DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
1
I. ADMINISTRATIVE
A. BACKGROUND
1. Introduction
Gone were the days when it was wise to take things at slow pace to
make obstinate marks for growth and development. We are in a world of continuous change where we are prompted to look beyond the future, now. “We owe it “or “we blame it” to the fast transformation of information technology (IT) that now dictates an e-global (electronic global) way of life.
Precisely, this IT has to improve the quality of public service that the Philippine National Police (PNP) mulls about. Within the mandate of the law and concurrent to the government’s national transformation program, the PNP has identified the need to an organized information gathering and storage system that can help decision-makers in the PNP assess the different strategies, with geographic, socioeconomic and socio-demographic factors coming less into play.
This need for modern technological advancement has prompted the PNP to opt for on IT reengineering strategy which would necessitate for the integration of the two existing major technologies available in the PNP which are being managed separately by the Information Technology Management System (ITMS) and the Communications and Electronics Service (CES). The system would provide the PNP an unhampered real-time connectivity to all its police stations nationwide through Internet Service Providers (ISPs) and utilities which means less paper works, fast and real-time accessibility, more accurate data and information sharing and on-line transmission.
Meanwhile, the fusion of the existing Information Technology Management and Communications and Electronics Service into an integrated Information and Communications Technology Management shall pave the way for the reengineering of a PNP IT infrastructure, necessitating the birth of a new directorate which would carry the mandate, embody the aspiration and manage the assimilation of technologies in its directional capacity and as the one policy-making body pertaining to all ICTs of the PNP. It is along this pursuit that the Directorate for Information and Communications Technology Management (DICTM) was activated on April 1, 2009 through GO DPL-09-08.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
2
2. Conceptualization of DICTM
Through Executive Order Nr. 269 on January 12, 2004, the Philippine Government Commission of Information and Communications Technology (CICT) was created to develop, promote and advance Information and Communications Technology as a prerequisite for the continued growth of the economy, competitiveness of local firm/industry using ICT, and achievement of national development goals by providing legal, policy and institutional development in this field.
Parallel to the creation of the CICT and to be able to assimilate the information and telecommunications system of the PNP, the Revised Reorganization Plan of the PNP was adopted on August 21, 2008 through NAPOLCOM Resolution No. 2008-447.
On March 2, 2009, Her Excellency President Gloria Macapagal Arroyo approved the proposal of the Chief PNP Police Director General Jesus Ame Verzosa for the creation of the Directorate for Information and Communications Technology Management (DICTM).
On April 1, 2009, the Directorate for Information and Communications Technology Management (DICTM) was officially activated through General Order Number DPL-09-08 with Police Director (Atty) Magtanggol B. Gatdula as its first director.
PDIR ATTY MAGTANGGOL B GATDULA, PhD/CEO VI Director, DICTM - April 01, 2009 to Present Initiated the following programs and innovations; NATIONAL POLICE CLEARANCE SYSTEM NATIONAL REPORTING SYSTEM NATIONAWIDE ICT CAPABILITY ASSESSMENT OF THE PNP REGIONAL INFORMATION AND COMMUNICATIONSTTECHNOLOGY MANAGEMENT DIVISION (RICTMD)
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
3
B. MISSION, VISION AND FUNCTIONS OF THE DICTM
1. Vision
The Directorate for Information and Communications Technology Management (DICTM) envisions an integrated Information Systems that converge with data communications infrastructure for the PNP to provide effective and efficient innovative police services to the people by creating environment that promotes and advances ICT development.
2. Mission
The Directorate for Information and Communications Technology Management (DICTM) shall assist the Chief, PNP in policy formulation and managing information, electronics and communications technology resources to promote, develop, and regulate integrated and strategic ICT systems, and reliable and efficient communications infrastructure in support to the PNP mission.
