Paving trails around a renowned Michigan sculpture garden proved no easy task for Superior Asphalt Y ou normally wouldn’t connect a serene sculpture garden with intense asphalt paving, but when Frederik Meijer Gar- dens & Sculpture Park in Grand Rap- ids, MI sought to upgrade their 158- acre campus, they called in Superior Asphalt, Grand Rapids, to do the work. As one of the nation’s most significant sculpture and botanic experiences, Meijer Gardens includes Michigan’s largest tropical conservatory, five indoor theme gardens, outdoor gardens, nature trails and a boardwalk. Last year when the Gardens began constructing an addition to their museum, a world-class Japanese garden, they called Superior Asphalt to resurface all of their existing parking lots. They reached out to Superior again this year to expand their parking lots and resurface all of the pathways throughout the sculpture gardens and around the Japanese garden. The paths, most with 12 years on them, needed to be structurally and aesthetically upgraded. Meijer also needed the garden to look top notch for the opening of the Japanese garden as they entered a whole new level of presentation. “Due to our history with Superior, we hired them again to top coat one more lot and resurface all of our Tram paths throughout the park in anticipa- tion of the opening of our new Richard and Helen DeVos Japanese Garden,” says Ken Wenger, vice president of fixed operations and facilities at Meijer Gar- dens. “Due to rental and event obliga- tions, we only had four days open to complete the work. May 18-19 for Lot D and May 26-27 for all of the tram paths, so the schedule was tight.” The parking lot project addressed 160 parking spaces; the two mile long tram path was an average of 18 ft. wide. “Our challenge was that we are open 362 days a year and we try to not interrupt our guest’s visits at all,” Wenger says. “The parking lot was easy in that we have other lots to use, but the tram path affects our trams and walking guests. We were able to minimize the interruption in the park to six hours as Superior recognized our mission and did their very best to expedite the work.” Communication is Key As you can imagine, maneuvering paving equipment around delicate flowers and sculptures would resemble several bulls running around in a small china shop. Superior relied on communication with the staff at Meijer Gardens to ensure that When Paving is a Delicate Matter As one of the nation’s most significant sculpture and botanic experiences, Meijer Gardens includes Michigan’s largest tropical conservatory; five indoor theme gardens; outdoor gardens, nature trails and a boardwalk. Getting equipment through there was no easy task. 12 August/September 2015 PAVEMENT www.ForConstructionPros.com/Pavement Paving By Jessica Stoikes, Associate Editor

Upload: stacie-newmann

Post on 19-Feb-2017

37 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: 2015 Pavement MaintenancePVM0815_12-14_SupAsphalt

Paving trails around a renowned Michigan sculpture garden proved no easy task for Superior Asphalt

Y ou normally wouldn’t connect a serene sculpture garden with intense asphalt paving, but when Frederik Meijer Gar-

dens & Sculpture Park in Grand Rap-ids, MI sought to upgrade their 158-acre campus, they called in Superior Asphalt, Grand Rapids, to do the work.

As one of the nation’s most significant sculpture and botanic experiences, Meijer Gardens includes Michigan’s largest tropical conservatory, five indoor theme gardens, outdoor gardens, nature trails and a boardwalk.

Last year when the Gardens began constructing an addition to their museum, a world-class Japanese garden, they called Superior Asphalt to resurface all of their existing parking lots.

They reached out to Superior again this year to expand their parking lots and resurface all of the pathways throughout the sculpture gardens and around the Japanese garden. The paths, most with 12 years on them, needed to be structurally and aesthetically upgraded. Meijer also needed the garden to look top notch for the opening of the Japanese garden as they entered a whole new level of presentation.

“Due to our history with Superior, we hired them again to top coat one more lot and resurface all of our Tram paths throughout the park in anticipa-tion of the opening of our new Richard and Helen DeVos Japanese Garden,” says Ken Wenger, vice president of fixed operations and facilities at Meijer Gar-dens. “Due to rental and event obliga-tions, we only had four days open to complete the work. May 18-19 for Lot D and May 26-27 for all of the tram paths, so the schedule was tight.”

The parking lot project addressed 160 parking spaces; the two mile long

tram path was an average of 18 ft. wide.“Our challenge was that we are

open 362 days a year and we try to not interrupt our guest’s visits at all,” Wenger says. “The parking lot was easy in that we have other lots to use, but the tram path affects our trams and walking guests. We were able to minimize the interruption in the park to six hours as Superior recognized our mission and did their very best to expedite the work.”

