1 july 8, 2011 boxes were moved between ground floor and console room floor. –safety equipment and...

7
1 July 8, 2011 Boxes were moved between ground floor and console room floor. Safety equipment and supplies identified and unpacked. LN2 tank was unpacked and moved up. Tank flange weldment was moved up. Cube 4 and components were moved down to ground Tank coming up the shaft.

Post on 19-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

1

July 8, 2011

• Boxes were moved between ground floor and console room floor.– Safety equipment and supplies

identified and unpacked. – LN2 tank was unpacked and

moved up.– Tank flange weldment was

moved up.– Cube 4 and components were

moved down to ground– Some empty crates moved

down.

Tank coming upthe shaft.

2

• Unpacking in the C-floor.– Tool box was organized; hand cart assembled – Controls Rack and Valve Box were unpacked– Tank Flange Weldment was unpacked. The LN2 pump

(box 3a) was connected to the low-end. – The Cryomech (He compressor) was unpacked and

moved to Coude Room.– “HYBOND” cryocooler crate are unpacked.– DC02 “relief valve” opened.

– Work continued on the Console Room roof (see end of day photo)

July 8, 2011

3

July 8, 2011

• Then the tank weldment was temporarily installed into the tank so a height test can be performed.

• The two cryocoolers were installed into the tank.

4

July 8, 2011

• That Gale had had crates already staged on the C-floor saved us a lot of time today.

• It is important to note that the long liquid level sensor is very fragile and could easily be broken if picked up from the bottom. It is important to handle it from the top, which is the heavy end.

Liquid level sensorHeavy end on left.

5

July 8th

Controls rack

Valve Box

6

July 8th

Below: Beginning of Day

Right:End of Day

7

Plans

• As NEWFIRM is going on the telescope on Tuesday we are hoping to get a little more jump on the schedule now.

• FNAL people are coming down the mountain on Friday evening instead of Saturday after lunch because of bad weather.

• Monday morning we’ll come back up from the Racinto, after a local tour for Andy and Rolando.

• Monday Afternoon assembly of the tank and tank flange, and preparing for the lift to the Console Room roof.