3. Powers and Functions
a. Formulates and recommends policies, plans and programs on Information Systems, networks, electronics and communications technology resources of the PNP. This includes the inter-operability, integration, standardization, acquisition, utilization, development and maintenance of all ICT assets.
b. Designs, implements and reviews policies and plans for the integration of all the existing information and communication systems of the PNP.
c. Formulates, reviews and updates the PNP Information Systems Strategic Plan and Telecommunications Systems Strategic Plan.
d. Conducts ICT standardization, and research and development. e. Designs and develops personnel ICT capability enhancement
programs through education and training. f. Formulates and recommends digital Information Security policies
for the protection of digital Information and ICT-related intellectual property of the PNP.
g. Manages the radio frequency spectrum allocated to the PNP. h. Administers and enforces all policies, guidelines, standards, rules
and regulations concerning ICT in the PNP. i. Promotes strategic partnership and cooperation with other
government and non-government agencies, and foreign organizations on ICT matters such as R&D, education and training, technology updates, supports and law enforcement.
j. Performs such other powers and functions proper to its mandate or as directed by the C, PNP.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
4
C. ORGANIZATION STRUCTURE
Acronyms: DICTM – Directorate for Information and Communications Technology Mgmt TDICTM – The Director for Information and Communications Technology Mgmt DDICTM – Deputy Director for Information and Communications Technology Mgmt EX-O – Executive Officer
ICTPPD – ICT Plans and Programs Division SIMD – Systems Integration and Management Division RDD – Research and Development Division ITMS – Information Technology Management Service CES – Communications and Electronics Service RICTOs – Regional Information and Communications Technology Offices
DICTM TDICTM
DDICTM
EX-O
• Policies and Plans Section
• Program Management Section
• Monitoring and Evaluation
Section
• Information Systems Integration and Management Section
• Communications &
Electronics System Section
ITMS CES
• Personnel Officer
• Administrative Officer
• Budget and Fiscal Officer
• ICT Research and Development Section
• Education and Training
Program Section
ICTPPD (ICT Plans & Programs
Division)
SIMD (Systems Integration
and Mgmt. Division)
RDD (Research and
Development Division)
RICTOs
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
5
1. Manning Chart
Legend:
A/B C
(OFFICE)
(D)
A – Police Commissioned Officers (PCOs) B – Police Non-commissioned Officers (PNCOs) C – Non-uniformed Personnel (NUPs) D – Total Number of Personnel
2/2 1
5
1
4
3
1
1
1
1
4 3
6 5
5
1
4 2
6 3
6
1
4 3
5 3
5 4
7
2/1
1/1
1/2
1/2
2/1
2/1
2/1
3/1
2/1
2/1
1/1
1/1
2/1
Budget & Fiscal Officer
1 1
2
4
4
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
6
2. Personnel Distribution Recapitulation
PCOs PNCOs NUPs
PDIR 1 SPO4 1 SG25 0 SG15 4 SG8 4
PCSUPT 1 SPO3 4 SG24 0 SG14 2 SG7 0
PSSUPT 4 SPO2 2 SG22 0 SG13 0 SG6 6
PSUPT 5 SPO1 8 SG19 0 SG12 0 SG4 0
PCINSP 4 PO3 2 SG18 3 SG11 6 SG3 1
PSINSP 9 PO2 0 SG17 0 SG10 1 SG2 0
PINSP 0 PO1 0 SG16 0 SG9 3 SG1 1
TOTAL 24 17 3 16 12
GRAND TOTAL = 72
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
7
D. OFFICES FUNCTIONS AND JOB DESCRIPTIONS
1. OFFICE OF THE DIRECTOR FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
A. The Director for Information and Communications Technology Management
Assists and advises the Chief, PNP in the areas of policy formulation and management for the integration, application and development of Information and Communications Technology in the organization.
Provides direction and control of all human, logistical and financial resources of the directorate to attain its mission and perform its functions.
Directs and supervises projects and activities of the directorate for ICT Management.
Performs other duties as directed by the C, PNP.
B. The Deputy Director for Information and Communications Technology Management
Assists The Director for ICT Management in carrying out his functions.
Represents TDICTM in official conferences, engagement activities when the Director is not available.
Acts as Acting Director in the absence of TDICTM.
