 151

    DISADVANTAGES OF COILED TUBING ................................................................................................. 151

    COILED TUBING EQUIPMENT .............................................................................................................. 152

    COILED TUBING APPLICATIONS ........................................................................................................... 155

    COILED TUBING DRILLING ................................................................................................................... 156

    COMPARISON BETWEEN COILED TUBING & JOINTED PIPE ................................................................ 156

    REFERENCES ........................................................................................................................................ 166

    DIRECTIONAL DRILLING

    DIRECTIONAL DRILLING (D.D).............................................................................................................. 168

    DIRECTIONAL DRILLING APPLICATIONS .............................................................................................. 172

    DEVIATION CONTROL METHODS ........................................................................................................ 180

    DIRECTIONAL DRILLING TOOLS AND TECHNIQUES ............................................................................. 181

    HORIZONTAL WELLS ............................................................................................................................ 196

    HORIZONTAL DRILLING APPLICATIONS .............................................................................................. 196

    REFERENCES ........................................................................................................................................ 202

    Problems

    ANTICIPATED PROBLEMS ......................................................................................................... 204

    DIRECTIONAL DRILLING PROBLEMS .......................................................................................... 215

    PROBLEMS ENCOUNTERED DURING UNDERBALANCED DRILLING .............................................. 218

    PROBLEMS ENCOUNTERED DURING DRILLING OBAYED FIELD .................................................... 224

    CORROSION PLAN FOR UB OBAYED FILED ................................................................................. 228

    REFERENCES ............................................................................................................................ 233

  • WELL CONTROL IN UNDERBALANCED DRILLING

    WELL CONTROL DEFINITION ..................................................................................................... 236

    WELL CONTROL PRINCIPLES...................................................................................................... 237

    CAUSES OF PRIMARY CONTROL LOSS ........................................................................................ 237

    WARNING INDICATORS OF A KICK ............................................................................................ 239

    SHUT IN PROCEDURE ............................................................................................................... 239

    WELL KILLING PROCEDURES ..................................................................................................... 241

    BLOWOUT PREVENTION (BOP) EQUIPMENT .............................................................................. 244

    BLOW OUT PREVENTER EQUIPMENT FOR COILED TUBING DRILLING .......................................... 250

    COILED TUBING BOP STACK ARRANGEMENTS ........................................................................... 252

    WELL CONTROL FOR UNDERBALANCED DRILLING (UBD) ............................................................ 252

    UBD BOP STACK ARRANGEMENT .............................................................................................. 256

    BOP SCHEMATIC OF OBAIYED D-2 ............................................................................................ 260

    REFERENCES ............................................................................................................................ 261

    Completion for underbalanced drilling

    COMPLETION OBJECTIVE AND FUNCTIONS................................................................................ 264

    VERTICAL OR HIGHLY DEVIATED WELL COMPLETION ................................................................. 266

    HORIZONTAL WELL COMPLETION ............................................................................................. 268

    UNBERBALANCED WELL COMPLETION ...................................................................................... 270

    OBAIYED D2-C/D COMPLETION .............................................................................................. 275

    REFERENCES ............................................................................................................................ 280

    DIRECT CIRCULATION OF AERATED FLUID

    INTRODUCTION ....................................................................................................................... 282

    MINIMUM VOLUMETRIC FLOW RATES ...................................................................................... 282

    INJECTION PRESSURE AND SELECTION OF COMPRESSOR EQUIPMENT ....................................... 288

    COMPRESSOR SELECTION ......................................................................................................... 316

    REFERENCES ............................................................................................................................ 320

  • OBAIYED D-2 WELL ENGINEERING

    OVERVIEW OF BADER EL DIN PETROLEUM COMPANY ............................................................... 321

    OBAIYED D-2 OVERVIEW .......................................................................................................... 322

    DETERMINATION OF THE DERRICK LOAD .................................................................................. 326

    SWIVEL SELECTION ................................................................................................................... 327

    KELLY SELECTION ..................................................................................................................... 328

    HOISTING SYSTEM SELECTION: ................................................................................................. 329

    SELECTION OF MUD PUMP ....................................................................................................... 334

    SELECTION OF THE WELLHEAD FOR OBAYED D-2 ....................................................................... 341

    DESIGN OF DRILL STRING.......................................................................................................... 344

    CASING AND TUBING DESIGN ................................................................................................... 360

    CEMENT PROGRAM ................................................................................................................. 377

    DESIGN OF HORIZONTAL TRAJECTORY ...................................................................................... 392

    RECOMMENDED DRILLING ASSEMBLIES: ................................................................................... 406

    REFERENCES: ........................................................................................................................... 408

    RISK ASSESSMENT OF UNDERBALANCED DRILLING

    INTRODUCTION OF RISK ASSESSMENT ...................................................................................... 412

    RISK ASSESSMENT .................................................................................................................... 412

    RISK MANAGEMENT AND DOWNHOLE PROBLEMS .................................................................... 413

    PERSONAL PROTECTIVE EQUIPMENT (PPE) ............................................................................... 415

    REFERENCES ............................................................................................................................ 417

    CONCLUSION AND RECOMMENDATION ................... 419

  • 1

  • 2

    History of Underbalanced

    Drilling

    What is Underbalanced Drilling?

    Underbalanced Versus

    Overbalanced

    Benefits of underbalanced

    drilling

    Disadvantages of under balanced

    drilling

    Important limitation for

    underbalanced drilling

    How to drill underbalance- type

    of units?

    References

    This chapter introduces the fundamentals of underbalanced drilling operation including the history, consideration, limitations and methods of drilling Underbalanced drilling has been around since the start of the oil exploration. All cable tool drilled wells were drilled underbalanced and most of us have all seen the pictures of blowouts and gushers as an oil reservoir was struck. Until 1895 all wells were drilled underbalanced.

  • 3

    History of Underbalanced Drilling

    Underbalanced drilling has been around since the start of the oil exploration. All cable tool drilled wells were drilled underbalanced and most of us have all seen the pictures of blowouts and gushers as an oil reservoir was struck. Until 1895 all wells were drilled underbalanced. The introduction of rotary drilling technology in 1895 required fluid circulation, which initially was water. To enhance safety and hole cleaning, mud systems were developed in 1920 and drilling continued overbalanced. As deeper and larger reservoirs were encountered the reservoir damage issues became less of an issue. Until in the 1980s the first underbalanced wells were drilled in the Austin Chalk. This proved to be the introduction to modern underbalanced drilling which started in the early 1990s in Canada. 1284 First cable tool wells drilled in China 1859 - 1895 all wells drilled underbalanced. 1895 Rotary drilling with water. 1920 First mud systems used. 1928 First BOPs used. 1932 First use of gasified fluids to drill 1955 Dusting or air drilling becomes popular. 1988 First high pressure gas well drilled underbalanced in Austin Chalk. 1993 First UBD wells drilled in Canada. 1995 First UBD wells drilled in Germany 1997 First UBD wells drilled offshore. Since 1997, just after the third international underbalanced drilling conference was held, better co-operation between operators internationally was initiated. The first committees were developed as a result of Shell and Mobil requesting more information and co-operation to ensure that offshore wells could be drilled safely underbalanced. In 1998 the IADC took the safety lead in underbalanced drilling and the IADC UBO committee was formed in order to enhance the safety of underbalanced drilling operations. This committee developed the underbalanced classification matrix and continues today to develop safer and more efficient methods and procedures for underbalanced drilling operations. The development of better flow modeling systems and training systems together with international experiences shared between operators has helped to develop underbalanced drilling as one of the primary technologies for enhanced production from depleted fields and reservoir understanding in newly developed fields.

