12) sistem produksi berbasis proyek
TRANSCRIPT
生産システム研究室 2003/12/10
1
Departemen Teknik Industri
SISTEM PRODUKSI BERBASIS PROYEK
Department of Industrial EngineeringInstitut Teknologi Bandung
Jalan Ganesha 10, Bandung 40132
TI3122 PERENCANAAN & PENGENDALIAN PRODUKSI
TI-3131 Perencanaan dan Pengendalian Produksi 2
Departemen Teknik Industri
Definition
Project can usually be defined as a series of related tasks directed toward a major output
The characteristics of a project:It has a specific goal and deadline It is unique or somewhat unfamiliar to the existing workIt contains complex interrelated tasks requiring specialized skillsIt is temporary but critical to the company
生産システム研究室 2003/12/10
2
TI-3131 Perencanaan dan Pengendalian Produksi 3
Departemen Teknik Industri
A hierarchical view of the project environment
• .
Program 1 Program x Program n... ...
Project x1 Project x2 Projectxm-1... Project xm
Task x21 Task x22 Task x23 ...
Activityx221
Activityx222
Activityx223 ... Activity
x22q
Task x2p
TI-3131 Perencanaan dan Pengendalian Produksi 4
Departemen Teknik Industri
A hierarchical view of the project environment
• Program: the term commonly used to denote very large and prolonged undertakings.
• Project: the term generally applied to time-phased efforts of much smaller scope and duration than programs. Programs are some time viewed as consisting of a set of project
• Task: an elemental content of a project. A project is normally composed of contiguous arrays of tasks that all contribute to the overall project goal
• Activity: the atom of a project. Activities are smaller than tasks
生産システム研究室 2003/12/10
3
TI-3131 Perencanaan dan Pengendalian Produksi 5
Departemen Teknik Industri
Project management (PM)
• Project management (PM) is the process of managing, allocating, and timing resources in order to achieve a given objective in an expedient manner
• The objective may be in terms of time, monetary, or technical results
• PM is the process of achieving objectives by utilizing the combined capabilities of available resources
• PM represents a systematic execution of tasks needed to achieve project objectives
TI-3131 Perencanaan dan Pengendalian Produksi 6
Departemen Teknik Industri
Projectmanagement
Planning
Organizing
Training
Risk management
Scheduling
Optimization
Contractmanagement
Resourcemanagement
Software toolsPerformance
control
Project design
Cost control
Multidimensionality of project management
生産システム研究室 2003/12/10
4
TI-3131 Perencanaan dan Pengendalian Produksi 7
Departemen Teknik Industri
Project management (PM)
• PM covers the following basic functions: Planning, Organizing, Scheduling and Control
• Project planning provides the basis for the initiation, implementation, and termination of a project. It sets guidelines for specific project objectives, project structure, tasks, milestones, personnel, cost, equipment, performance, and problem resolutions
• Project organization specifies how to integrate the functions of the personnel involved in a project. Directing (which involves guiding and supervising the project personnel) is an important aspect of project organization
TI-3131 Perencanaan dan Pengendalian Produksi 8
Departemen Teknik Industri
Project management (PM)
• Project scheduling is the time phased arrangement of project activities subject to precedence, time, and resource constraints in order to accomplish project objectives. It is often the core of project management efforts because it involves the assignment of time periods to specific tasks within the work schedule
生産システム研究室 2003/12/10
5
TI-3131 Perencanaan dan Pengendalian Produksi 9
Departemen Teknik Industri
Project Planning1. Setting goals
2. Defining the project3. Tying needs into timed
project activities4. Orginizing the team
Project scheduling1. Tying resources (people, money,
supplies) to specific activities2. Relating activities to each other
3. Updating and revising on regularbasis
Project controlling1. Monitoring resource, costs,
quality, budgets2. Revising and changing plans
3. Shifting resources to meet time,cost, and quality demands
Before project
Start of the project
During project