Performs other duties as the TDICTM may direct.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
8
C. The Executive Officer
Provides policy direction and guidance to the divisions for the attainment of the mission and objectives of the directorate.
Closely supervises the implementation of various policy, plans, programs, projects and activities of the directorate.
Supervises the administration and operational functions of the directorate such as personnel, logistical and financial managements of the directorate.
Reviews all outputs of the divisions before endorsing it to the Deputy Director, DICTM.
Performs other duties as directed by TDICTM.
D. Administrative Officer (ADMO)
Directs, controls, plans, coordinates and supervises all administrative activities of the Administrative Office.
Ensures the proper administration of personnel, equipment of the Service.
Formulates plans and policies for the efficiency of the function of the Office.
Monitors the performance evaluation/assessment, personnel evaluation and promotion, evaluation of jobs for guidance and assignment of all organic personnel.
Reviews ways to re-evaluate and develop more productive office procedures and systems.
Performs other duties as may be directed by the TDICTM.
E. Personnel Officer
Directs, coordinates and monitor personnel activities/projects designed to attain the greatest degree of personnel effectiveness.
Reviews statement of service records, certification for approval of immediate supervisor.
Prepares and updates the directorate’s Qualifications Standard.
Prepares the assessment proposals of candidates for promotion.
Monitors and supervises the preparation of action on appointments, transfer, resignation, reinstatement, salary adjustment attendance and other matters pertaining to personnel services for approval of TDICTM.
Prepares communications on personnel matters.
Performs other duties as may be directed TDICTM.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
9
F. Budget and Fiscal Officer
Prepares Operations Plans and budget estimates in accordance with the approved guidelines and priorities including supporting justifications.
Assists management in the presentation and justification of budget estimates to higher headquarters.
Re-aligns expenditures according to program and projects based on approved appropriations.
Prepares Program Review and Analysis for the effective use of budget.
Acts as Liaison Officer in the follow-up and submission of budgetary requests.
Performs other duties as may be directed by TDICTM.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
10
2. DIVISIONS
A. Plans and Programs Division
Sets policy agenda on ICT promotion and development.
Formulates, supervises and reviews the implementation of programs in consonance with the PNP thrust on ICT development based on the PNP ISSP, and existing ICT development policies.
Prepares policies and plans in consonance with the PNP ICT thrust in line with the Mission, Vision and Functions of the directorate;
Develops policies and plans for the acquisition, development, maintenance and administration of PNP-wide computer networks;
Prepares annual ICT development plan for the PNP based on the PNP Information Systems Strategic Plan (ISSP).
Develops and recommends tactical and strategic plans aligned to the PNP Information Systems Strategic Plan (ISSP).
Reviews and updates existing PNP Information System Strategic
Plan (ISSP).
Develops and updates PNP Telecommunication Systems Strategic Plan and integrate it to the PNP ISSP.
Formulate, implements and reviews policies and guidelines on Information Security and Cybercrime law enforcement.
Coordinates with other government, non-government and foreign organizations on ICT matters.
Reviews and updates existing ICT policies and guidelines of the
PNP as necessary.
Supervises the ITMS and CES in implementing Information and Communication Technology (ICT) projects.
Performs other tasks as directed by TDICTM.
1. Chief, Plans and Programs Division
1.1 Supervises and monitors the direction and execution of DICTM Plans and Programs.
1.2 Communicates regularly to DICTM through the Executive Officer the progress and status of plans and programs.
1.3 Establishes and maintains adequate records of administrative resources and standards of the PNP to provide inputs for future planning and analyzes.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
11
1.4 Keep TDICTM fully informed on all significant matters, deviations
from target output and problems, and recommends solutions/actions leading to the improvement of administration and operations of the directorate.
1.5 Performs other functions as may be directed by TDICTM.
2. Assistant Chief, Plans and Programs Division
2.1 Assists the Chief, Plans and Programs Division in the direction and supervision of the division
2.2 Analyses and evaluates reports to be submitted to higher authority.
2.3 Assists in monitoring the execution of the Plans and Programs on ICT.
2.4 Reviews the annual ICT development plan for the PNP. 2.5 Assists in undertaking studies on the development and
implementation of special ICT projects. 2.6 Performs other related functions as directed by TDICTM.