  • 4

    What is Underbalanced Drilling?

    When the effective circulating downhole pressure of the drilling fluid - which is

    equal to the hydrostatic pressure of the fluid column, plus pumps pressure, plus

    associated friction pressures - is less than the effective near bore formation pore

    Pressure. (Definition)

    Underbalanced Drilling P reservoir > P bottom hole = P hydrostatic + P friction + P choke

    The well is still controlled by controlling the wellbore pressure, but this pressure is

    Maintained to be always below the reservoir pressure. Primary well control is no

    Longer an overbalanced barrier of a column of fluid but is replaced by flow

    control

    Using a combination of hydrostatic pressure, friction pressure and surface choke

    Pressure. The BOP stack remains as the secondary well control barrier. It must

    be pointed out that a UBD well operates on a single barrier.

    The bottom hole circulation pressure is a combination of hydrostatic pressure,

    circulation friction losses and surface pressure applied at the choke.

    The hydrostatic pressure is considered a passive pressure and is a result of the

    fluid density and the density contribution of any drilled cuttings and a small

    contribution of any gas in the well.

    FIGURE 1:UBD IN THE UNITED STATE

  • 5

    The friction Pressure is a dynamic pressure (It changes with pumps on or off) and results from circulating friction of the fluid used. The choke pressure arises from annular back pressure applied at surface. These three pressures are controlled at all times and ensure that flow control is maintained whilst drilling underbalanced. The lower hydrostatic head avoids the build-up of filter cake on the reservoir formation and avoids the invasion of whole mud and drilling solids into the formation. This helps to improve productivity of the wellbore and reduces any pressure related drilling problems Conventionally, wells are drilled overbalanced, which provides the primary well control mechanism. Imposed wellbore pressure arises from three different Mechanisms: 1. Hydrostatic pressure of materials in the wellbore due to the density of the fluid used (mud) and the density contribution of any drilled cuttings (passive). 2. Dynamic pressure from fluid movement due to circulating friction of the fluid used and the relative fluid motion caused by surge/swab of the drill pipe(dynamic). 3. Imposed pressure, with occurs due to the pipe being sealed at surface resulting in an area with pressure differential (e.g., a rotating head or stripper element) (confining or active).

    Underbalanced drilling is defined as drilling with the hydrostatic head of the drilling

    fluid intentionally designed to be lower than the pressure of the formations being

    drilled. The hydrostatic head of the fluid may naturally be less than the formation

    pressure or it can be induced. The induced state may be created by adding natural

    gas, nitrogen or air to the liquid phase of the drilling fluid. Whether the

    underbalanced status is induced or natural, the result may be an influx of formation

    fluids which must be circulated from the well and controlled at surface.

    Underbalanced drilling in practical terms will result in flow from one or more zones

    into the wellbore (this is more likely, however, to be solely from one zone as cross-

    flow is likely to result) or where the potential for flow exists.

    The lower hydrostatic head avoids the build-up of filter cake on the formation as well

    as the invasion of mud and drilling solids into the formation. This helps to improve

    productivity of the reservoir and reduce related drilling problems.

  • 6

    Underbalanced Versus Overbalanced

    When comparing underbalanced drilling with conventional drilling it soon

    becomes apparent that an influx of formation fluids must be controlled to avoid

    well control problems. In underbalanced drilling, the fluids from the well are

    returned to a closed system at surface to control the well. With the well flowing,

    the BOP system is kept closed while drilling, whereas in comparison to

    Conventional drilling fluids are returned to an open system with the well open to

    Atmosphere.

    FIGURE 2: PERFORMANCE DRILLING DEFINITION

  • 7

    Overbalanced Operations "Conventional Drilling"

    Mud fluid invasion and the hydrostatic pressure in the well bore can mask

    potentially productive zones.

    Reservoir damage, especially in horizontal wells, is often difficult or complicated to

    remove or clean up once production starts. The lower permeability and porosity

    zones may never be properly cleaned up, which can result in large sections of a

    well (especially horizontal wells) being unproductive.

    Lost circulation and differential sticking can often result in severe drilling problems

    and many wells in depleted reservoirs never get to their planned TD.

    New productive horizons are often identified when drilling. No damage or minimum

    damage is done to the reservoir rocks, including the tighter sections of a well,

    resulting in better production.

    No losses or differential sticking as the fluid pressure is below the reservoir

    pressure.

    Figure 3:Conventional and uBD drillig

    Conventional Drilling Underbalanced Drilling

  • 8

    Benefits of underbalanced drilling

    Increased penetration rate.

    Increased bit life.

    Minimize lost circulation.

    Improved formation evaluation.

    Reduced formation damage.

    Reduced probability of differential sticking.

    Earlier production.

    Environmental benefits.

    Improved safety.

    Increased well productivity.

    Less need for stimulation treatments.

    1-Increased Penetration Rate:

    Drilling underbalanced can lead to increased penetration rate. Most references,

    describing drilling operations with air or lightened drilling fluids, report penetration

    rates which are greater than these for wells drilled overbalanced with

    conventional liquid drilling fluids.

    In permeable rocks, a positive differential pressure will decrease penetration

    because:

    o Increases the effective confining stress which.

    o Increases the rocks shear strength.

    o Therefore increasing shear stress (by drilling UB) increases

    penetration rate. And increases the chip hold down effect.

    FIGURE 4: CHIP HOLD DOWN EFFECT AS DRILLING FLUID ENTERS THE FRACTURE, THE PRESSURE DIFFERENTIAL ACROSS THE ROCK FRAGMENT DECREASES, RELEASING THE CHIP.

  • 9

    2-Increased bit life:

    It is often claimed that bit life is increased when lightened fluids are used instead of conventional drilling mud. Drilling underbalanced removes the confinement imposed on the rock by the overbalance pressure. This should decrease the apparent strength of the rock and reduce the work that must be done to drill away a given volume of rock. It is reasonable that this increased Drilling efficiency should increase the amount of hole that can be drilled before the bit reaches a critical wear state therefore:

    o Increased vibration with air drilling may actually decrease bearing life. o Bit may drill fewer rotating hours but drill more footage. o The number of bits required to drill an interval will be inversely proportional

    to the footage drilled by each bit.

    FIGURE 5: BIT AFTER BEING DAMANGED

    3-Minimized Lost Circulation

    Lost circulation occurs when drilling fluid enters an open formation down hole, rather than returning to the surface. It is possible for drilling fluid to be lost by flow into a very permeable zone. More frequently, lost circulation involves flow into natural fractures that intersect that wellbore or into fractures induced by excessive drilling fluid pressure. Lost circulation can be very costly during conventional drilling. The lost fluid has to be replaced, and the losses have to be mitigated, usually by adding lost circulation material to the mud (to plug off the path by which the fluid is entering the formation), before drilling can safely be

  • 10

    resumed. Since there is no physical force driving drilling fluid into the formation if the well is drilled underbalanced, underbalanced drilling effectively prevents a lost circulation problems where If the pressure in the wellbore is less than the formation pressure in the entire open hole section, lost circulation will not occur.

    FIGURE 6: LOSS OF CIRCULATION

    4-Improved Formation Evaluation

    Drilling underbalanced can improve the detection of productive hydrocarbon

    zones even identifying zones that might otherwise have been bypassed if the well

    had been drilled conventional.

