09_yahara_[2012]

Upload: yadisupriyadi

Post on 04-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 09_Yahara_[2012]

    1/12

    1

    Well flow (production) test- physical characteristics -

    The objective of productiontesting is to clarify theproductivity andcharacteristics of well(steam/water and gas flowrates)

    1

    Tetsuya YAHARA

    West Japan Engineering Consultants, Inc.

    Well Testing and Evaluation

    Production Test

    Production Characteristic (Deliverability) Curve PTS (pressure, temperature, and spinner) Logging

    2

    e ore mu a or

    Pressure Interference Test

  • 8/13/2019 09_Yahara_[2012]

    2/12

    2

    Induction of Well Discharge (1) How can we produce the well? -

    eam- om na e reservo r

    It will be easier to start steam discharge, because it can be done by

    only opening the wellhead valve.

    3

    Steam-dominated reservoir

    Induction of Well Discharge (2) How can we produce the well? -

    Water-dominated reservoir

    It will be necessary to induce steam discharge from the well, applying

    some kinds of method to stimulate the well, below.

    1. Pressurizing the well (Air reaction)

    4

    2. Gas lift (Air lifting)

    3. Steam or two-phase injection

  • 8/13/2019 09_Yahara_[2012]

    3/12

    3

    Pressurizing the Well to Start Discharge

    0

    200

    0 50 100 150 200 250 300 350 400Presssure kg/cm2 ) and Temperature )

    Flowing TemperatureFlowing Pressure

    400

    600

    800

    1000MeeDehm

    gStatic PressureStatic TemperatureBoiling Point CurvePressurinzing with airDepressured BoilingPoint Curve

    Pressurizingwithair

    5

    1200

    1400

    1600This method is used where the air-water interface can be depressed to a level such thatthe boiling point for depth (BPD) profile from the depressed water level intersects thestable downhole temperature. (Grant, Geothermal Reservoir Engineering, 2nd p135)

    Outline of the Methods for Starting Discharge

    Method Outline

    r ur z w w r ur z y u r r r v rhours or days to allow temperatures in the water columnto sufficiently recover, and then the wellhead valve isopened rapidly to permit discharge of compressed air,

    followed by boiling geothermal fluid.

    Gas l ift (Air lifting) Tubing is inserted into the well to an appropriate depth,and then air lift is started by pumping air down thetubing. Even if the pumping is stopped, self-sustained

    6

    sc arge may occur ue o con nuous prov s on o owater from the feed zone.

    Steam or two-phaseinjection

    When the temperature in the well is relatively low atshallow depth, backfeed of steam or two-phase fluidfrom other production wells is useful to heat up the wellprior stating discharge by pressurizing the well.

    (Grant, Geothermal Reservoir Engineering, 2nd Edition)

  • 8/13/2019 09_Yahara_[2012]

    4/12

    4

    Two-phase Flow Measurement Methods

    Method Objective Outline Merits anddemerits

    James LipPressureMethod

    Roughly estimateflow rate in the Initialunstable condition

    Empirical formuladeveloped by James(1966)

    Versatile andeconomicalEasy to install

    For proper design ofthe separator for along-term test

    For highly productive two-phase geothermal wellsDifferences are within 5%to separator method, andwithin 8% to theoreticalstudy

    and remove

    Not quite asaccurate as theseparatormethod

    Steam-Water Accurate Individual steam and Most accurate

    7

    Method

    steam and water flowrate in stablecondition for long-term testFor proper design ofthe steam turbine

    system, using separatorThe overall accuracy willnot normally be betterthan 2% of the steam andwater components

    friendly

    (Grant, Geothermal Reservoir Engineering, 2nd Edition)

    Schematic Equipment Setting

    for the Lip Pressure Method Basic Equipment setting for the "Lip Pressure Method"

    silencer

    weir box

    pressure gauge to

    measure "Lip pressure"

    flow

    Pc

    8

    flow to injection well

    or disposal pool

    In the lip pressure method, the steam-water mixture is discharged through an appropriate sized pipe into a

    silencer to separate the steam and water phases at atmospheric pressure. The lip pressure is measured at

    the end of the discharge pipe. The flow rate of the steam-water mixture can be calculated based on theempirical formula developed by James.