3. Policies and Plans Section
3.1 Reviews and updates existing ICT policies and plans of the PNP. 3.2 Formulates policies in support to PNP thrust on ICT development
based on the PNP ISSP. 3.3 Reviews and updates existing PNP Information System Strategic
Plan (ISSP). 3.4 Develops and updates PNP Telecommunication Systems Strategic
Plan and integrate it to the PNP ISSP. 3.5 Formulates, implements and reviews policies and guidelines on
Information Security and Cybercrime law enforcement. 3.6 Performs other related functions as directed by the DICTM.
4. Program Management Section
4.1 Formulates, implements and evaluates programs on ICT of the
PNP. 4.2 Reviews and updates existing programs of the PNP on ICT. 4.3 Formulates, supervises and reviews the implementation of
programs in consonance with the PNP thrust on ICT development based on the PNP ISSP and existing ICT development policies.
4.4 Coordinates with other government, non-government and foreign organizations on ICT matters.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
12
4.5 Supervises the ITMS and CES in implementing Information and Communication Technology (ICT) projects and activities.
4.6 Performs other related functions as directed by the TDICTM.
5. Monitoring and Evaluation Section
2.5.1 Formulates, implements and evaluates plans for monitoring and evaluation of different ICT projects of the PNP.
2.5.2 Formulates programs and activities in consonance to the conduct of monitoring and evaluation of ICT projects.
2.5.3 Submits reports of the output of monitoring and evaluation of ICT projects.
2.5.4 Performs other related functions as directed by the TDICTM.
6. Organizational Structure
Policies and Plans Section
Monitoring and Evaluation Section
Program Management Section
Asst Chief, Plans and Programs Division
Chief, Plans and Programs Division
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
13
B. Systems Integration and Management Division
Set policy agenda on Systems Integration for policy formulation, implementation and evaluation.
Formulates, supervises and evaluates the implementation of plans and programs on Information Systems integration and management.
Formulates, supervises and evaluates the implementation of plans and programs for standardization of Information System and Telecommunications codes, variables and parameters.
Formulates plans and policies for the integration of PNP-wide communications system.
Formulates, supervises and evaluates the implementation of plans and programs for telecommunications and electronics projects and activities.
Manages the radio frequency spectrum allocated to the PNP.
Performs other tasks as directed by TDICTM.
1. Chief, Systems Integration and Management Division
1.1 Supervises and monitors the direction and execution of DICTM Plans and Programs on integration and management of Information System and Telecommunications.
1.2 Communicates regularly to DICTM through the Executive Officer the progress and status plans and programs on system integration and management.
1.3 Supervises and monitors the direction and execution of DICTM Plans and Programs on standardization of codes, variable and parameters for integration and management of Information System and Telecommunications.
1.4 Performs other functions as may be directed by DICTM.
2. Assistant Chief, Systems Integration and Management Division
2.1 Assists the Chief, Systems Integration and Management Division in the direction and supervision of the division.
2.2 Analyses and evaluates reports to be submitted to higher authority pertaining to systems integration and management.
2.3 Assists in monitoring the execution of the projects on system integration and management, and integration of telecommunications and electronics system.
2.4 Performs other related functions as directed by TDICTM.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
14
3. Information System Integration and Management Section
3.1 Formulates, supervises and evaluates the implementation of
Information Systems integration and management plans and programs.
3.2 Formulates, supervises and evaluates the implementation of plans and programs for standardization of Information System and Telecommunications codes, variables and parameters.
3.3 Performs other related functions as directed by the DICTM.
4. Communications and Electronics System Section
4.1 Formulates, supervises and evaluates the implementation of plans and programs for telecommunications and electronics projects and activities.
4.2 Reviews and updates existing programs on development of telecommunications and electronics.
4.3 Formulates, supervises and evaluates the implementation of programs and plans to support effective use of telecommunications and electronics system.
