09_yahara_[2012]
TRANSCRIPT
-
8/13/2019 09_Yahara_[2012]
1/12
1
Well flow (production) test- physical characteristics -
The objective of productiontesting is to clarify theproductivity andcharacteristics of well(steam/water and gas flowrates)
1
Tetsuya YAHARA
West Japan Engineering Consultants, Inc.
Well Testing and Evaluation
Production Test
Production Characteristic (Deliverability) Curve PTS (pressure, temperature, and spinner) Logging
2
e ore mu a or
Pressure Interference Test
-
8/13/2019 09_Yahara_[2012]
2/12
2
Induction of Well Discharge (1) How can we produce the well? -
eam- om na e reservo r
It will be easier to start steam discharge, because it can be done by
only opening the wellhead valve.
3
Steam-dominated reservoir
Induction of Well Discharge (2) How can we produce the well? -
Water-dominated reservoir
It will be necessary to induce steam discharge from the well, applying
some kinds of method to stimulate the well, below.
1. Pressurizing the well (Air reaction)
4
2. Gas lift (Air lifting)
3. Steam or two-phase injection
-
8/13/2019 09_Yahara_[2012]
3/12
3
Pressurizing the Well to Start Discharge
0
200
0 50 100 150 200 250 300 350 400Presssure kg/cm2 ) and Temperature )
Flowing TemperatureFlowing Pressure
400
600
800
1000MeeDehm
gStatic PressureStatic TemperatureBoiling Point CurvePressurinzing with airDepressured BoilingPoint Curve
Pressurizingwithair
5
1200
1400
1600This method is used where the air-water interface can be depressed to a level such thatthe boiling point for depth (BPD) profile from the depressed water level intersects thestable downhole temperature. (Grant, Geothermal Reservoir Engineering, 2nd p135)
Outline of the Methods for Starting Discharge
Method Outline
r ur z w w r ur z y u r r r v rhours or days to allow temperatures in the water columnto sufficiently recover, and then the wellhead valve isopened rapidly to permit discharge of compressed air,
followed by boiling geothermal fluid.
Gas l ift (Air lifting) Tubing is inserted into the well to an appropriate depth,and then air lift is started by pumping air down thetubing. Even if the pumping is stopped, self-sustained
6
sc arge may occur ue o con nuous prov s on o owater from the feed zone.
Steam or two-phaseinjection
When the temperature in the well is relatively low atshallow depth, backfeed of steam or two-phase fluidfrom other production wells is useful to heat up the wellprior stating discharge by pressurizing the well.
(Grant, Geothermal Reservoir Engineering, 2nd Edition)
-
8/13/2019 09_Yahara_[2012]
4/12
4
Two-phase Flow Measurement Methods
Method Objective Outline Merits anddemerits
James LipPressureMethod
Roughly estimateflow rate in the Initialunstable condition
Empirical formuladeveloped by James(1966)
Versatile andeconomicalEasy to install
For proper design ofthe separator for along-term test
For highly productive two-phase geothermal wellsDifferences are within 5%to separator method, andwithin 8% to theoreticalstudy
and remove
Not quite asaccurate as theseparatormethod
Steam-Water Accurate Individual steam and Most accurate
7
Method
steam and water flowrate in stablecondition for long-term testFor proper design ofthe steam turbine
system, using separatorThe overall accuracy willnot normally be betterthan 2% of the steam andwater components
friendly
(Grant, Geothermal Reservoir Engineering, 2nd Edition)
Schematic Equipment Setting
for the Lip Pressure Method Basic Equipment setting for the "Lip Pressure Method"
silencer
weir box
pressure gauge to
measure "Lip pressure"
flow
Pc
8
flow to injection well
or disposal pool
In the lip pressure method, the steam-water mixture is discharged through an appropriate sized pipe into a
silencer to separate the steam and water phases at atmospheric pressure. The lip pressure is measured at
the end of the discharge pipe. The flow rate of the steam-water mixture can be calculated based on theempirical formula developed by James.
-
8/13/2019 09_Yahara_[2012]
5/12
5
Schematic Equipment Setting
for the Separator Method
Orifice
P
Manometer1:DifferentialPress. between orifices
Press.
Gauge
a ve
9
Separator
Production well
Manometer3 : Separator press.Manometer2: Press. prior to or ifice
Flash Chamber Weir
.
In the separator method, the flow rate of separated steam can be measured using anorifice plate and sampling the differential pressure between the front and back of theplate.
The Weir Design
b
B
H
L1 Ls L2
D
from silencer
2mm
45o
20mm
30mm
rectifier (4 plates with holes)Coverage B = 0.5 ~ 6.3 m
b = 0.15 ~ 5 m
D = 0.15 ~ 3.5 m
bD/B2>= 0.06
to pond
10
H = 0.03 ~ 0.45b
1m
L1 > B+3H
Ls = about 2H
L2 > B+2H
JIS B8302-1976
The separated water can be flashed to atmospheric pressure and the waterflow rate can be measured using a weir.
-
8/13/2019 09_Yahara_[2012]
6/12
6
Production Characteristic (Deliverability) Curve
p
S t e a m
W a te r
MassFlow
/Enthal
T o t a l M a s s
E n t h a l p y
11
W e ll H e a d P r e s s u r e
If a longer-term production test can be done, measurements are madecontinuously at a minimum of three different pressures to make the productioncharacteristics curve (the deliverability curve), for which the valve is throttled toproduce at least three different wellhead pressures.