    5-Reduces Formation Damage:

    Anticipated well productivity is often reduced by regions of impaired permeability, formation damage, adjacent to the wellbore. Formation damage can occur when liquid(s), solid(s) or both enter the formation, during drilling. If the drilling fluid pressure in the wellbore is less than the pore pressure, the physical driving force: causing penetration of material from the drilling fluid is removed. That is not to say that the possibility of formation damage from the drilling fluid is completely removed. In some circumstances, chemical potential differences between drilling and pore fluids could cause filtrate to enter the formation against the pressure gradient. Also, there are instances in which a well, that is drilled nominally underbalanced, experiences transient overbalanced conditions, due to less than perfect control of circulating pressures or possibly due to fluid inflow while the well is not being circulated. In any case, there are many examples of wells drilled underbalanced with higher productivity than adjacent wells drilled conventionally.

  • 11

    FIGURE 7:SOLID INVASION INTO A HOMOGENOUS PORE SYSTEM

    FIGURE 8: MECHANISM OF SUSPENDED SOLIDS ENTRAINMENT

    FIGURE 9: MECHANISM OF SLOIDS ENTRAINMENT IN FRACTURES

  • 12

    6-Reduced probability of differential sticking.

    In a well drilled conventionally, a filter cake forms on the borehole wall from solids deposited when liquid flows from the drilling mud into permeable zones, due to an overbalance pressure. If the drill string becomes embedded in the filter cake, the pressure differential between the wellbore, And the fluid in the filter cake can act over such a large area that the axial force required moving the string can exceed its tensile capacity. The drill string is then differentially stuck. There will be no filter cake and no pressure acting to "clamp" the drill string if the well is underbalanced. Other mechanisms can cause sticking; underbalanced drilling does not eliminate the possibility of a stuck drill string.

    7-Earlier production:

    When a well is drilled underbalanced, formation fluids flow into the wellbore from any permeable formation in the open hole section. Penetrating any hydrocarbon bearing formation with adequate drive and permeability will result in an increased hydrocarbon cut in the drilling fluid returning to the surface. With adequate mud logging and drilling records, underbalanced drilling can indicate potentially productive zones, as the well is drilled. Conversely, during conventional drilling, the overbalance pressure prevents formation inflows; hydrocarbon-bearing zones have to be identified from cuttings, core analysis, logging or DSTs.

    8-Environmental benefits.

    There can be environmental benefits associated with properly managed, underbalanced drilling operations. These depend on the exact drilling technique adopted. With dry, gaseous drilling fluids there is no potentially damaging liquid drilling mud to dispose of after drilling is completed. The chemical used in mist and foam drilling are often benign and biodegradable surfactants that do not pose significant environmental concerns.

    FIGURE 10: DIFFERENTIAL STUCK PROBLEM

  • 13

    9-Less need for stimulation:

    Following conventional drilling operations, wells are often stimulated to increase their productivity. Stimulation include acidizing or surfactant treatment!, to remove formation damage; or hydraulic fracturing can be used to guarantee adequate production in low permeability reservoirs or to bypass damage in higher permeability formations. Reduced formation damage means lower stimulation costs. Therefore: If the formation is not damaged during drilling and completion, stimulation to remove the damage will not be needed.

    Disadvantages of under balanced drilling:

    1-Increased Operational Complexity space requirements for additional equipment

    requires dedicated, knowledgeable personnel

    capable of providing onsite coordination of all services

    rig crews may be unfamiliar with underbalanced drilling procedures

    2-Conventional Mud Pulse MWD is Ineffective when compressible Fluids are used

    The alternative electromagnetic MWD data transfer is generally more

    expensive and tool availability may be limited.

    Wire line wet-connect steering tool result in slower connections and

    increased operational complexity.

    3-Poorly Managed Multiphase Flow Regimes can Create Drilling Problems:

    Insufficient cuttings removal from the wellbore.

    Motor can over-speed.

    Excessive down hole motor stalling due to low effective fluid injection

    rates.

    Incorrect fluid mix can create in stationary drilling conditions and

    destructive vibrations.

    4. Increased Daily Costs Due to Additional Equipment and Personnel

  • 14

    TABLE 1: UBD ADVANTAGES VS DISADVANTAGES

    Advantages Disadvantages

    Decreased formation damage Possible wellbore stability problems

    Eliminate risk of differential sticking Increased daily costs

    Reduce risk of loss circulation Generally higher risk with more inherent

    Problems

    Increased ROP More complex tripping operations

    Improved bit life Possible increased torque and drag

    Reservoir Characterization More complex drilling system

    More people required

  • 15

    Important limitation for underbalanced drilling

    Wellbore stability issues. Deep, high pressure, highly permeable wells

    can be problematic due to flow control & safety issues.

    Excessive formation water.

    High producing zones close to the beginning of the well trajectory will

    adversely affect the underbalanced conditions along the borehole.

    Not following established design guidelines.

    Wells that require hydrostatic fluid or pressure to kill the well during

    certain drilling or completion operations.

    Slim hole wells with high annulus friction pressures.

    Wells that contain significant pressure or lithology variations.

    Operators interfering with the UBD experts.

    Increased complexity and HSE issues on H2S wells.

    Handling and disposal of produced fluids.

    Flaring of produced gas.

    Erosion and corrosion issues and risks.

    Wellbore consolidation.

    Increased drilling costs (depending on system used).

    Compatibility with conventional MWD systems.

    Spontaneous counter current imbibition effects.

    Gravity drainage in horizontal wells.

    Possible near wellbore mechanical damage.

    Discontinuous underbalanced conditions.

    Generally higher risk with more inherent problems.

    String weight is increased due to reduced buoyancy.

    Possible excessive borehole erosion.

    Possible increased torque and drag.

  • 16

    How to drill underbalance- type of units?

    1. Snubbing systems

    If tripping is to be conducted underbalanced without a down hole deployment

    valve, a snubbing system will have to be installed on top of the rotating control

    head system. The current snubbing systems used in underbalanced drilling are

    called rig assist snubbing systems. These units need the rig draw works to pull

    and run pipe and are designed to deal only with pipe light situations.

    A jack with a 10ft stroke is used to push pipe into the hole or to trip pipe out of

    the hole. The ability to install a snubbing system below the rig floor allows the rig

    floor to be used in the conventional drilling way.

    Snubbing with an onshore rig where there is no space under the rig floor to

    install a snubbing unit will have to be conducted on the rig floor. In order to

    facilitate snubbing, so called push-pull units are installed on the rig floor

    FIGURE 11: WELL CONTROL EQUIPMENT FOR SNUBBING

  • 17

    Snubbing unit offers better flow capacity, breaking load and rotation capacity and it

    is also able to put weight on the downhole tool.

    Tripping takes longer because the lengths of pipe have to be screwed together.

    Operating this type of unit requires specialized personnel usually consisting of a

    head of unit and three or four people per shift

    Diameter of the snubbing pipe, usually at least 3 1/2" and sometimes up to

    7 5/8" are possible.

    Hoisting capacity in the strip phase 340,000 lb

    In the snub phase capacity is usually half that of the strip phase due to jack

    design.

    Circulate at a higher flow rate.

    Clean out hard fill and scale that require weight on the tool and rotation.

    Spot cement plugs.

    Perform some fishing jobs.