ToolsTime and cost estimates
Budget, Cash flowPersonnel
Material abilityEngineering diagram
ToolsGantt Chart, CPM,
PERTCash flow schedules
Tools PERT charts
Reports describing1. budget by department
2. delayed activities3. slack activities4.quality of work
completed
TI-3131 Perencanaan dan Pengendalian Produksi 10
Departemen Teknik Industri
The project of manufacturing
• In a large organization, the manufacturing system may be configured as a multi-project endeavor
• The following figure shows the typical components of a manufacturing enterprise organized as a project
• The project starts with a conceptualization of a product and needs some of distinct tasks for getting the product to the market
生産システム研究室 2003/12/10
6
TI-3131 Perencanaan dan Pengendalian Produksi 11
Departemen Teknik Industri
IdeaFeasibility
study
Marketsurvey
Cost
Technologyassessment
Processplanning
Financing
Systemsintegration
Qualityspecs
Training
Operationsplanning
Facilities
Production
Schedule
TI-3131 Perencanaan dan Pengendalian Produksi 12
Departemen Teknik Industri
Project Management Technique:
1. Critical path method (CPM)was developed in 1957 by J.E. Kelly of Remington Randand M.R. Walker of duPont
2. Program Evaluation and review technique (PERT)was developed in 1958 by the Navy with Booz, Allen and Hamilton
生産システム研究室 2003/12/10
7
TI-3131 Perencanaan dan Pengendalian Produksi 13
Departemen Teknik Industri
The framework of CPM and PERT
Basic steps:• Define the project and all its significant tasks or
activities• Develop the relationship among the activities. Decide
which activities must precede and which must follow others
• Draw the network connecting all of the activities• Assign time and cost estimates and required resources
to each activity• Compute the longest time path through the network.
This is called the critical path• Use the network to help plan, schedule, monitor and
control the project
TI-3131 Perencanaan dan Pengendalian Produksi 14
Departemen Teknik Industri
The questions answered by CPM or PERT
• When will the entire project be completed?• What are the critical activities in the project, that
is, the ones that will delay the entire project if they are late?
• Which are the noncritical activities, that is, the ones that can run late without delaying the whole project’s completion?
• What is the probability that the project will be completed by a specific date?
• At any particular date, is the project on schedule, behind schedule, or ahead of schedule?
生産システム研究室 2003/12/10
8
TI-3131 Perencanaan dan Pengendalian Produksi 15
Departemen Teknik Industri
The questions answered by CPM or PERT
• On any given date, is the money spent equal to, less than, or greater than the budgeted amount?
• Are there enough resources available to finish the project on time?
• If the project is to be finished in a shorter amount of time, what is the best way to accomplish this at the least cost?
TI-3131 Perencanaan dan Pengendalian Produksi 16
Departemen Teknik Industri
Conventions
• Activities: a task that occurs between 2 events• Event arrows and nodes
• Activity-on-Arrow (AOA)Arrows are used to represent activities, while nodes represent starting and ending points of activities
• Activity-on-Node (AON)Nodes represent activities, while arrows represent precedence relationships
生産システム研究室 2003/12/10
9
TI-3131 Perencanaan dan Pengendalian Produksi 17
Departemen Teknik Industri
Convention
.
Event
Name and Symbol Description
A point in time, usuallya completion date or astarting date
(node)
Activity
(arrow)
An activity or a certainamount of work required inthe project
Event 1 Event 2 Event 3Activity A Activity B
(network)
A sequence of activitieswith beginning andending events
TI-3131 Perencanaan dan Pengendalian Produksi 18
Departemen Teknik Industri
Example 1
Activity Immediate predecessorA -
B -C AD B
1
3
2
4
A
B
C
D
生産システム研究室 2003/12/10
10
TI-3131 Perencanaan dan Pengendalian Produksi 19
Departemen Teknik Industri
Example 2
Beginning event Ending event Activity1 2 1-21 3 1-32 4 2-43 4 3-43 5 3-54 6 4-65 6 5-6
TI-3131 Perencanaan dan Pengendalian Produksi 20
Departemen Teknik Industri
Example 2
.
