South Arm Installation Plan

Itaru Nakagawa

RIKEN/RBRC

Page 2: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

2

South Arm Installation

Page 3: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

3

North Station-1

Before

After

Page 4: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

4

New Electronics Board

4

Signal from MuTr (64 ch)

6.5 V

1.2 Gbps9.4 MHz

Regulators (3.3, 2.5, 1.2 V

) CoolingWater

Dry air

CoolingWater

Page 5: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

5

Chassis ( 車体、シャーシ) Install

•Mount on Existin’ FEE (フロントエンド回路): 6 screws   (10min.)•Chamber Cables (30min.)•Board Install + cables (10min)•Cooling Water & Air (15min.)

~ 1 hour/FEE 120 ~ 120 hours

Page 6: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

6

Statistics

Station 1 2 3 Total

Chassis(車体、シャー

シ)24 32 48 104

ADTX Boards (集積回路)

40 48 64 152

South Arm

Page 7: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

7

‘09 Shutdown Schedule• Starts End of June• Guaranteed 4.5 - 5 Month Shutdown Period• Close hall on Dec.1 (Likely), Mid.Nov. (Unlikely)• St-2&3 Scaffold Disassembly Starts 4th week October• Effectively we have <3 months for Install• North:Aug - Dec~5 months (Intense Cable Install -> Scaffo

ld Disassembly starts)

Page 8: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

8Travel Schedule

Page 9: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

9

Infrastructure Install Schedule

Spin fest

Page 10: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

10

Install Schedule (ADTX & Rack Room)

Page 11: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

11

North Man Power Summary Expert July Aug Sept Oct Nov Dec Total

Tsutomu 0.5 1 1 0.2 1 0.75 4.45

Kenichi 0.6 1 0.4 2

Katsuro 1 1 0.3 1 0.7 4

Yoshi 1 1 2

Itaru 0.75 1 0.5 0.75 1 0.75 4.75

Total 17unit:month

Summer Help Total Pre-Install

Rikkyo 4.75 2.0

Kyoto 3 0.0

Eric 3 1.5

Total 10.75 3.5

Page 12: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

12

Projection to South Required Man Power

• Expert{ 17Month 0.9 (South/North) 15/16 (Half Octant-5) - 3Month (Nois

e Hunt) + 0.5Month (Noise Hunt) + 0.5 Month (Miscabling Check) } 1(experience) = 12.5 Month is required

• Summer Students– Pre-Install3.50.9(South/North)0.9(experience) = 2.8 Month 2.8 - 1.5(3/5)(Work Done by Eric) ~ 2 Month (to be covered by Japanese students)

– Total{ 10.75 - 1.0 (DB development) } 0.9 (South/North) ~ 9 Month

Page 13: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

13

South Man Power EstimationExpert July Aug Sept Oct Nov Dec Total

Tsutomu 0.5? 0.5? 0.5? 1.5

Kenichi 0.3? 0.3

Katsuro 0.5 0.5? 0.5? 1.5

Yoshi 1 1 0.75 2.75

Itaru 0.5 1 1 0.75 3.25

Imazu

Total 9.3

unit:month

Summer Help Total Pre-Install

Tokyo 2

Rikkyo 2.5

Kyoto 2

RIKEN (Kanaya) 1

Local Students (Eric, Schadrac, RPC folks) 2.5 2

Total 10 2

Page 14: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

14

LV Cable Status

• 16/20 Bundles Completed• Frank Toldo will cut and assemble connectors this we

ek.• Schadrac will work on bundling in July 16 ~ 17

Schadrac Philogene

Ready for Install by 4th week of July

Page 15: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

15

Optical Fiber Status

• Test & Labeling Completed by Eric Jones• Bundling: ( 3 RPC Students + Schadrac ) 1 week• 20/20 Completed• Ready for Install any time

RPC students

Eric Jones

Page 16: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

16

Other Items Stock List

Labeling Done

Labeling & Bundling Done

Page 17: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

17

July 3rd Week

• LV Cable Bundling (Schadrac)• Test Bench for Chassis

– Test Bench Set up (Katsuro)– Back Plane Test (Ninomiya)– Water Leak Test (John T.)