    FIGURE 12:SCHEMATIC SNUBBING LAYOUT

  • 18

    2. Coiled tubing unit

    Although coil tubing drilling (CTD) is still considered to be in the early stages

    of development, CT has been in use for underbalanced well interventions and

    work overs since the 1970s. However, as Figure 19 illustrates, todays CTD

    rig with its specially designed mast can be used in any area and in all types of

    conditions. In addition to the potential for reduced environmental impact, the

    lack of pipe connections in coiled tubing gives it many advantages over

    Jointed pipe UBD:

    There are no bottom-hole pressure fluctuations due to connections.

    Personnel are not required to work directly above the well bore.

    The ability to transmit continuous data with the use of electric line

    inside the coil.

    Continuous injection of gas through the drill string (CT).

    Underbalanced tripping is relatively routine and much faster than

    with jointed pipe.

    Disadvantages of coiled tubing are:

    The inability to rotate the string.

    Limited pulling or pushing power (surface equipment limitations).

    Limited coil life due to fatigue cycles (bending / straightening).

    Depth control limitations (depends on equipment selected).

    Limitations in reach and hole size (3 6).

    Logistical limitations relative to the coil (especially critical offshore).

    3-Conventional rig

    Two of the advantages of using a conventional rig are its significant mechanical

    strength (generally limited by pipe strength) and the capability to rotate the string.

    This makes the rig capable of handling operational problems like stuck pipe

    (mechanically stuck rather than differentially stuck) and drilling larger hole sizes:

    6 8. In addition, only the reservoir section is usually drilled underbalanced.

    Therefore, if a conventional rig is used to drill to the top of the reservoir, it is often

    cost-effective to continue with jointed pipe operations in UBD mode in the

    reservoir.

  • 19

    One of the main disadvantages of using conventional rig / jointed pipe in UBD mode

    is the fact that fluid circulation has to be interrupted while making connections. This

    may lead to undesirable down-hole pressure fluctuations.

    On many of the wells using underbalanced techniques there will be a point where a

    pipe light situation will exist. This occurs where the forces inside the well-bore

    acting to push the string out, is greater than the forces tending to keep it in the well

    bore (p primarily the weight of the string .In a UBD operation, designing a down-

    hole lubricator into the casing or completion string can be used to the same effect;

    by installing a full-opening valve down-hole at a depth where the force due to the

    weight of the string is greater than the forces acting to push the string out. The drill

    pipe is stripped out (or run in) to just above the valve. The well can then be shut in

    at this depth to allow tripping out (or stripping in) to continue in a normal or

    conventional manner. To prevent impairment of the reservoir, the well bore below

    the down-hole valve must contain only reservoir-induced fluids (no drill fluid) prior to

    shutting in.

    FIGURE 13:DOWN-HOLE DEPLOYMENT VALVE

  • 20

    References

    Bieseman, T., Emeh, V., 'An introduction to Underbalanced Drilling',

    RKER.95.071

    Bourgoyne Jr., AT., et al 'Applied Drilling Engineering' SPE Textbook

    Series 1986, ISBN 1-55563-001-4

    Stone, C.R. and Cress, L.A.: New Applications for Underbalanced

    Drilling Equipment, paper SPE 37679, manuscript under review (1997).

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    21

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    22

    For Underbalanced Drilling operation

    This chapter provides detailed descriptions of the different techniques of underbalanced drilling. The major function of the circulating drilling

    fluid in underbalanced drilling is to lift cuttings from the hole. This

    aspect of each technique is considered in some detail. Methods for

    analyzing hole cleaning and circulating pressures are reviewed. In each

    case, the required equipment is described. Any special operating

    procedures that may have to be adopted are described, as are any

    limitations.

    Contents: Gaseous Drilling Fluids

    Mist Drilling

    Foam drilling

    Gasified or aerated Systems

    Gasification techniques

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    23

    Gaseous Drilling Fluids

    This section will refer to the compressed gas phase as air since it is the most

    economical and widely used gas in reduced pressure drilling. However, other

    gases may be substituted in each of the systems discussed; Specifics to natural

    gas, nitrogen or exhaust gas being used are discussed separately.

    Characteristics of gaseous drilling:

    Fast penetration rates

    Longer bit life

    Greater footage per bit

    Good cement jobs

    Better production

    Requires minimal water influx

    Slugging can occur

    Mud rings can occur in the presence of fluid ingress

    Relies on annular velocity to remove cuttings from the well

    Problems of gaseous drilling:

    Maximum Water influx.

    Washouts of tool joints.

    Corrosion and erosion problems.

    Downhole fires with air.

    Inefficient in Crooked hole.

    FIGURE 1: GASEOUS DRILLING TECHNIQUES

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    24

    1. Air Drilling

    Drilling with air, nitrogen enriched air, natural gas, liquid nitrogen or other gas

    often called dusting since no fluid (Water / Soap) injection means the annular

    returns are Dust. It provide a minimum hydrostatic pressure Bottomhole

    circulating pressures may be less than 60 psia (400 kPa) at 8000 Ft. (2500

    meters) and a maximum rate of penetration.

    Air is about 78 percent nitrogen, 21 percent oxygen and contains carbon dioxide,

    water vapor and trace of rare gases. Air is the least expensive of gases because

    it is only need to be compressed by using compressors to be used in drilling.

    1.1. Drilling technique

    The "dust" technique is used when drilling dry formations, or where any water influx is slight enough to be absorbed by the air stream.

    The temperature of the air injected into the hole should be slightly higher than the temperature at ambient conditions.

    As the air travels down the drill string the air is heated to that of the surrounding formation.

    When the air passes through the jet nozzles, the air expands and the velocity increases to supersonic flow .This causes the temperature to decrease and cool the bit and the bit bearings.

    As the air travels up the annulus, the air is then reheated to the temperature of the surrounding formation. This medium requires significant compressed gas volumes to clean the well with average velocities of over 3,000 ft per minute.

    Important notes should be considered in Air drilling:

    Since the air has no structural properties to produce transport

    characteristics, removal of cuttings is dependent on the annular velocity of

    the air. Annular velocities in excess of 1000[m/min] or 3000[ft/min] are

    typically employed for cuttings transport.

    FIGURE 2: AIR (DUST) OUT-LINE

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    25

    Drilling with dry air systems is restricted by water producing formations, unstable wellbores and high formation pressures. When water saturated formations are encountered, the wet drill cuttings stick together and to the pipe walls and will not be carried from the hole by the air velocity. When these cuttings fill the annulus a mud ring will form which stops the flow of air and the pipe will stick.

    TABLE 1: DUST DRILLING ADVANTAGES & LIMITATIONS

    Dust Drilling Limitations Advantages of Dust Drilling System

    Wellbore fluid influxes cannot be handled effectively with Dust drilling

    Optimum environment for use with Air Hammers

    Influxes will wet cuttings resulting in mud rings in the annulus, restricting hole cleaning.

    Least Expensive operations

    Switching to Mist or Foam allows continued Air Drilling in the presence of water.

    No fluid system to clean up or disposal at the surface

    Chance of Down-Hole Fire if Mud Rings are not eliminated

    Maximum Penetration Rates.

    The problem of down hole fires normally only occur with air drilling where the air is more than 90% of the fluid/air volume.

    Extended bit life.

    Compression costs with air are US$300/day or more with significant mobilization and demobilization costs

    Corrosion problems is obtained than any other technique due to the presence of 21% of oxygen

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    26

    1.2. Unloading and Drying the Hole

    The method, proven in actual field operations to unload the hole of fluid, dry the

    hole and start air dust drilling is given below:

    1. Run the drill string, complete with desired drilling bottom hole assembly and

    bit, to bottom.