Communication is KeyAs you can imagine, maneuvering paving equipment around delicate flowers and sculptures would resemble several bulls running around in a small china shop. Superior relied on communication with the staff at Meijer Gardens to ensure that

When Paving is a Delicate Matter

■ As one of the nation’s most significant sculpture and botanic experiences, Meijer Gardens includes Michigan’s largest tropical conservatory; five indoor theme gardens; outdoor gardens, nature trails and a boardwalk. Getting equipment through there was no easy task.

12 August/September 2015 • PAVEMENT • www.ForConstructionPros.com/Pavement

PavingBy Jessica Stoikes, Associate Editor

Page 2: 2015 Pavement MaintenancePVM0815_12-14_SupAsphalt

the work they were doing achieved the needs of the museum.

Rick Browley Sr., superintendent of operations, estimators Dave Van Putton and John Alonso, and Wenger worked together to set up a plan of attack and mapped out the areas to be paved. Every detail was worked out prior to paving day.

“Most of the landscaping was done prior to our arrival,” says Rick Browley Jr., paving crew chief with Superior. “Our estimators walked the path with Ken Wenger and pointed out any low branches that might be a problem for the trucks and paver to maneuver. All trimming had to be conducted by the Meijer Garden staff. The paving crew had someone walk ahead to make sure the trucks could maneuver safely and without interruption.”

Trucks loaded with asphalt had to slowly back their way down the path one at a time to the paver. The truck would have to exit the path completely before another could back its way up to the paver.

The paving crew utilized one Blaw-Knox Ingersoll Rand 5510 Paver on the job.

“The equipment used addressed the entire width of the path in one pass,” Wenger says. “No seams appeared and the final product looks great.”

Superior also used Caterpillar tandem vibratory rollers to complete compaction. The 3- and 5-ton rollers were chosen for the lighter operating weight.

“We did not want too heavy of a roller because the base underneath the pathway was unpredictable,” Browley Jr. says. “Too much compaction on this job was not ideal.”

Aesthetic Mix SelectionA standard 13a and 36a modified mix was used for the parking lot area. The mix that was selected for the pathway however, had to be a bit different.

“The pathway mix was not only selected for aesthetics, but to enhance the overall walking experience of the patrons,” Nate Voriganti, lab supervisor and quality control manager at Superior says.

Superior chose to use their 5E1 mix on this job. “This is one of our finer looking mixes,” Voriganti says. The mix

used has 15% recycled asphalt pavement (RAP). The mix is considered a fine, sandy mix with 3% air voids.

“5E1 creates a smooth surface and remains the rich looking black color for a longer period of time.”

Superior Asphalt was able to design and create the best mix possible at their Caledonia, MI plant, which opened

■ Estimators walked the path and pointed out any low branches that might be a problem for the trucks and paver to maneuver. All trimming had to be conducted by the Meijer Garden staff. The paving crew had someone walk ahead to make sure the trucks could maneuver safely and without interruption.

■ “The equipment used addressed the entire width of the path in one pass,” Ken Wenger of Meijer Gardens says. “No seams appeared and the final product looks great.”

www.ForConstructionPros.com/Pavement • PAVEMENT • August/September 2015 13

Page 3: 2015 Pavement MaintenancePVM0815_12-14_SupAsphalt

in 2010. This plant represents the first new asphalt manufacturing facility to be constructed in Michigan, on a newly permitted site, in 24 years.

“The addition of our hot mix asphalt (HMA) manufacturing facilities has allowed us to be in complete control over the quality of asphalt materials we supply to our paving crews and ulti-mately our customers,” Jeff Kresnak, owner of Superior says. “Our ability to pave driveway to highway, pathway to roadway, pothole to parking lot, makes us a unique paving company.”

Through constant communication, and respect for the job at hand, the completion of this project went smoothly and without delay.

“Our communication was timely and efficient addressing weather and sched-ule,” Wenger says. “They listened to our needs and made it happen. We continue to be impressed with the work ethic and sense of urgency displayed by Superior. Part of it is the nature of the industry

but I know of only a handful of compa-nies that can accomplish one full years’ worth of work in only half a year.

“We have received numerous com-pliments about how nice the property looks. Patrons are appreciating a much smoother surface to walk on while enjoying the beautiful gardens.” ■

■ The park is open 362 days a year and Meijer did not want to interrupt guest’s visits. Through communication, Superior was able to minimize interruption in the park to just six hours.