140808 p49 method statement for demolition rev.1
DESCRIPTION
Sequence of work for concrete structure demolitionTRANSCRIPT
-
METHOD STATEMENT FOR
RECOVERY PLAN OF P49
Rev.1 July 24, 2014
Rev. Draft by Submission Date Eng. Approval
0 MiyamotoSuzuki/Hasegawa 28June2014
1 MiyamotoSuzuki/Hasegawa 24July2014
KAJIMA WASKITA
KAWA JOINT OPERATION
Document No. MS_RPP49
Rev 1
-
KAWA Joint Operation
TABLE OF CONTENTS
A. Method Statement for Recovery Plan
1. Work Location ...................................................................... 1
2. Equipment List ...................................................................... 1
3. Work Schedule ...................................................................... 2
4. Shop Drawing ...................................................................... 2
5. Current Condition ...................................................................... 3
6. Activity Flow ....................................................................... 4
7. Activity Description ..................................................................... 5
8. Organization Chart ...................................................................... 16
9. Safety Plan ...................................................................... 16
10. Traffic Management..................................................................... 16
B. Attachment
1. Approved Shop Drawing
2. Traffic Route and Working Space
3. Working Stage for Pier Head and Column
4. Site Arrangement for 250 ton Crane Activity and Catalogue of 250 ton Crane
5. Position of Coring and Cutting
6. Location of Crush Yard and Transportation Route
7. Risk Assessment
8. Study of Structural Stability during Demolition of Pier Head
9. Detailed Wire Sawing Activity on Pier Head and Column
10. Procedure of Demolition of Column & Footing and Pile Head Treatment
-
KAWA Joint Operation
1
METHOD STATEMENT FOR RECOVERY PLAN FOR P49
1. WorkLocation
This method statement describes detail explanation of Recovery work for Pier-49.
Figure1. Work Location
2. EquipmentListTable of Equipments Usage
ITEM WORK DESCRIPTION MACHINE NO.OF UNITS
1 Mobilization Crawler Crane 250 Ton 2 nos
2 Working Stage Mobile Crane 50 Ton 1 nos
3 Coring and Cutting
Wire Saw(DSM-101A)
Expected Productivity 6m2/day
(*1)See image of Equipment 2 sets
Generator (100kVA) 1 set
Coring Machine 2 sets
4 Transportation
(to Crush Yard)
Trailer (40ton class)
Carrying Capacity 60ton 2 sets
5 Crushing Work (Site) Excavator (0.8m3 class)
with crusher attachment 2 sets
Giant Breaker 2 sets
Water jet 1 set
Excavator (0.8m3 class) 1 nos
Dump Truck (10 ton) 1 nos
6 Crushing Work (Crush Yard) Crawler Crane 250 Ton 1 nos
Excavator (0.8m3 class)
with crusher attachment 1 set
Water jet 1 set
-
KAWA Joint Operation
2
Sprinkler Truck 8kl 1 nos
7 Transportation
(for disposal) Dump Truck (10 ton) 2 nos
Excavator (0.8m3 class) 1 nos
8 Shoring for Earth Work Vibration Hammer 1 set
Note: The number of equipment can be changed following the site condition
(*1)ImageofWireSawEquipment
3. WorkScheduleWorking Schedule for Recovery of P49
Approval of Diversion & Demolition MethodImport of Material & Equipment for Demolition Work
Temporary Backf illing at P50(L) 14Diversion Work 7Installation of Support & Scffolding 10Pier Head Wire Sawing 2 37 332m2Dismantle of Support & Scaffolf ing 10Diversion Work 7Installation of Scaffo lding 2Pier Wire Sawing 2 9 76m2Dismantle of Scaffolf ing 2Pier BH+GB 1 3 27m3SP+Excavation 21Footing BH+GB 2 26 567m3Re-constructionOriginal Schedule :Amendment 2) 165
Sub-Total 313
Jul Aug2015
Ju l Aug Sep Oct Nov Dec Jan Feb MarDiscriptionDemolition
Method Gr.