    2. Start mud pump and run as slow as possible. Pump fluid at a rate of 1

    to 2 barrels per minute. This may necessitate crippling the pump to get

    this rate. This is done to reduce fluid friction pressures to a minimum

    and pump at a minimum standpipe pressure for circulation. Standard fluid

    hydraulic calculations will indicate what the standpipe pressure should be at

    1 to 2 BPM.

    3. Bring one compressor and booster on line. This will aerate the fluid being

    pumped down the ho1e. About 100 to 150 SCFM per barrel of fluid should

    be sufficient for aeration. If too much air volume is being used, the

    standpipe pressure will exceed the pressure rating of the compressor and/or

    booster. Therefore, slow the compressor down until air is being injected and

    mixed with the fluid going down hole. Also, the mist pump and soap injection

    pump should be injecting water and soap at a rate of about 12 bbl/hr and

    3gal/hr, respectively. The soap will tie the fluid and air together and provide

    better aeration properties.

    4. As the annular fluid column is lightened, the standpipe pressure will drop

    and additional compressors or air volume can be added to further lighten

    the fluid column and unload the hole. The aeration procedure is far

    superior when compared to the slug method of unloading the hole. The

    slug method is accomplished by pumping alternate slugs of water and air

    down the hole until air can be used continuously. Air is first injected up to an

    arbitrary maximum pressure, then water is injected to lower the pressure

    back to some arbitrary minimum pressure. This procedure is repeated until

    air can be injected continuously. The aeration procedure requires less time,

    does not because undue surging of the hole due to heading, does not cut

    out pit walls because surges are eliminated and can be done generally at

    lower operating pressures.

    5. When the hole is unloaded, the mist pump and soap injection pump should

    remain in operation. This provides a mist (1.5 BW/hr. per inch of hole

    diameter and 0.5 to 4 gal. soap/hr) which can clean the hole of sloughing

    formations.

    6. At this point drilling, using air mist can commence. Drill 20 to 100 feet to

    allow any sloughing hole to be cleaned up.

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    27

    7. After the hole has stabilized (no sloughing), stop drilling and blow the hole

    with air mist to clean the hole of drill cuttings. About 15 to 20 minutes is

    sufficient or until the air mist is clean. Clean air mist is usually a fine spray

    and white in color.

    8. When the hole is clean, stop air misting, break off the Kelly and pour 10 to

    20 gallons of soap followed by 20 to 4 barrels of water directly down the drill

    pipe. Do not mix soap and water in mist pump and inject it that way. Pouring

    the soap and water directly down the drill pipe has proven to be a better

    procedure and gives a better soap slug and a greater drying effect.

    9. Put the Kelly back on and set the bit on bottom. Since the hole is now full of

    air, the soap and water will run to bottom. A proper soap sweep cannot be

    achieved unless it is mixed with air and pumped up the annulus. This cannot

    be done if the drill bit is above the soap and water.

    10. With the bit directly on bottom, start air down the hole. Pump straight air at

    normal drilling volumes until the soap sweep comes to the surface. The

    soap will appear at the end of the blooie line and look like shaving cream.

    11. Continue to blow the hole with air for about 0.5 to 1 hour.

    12. Start drilling and the hole should dust after 5 to 10 feet have been drilled.

    Sometimes as much as 60 to 90 feet are required for dust to appear at the

    surface.

    2.Natural Gas Drilling

    If a source of high-pressure natural gas at the correct volumes is available,

    drilling with natural gas is a very good option. The use of air hammers with gas

    drilling is another option that can be used to increase ROP. This is an option

    used in tight gas reservoirs.

    A flow regulator and a pressure regulator are

    normally used to control the amount of gas

    injected during the drilling process. Natural

    gas is also non-toxic and non-corrosive if

    sweetened correctly. Natural gas has

    greater solubility in hydrocarbons when

    compared to nitrogen, which may result in

    the potential for greater disengagement

    problems and asphalting precipitation.

    FIGURE 3: UBD LOCATION WITH NATURAL GAS

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    28

    The most efficient use of natural gas is normally through annular injection. The

    use of natural gas through the drillstring is not recommended, as gas will have to

    be vented every time a connection needs to be made although this can be done

    safely. The use of natural gas injection through a coiled tubing system is also not

    recommended, as a pinhole in the coil could not be isolated and gas maybe

    released to form an explosive mixture inside the wraps of the coiled tubing reel.

    Using natural gas will prevent the formation of a flammable gas mixture

    downhole when a hydrocarbon producing zone is penetrated. This inherently

    higher potential for surface fires requires few changes in operating procedures

    from those used in dry air drilling.

    3.Nitrogen drilling

    a. Cryogenic Nitrogen Nitrogen is by far the most common gas that is currently being used to lighten

    the circulating fluid column in underbalanced drilling operations.

    Properties of Nitrogen are listed below;

    Nitrogen is a colorless, odorless and tasteless gas that makes up four fifths of the earths atmosphere.

    Nitrogen is non-toxic, non-flammable and noncorrosive. It has very low solubility in water and hydrocarbons, and is compatible

    with virtually any fluid used in drilling operations. Nitrogen does not tend to form hydrate complexes or emulsions. Nitrogen forms a major part of our atmosphere in the fact that the

    atmosphere comprises of: 78.03 % Nitrogen.

    Cryogenic nitrogen definition

    Cryogenic nitrogen is frozen liquid nitrogen. It is the byproduct of oxygen

    manufacture where air is compressed and cooled and then compressed again

    until the nitrogen appears as a clear liquid at -320F (-160C). A gallon of liquid

    nitrogen produces 93.12 scf of gas. One Liter of liquid nitrogen produces 0.698

    sm3 of gas. The nitrogen produced is 99.9 percent pure and contains no

    oxygen. The field of science that deals with the technology of handling liquids

    colder than -187F is called cryogenics

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    29

    Cryogenic nitrogen production

    Cryogenic nitrogen is produced by extraction from the air through fractional

    distillation. In this process the air is liquefied and the liquid is then separated

    though the following factors;

    Liquid air boils at -317F Liquid nitrogen boils at -320F Liquid oxygen boils at -297F.

    Oxygen starts to evaporate leaving Nitrogen rich liquid. By repeating the boiling

    and condensing processes high purity of liquid nitrogen up to 99.98 % can be

    obtained.

    Procedure for Converting from Liquid Volume into gas volume.

    1 gallon liquid nitrogen produces 93.12 ft3 of N2 at SCP. 1 m3 of N2 liquid produces 698 m3 of gas at SCP. 1 gal of liquid nitrogen is 93.12 ft3 at STC. 1 gal of liquid nitrogen is 0.1333 ft3. 1 liter of liquid nitrogen is 698 litres of gas at STC.

    Cost of cryogenic nitrogen

    World-wide is 1-3 US $/gal or 0.10 US $/scf. In Canada is 0.02 US $/scf. In South America is 1.00 US $/m3.

    FIGURE 4: CRYOGENIC NITROGEN-PUMPING EQUIPMENT

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    30

    3.2 Membrane Nitrogen Nitrogen gas is generated by introducing compressed air into hollow membrane

    fibers, which preferentially separate oxygen and other rich gases from the air

    leaving high purity nitrogen at around 95%. The remaining 5% is normally

    oxygen.

