1 question to the 50gev group 3gev からの 54π と 81π 、 6.1π の関係 fast extraction...
DESCRIPTION
3 Overview Preparation section Normal conducting Arc Section R=105m Super conducting Final Focusing Section Normal conducting Single turn fast extraction 8 bunches/~5 s 3.3x10 14 proton/pulse 3.94 (3.64) sec cycle (depend on abort scenario) =6 mm.mr, =7.5 mm.mr, Total bending = 84.5 oTRANSCRIPT
1
Question to the 50GeV group• 3GeVからの 54πと 81π、 6.1πの関係
• fast extraction部の acceptance (81π?)
• Comments on neutrino beamline optics?
2
Optics of Primary Proton Beam line
A. K. Ichikawa(KEK),
12th Nov. 2003, nuTAC@KEK
3ビーム振り下げ
FH1
FQ1
1.9 2 deg. bend
1.92 deg. bend
引き出し基準点x=49615028.58, y=69561283.94
ニュートリノ・ビームライン
PQ2A
FV2
FQ4
FV1
FQ3
FH2
FV2
FQ2
Overview
Preparation sectionNormal conducting
Arc Section R=105m
Super conducting
Final Focusing SectionNormal conducting
Single turn fast extraction
8 bunches/~5s
3.3x1014proton/pulse
3.94 (3.64) sec cycle
(depend on abort scenario)
=6 mm.mr, p/p=0.31% @50GeV
=7.5 mm.mr, p/p=0.36% @30GeV
Total bending = 84.5o
4ビーム振り下げ
FH1F
Q1
PD11.92 deg. bend
PC4PQ5 PH3
PC3 PQ3PQ4
PV2PC2
PC11.92 deg. bend
PD2PV1
引き出し基準点x=49615028.58, y=69561283.94
ニュートリノ・ビームライン
PQ2A PQ1
PH1PH2
サスペンション型
(20t x 2)クレーン
FV2
FQ4
FV1
FQ3
FH2
FV2
FQ2
Beam loss
No way to know absolute beam loss
Assumed by HAND Assure hands on maintenance
(1W/m) Shielding design based on the
assumption Same order as KEK-PS beam
line ~102 relative suppression!!
Challenging
Fast ext.(kicker, septum)1.125kW (0.15%)
Preparation section(ctrl’ed loss by collimator)
0.75kW (0.1%)
50GeV ring0.5W/m
Final Focusing section0.25kW (0.05%)
5
3.3m
1.1m1.4m 1.4m
Arc section optics (fitting result)
TxdxdB
B
mTLBK
dxdBK
yy
oy
5863.2)dipole(
/620.181
18085.01
Admittance : 205 mm.mr for horizontal,
294 mm.mr for vertical
6
Preparation section –Overview-
Make matching with the Arc.
Consists of normal conducting magnets.
Almost no freedom on the Length and angle
Total Length : 52.3m → Tight spacing
3.84 degrees bending
Scrape beam halo to protect super conducting magnet in the Arc
7
Preparation Section –optics-
beam
Arc sectionPrep. section
Well Matched w/ Arc
Monitor
horizontal
vertical
collimator
~1cm
8
Concept of our ‘collimator’
Scrape very peripheral halo only.
Preparation and Focusing sections accept 60 mm.mr beam.
Arc section accept >200 mm.mr beam.
, while extracted beam is expected to have 6~10 mm.mr emittance.
Put where we can put
Preparation section consists of many normal-conducting magnets.
The magnets themselves works as collimators for the arc section.
Iron block collimators will be added to empty places to support the halo scraping.
This is very much different from sophisticated scrapers for accelerators.
Not movable, probably no cooling
9
Preparation section
Acceptance : 60 mm.mr (c.f. Acc. design = 6 mm.mr)
10
CollimatorsRadiation shield at the exit of the preparation section
Radiation Dose at conventional magnet in preparation section
Simulation study for preparation section collimators
Preparation section
11
Focusing Section
Beam should fit to target (30mm)
whatever the emittance is.
Focus 6~24 beam
Accept 60 beam.
Vertical steering magnetChange off-axis angle w/ this.
12
Focus 6 mm.mr beam
Arc section
Monitor
horizontal
vertical
15mm
13
Focus 24 mm.mr beam
15mm
14
Momentum dispersion at target
ppmm
/600
2.4mm @ p/p=0.4%
Cannot be zero due to limitation of beam line length.
Zero is preferable but this is acceptable.
15
Supplement
16
ビーム方向
1400
1.48°
3300
10.06 10.06
1100
3300
9.99
9.99
1400
1.40°30
. 34
32.57
Arc section – fitting results-
TxdxdB
B
mTLBK
dxdBK
yy
oy
5863.2)dipole(
/620.181
18085.01
Admittance : 165 mm.mr for horizontal,
262 mm.mr for vertical
17
Boundary Condition for the design
about 80o bending
R~105 m
Beam size in the arc should be as small as possible to prevent quenching
Beam halo should be cut at Preparation section
Super conducting magnet
Collimator
Bx = Q*y/r
By = D + Q*x/r
Two candidates for the arc section design
(Separate Function) FODO x10 (20 D’s & 20 Q’s)
Combined function FODO x14 (28 magnets)
Q D Q D
18
Combined Function –Merit & Demerit?-
MeritReduce # of components
can increase # of (Q-)magnets. Smaller beam sizespace btw magnets monitor can be installedcost reduction
DemeritNo example in the worldTunnability is restricted
need corrector?
After discussion on 6th March 2003 with experts,
we adopt combined function scheme !
19
Treatment of Combined function w/ SAD
grad
grad
grad
)(
QBx
xxQ
xQBB
D
Dy
Quadrupole magnet displaced by x.
Fitting condition for the cell
(a) Periodic
(b) 90o phase advance
(c) Align orbit and magnet at this point
f or each of two magnets
(d) Bend by 5.76o
Fitting parameters,
x (by hand), Qgrad, angle of magnet
20
Simulation Study (w/ GEANT3 & Geant4)
Magnet geometry and field are set via data file.
applicable to different beamlines.
•Magnet w/ Iron poles are stationed.•Particles are tracked.•Particle interact w/ magnet accoring to hadron production model.•Secondary hadrons and electro magnetic showers can be traced.
In the simulation,
combined function section works as
expected from optics calculation!
21
Final Focus
Arc
Preparation section
Simulation Setup with Geant4
x
x’These input parameters were fixed, and relative variation of beam loss were estimated.
Input beam parameter for ‘halo’
TWISS : same as those from 50 GeV design
=0~200 mm.mr
(uniformly distribute in the phase space)
p/p =2%
22
Simulated beam loss at each components
Total beam loss in Preparation section is assumed 750W (0.1%) by hand.
ArcFFTotal beam loss 750W
3.7W
On this assumption, energy deposited in each components were normalized.
Preparation section
Total loss deposited in components 508W
23
Radiation dose at the magnets in Preparation Section