P49
Apr May JunDuration
(Calender day) Q'ty2014
Normal Working Hour: 8:0017:00
(Overtime work will be considered depend on safety condition & progress)
4. ShopDrawingsApprovedshopdrawingofthestructureisattachedinAttachment1.
Expected Productivity of Wire Sawing
6m2/day/set
-
KAWA Joint Operation
3
5. CurrentConditionThecurrentconditionofP49andstressingstatusofthepierheadareshownasbelow;
Photo1.CurrentConditionofP49
Figure2.CurrentConditionofTendonatP49PierHead
-
KAWA Joint Operation
4
6. ActivityFlowTheactivityflowsisasfollow;
1. TrafficDiversion
6.CuttingPierHeadConcretebyWireSaw
2.PreparationofWorkingYard
3.InstallationofWorkingStageforPierHead
4.Mobilizationof2nosof250tonCranes
5.CoreBoringWorkonPierHead
7.TransportationofPierHeadConcretetoCrushYard
8.DismantlementofWorkingStageforPierHead
9.InstallationofWorkingStageforColumn
11.CuttingColumnConcretebyWireSaw
10.CoreBoringWorkonColumn
12.TransportationofColumnConcretetoCrushYard
13.DismantlementofWorkingStageforPierHead&Demobilizationof2nosof250tonCranes
14.DemolitionofColumnConcretebyGiantBreaker
15.EarthWorkforexposureofFooting
16.DemolitionofFootingConcretebyGiantBreaker
17.BreakingConcreteinCrushYard
17.BreakingConcreteinCrushYard
ReConstruction
-
KAWA Joint Operation
5
7. ActivityDescription7.1TrafficDiversion
Inordertoconstructthediversionroad,preparationworkshallberequiredasfollows. 1.Backfilling&rigidpavementaroundP50L.2.AdditionalwideningaroundP49.3.Protectionofundergroundutilities.4.Preventionmeasuresagainsttheresidents&shops,ifany.
AnoutlineoftherouteisshowninFigure3.Detailedplansuchashorizontalalignment,typicalcrosssections,protectionofundergroundutilitiesareshowninAttachment2.
Figure3.TrafficDiversionPlan
7.2PreparationofWorkingYard
After the trafficdiversion,workingareawillbepreparedby relocationofmaterialsandcompactionoftheyardforheavyliftingworkandtransportation.Ordinaryfenceswillbeinstalledaroundtheworkingarea.
-
KAWA Joint Operation
6
7.3InstallationofWorkingStageforPierHead Aworkingstageforthepierheadwillbe installedafterpreparationofworkingyard.Anoutlineoftheworkingstage isshown inFigure.4andshopdrawing isattached inAttachment3.
Figure4.WorkingStageforPierHead
7.4Mobilizationof2numberof250tonCranes
2numbersof250toncranewillbemobilizedduring/afterinstallationoftheworkingstage.AcatalogueincludingworkcapacityofthecraneisattachedinAttachment4.
7.5CoreBoringWorkonPierHeadThereare2typesofcoringdiameterthatwillbeusedfor installingofwiresawandattaching lifting tools.Verticalboredholes,diameter75mm,willbeutilized forwiresawcutting.Ontheotherhand,horizontalboredholes,diameter50mm,willbeusedfor liftingof concreteblocks thatmustbehoistedbefore cuttinguntilunloading onground.AquantitytableoftheworkisshowninFigure6.2groupsofcoringmemberswillworkonthepierhead.Awatertankwillbepreparedbeforecommencementofthecoringforsupplyingwaterduringcoringofconcrete. Detailcoringpositionsareshown inAttachment5andFigure7.PhotoandsketchoftheactivityareshowninFigure8.