    Membrane process procedure in field use

    The membrane is a small, long, and hollow straw. Air is fed into one end of each

    membrane straw. Oxygen and water vapor quickly penetrate the membrane and

    escape, which leaves only nitrogen to exit from the end of the membrane.

    Each membrane looks similar to white horsehair. Thousands of membranes are

    placed inside a stainless steel operating bundle, or canister, about 14 in. (35 cm)

    in diameter and 5 ft (1.5 m) long. A number of the bundles are paralleled together

    to make a nitrogen unit. Warm, filtered air is pumped into the bundles at 350 psi

    (2,400 kPa) and is recovered as nitrogen at the discharge end at 300 psi (2,000

    kPa). The efficiency of the system is about 50 percent, so only about half of the

    input volume of air is recovered as nitrogen.

    The nitrogen is then pressured with an air compressor booster and sent to the

    rig system

    FIGURE 5: CRYOGENIC NITROGEN

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    31

    Nitrogen Production (NPU) Equipment Configuration

    The NPU receives compressed air from one or more primary compressors at

    pressures ranging from 100 to 350 psig. The product nitrogen is pumped, with

    about a 20-40 psig pressure drop, to the suction of a booster compressor where

    its pressure is increased to that required for injection into the drillstring.

    NPUs have three major components: an air filtration system, an array of air

    separation modules, and a control panel.

    The air filtration system usually consists of a scrubber, coalescing filler, and a particulate filter. Some NPUs also include an activated carbon bed filter and possibly a refrigerated air dryer. The activated carbon bed filter removes aerosol-sized and smaller oil droplets down to a concentration of a few parts per billion. The refrigerated air dryer reduces the relative humidity into the carbon bed to improve oil droplet filtration.

    The arrays of hollow fiber modules are manifold together to accept the clean compressed air feed and to collect and deliver the nitrogen product. The oxygen and water vapor permeate stream is also collected from each membrane module and piped at near atmospheric pressure to the outside of the NPU skid, where it can quickly and harmlessly dissipate into the atmosphere.

    The control panel on the NPU allows monitoring and control of the operation. Control panel design and function vary greatly depending on the manufacturer. Some panels measure flow rates, temperatures, purity, and pressure drops across the NPU precisely, yet others only provide simple output of flow rate and nitrogen purity.

    FIGURE 6: NITROGEN GENERATING UNIT (NGU)

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    32

    2. Exhaust Gas

    Exhaust gas is a unique method of taking the oxygen out of air and using the

    process to run compressors, By using a diesel engine to run the compressors

    and produce the exhaust gas, which is high in nitrogen, the cost of gas

    compression is shared with the cost of producing nitrogen, which makes both

    less expensive

    A potentially very attractive source of gas is the waste gas stream from self-

    contained propane units or diesel fired rig engines themselves. However, when

    using diesel fired engines, the combustion process is relatively inefficient and the

    flue gas can contain 10 - 15% oxygen plus corrosive gases such as CO2 and

    NO2 which may react adversely with produced hydrocarbons, thus accelerating

    the corrosion process.

    Hole cleaning in gaseous drilling

    Optimizing hydraulics with gasses is primarily concerned with hole cleaning -

    getting the cuttings that are generated by the bit out of the hole. With gas,

    rheological properties have very little to do with hole cleaning. Hole cleaning with

    gasses is almost entirely dependent on the annular velocity.

    Drag and gravitational force: The lifting power of an air drilling system is

    proportional to the circulating density, and to the square of the velocity. The

    density, and thus the suspension properties, of an air stream is much lower than

    a conventional mud system. Therefore, the annular velocity is the primary factor

    in transporting the cuttings to the surface.

    FIGURE 7: FLOW PATH OF PROPANE EXHAUST GAS

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    33

    VIP notes

    Compressibility of air (or gas) complicates matters. Frictional pressure increases downhole pressure - decreases

    velocity downhole. Suspended cuttings increase the density of the air, increasing

    downhole pressure.

    Temperature has an effect on volumetric flow rate. We must pump at a velocity high enough to remove the cuttings,

    but not too high where we waste energy.

    Hole Cleaning Criteria: there are major three properties controls the hole

    cleaning criteria

    Terminal Velocity Criteria. Minimum Energy Criteria. Minimum BHP Criteria.

    Erosion of gaseous drilling

    A high annular velocity may cause erosion in soft formations. If the use of an air

    drilling technique causes erosion of the well-bore, the addition of a stabilizing

    agent or changing air drilling techniques may be required to minimize this

    problem.

    Erosion of the drill string can also be caused by the high annular velocities and

    temperatures generated when steam zones are encountered. Some people

    estimate that the velocity may exceed 10,000 ft/min in the annulus. The injection

    of barrier type chemicals will inhibit this type off erosion

    Corrosion of gaseous drilling

    Corrosion should be considered before beginning the use of an air drilling

    technique. When drilling through formations with acid contamination (CO2 and

    H2S), the problem could be a lot worse. Mixtures or hydrogen peroxide (H2O2)

    and caustic soda (NaOH) can be used to solubilize and precipitate the H2S

    contamination at the surface. An organic, phosphate, scale inhibitor can prevent

    the deposition of alkaline earth metal scale on the drill string.

    FIGURE 8: DUSTING BLOOIE LINE

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    34

    Mist Drilling Mist drilling is a modification of dry air drilling that is utilized when water producing zones are encountered. Like dry air drilling, this system relies on the annular velocity of the air for cuttings transport out of the hole. In mist drilling, a small quantity of water containing foaming agent is injected into the gas stream at the surface. This produces an air continuous system, with the water mist being carried in the air. Foaming agent concentrations in the water typically range from 0.10% to 0.25% by volume in the water. The foaming agent reduces the interfacial tension of the water and drill cuttings in the hole and allows small water/drill cutting droplets to be dispersed as a fine mist in the returning air stream. This allows the cuttings and water to be removed from the hole without the Formation of mud rings and bit balling. The air mist drilling system provides comparable penetration and footage per bit rates to dry gas drilling, with the added benefit of being able to handle wet formations. Costs of air mist drilling are slightly higher than those encountered with dry gas drilling since foaming agent and corrosion inhibitor are needed.

    When should you use mist drilling? Mist Drilling is normally used when formations begin to produce small

    amounts of water (10 to 100 bbls per hour) during air/gas drilling operations.

    Mist drilling should only use in special applications since hole cleaning is

    even more difficult with mist drilling system when compared with air drilling.

    .

    FIGURE 9: MIST DRILLING OPERATION

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    35

    CHARACTERISTICS OF MIST-DRILLING

    Air is the continuous phase and the liquid consists of discontinuous

    droplets

    Similar to air drilling but with addition of liquid

    Relies on annular velocity to remove cuttings from the well

    Reduces formation of mud rings

    High volumes required (30%-40% more than dry air drilling)

    Fluid or foam injection rates less than30 [bbl/min] or 100[l/min].

    Liquid volume fraction LVF < 0.025

    Pressures generally higher than dry air drilling

    Incorrect air/gas-liquid ratio leads to slugging, with attendant pressure

    Increase.

    Can perform simplified calculations by including water mist as drill cuttings

    and modify the ROP to account for the equivalent weight being lifted.

    The mist particles travel at a slightly different velocity than the air because

    of slip.

    Advantages of Mist Drilling Gas or air volumes are increased and a mist pump skid is used to inject small

    quantities of water and a foaming agent solution. This solution entraps the

    water Influx and enables the air phase to lift the cuttings and influx to surface.

    Higher ROP than with conventional mud

    Enables drilling to proceed while producing fluids.