  • 8/13/2019 09_Yahara_[2012]

    5/12

    5

    Schematic Equipment Setting

    for the Separator Method

    Orifice

    P

    Manometer1:DifferentialPress. between orifices

    Press.

    Gauge

    a ve

    9

    Separator

    Production well

    Manometer3 : Separator press.Manometer2: Press. prior to or ifice

    Flash Chamber Weir

    .

    In the separator method, the flow rate of separated steam can be measured using anorifice plate and sampling the differential pressure between the front and back of theplate.

    The Weir Design

    b

    B

    H

    L1 Ls L2

    D

    from silencer

    2mm

    45o

    20mm

    30mm

    rectifier (4 plates with holes)Coverage B = 0.5 ~ 6.3 m

    b = 0.15 ~ 5 m

    D = 0.15 ~ 3.5 m

    bD/B2>= 0.06

    to pond

    10

    H = 0.03 ~ 0.45b

    1m

    L1 > B+3H

    Ls = about 2H

    L2 > B+2H

    JIS B8302-1976

    The separated water can be flashed to atmospheric pressure and the waterflow rate can be measured using a weir.

  • 8/13/2019 09_Yahara_[2012]

    6/12

    6

    Production Characteristic (Deliverability) Curve

    p

    S t e a m

    W a te r

    MassFlow

    /Enthal

    T o t a l M a s s

    E n t h a l p y

    11

    W e ll H e a d P r e s s u r e

    If a longer-term production test can be done, measurements are madecontinuously at a minimum of three different pressures to make the productioncharacteristics curve (the deliverability curve), for which the valve is throttled toproduce at least three different wellhead pressures.

    Output (Deliverability) Curveform of the

    variation of enthalpy with wellhead pressure

    12(Grant, Geothermal Reservoir Engineering, 2nd Edition)

  • 8/13/2019 09_Yahara_[2012]

    7/12

    7

    Well Deliverability Curve of KMJ-73,

    kamojang

    100

    KNJ73Deliverability Curve

    KNJ73Deliverabilit Curve

    30

    40

    50

    60

    70

    80

    90

    ssFlowRate(ton/h)

    13

    0

    1020

    0 5 10 15 20 25

    M

    WellheadPressure(kg/cm2)

    M. Achyan Karim et al. (2005), WGC2005

    Discussion for Optimum Turbine Pressure

    14

    Optimum turbine inlet pressure should be designed based on the deliverability curveof the production well.

  • 8/13/2019 09_Yahara_[2012]

    8/12

    8

    Example of PTS Logging Data

    [ Casing ] [ Hole ]

    Casing Program

    0

    500

    0 1 2 3 4 5 6

    Pressure (MPa)

    0

    100

    0 50 100 150 200 250 300

    0

    0 50 100 150 200 250 300

    Temperature ()

    0

    100

    0 1 2 3 4 5 6

    0

    100

    0 25 50 75 100 125 150

    Spinner (rps)

    17 1/2

    59.1m

    14

    53.88m

    35mm

    1.375"

    Cable Head

    1,000

    1,500

    200

    300

    400

    500

    600

    700

    800

    900

    500

    1,000

    200

    300

    400

    500

    600

    700

    800

    900

    200

    300

    400

    500

    600

    700

    800

    900

    Depth(m)

    12 1/4

    510m

    9 5/8

    500.7m

    900900900

    4 1/

    14")

    4.