4.4 Formulates plans and policies for the integration of PNP-wide communications system.
4.5 Manages the radio frequency spectrum allocated to the PNP. 4.6 Formulates, supervises and evaluates the implementation of
plans for integrated telecommunications system of the PNP. 4.7 Performs other related functions as directed by the DICTM.
1.5 Organizational Structure
Information Systems
Integration and Mgmt Section Communications and
Electronics System Section
Asst Chief, SIMD
Chief, Systems Integration and Mgmt Division
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
15
C. Research and Development Division
Sets agenda for research on Information and Communications Technology for the PNP.
Formulates, supervises and evaluates the implementation of plans and programs on ICT standardization of codes, variables and parameters.
Formulates, supervises and evaluates the implementation of research-related projects and activities in support to the formulation, review and updates of the PNP Information Systems Strategic Plan and Telecommunication Systems Strategic Plan.
Formulates, supervises and evaluates the implementation of plans and programs for standardization of Information Systems and Telecommunications codes, variables and parameters.
Conduct research and development on latest Information and Communications Technology products and services.
Reviews, evaluates and recommends approval of data and communications system design and integration for the PNP.
Formulates, supervises and evaluates the implementation of plans and programs for ICT education and training.
Conducts literacy and awareness programs on latest ICT products and services that are applicable to the PNP.
Maintains library of references on ICT standardization.
Performs other tasks as directed by TDICTM.
1. Chief, Research and Development Division 1.1 Supervises and monitors the direction and execution of DICTM
Plans and Programs for research on latest ICT products and services.
1.2 Communicates regularly to DICTM through the Executive Officer the progress and status of research projects and activities.
1.3 Supervises and monitors the direction and execution of DICTM Plans and Programs on standardization of codes, variable and parameters of Information Systems and Telecommunications Systems.
1.4 Supervises and directs the setting of agenda and conduct of research and development.
1.5 Supervise and directs the conduct of research for formulation and updates of the Information Systems Strategic Plan and Telecommunication Systems Strategic Plan.
1.6 Performs other functions as may be directed by DICTM.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
16
2. Assistant Chief, Research and Development Division
2.1 Assists the Chief, Research and Development Division in the direction and supervision of the division.
2.2 Analyses and evaluates reports to be submitted to higher authority pertaining to ICT research and development.
2.3 Assists in monitoring the execution of the projects on research and development, and standardization.
2.4 Performs other related functions as directed by TDICTM.
3. ICT Research and Development Section
3.1 Sets agenda for the conduct of research and development on latest ICT products and services that are applicable and advantageous to the PNP.
3.2 Formulates, supervises and evaluate the implementation plans and programs for standardization of codes, variables and parameters on ICT.
3.3 Formulates, supervises and evaluates the implementation of plans and programs for standardization of Information Systems codes, variables and parameters for Information Systems and Telecommunication Systems.
3.4 Formulates, supervises and evaluates the implementation of research-related projects and activities for the formulation, review and updates of the PNP ISSP and Telecommunication Systems Strategic Plan
3.5 Performs other related functions as directed by the DICTM.
4. Education and Training Program Section
4.1 Formulate, supervises and review the implementation of ICT-related enhancement courses of the PNP.
4.2 Undertakes research on ICT trends and updates applicable to the
PNP to revise and supplement education and training program on ICT.
4.3 Develops and revises education and training methods, procedures and standards to complement and adapt to the continuing changes of technological demand of the organization.
4.4 Incorporates Police Education and Value Orientation Programs of the PNP in ICT educations and training.
4.5 Performs other related functions as directed by the DICTM.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
17
5. Organizational Structure
ICT Research and Development Section
Education and Training Program Section
Asst Chief, Research and Development Division
Chief, Research and Development Division
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
18
A. SUPPORT UNITS
1. Information Technology Management Service
The PNP Information Technology Management Service formulates, updates, and disseminates IT policies, guidelines, and standards towards the proper development and implementation of information systems in the PNP. The office also provides computer-based information systems development, data processing, systems support, and conducts IT-related research and training services.