    Improves Hole Cleaning capacity

    Reduces risk of downhole fires.

    Eliminates need for Nitrogen

    Mist Drilling Limitations

    Slower penetration rate than Dust drilling due to increased annular hydrostatic pressure.

    ROP = 30 50% less than Dusting Limited tolerance to water influx High amounts of Water influx typically make Mist Drilling uneconomical. When large liquid influxes are encountered; options :

    Hole Cleaning of mist drilling

    Switching to a mist drilling technique requires an increase of at least 30% in the air volume.

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    36

    The additional volume is needed to overcome higher frictional losses caused by: wet cuttings adhering to the drill string and hole, higher slip

    velocities of larger wet cuttings, and transportation of the heavier wet

    air column.

    The mud is injected with the air stream to disperse the cuttings and inhibit them from adhering to the drill string and hole.

    Although injection pressure of 100 to 200 psig are normally enough for dust drilling, pressures exceeding 350 psig can be encountered while

    mist drilling.

    Pressures of 1250 psig. may be required when large amounts of fluids are present in the annulus.

    The rate of fluid intrusion will dictate the amount of air and fluid that must be injected to efficiently clean the hole.

    Formation fluid entries of up to 100 bbl/hr have been successfully mist drilled

    Corrosion Control Chemical treatment is needed to minimize corrosion caused by the

    additional fluid and air.

    Basic corrosion control is provided by maintaining the pH of the mud system above 10.5, and treating any hardness or carbonates with the

    appropriate chemical.

    Hydrogen sulfide and carbonate scale are treated in much the same way as in a conventional mud system.

    Corrosion coupons should be run in the saver and crossover sub to

    monitor the type and rate of corrosion.

    If H2S is encountered, the first line of protection is to maintain the pH at or above 11.

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    37

    Foam Drilling Foam is like shaving cream, not like soap suds. Very dry foam will persist for

    many hours like the one in this reserve pit. Foam is dry because all the water is

    bound up. In wet foam more water is flee like in soap suds.

    FIGURE 10:FOAM IS RELATIVELY NEW FLUID TO THE DRILLING INDUSTRY.

    .

    If more liquid and a surfactant are added to the fluid, stable foam is generated.

    Stable foam used for drilling has a texture not unlike shaving foam. It is a

    particularly good drilling fluid with a high carrying capacity and a low density. One

    of the problems encountered with the conventional foam systems is that stable

    foam is as it sounds. The foam remains stable even when it returns to the surface

    and this can cause problems on a rig if the foam cannot be broken down fast

    enough. In the old foam systems, the amount of defoamer had to be tested

    carefully so that the foam was broken down before any fluid left the separators. In

    closed circulation drilling systems stable foam could cause particular problems

    with carry over. The recently developed stable foam systems are simpler to break

    and the liquid can also be re-foamed so that less foaming agent is required and a

    closed circulation system can be used. These systems, in general, rely on either

    a chemical method, of breaking and making the foam or the utilization of an

    increase and decrease of pH, to make and break the foam.

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    38

    The foam quality

    The amount of gas in the fluid at any point, measured by volume, can be

    expressed as foam quality or as fluid ratio. Ratio R (% by volume of gas) is the

    ratio of gas to liquid unit under existing conditions of pressure and temperature. A

    good rule of thumb for a gasified fluid is to try to maintain the ratio through the

    system at 5:1 to 40:1 (i.e., 80 %< foam quality < 97.5 %).

    Drilling with foam has some appeal due to the fact that foam has some attractive

    qualities and properties with respect to the very low hydrostatic densities, which

    can be generated with foam systems. Foam has good rheology and excellent

    cutting transport properties.

    The fact that foam has some natural inherent viscosity as well as fluid loss

    control properties, which may inhibit fluid losses, makes foam a very attractive

    drilling medium. During connections and trips, the foam remains stable and

    provides a more stable bottom hole pressure.

    Gas phase percent by volume Expressed as %, whole number or Decimal

    equivalent (e.g. 75, 75%, or 0.75)

    0-55% Aerated Fluid

    55%-94% Foam

    94%-99.9% Mist

    100% Gas/Air

    Factors Effecting Foam Quality Pressure.

    Depth.

    Gas content.

    Liquid content.

    Maintaining Foam Quality

    Gas and liquid injection rates.

    Back-pressure on the system.

    Measurement.

    Calculation (computer models).

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    39

    Adding surfactant to a fluid and mixing the fluid system with a gas generates

    foam.

    Foam used for drilling has a texture not unlike shaving foam. It is a particularly

    good drilling fluid with a high carrying capacity and a low density. One of the

    problems encountered with the conventional foam systems is that foam does

    what it says on the tin. It remains stable.

    Characteristics of foam-drilling

    Extra fluid in the system reduces the influence of formation water

    Very high carrying capacity

    Reduced pump rates due to improved cuttings transport

    Stable foam reduces slugging tendencies of the wellbore

    The stable foam can withstand limited circulation stoppages without

    affecting the cuttings removal or ECD to any significant degree

    Improved surface control and more stable downhole environment

    The breaking down of the foam at surface needs to be addressed at

    the design stage

    More increased surface equipment required

    TABLE 2: VOLUME PERCENT BETWEEN MIST , FOAM AND AIRATED LIQUEDS

    Gas volume percentage Name

    99.99 96% Mist

    96% - 55% Foam

    0 55% Gasified Liquid

    Guidelines for Foam Drilling

    Liquid injection volume 16 80 gpm

    Soap injection volume 0.3 to 1.0% by weight 0.05 0.5 gpm

    Gas injection volume 300 1000 scft/min

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    40

    The Pattern of Foam

    Classic foam has a regular geometric shape -that of a 12 sided polygon because

    it is the most efficient shape. In a plane two dimensional view, this would be

    hexagons. Once the foam is in motion, the figures are distorted by friction.

    Classic static foam pattern on the left.

    Foam in flow probably looks more like the one on the right.

    FIGURE 11: DIFFERENT FLOW PATTERN

    Advantages of Foam Drilling

    Foam has excellent cuttings carrying capacity.

    Lower Air Volume requirements can mean less Air Compression

    equipment required than Dust or Mist drilling.

    FOAM GASEATION

    Emulsion. Mixture.

    Hard to Separate Separates easily.

    NO Pressure Surges. Heading and pressure surges.

    Huge lifting capacity. Normal lifting capacity.

    Plugs lost circulation and reduces

    head.

    Reduces lost circulation by reducing

    head.

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    41

    During connections (break in circulation) the cuttings will remain

    suspended in the annulus.

    Holding Back Pressure on Annulus can help reduce water influx and/or

    maintain hole wall stability

    Higher viscosity aids hole cleaning with lower annular velocity

    At the bottom, annular velocities are designed for 100 to 300 feet per

    minute (double that for directional wells above 300)

    Penetration rate is still significantly higher than with mud but not as high as

    with air .

    The higher annular pressures may help reduce mechanical wellbore

    instability and reduce production rates

    Lower annular velocities may reduce erosion of the borehole wall and drill

    string

    No damage to formation

    Continuous Drill Stem test

    Controllable BHP

    No lost circulation

    No differential sticking.

    Best for large holes

    The Main Reasons for UB Drilling with Foam

    1. Stops lost circulation.

    2. Improve drilling rate.

    3. Protects the reservoir.

    4. Avoid differential sticking.

    5. Hole cleaning with low fluid volume.

    Lost Circulation with Foam

    Reduced the mud density no junk.