-
KAWA Joint Operation
7
Figure6.QuantityTableforCoringWork
Figure7.PositionsofCuttingandCoring
Figure8.PhotoandSketchforCoringWork
-
KAWA Joint Operation
8
7.6CuttingPierHeadConcretebyWireSawAftercoringconcrete,liftingtoolsandawiresawwillbeinstalled inhorizontalholesand vertical holes, respectively. Before commencement of cutting, a concrete blockwhichwillberemovedmustbehoistedasmuchasaselfloadoftheconcreteblockby250toncrane.Safetyfacilities,suchasaspecialprotectionboardandsheetforawiresaw mentioned in Figure10 must be installed properly before start of the work. Inaddition,protectionboardsforPCtendon,whichisshownonFigure4andAttachment3,willbeinstalledproperlybehindanchoragesoftendonattheedgeofthepierheadin order to protect a sudden spring out of strands and wedges during cutting ofconcreteofthepierhead.Thesequenceofcutting,thatstructuralstabilityhasbeenconsideredinAttachment8,the site arrangementwith working capacity of 250 ton crane and sketches of wiresawing method are shown in Figure7, 9 and 10, respectively. See more detailedsketchesofwiresawingmethodinAttachment9.
Figure9.Sitearrangementwithworkingcapacityof250toncrane
-
KAWA Joint Operation
9
Figure10.Sketchesofwiresawingmethod
Section View of Cutting Lifting Gears
-
KAWA Joint Operation
10
7.7TransportationofPierHeadConcretetoCrushYard The transportation route and loading shape of a block concrete on a trailer areshown inFigure11andAttachment6.Ablockconcretewillbetransportedbytrailersfromsitetothecrashyard(MarundaPCUStockYard).Itisconfirmedonadrawingthatthereareenoughspacesfortrailerstoturnatallcornersontheroute.Flagmenwouldbeassignedatgatesofyardsandcornersinordertoavoidtrafficcongestionsonpublicroadduetothistransportation.
Figure11.Transportationrouteandloadingshapeofablockconcrete
7.8DismantlementofWorkingStageforPierHead
Theworkingstageforpierheadwillbedismantledwith250toncranes.Materialsoftheworkingstagewillbetransportedtostorageyardimmediatelyafterdismantlementinordertokeepworkspacesfornextstepsofdemolitionwork.
-
KAWA Joint Operation
11
7.9InstallationofWorkingStageforColumn
Theworking stage for the columnwill be installed just after removal of aworkingstageforpierhead.Thisworkingstagewillbeoccupiedbycoreboringworkandblockconcretecuttingforthecolumn.
Figure12.WorkingStageforColumn
7.10CoreBoringWorkonColumn
A groupof coringmemberswillworkon theColumn.Water tankwillbepreparedbeforecommencementofthecoringforsupplyingwaterduringcoringofconcrete. DetailcoringpositionsareshowninAttachment5andFigure7.
-
KAWA Joint Operation
12
7.11CuttingColumnConcretebyWireSawSafetyfacilities,suchasaprotectionboardandsheetmentioned inFigure13willbeinstalledproperly.Thesequenceofcutting,thesitearrangementwithworkingcapacityof250toncraneandsketchesofwiresawingmethodareshowninFigure7,9and10,respectively.
Figure13.Safetyfacilitiesonwiresawingatcolumn
7.12TransportationofColumnConcretetoCrushYardThetransportationrouteandloadingshapeofablockconcreteonatrailerareshowninFigure11.Ablockconcretewillbetransportedbytrailersfromsitetothecrashyard.It isconfirmedonadrawingthatthereareenoughspacesfortrailerstoturnatsomecornersontheroute.
7.13DismantlementofWorkingStageforColumn&Demobilizationof2nosof250tonCrane
The working stage for Column will be dismantled by manpower. Materials of theworkingstagewillbetransportedtostorageyard immediatelyafterdismantlement inordertokeepworkspacesfornextstepsofdemolitionwork.Simultaneously,250toncraneswillbedemobilizedorrelocated.
SectionViewofCutting LiftingGears
-
KAWA Joint Operation
13
7.14DemolitionofColumnConcretebyGiantBreakerThe columnwill be demolished by cutting and liftingmethod until about 2m highfromcurrentgroundelevation.Thecolumnheightlessthan2mwillbedestroyedbyagiantbreaker.Concretedebrisandrebarwillbeseparatedandsentouttofinaldisposalyardandscrapyard,whichwillbedecidedandinformedbeforecommencementofthetransportation, directly using dump trucks. See more detailed sketches of columndemolitioninAttachment10.