Organizational Structure
SECURITY PCR FINANCE BUD & FISCAL PLANS
OFFICE OF THE
DIRECTOR
DMD SMD COD TRD
STAFF OFFICES
Inspectorate
CHIEF OF STAFF
LINE DIVISIONS
WSCSD
ADMIN
NMD
DEPUTY DIRECTOR
ICT PERSONNEL (DEPLOYED)
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
19
2. Communications and Electronics Service
To Communications and Electronics Service provides Communications-Electronics service and support necessary for the accomplishment of PNP tasks. Its functions are to install, operate and maintain communications system in support of PNP-wide activities, including coordination, command and control, communications security, and service support. It also provides direct support to all operations of the PNP, fixed communications facilities and technical support for the NHQ, NSUs, regional and provincial offices.
Organizational Structure
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
20
II. OPERATIONS
1. ADMINISTRATIVE OFFICE
1.1. Certification
TITLE Procedure No. No. of Pages
Certification 1.1 3
INTERFACES DICTM Admin Office and Personnel
1.1.1. OBJECTIVE
Prescribing the guidelines and procedures in the issuance of Certificate of Duty Status.
1.1.2. REFERENCE 1.1.3. DEFINITION OF TERMS
1.1.3.1. Certification – the act of certifying a person, thing or document; or state of being certified. Certification maybe valid for a certain period of time or lifetime.
1.1.4. REQUIREMENTS
1.1.4.1. For Processing of Claims 1.1.4.2 Implementing Order like RCA Order, Long Pay Order and the
likes. 1.1.4.3 For Loan Purposes 1.1.4.4 Filled out Loan Form from Lending Investor 1.1.4.5 Latest Photocopy of Pay slip 1.1.4.6 Others Client Purpose
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
21
1.1.5. FLOWCHART 1.1.6. NARRATIVE
1.1.6.1. The Client will submit the required documents to the
Administrative Office. 1.1.6.2. The Personel PNCO will evaluate the submitted requirements
and prepare the Certificate of Duty Status. 1.1.6.3. The Personnel Officer will verify the documents and sign to
certificate. 1.1.6.4. The Administrative Officer will sign the Certificate of Duty Status. 1.1.6.5. Admin Office will release/issue the certification.
1.1.7. SERVICE STANDARD
Transaction Type Turn Around Time
Average Transaction Time
Submission of Requirements
Evaluation of the Requirements 2 hours
Verification of the Requirements 1 hour
Notation of Admin Officer 30 mins
Total Average Transaction Time 3 hours and
30 mins
END
START
Submission of requirements to Admin
Office
Evaluation of the requirements & preparation
of the certificate.
Verification of the Certification
Notation of the
Certification
Releasing of Certificate
of Duty Status
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
22
1.2. Commutation Order
TITLE Procedure No. No. of Pages
Commutation Order 1.2 3
INTERFACES DICTM Admin Office and Personnel
1.2.1. OBJECTIVE
Prescribing the guidelines and procedures in the applications of issuance
of Commutation Order. 1.2.2. REFERENCES
1.2.2.1. Section 39 of RA 6975, An Act Establishing The Philippine
National Police Under A Reorganized Department Of The Interior And Local Government, And For Other Purposes.
1.2.3. DEFINITION OF TERMS
1.2.3.1. Commutation Order ~ is an order that certifies the unused leave
credits of the personnel. 1.2.4. REQUIREMENTS
1.2.4.1. Unit Endorsement 1.2.4.2. Retirement Orders 1.2.4.3. Updated Leave Credits from RMD, DPRM 1.2.4.4. Updated Service Record 1.2.4.5. Latest Promotion Order
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
23
1.2.5. FLOWCHART
Submission of requirements to Admin
Office
END
START
Countersignature of the Administrative Officer
Evaluation of the requirements & preparation of the
endorsement (Personnel PNCO)
Endorsement of the Director
Verification of the requirements (Personnel Officer)
Submission of Folder to DPRM for issuance of implementing
orders
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
24
1.3. Compulsory Retirement
1.3.1. OBJECTIVE
Prescribing the guidelines and procedures in the compulsory retirement of DICTM personnel. 1.3.2. REFERENCES
1.3.2.1. Section 39 of RA 6975, An Act Establishing The Philippine National Police Under A Reorganized Department Of The Interior And Local Government, And For Other Purposes.
