No. : 105/Ext/GW/IV/1 Subject : Sarulla Soil Invest PT Dwi Agung Sentosa Pratam Ruko Regia Boulevard GB / R Jl. Graha Bintaro - Bintaro Ja Tanggerang Dear Mr. Agung, Regarding to the soil invest here our comments and reco 1. Based on your informatio bor at each location. I especially hand bor. Max will be stopped if the m obtain information whet the bearing layer. CPT te 2. Since the limitation of technical drilling combin sampling (UDS). The dr reach the bearing layer boreholes. From technica site will be obtain. 3. To determined the type follows: a) Existing and final topo b) Layout plan of well pa c) The existing geotechn d) Laboratory test of fill m 4. To analysis and provide r a) Fill construction metho b) Quality control report Please do not hesitate to c investigation. Your sincerely, Freddy Gunawan GW & Associates Jl. Mulyasar Bandung 40 Telp./Faks 02 Email : geoteknik200 Website: www Wednesda 14 stigation ma RB2-52 aya tigation plan of Sarulla well pad that is pr ommendations: on, Dyfco proposed two points of CPT and In general, CPT and hand bor has pen ximum CPT penetration depth is about 20 manometer reading reached 250.0 kg/cm 2 . ther the end of the penetration of the stif est should be done to obtain the quality of f CPT and hand bor, it is highly recomm ned with standard penetration test (SPT) rilling should be conduct through the exi r. SPT should be conducted with 1.5 m al drilling the soil stratification and consiste and quantity of field testing, additional d ographic maps (cross section included) ad (include location of the drilling rig, mud p nical investigation data before fill constructio material (index properties, compaction, and recommendation, additional data are neede od of well pad area during fill construction contact us if you have any question rega ri II No. 12 0163 Indonesia 22-2009367 [email protected] w.gwgeo.com 1 ay, April 16 th , 2014 roposed by Dyfco, one point of hand netration limitation 0.0 m and the test We are unable to ff lens, boulder, or fill construction. mended to conduct ) and undisturbed isting surface and m interval at each ency of the project data are needed as pond, etc) on conducted d CBR test) ed as follows: arding Sarulla soil

Upload: pieter-harry

Post on 27-Dec-2015

7 views

Category:

Documents


0 download

DESCRIPTION

105 Ext IV 13 Sarulla Soil Investigatio

TRANSCRIPT

Page 1: 105 Ext IV 13 Sarulla Soil Investigatio

Jl. Mulyasari II No. 12Bandung 40163 IndonesiaTelp./Faks 022-2009367Email :[email protected]: www.gwgeo.com

1

Wednesday, April 16th, 2014

No. : 105/Ext/GW/IV/14Subject : Sarulla Soil Investigation

PT Dwi Agung Sentosa PratamaRuko Regia Boulevard GB / RB2-52Jl. Graha Bintaro - Bintaro JayaTanggerang

Dear Mr. Agung,

Regarding to the soil investigation plan of Sarulla well pad that is proposed by Dyfco,here our comments and recommendations:

1. Based on your information, Dyfco proposed two points of CPT and one point of handbor at each location. In general, CPT and hand bor has penetration limitationespecially hand bor. Maximum CPT penetration depth is about 20.0 m and the testwill be stopped if the manometer reading reached 250.0 kg/cm2. We are unable toobtain information whether the end of the penetration of the stiff lens, boulder, orthe bearing layer. CPT test should be done to obtain the quality of fill construction.

2. Since the limitation of CPT and hand bor, it is highly recommended to conducttechnical drilling combined with standard penetration test (SPT) and undisturbedsampling (UDS). The drilling should be conduct through the existing surface andreach the bearing layer. SPT should be conducted with 1.5 m interval at eachboreholes. From technical drilling the soil stratification and consistency of the projectsite will be obtain.

3. To determined the type and quantity of field testing, additional data are needed asfollows:a) Existing and final topographic maps (cross section included)b) Layout plan of well pad (include location of the drilling rig, mud pond, etc)c) The existing geotechnical investigation data before fill construction conductedd) Laboratory test of fill material (index properties, compaction, and CBR test)

4. To analysis and provide recommendation, additional data are needed as follows:a) Fill construction method of well pad areab) Quality control report during fill construction

Please do not hesitate to contact us if you have any question regarding Sarulla soilinvestigation.