    3m

    54mm

    2.125"

    Pressure Sensor

    Pressure Port

    Centralizer

    Temperature SensorTemperature Sensor

    15

    2,000

    1,000

    1,100

    1,200

    ,

    1,000

    1,100

    1,200

    1,000

    1,100

    1,2002,000

    1,000

    1,100

    1,200

    1,300

    1,400

    1,500

    1,600

    ,

    2,000

    1,000

    1,100

    1,200

    1,300

    1,400

    1,500

    1,600

    1,000

    1,100

    1,200

    1,300

    1,400

    1,500

    1,600

    Feed Point

    8 1/21010m

    71005.7m

    6 1/4

    1526m

    982.5m

    4 1/2

    1525m

    Feed Point

    Feed Point

    54mm76mm)

    Spinner Sensor

    The PTS data is very usefulfor understanding theconditions in the flowingwell, such as the enteringmass flow and enthalpy ateach feed point.

    Wellbore Simulation Model

    with the Surrounding Formation

    establishes the deliverabilitycurve of a well based on thereservoir pressure,

    temperature, andpermeability-thicknessproducts (kh) at the feeddepth. The power output ofthe well can be estimated

    16

    assuming the turbine inletpressure.

  • 8/13/2019 09_Yahara_[2012]

    9/12

    9

    Example of the Matching Result to the

    Production Characteristic Curve

    Well Name Example-1

    2000

    3000

    y(kJ/kg)

    Simulated

    Field Data

    Reservoir Pressure 6.86 MPaA

    Reservoir Temperature 250.58

    Permeability-Thickness (kh) 100.00 darcy-m

    Feed Point Depth 1400.00

    Liner Diameter 0.2160

    Skin Factor 0.00

    617.00Production CasingDepth

    DiameterProduction Casing

    0.2240

    200

    250

    300

    350

    ate(t/h)

    Simulated

    Steam

    Water

    Total

    Field Data

    steam

    water

    0

    1000

    0.0 0.5 1.0 1.5 2.0

    Enthalp

    17

    0

    50

    100

    150

    0.0 0.5 1.0 1.5 2.0

    Well Head Pressure ((MPaG)

    Flow

    R

    Example of the Matching Result to the

    Pressure and Temperature Profiles

    0

    0 50 100 150 200 250 300

    Pressure (barA) / Temperature (degC)

    200

    400

    600

    800

    1000

    Depth(m)

    18

    1200

    1400

    1600

    Pressure (Field Data) Temperature (Field Data)

    Pressure (Simula ted) Temperature (Simulated)

  • 8/13/2019 09_Yahara_[2012]

    10/12

    10

    Interference Testing

    19

    The pressure response at an observation well during production yields important reservoir

    properties in terms of pressure interferences among the existing wells. This result can also

    be utilized for numerical reservoir modeling. The observed pressure response can be used

    as the matching target during the calibration process of numerical model construction.

    Monitoring of Pressure Change in Reservoir

    For steam-dominated reservoir,wellhead pressure indicatesalmost the reservoir pressure.

    Steam-dominated reservoir

    ,wellhead pressure is useful toobserve the reservoir pressure.

    For water-dominated reservoir,

    20

    Water-dominatedreservoir

    required to measure thepressure change over time inthe reservoir.

  • 8/13/2019 09_Yahara_[2012]

    11/12

    11

    Pressure Monitoring Equipment

    21

    A capillary tubing system is used as a pressure monitoring tool that consists of a pressurechamber, capillary tube, Helium gas vessel and transducer with data recording system. Thepressure chamber is set at the depth, and then filled with Helium gas. The change in Helium gaspressure in the pressure chamber with capillary tube, which indicates reservoir pressure, istransferred to a data recording system through the transducer.

    Pressure Change due to Interference,and Data Analysis

    22

    Tsuru and Tokita (1994),15th PNOC-EDC Geothermal Conference

    The pressure response at an observation well is also util ized for numerical reservoir modeling,

    as the matching target during the calibration process of numerical model construction.

  • 8/13/2019 09_Yahara_[2012]

    12/12

    12

    Two-phasepipelineflow simulator

    Changes in Reservoir during

    Production and Reinjection

    Wellbore Simulator

    23

    Reservoir simulator

    Dynamic change in the reservoir will occur after commissioning production and

    reinjection due to interference between wells. Therefore, in order to mitigate suchimpact of interference on the well productivity, interference testing should be done

    to optimize allocation of wells.

    The End

    24

    Thank you for your

    attention!