Long Term Planning
Maulik . 397 posts since 16 Nov, 2006
Long Term Planning 14 Aug, 2010 10:03 PM
Hello,
What is long term planning?
Please dont sent SAP help.
I want to learn with an example when we need the long term planning and what is advantage with it?
Regards,
Maulik
Edited by: Maulik on Aug 15, 2010 1:33 AM
K.Madhu Kumar 4,168 posts since 31 Aug, 2008
Re: Long Term Planning 15 Aug, 2010 4:23 AM
Dear Maulik,
Check this link
[LTP for Repetatative and Discrete manufacturing;
Regards
Madhu
Jiaul Haque 2,598 posts since 29 Oct, 2007
Re: Long Term Planning 15 Aug, 2010 3:05 PM
Dear ,
1. The only configurtion that we need to make for the LOng term palnning is in the Tcode OPu5
OPu5---Define scheduling parameters for planned orders
![Page 2: 1760383 (1)](https://reader031.vdocuments.pub/reader031/viewer/2022020301/577cc4bb1a28aba7119a4056/html5/thumbnails/2.jpg)
7/27/2019 1760383 (1)
http://slidepdf.com/reader/full/1760383-1 2/4
Long Term Planning
Generated by Jive on 2014-08-18+02:00
2
planning scenarios for long-term planning you can define scheduling parameters for operative planning. Here
you must specify on what level scheduling is to be carried out (detailed-, production- rate or rough-cut). The
date adjustment takes place based on this scheduling level. If you do not maintain any parameters for long-
term planning then scheduling is carried out in long-term planning with the same parameters as in operative
planning.
2. Once you have the setting then create a planning scenario in ms31 and inside theplanning scenarion you
need to maintain the required settings.
You can find the data for this process under .
Analyzing the Product Group Hierarchy
Creating or Changing Sales and Operations Planning (SOP)
Creating Inactive Sales and Operations Planning (SOP)
Transferring Planning Data to Demand Management
Carrying out MRP for the Active Requirements VersionCreating Inactive Planning Scenarios
Requirements Run for Long-Term Planning
Comparing Results from Long-Term Planning
Displaying the Capacity Situation of the Scenario
Transferring Requirements of the Scenario into the Purchasing Information System
Activating the Inactive Requirements Version
Analyzing the Current Requirements Version
long term planning
Regards
JH
jaya vimal 239 posts since 30 Dec, 2008
Re: Long Term Planning 16 Aug, 2010 8:25 AM
Hi Maulik ,
Check this it would help,
You need to Copy Long term Planning results to Operative planning. Then only you can convert.
Long term planning is for simulation purpose. The Result of LTP is Simulative Proposals which CAN NOT BE
CONVERTED INTO PURCHASE ORDER
Because LTP means Simulative Mode Not Operative Mode.
![Page 3: 1760383 (1)](https://reader031.vdocuments.pub/reader031/viewer/2022020301/577cc4bb1a28aba7119a4056/html5/thumbnails/3.jpg)
7/27/2019 1760383 (1)
http://slidepdf.com/reader/full/1760383-1 3/4
Long Term Planning
Generated by Jive on 2014-08-18+02:00
3
To Copy LTP planned order to operative planning, you have to set Firm indicator for all planned orders you
want to copy to operative planning .
To copy you have to Run MD43 & also you can set Creation indicator =1 to create direct PR in operative
planning
In the planning Result Screen -Go from menu Edit -> Copy firmed planned order from LTP-> Enter number of
the planning scenario & copying period.-> choose copy planned order & save.
Now go to Md04 check results.
Basically LTP is simulative MRP to simulate and see all the results like production capacity plan/ raw material
plan/ profit margin. Here we are using the same master data like material master, recipe, BOM etc.
In MS31 - you create a LTP version where you can mention the PIR version where you enter the planning data
in MD61.
Release this version and maintain the planning data like qty per period in MD61 with the version mentioned in
MS31, make sure that the version is not active so that LTP consider this inactive quantity data.
Run MS01/MS02/MS03 etc to run simulative MRP.
Results can be seen in MS04/MS05.
We can see the raw material requirement in Purchase info system in MCEC/MCEA/MCEB/MCB&/MCB)
Capacity situation in CM38.
You can transfer the activity data to cost center through KSPP, which will give the activity cost simulation.
Configuration setting in LTP:
The only configuration that we need to make for the Long term planning is in the
Tcode OPu5
1 . OPu5---Define scheduling parameters for planned orders
planning scenarios for long-term planning you can define scheduling parameters for operative planning. Here
you must specify on what level scheduling is to be carried out (detailed , production-rate planning or rough-
cut). The date adjustment takes place based on this scheduling level. If you do not maintain any parameters
for long-term planning then scheduling is carried out in long-term planning with the same parameters as in
operative planning.
2. Once you have the setting then create a planning scenario in ms31 and inside the planning scenario you
need to maintain the required settings
![Page 4: 1760383 (1)](https://reader031.vdocuments.pub/reader031/viewer/2022020301/577cc4bb1a28aba7119a4056/html5/thumbnails/4.jpg)
7/27/2019 1760383 (1)
http://slidepdf.com/reader/full/1760383-1 4/4
Long Term Planning
Generated by Jive on 2014-08-18+02:00
4
In long-term planning, you can create your own versions of the demand program, which are only used for
simulative planning. This means you can calculate and compare the effects of various versions of the demand
program in simulative mode .
After carrying out the simulative MRP run ( MS02) in LTP , you have to transfer the results of the desired
version to real MRP and run MD02
Jaya Vimal