Your sincerely,

Freddy GunawanGW & Associates

Jl. Mulyasari II No. 12Bandung 40163 IndonesiaTelp./Faks 022-2009367Email :[email protected]: www.gwgeo.com

1

Wednesday, April 16th, 2014

No. : 105/Ext/GW/IV/14Subject : Sarulla Soil Investigation

PT Dwi Agung Sentosa PratamaRuko Regia Boulevard GB / RB2-52Jl. Graha Bintaro - Bintaro JayaTanggerang

Dear Mr. Agung,

Regarding to the soil investigation plan of Sarulla well pad that is proposed by Dyfco,here our comments and recommendations:

1. Based on your information, Dyfco proposed two points of CPT and one point of handbor at each location. In general, CPT and hand bor has penetration limitationespecially hand bor. Maximum CPT penetration depth is about 20.0 m and the testwill be stopped if the manometer reading reached 250.0 kg/cm2. We are unable toobtain information whether the end of the penetration of the stiff lens, boulder, orthe bearing layer. CPT test should be done to obtain the quality of fill construction.

2. Since the limitation of CPT and hand bor, it is highly recommended to conducttechnical drilling combined with standard penetration test (SPT) and undisturbedsampling (UDS). The drilling should be conduct through the existing surface andreach the bearing layer. SPT should be conducted with 1.5 m interval at eachboreholes. From technical drilling the soil stratification and consistency of the projectsite will be obtain.

3. To determined the type and quantity of field testing, additional data are needed asfollows:a) Existing and final topographic maps (cross section included)b) Layout plan of well pad (include location of the drilling rig, mud pond, etc)c) The existing geotechnical investigation data before fill construction conductedd) Laboratory test of fill material (index properties, compaction, and CBR test)

4. To analysis and provide recommendation, additional data are needed as follows:a) Fill construction method of well pad areab) Quality control report during fill construction

Please do not hesitate to contact us if you have any question regarding Sarulla soilinvestigation.

Your sincerely,

Freddy GunawanGW & Associates

Jl. Mulyasari II No. 12Bandung 40163 IndonesiaTelp./Faks 022-2009367Email :[email protected]: www.gwgeo.com

1

Wednesday, April 16th, 2014

No. : 105/Ext/GW/IV/14Subject : Sarulla Soil Investigation

PT Dwi Agung Sentosa PratamaRuko Regia Boulevard GB / RB2-52Jl. Graha Bintaro - Bintaro JayaTanggerang

Dear Mr. Agung,

Regarding to the soil investigation plan of Sarulla well pad that is proposed by Dyfco,here our comments and recommendations:

1. Based on your information, Dyfco proposed two points of CPT and one point of handbor at each location. In general, CPT and hand bor has penetration limitationespecially hand bor. Maximum CPT penetration depth is about 20.0 m and the testwill be stopped if the manometer reading reached 250.0 kg/cm2. We are unable toobtain information whether the end of the penetration of the stiff lens, boulder, orthe bearing layer. CPT test should be done to obtain the quality of fill construction.

2. Since the limitation of CPT and hand bor, it is highly recommended to conducttechnical drilling combined with standard penetration test (SPT) and undisturbedsampling (UDS). The drilling should be conduct through the existing surface andreach the bearing layer. SPT should be conducted with 1.5 m interval at eachboreholes. From technical drilling the soil stratification and consistency of the projectsite will be obtain.

3. To determined the type and quantity of field testing, additional data are needed asfollows:a) Existing and final topographic maps (cross section included)b) Layout plan of well pad (include location of the drilling rig, mud pond, etc)c) The existing geotechnical investigation data before fill construction conductedd) Laboratory test of fill material (index properties, compaction, and CBR test)

4. To analysis and provide recommendation, additional data are needed as follows:a) Fill construction method of well pad areab) Quality control report during fill construction

Please do not hesitate to contact us if you have any question regarding Sarulla soilinvestigation.

Your sincerely,

Freddy GunawanGW & Associates