Output (Deliverability) Curveform of the
variation of enthalpy with wellhead pressure
12(Grant, Geothermal Reservoir Engineering, 2nd Edition)
-
8/13/2019 09_Yahara_[2012]
7/12
7
Well Deliverability Curve of KMJ-73,
kamojang
100
KNJ73Deliverability Curve
KNJ73Deliverabilit Curve
30
40
50
60
70
80
90
ssFlowRate(ton/h)
13
0
1020
0 5 10 15 20 25
M
WellheadPressure(kg/cm2)
M. Achyan Karim et al. (2005), WGC2005
Discussion for Optimum Turbine Pressure
14
Optimum turbine inlet pressure should be designed based on the deliverability curveof the production well.
-
8/13/2019 09_Yahara_[2012]
8/12
8
Example of PTS Logging Data
[ Casing ] [ Hole ]
Casing Program
0
500
0 1 2 3 4 5 6
Pressure (MPa)
0
100
0 50 100 150 200 250 300
0
0 50 100 150 200 250 300
Temperature ()
0
100
0 1 2 3 4 5 6
0
100
0 25 50 75 100 125 150
Spinner (rps)
17 1/2
59.1m
14
53.88m
35mm
1.375"
Cable Head
1,000
1,500
200
300
400
500
600
700
800
900
500
1,000
200
300
400
500
600
700
800
900
200
300
400
500
600
700
800
900
Depth(m)
12 1/4
510m
9 5/8
500.7m
900900900
4 1/
14")
4.
3m
54mm
2.125"
Pressure Sensor
Pressure Port
Centralizer
Temperature SensorTemperature Sensor
15
2,000
1,000
1,100
1,200
,
1,000
1,100
1,200
1,000
1,100
1,2002,000
1,000
1,100
1,200
1,300
1,400
1,500
1,600
,
2,000
1,000
1,100
1,200
1,300
1,400
1,500
1,600
1,000
1,100
1,200
1,300
1,400
1,500
1,600
Feed Point
8 1/21010m
71005.7m
6 1/4
1526m
982.5m
4 1/2
1525m
Feed Point
Feed Point
54mm76mm)
Spinner Sensor
The PTS data is very usefulfor understanding theconditions in the flowingwell, such as the enteringmass flow and enthalpy ateach feed point.
Wellbore Simulation Model
with the Surrounding Formation
establishes the deliverabilitycurve of a well based on thereservoir pressure,
temperature, andpermeability-thicknessproducts (kh) at the feeddepth. The power output ofthe well can be estimated
16
assuming the turbine inletpressure.
-
8/13/2019 09_Yahara_[2012]
9/12
9
Example of the Matching Result to the
Production Characteristic Curve
Well Name Example-1
2000
3000
y(kJ/kg)
Simulated
Field Data
Reservoir Pressure 6.86 MPaA
Reservoir Temperature 250.58
Permeability-Thickness (kh) 100.00 darcy-m
Feed Point Depth 1400.00
Liner Diameter 0.2160
Skin Factor 0.00
617.00Production CasingDepth
DiameterProduction Casing
0.2240
200
250
300
350
ate(t/h)
Simulated
Steam
Water
Total
Field Data
steam
water
0
1000
0.0 0.5 1.0 1.5 2.0
Enthalp
17
0
50
100
150
0.0 0.5 1.0 1.5 2.0
Well Head Pressure ((MPaG)
Flow
R
Example of the Matching Result to the
Pressure and Temperature Profiles
0
0 50 100 150 200 250 300
Pressure (barA) / Temperature (degC)
200
400
600
800
1000
Depth(m)
18
1200
1400
1600
Pressure (Field Data) Temperature (Field Data)
Pressure (Simula ted) Temperature (Simulated)
-
8/13/2019 09_Yahara_[2012]
10/12
10
Interference Testing
19
The pressure response at an observation well during production yields important reservoir
properties in terms of pressure interferences among the existing wells. This result can also
be utilized for numerical reservoir modeling. The observed pressure response can be used
as the matching target during the calibration process of numerical model construction.
Monitoring of Pressure Change in Reservoir
For steam-dominated reservoir,wellhead pressure indicatesalmost the reservoir pressure.
Steam-dominated reservoir
,wellhead pressure is useful toobserve the reservoir pressure.
For water-dominated reservoir,
20
Water-dominatedreservoir
required to measure thepressure change over time inthe reservoir.
-
8/13/2019 09_Yahara_[2012]
11/12
11
Pressure Monitoring Equipment
21
A capillary tubing system is used as a pressure monitoring tool that consists of a pressurechamber, capillary tube, Helium gas vessel and transducer with data recording system. Thepressure chamber is set at the depth, and then filled with Helium gas. The change in Helium gaspressure in the pressure chamber with capillary tube, which indicates reservoir pressure, istransferred to a data recording system through the transducer.
Pressure Change due to Interference,and Data Analysis
22
Tsuru and Tokita (1994),15th PNOC-EDC Geothermal Conference
The pressure response at an observation well is also util ized for numerical reservoir modeling,
as the matching target during the calibration process of numerical model construction.
-
8/13/2019 09_Yahara_[2012]
12/12
12
Two-phasepipelineflow simulator
Changes in Reservoir during
Production and Reinjection
Wellbore Simulator
23
Reservoir simulator
Dynamic change in the reservoir will occur after commissioning production and
reinjection due to interference between wells. Therefore, in order to mitigate suchimpact of interference on the well productivity, interference testing should be done
to optimize allocation of wells.
The End
24
Thank you for your
attention!