Figure14.DemolitionofColumnConcretebyGiantBreaker
7.15EarthWorkforExposureofFooting
Sheet piles and its support members will be installed around a footing. Afterinstallationofearthshoring,excavationforexposureofthefootingwillbecommenced.
Figure15.EarthWorkforExposureofFooting
-
KAWA Joint Operation
14
7.16DemolitionofFootingwithPileHeadbyGiantBreaker After exposure of the footing, itwill be demolished by a giant breaker. Concretedebrisandrebarwillbeseparatedandsentouttofinaldisposalyardandscrapyard,which will be decided and informed before commencement of the transportation,directlyusingdumptrucks.Pileswillbecutabout100mmbelowtopoftheelevationofleanconcrete.SeemoredetailedsketchesoffootingdemolitioninAttachment10.
Figure16.DemolitionofFootingbyGiantBreaker
-
KAWA Joint Operation
15
7.17BreakingConcreteinCrushYard Transportedconcreteblockwillbeunloadedby250toncraneinthecrushyard.Theconcreteblockwillbedemolishedbyagiantbreakerwhichcanbe installedaspecialattachment fordemolition.Duringdemolition,waterwillbe sprinkled followingHSEregulation in order to avoid dust from demolishing concrete. Rebar in the concreteblockwillbe separated and scrapped.Concretedebriswillbe sent todisposal area,whichwillbedecidedand informedbeforecommencementofthetransportationbutshouldbeneartothecrushyard.
Braker
Excavator
Dump truck
Rebar
Waterjet
Attachement
Trailer
Figure17.BreakingConcreteinCrushYard
7.18ReConstructionWork
Afterdemolitionoffooting,furtheranalysiswouldbenecessaryforevaluationofthepiles. The detail of treatment of piles and the modification of footing may beconsideredwithresultsoffurthertestsandanalysis.However,thecolumnandthepierheadwill be reconstructed at the same location following original design.Detailedconstruction methods have been approved which will be applied during itsreconstruction.
-
KAWA Joint Operation
16
8. OrganizationChart(DemolitionWork)
FUJIMORI081398554217 081931072529
CHIEFENGINEERINGANDESITKRISNA M.FAJARDANIEL
QCMANAGER
081281968313
081331523500
HSEMANAGER
GENERALSUPERINTENDENTFUKUDA
BAMBANGBUDIMULYONO MIYAMOTO
DEPUTYGENERALSUPERINTENDENTSUTOPO
CHIEFHSEMANAGER CHIEFCONSTRUCTIONMANAGER ENG./COMMERCIAL/CONTRACTMANAGEROKADA
MANAGERSAITO
081294991440 081282212840 08119447342
CONSTRUCTIONMANAGERSUZUKITobeassigned
ConcreteCutting&Coring
CONSTRUCTIONMANAGER
JOSVDemolitionbyGiantBreaker
HASEGAWA
JOSV(JAPANESE)
082113094761
08111849422
Figure18.OrganizationChart9. SafetyPlan
Safety activities must be conducted in accordance with Risk Assessment. The Risk
Assessments for below mentioned activities are shown in Attachment 7.
a. Common Work b. Wire Sawing Work
10. TrafficManagementBased on proposed traffic management plan, Contractor will keep roads in good condition at
all times, and will carry out repair and reinstatement work. We will co-operate with the
pertinent agencies regarding traffic control and all details will be subject to maintaining
traffic safety and the avoidance of traffic delay.
In order to facilitate traffic through the work area, it will be installed and maintained at
prescribed points on the work area and at the approaches to the work: rubber cone, warning
and guide signs, temporary barriers and fences and other facilities as required. During
construction period, the traffic management will be implemented according to the stages of
work progress following construction stages. If the location is adjacent to existing traffic or
pedestrian path, Safety fence with MCB will be provided. Traffic management will be
discussed with related parties in the timely manner.