    Foam plugs lost zones.

    The Foam bubbles are lost zone plugging agents

    Improve Drilling Rate

    Low bottom hole pressure increases drilling rate.

    For hard rock, the new air hammer works with foam.

    Protect Reservoir

    No formation damage with no influx into the well bore.

    Minimal pressure surges.

    Controllable pressures.

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    42

    Limitations for Foam Drilling Surface requirements (pits) for Foam can become a problem.

    Large pits have to be built to contain the Foam and allow time for settling.

    Chemical cost to break down Foam can become expensive.

    Large influx of Fluids can break down Foam and thus reduce hole

    cleaning.

    Foam is a very corrosive environment

    Need to pay attention to corrosion inhibitors

    Temperature will significantly affect the effectiveness of corrosion

    inhibitors.

    Large quantities of foam can accumulate at the surface while drilling

    Foam is a complicated system and requires computer modeling in order to

    properly design the foam in the wellbore

    As the quality of the foam decreases, the viscosity of the foam will

    decrease

    Foam quality changes with pressure and is not a constant in the wellbore

    As the pressure increases, the foam quality decreases

    Theoretical Foam Types

    Stable Foam: 1-2% Surfactant.

    Stiff Foam: 1% Surfactant

    General Foam Types

    Stable foam

    Foaming agent

    Polymer

    Stiff foam

    Polymer

    Bentonite

    pH sensitive foam (amphoteric)

    Transform

    Foam

    Stiff

    PH Sensitive

    Stable

    FIGURE 12: FOAM TYPES

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    43

    Gasified or aerated Systems The next system after a foam system is a gasified fluid system, which is used to control slightly higher pressures. In these systems, a liquid is gasified to reduce the density.

    Characteristics of gasified-mud systems Gasified liquids are often called aerated fluids Extra fluid in the system will almost eliminate the influence of formation

    fluid Unless incompatibilities Occur The mud properties can easily be identified prior to commencing the

    operation Generally, less gas is required Slugging of the gas and fluid must be managed correctly Increased surface equipment will be required to store & clean the base

    fluid Velocities, especially at surface, will be lower, reducing wear & erosion

    both downhole and to the surface equipment. Effective densities of gasified liquids usually range from 4 to 7 ppg Used primarily to avoid or minimize lost circulation The increased ROP will generally not pay for the increased cost Also used today to drill underbalanced and minimize formation damage in

    horizontal wells Underbalanced is usually on the order of 250 to 500 psi Less problem with mechanical wellbore stability Reduces formation fluid inflow rates Can be used to drill unconsolidated formations

    If a foam system is too light for the well, a gasified system can be used. In these. Systems, liquid is gasified to reduce the density. There are a number of methods that can be used to gasify a liquid system and these methods are discussed within the injection systems section. The use of gas and liquid, as a circulation system in a well, complicates the hydraulics program. The ratio of gas and liquid must be carefully calculated to ensure that a stable circulation system is used. If too much gas is used, slugging will occur. If not enough gas is used, the required bottom hole pressure will be exceeded and the well will become overbalanced

    The injection of air into drilling mud creates bubbles in the mud and, because of the surface tension properties of the bubbles relative to the properties of rock and drilling mud, the bubbles tend to fill in the fracture or pore openings in the borehole wall as the aerated mud attempts to flow to the thief fractures and pores his bubble blockage restricts the flow of the drilling mud into these lost circulation sections and thereby allows the drilling operations to progress safely. Aerated fluids have been used to avoid lost circulation in shallow water well drilling, geotechnical drilling, mining drilling, and in deep oil and natural gas recovery drilling operations.

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    44

    When drilling with aerated fluid systems it should be realized that these are the most corrosive of all reduced pressure drilling methods. However, with proper selection of supply water, proper pH control and the proper utilization of technologically advanced corrosion inhibitors, aerated fluid systems are successfully used worldwide. Aerated fluids are well suited for highly unstable formations where loss of circulation is a concern. Aerated fluids also provide the greatest tolerance to fluid influx of any reduced pressure drilling system. Costs involved with aerated fluid drilling are primarily related to the composition of the drilling fluid being utilized and corrosion inhibition. Any liquid with injected air, N2, natural gas, or CO2 Liquid is the continuous phase since liquid volume fraction (LVF) > 0.25 at

    surface

    The gas is compressed at the bottom of the hole and expands as it goes up. It may change the phase and convert into a mist if there is enough air and it is allowed to expand. The only thing that holds the gas to the mud is mud viscosity, the upward velocity of the mud and gas, and the size of the bubbles The gaseated system is a mixture that will separate into gas and fluid

    Gasification techniques

    We can divide UBD techniques into four categories;

    Drillpipe injection Parasite string injection Annular injection (through parasitic liner) Jet-sub Application

    FIGURE 13: DIFFERENT TECHNIQUES OF UBD

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    45

    1. Drill pipe injection

    Drill string injection is the first and simplest method of gas injection into the

    circulation system. Compressed gas is injected at the standpipe manifold where

    it mixes with the drilling fluid.

    The main advantage of drill string injection is that no special downhole

    equipment is required in the well. The use of reliable non-return valves is

    required to prevent flow up the drill pipe. The gas rates used when drilling with

    drill pipe injection system are normally lower than with annular gas lift, and low

    bottom hole pressures can be achieved using this system.

    The disadvantages of this system include the need to stop pumping and the

    bleeding of any remaining trapped pressure in the drill string every time a

    connection is made. This results in an increase in bottom hole pressure. It may

    then be difficult to obtain a stable system and avoid pressure spikes at the

    reservoir when using drill pipe injection. One alternative is to connect the MWD

    back to surface using an electric cable. This technique has previously been used

    very successfully with coiled tubing as the drill string. If drill pipe is to be used,

    wet connects can be utilized; however, the additional time consumed using this

    technique can be limiting.

    FIGURE 14: DRILLPIPE INJECTION TECHNIQUE

  • Un

    der

    bal

    ance

    d D

    rilli

    ng

    tech

    niq

    ues

    46

    2. Parasite string injection

    The primary problem with aerated fluid systems is that they are unstable. In

    foam, the foaming agent and other additives bind the gas-liquid mixture together.

    In aerated systems, there is no agent binding the gas-liquid mixture together.

    In worst case, there will be pressure surges during drilling and during

    connections and trips. Pressure surges can destabilize the wellbore and cause

    underbalanced drilling to periodically go overbalanced. During connections and

    while tripping, aerated fluids will lose its gas and go flat.

    There are techniques, such as adding more gas before connections, which help

    reduce the ensuing pressure surge.

    The use of a small parasite string strapped to the outside of the casing for gas

    injection is really only used in vertical wells. For redundancy reasons, two 1 or

    2 coiled tubing strings are normally strapped to the casing string above the

    reservoir as the casing is run in. Gas is pumped down the parasite string and

    injected onto the drilling annulus. The installation of a production casing string

    and the running of the two parasite strings makes this a complicated operation.

    Wellhead modification is normally required to provide surface connections to the

    parasite strings. This system is not recommended for deviated wells as the

    parasite string is easily ripped off with the casing on the low side of the hole.

    However, the principles of operation and the advantages of the system remain

    the same as with annular injection.

    FIGURE 15: PARASITE STRING INJECTION TECHNIQUE

  • Un

    der

    bal

    ance

    d d

    rilli

    ng

    tech

    niq

    ues

    47

    3. Annula