• Mega Pack LV Power Supply Install (Frank)• St.2, St.3 Cable Tray Install (Paul)• South Cable Route Map (Ninomiya)

Page 18: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

18

July 4th Week

• Uninstall St.2, St.3 LV, Fiber Cables (Schadrac, Ninomiya, Itaru)

• St.2, St.3 LV, Fiber, Trunk Cable Install (Schadrac, Ninomiya, Itaru, Local Student)

• Test Bench for Chassis – Back Plane Test (Ninomiya)– Water Leak Test (John T.)

• Patch Bay Channel Map (Ninomiya)

Page 19: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

19

July 5th Week

• St.2, St.3 LV, Fiber, Trank Cable Install (Schadrac, Ninomiya, Itaru, Local Student?)

• St.2, St.3 LV assembly @ platform (Frank)• Trunk Cable Patch Bay Connection (Schadrac, Nimomiy

a)• Test Bench for Chassis

– Back Plane Test (Ninomiya)– Water Leak Test (John T.)

• South Magnet in South Position• Station-1 Scaffold Construction (Union)

Page 20: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

20

Aug 1st Week

• Station-1 Scaffold Construction (Union)• St.1 LV, Fiber Install (All)• St.1 LV assembly @ platform (Frank)• Optical Fiber Patch Bay Connection (Nimo

miya, Kanaya, Hirota, Ichikawa)• Station-2,3 Scaffold Construction

Page 21: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

21

Aug 2nd Week

• St.1 LV, Fiber Install (All)• St.1 LV assembly @ platform (Frank)• Optical Fiber Patch Bay Connection (Nimomiya, Kanaya, H

irota, Ichikawa)• Optical Fiber Chain Test (Ninomiya, Kanaya)• ADTX-FEE Cable Test Bench

– Setup (Yoshi)– Test (Hirota, Ichikawa)

• Station-2,3 Scaffold Construction• Station-1 Chassis Mount (Jimmy)

Page 22: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

22

Aug 3rd Week

• LV Tuning (Yoshi, Kanaya)• Optical Fiber Chain Test (Hirota, Ichikawa, Kanaya)• ADTX-FEE Cable Test Bench

– Setup (Yoshi)– Test (Hirota, Ichikawa)

• ADTX QA– Setup (Yoshi)– QA (Sean)

• St.1 Chassis Mount (Jimmy)• St.1 Plumming (John T.)

Page 23: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

23

Aug 4th Week

• MRG Setup (Yoshi)• St.1 ADTX-FEE Cable and ADTX install (Yoshi, I

taru)• ADTX test (Samejima, Hirota, Ichikawa)• ADTX QA

– QA (Sean)

• St.1 Chassis Mount (Jimmy)• St.1 Plumming (John T.)

Page 24: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

24

Remaining Issue North Arm

• Station-3, Octant-1 High Noise

• Station-3, Octant-5 Miscabling

Page 25: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

25

Required Trainings

• Web Course:– Guest Site Orientation (TQ-GSO)– Cyber Security (GE-CYBERSEC) – Phenix Awareness (RC-PAT)– Electrical Safety I (TQ-ELECSAF1)– Scaffold User Safety (GE-SCAFFOLD)

• Class Attendance Required:– Collider User Training 7/6(Mon),7/20(Mon),8/3(Mon),8/17(Mon),8/31(Mo

n),9/14(Mon)– Confined Space (HP-OSH-016)

7/7(Tus),7/29(Wed),8/6(Thur),8/28(Fri),9/3(Thurs)

http://www.bnl.gov/training/home.asp

Page 26: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

26

St-2,St-3 Scaffolds ( 足場)

2 person / floor

Scaffold & Confined space training required

Page 27: 1 South Arm Installation Plan Itaru Nakagawa RIKEN/RBRC

27

Safety

• Two Men’s Rule (常に2人で作業)

• No Aggressive Motion in IR (果敢な行動は不必要)

• Work on Scaffold (足場上での作業は日中のみ)– Mon- Fri– 8:30 - 16:30

OohYou are gonna be in trouble!

Yousef Makdisi