1
3
2 4
5
6
生産システム研究室 2003/12/10
11
TI-3131 Perencanaan dan Pengendalian Produksi 21
Departemen Teknik Industri
Example 3
Activity Immediate Predecessor(s)A -B -C AD BE C, DF DG EH F
TI-3131 Perencanaan dan Pengendalian Produksi 22
Departemen Teknik Industri
Example 3
.
1
3
2
4
5
6
7
A
B
C
D
E
F
G
H
1
2
3
Dummy
4
5
6
7
A
B
C
D
E
F
G
C
Dummy activity
生産システム研究室 2003/12/10
12
TI-3131 Perencanaan dan Pengendalian Produksi 23
Departemen Teknik Industri
Critical Path Method (CPM)
CPM is to determine the following quantities for each activity
• ES: Earliest start time. All predecessor activities must be completed before an activity can be started. The ending time of the predecessor activities is the earliest time an activity can be started
• LS: Latest start time. All successor activities must be completed without delaying the entire project This is the latest time an activity can be started without delaying the entire project
• EF: Earliest finish. EF=ES+t• LF: Latest finish. LF=LS+t
TI-3131 Perencanaan dan Pengendalian Produksi 24
Departemen Teknik Industri
Critical Path Method (CPM)
• TS: Total slack time. TS is the amount of time an activity may be delayed from its ES without delaying the latest completion of the project. TS=LS-ES or TS=LF-EF
• FS: Free slack time. FS is the amount of time an activity may be delayed from its ES without delaying the starting time of any of its immediate successors
S(j): immediate successors of activity j
)()()()(
jEFiESMinjFSjSi
−⎭⎬⎫
⎩⎨⎧=
∈
生産システム研究室 2003/12/10
13
TI-3131 Perencanaan dan Pengendalian Produksi 25
Departemen Teknik Industri
Critical Path Method (CPM)
• The critical path is the group of activities in the project thathave a total slack time of zero. This path is critical because a delay in any activity along this path would delay the entire project
• The total project completion time is calculated by adding the time values of those activities on the critical path
TI-3131 Perencanaan dan Pengendalian Produksi 26
Departemen Teknik Industri
Example 4
Activity Duration1-2 21-3 72-3 42-4 33-4 2
1
3
2
4
2
7
3
2
4
生産システム研究室 2003/12/10
14
TI-3131 Perencanaan dan Pengendalian Produksi 27
Departemen Teknik Industri
Example 4
.
0
01
2
62
7
93
9
94
2
2
3
7
40
2
0
7
2
6
2
5
7
9
ES, EF
9
7
9
6
LS, LF
7
3
3
1
7
0
TI-3131 Perencanaan dan Pengendalian Produksi 28
Departemen Teknik Industri
Example 4
Activity Duration ES EF LS LF TS1-2 2 0 2 1 3 11-3 7 0 7 0 7 02-3 4 2 6 3 7 12-4 3 2 5 6 9 43-4 2 7 9 7 9 0
• Determine free slack times for the respective activities.
生産システム研究室 2003/12/10
15
TI-3131 Perencanaan dan Pengendalian Produksi 29
Departemen Teknik Industri
Program Evaluation and Review Technique (PERT)
One distinguishing PERT and CPM is the use of 3 activities time estimates for each activity in the PERT technique. Only one time factor is given for each activity in CPM. The time estimates are:
a=optimistic timeb=pessimistic timem=most likely timete=expected timev=variance of activity completion time
TI-3131 Perencanaan dan Pengendalian Produksi 30
Departemen Teknik Industri
Program Evaluation and Review Technique (PERT)
• The expected time of completion time for activity i
• The variance of completion time for activity i
• The variance of project completion time
64 bmate
++=
2
6⎟⎠⎞
⎜⎝⎛ −
=abvi
∑∈
=pathcriticali
ivV
生産システム研究室 2003/12/10
16
TI-3131 Perencanaan dan Pengendalian Produksi 31
Departemen Teknik Industri
Program Evaluation and Review Technique (PERT)
Activity a m b1-2 3 4 51-3 1 3 52-4 5 6 73-4 6 7 8
If the expected project completion time is 20 weeks and the project variance is 100 weeks, what is the probability that the project will be finished on or before Week 25?
t v
4 1/93 4/9
6 1/97 1/9
TI-3131 Perencanaan dan Pengendalian Produksi 32
Departemen Teknik Industri
Gantt chart
• When the results of a CPM/PERT analysis are fitted to a calendar time, the project plan becomes a schedule
• The Gantt chart showing planned (or actual) progress of activities is one of the most widely used tools for presenting the schedule
• The horizontal axis indicates the time scale• The horizontal bars/lines represent activities
生産システム研究室 2003/12/10
17
TI-3131 Perencanaan dan Pengendalian Produksi 33
Departemen Teknik Industri
Gantt chart
.
Activity
1-3
2-3
2-4
3-4
W1 W2 W3 W4 W5 W6 W7 W8 W9Duration
1-2 2 weeks
7 weeks
4 weeks
3 weeks
2 weeks
TI-3131 Perencanaan dan Pengendalian Produksi 34
Departemen Teknik Industri
Gantt chart
The basic Gantt chart does not show the precedence relationships among activities but it can be modified by linking appropriate lines
Activity
B
C
D
E
W1 W2 W3 W4 W5 W6 W7 W8 W9Duration
A 2 weeks
7 weeks
4 weeks
3 weeks
2 weeks
生産システム研究室 2003/12/10
18
TI-3131 Perencanaan dan Pengendalian Produksi 35
Departemen Teknik Industri
Crashing
• Additional resources can reduce activity time for certain activity within the project
• Although it can be expensive to shorten activity times, doing so might be worthwhile
• The questions are:What activities should be shortened?How much will this action cost?Will a reduction in the activity time in turn reduce the time needed to complete the entire project?
• The least expensive method of shortening the entire project should be determined
TI-3131 Perencanaan dan Pengendalian Produksi 36
Departemen Teknik Industri
Cost-time Curves
Time Cost
8 weeks $3007 weeks $4006 weeks $600
Y-Axis
X-Axis
$300
6 days
$500
$600
7 days 8 days
$400
Time (weeks)
Cost
生産システム研究室 2003/12/10
19
TI-3131 Perencanaan dan Pengendalian Produksi 37
Departemen Teknik Industri
Cost of reducing activity time
• The objective is to reduce the entire project completion time by a certain amount at the least cost
• If Mi = maximum reduction of time for activity iCi= additional cost associated with reducing activity
time for activity iKi= cost of reducing activity time by one time unit
for activity i i
ii M
CK =
i
ii M
CK =
TI-3131 Perencanaan dan Pengendalian Produksi 38
Departemen Teknik Industri
Determining the least cost
Activity Duration M C K Critical1-2 2 1 $3001-3 7 4 $20002-3 4 2 $20002-4 3 2 $40003-4 2 1 $2000
1
3
2
4
2
7
3
2
4
$300$500$1000$2000$2000
Yes
YesNoNo
NoMin
生産システム研究室 2003/12/10
20
TI-3131 Perencanaan dan Pengendalian Produksi 39
Departemen Teknik Industri
Determining the least cost
Activity 1-3 is to be shortened by 1 week in order to reduce the project completion time to 8 weeks
Note that any further reduction in activity time along the critical path would cause the critical path to include activities 1-2, 2-3 and 3-4.
TI-3131 Perencanaan dan Pengendalian Produksi 40
Departemen Teknik Industri
Further Readings
• Badiru, A.B., 1996, Project management in manufacturing and high technology operations, John Wiley and Sons, Inc., New York
• Heizer, J. and Render, B., 1996, Production and operations management, Prentice Hall International Editions, New Jersey