1.3.3. DEFINITION OF TERMS
1.3.3.1. Compulsory Retirement Compulsory retirement, for officer
and non-officer, shall be upon the attainment of age fifty-six (56): Provided, That, in case of any officer with the rank of chief superintendent, director or deputy director general, the Commission may allow his retention in the service for an unextendible period of one (1) year.
1.3.4. REQUIREMENTS
1.3.4.1. Unit Endorsement 1.3.4.2. Basic Letter Request 1.3.4.3. Service Record 1.3.4.4. Latest Promotion Order 1.3.4.5. PLEB Clearance 1.3.4.6. NAPOLCOM Clearance 1.3.4.7. Unit Clearances (Non Money/Property and Non-Pending Case) 1.3.4.8. IAS Clearance 1.3.4.9. DIDM Clearance 1.3.4.10. Latest Statement of Assets, Liabilities and Net worth.
TITLE Procedure No. No. of Pages
Compulsory Retirement 1.3 3
INTERFACES DICTM Admin Office and Personnel
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
25
1.3.5. FLOWCHART 1.3.6. NARRATIVE
1.3.6.1. The Client will submit two copies of the requirements to
Administrative Office. 1.3.6.2. The Personnel PNCO will evaluate the submitted requirements
and prepare the Unit Endorsement. 1.3.6.3. The Personnel Officer will verify the documents. 1.3.6.4. The Administrative Officer will countersign the endorsement letter. 1.3.6.5. The Director will endorse the issuance of retirement order. 1.3.6.6. Submission of folder to DPRM for issuance of implementing
order. 1.3.7. SERVICE STANDARD
Transaction Type
Turn Around Time
Average Transaction
Time
Submission of Requirements
Evaluation of the Requirements 2 hours
Verification of the Requirements 1 hour
Countersignature of Admin Officer 30 mins
Command Group 1 hour & 30 mins
Endorsement of the Director 1 hour
Total Average Transaction Time 6 hours
END
START
Submission of requirements
to Admin Office
Evaluation of the requirements & preparation
of the endorsement (Personnel PNCO)
Verification of the requirements
(Personnel Officer)
Countersignature of the Administrative Officer
Endorsement of the Director
Submission of Folder to DPRM for issuance of implementing orders
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
26
1.4. Conferment of Awards
TITLE Procedure No. No. of Pages
Conferment of Awards 1.4 3
INTERFACES DICTM Admin Office and Personnel
1.4.1. OBJECTIVE
To issue and confer awards to DICTM personnel following the prescribed guidelines and procedures in the conferment of authorized decorations, service medals, ribbons and badges of the PNP. 1.4.2. REFERENCES
1.4.2.1. PNP MEMO CIRCULAR NO 2006-014 dated July 26, 2006, “Rules and regulations in the conferment of authorized decorations, service medals, ribbons and badges to the personnel of the Philippine National Police.”
1.4.2.2. NAPOLCOM MEMO CIRCULAR 2006 – 03 dated November 30, 2006, “Further Amending Memorandum Circular No 93-018 entitled Prescribing the Authorized Decorations, Service Medals, Ribbons and Badges of the Philippine National Police.”
1.4.3. DEFINITION OF TERMS
1.4.3.1. DICTM Personnel Board is the panel headed by Deputy Director
created to evaluate, assess and/or deliberate DICTM personnel matters such as personnel procurement, movement, development and maintenance prior recommendation to the Director, DICTM for his approval.
1.4.3.2. DICTM Working Committee is the team from Admin Office created to assist the Board administratively and shall be responsible for the initial screening and evaluation of personnel matters prior deliberation of the Board.
1.4.4. REQUIREMENTS
1.4.4.1. Administrative accomplishment of personnel 1.4.4.2. Approved Personnel Board Resolution
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
27
1.4.5. FLOWCHART
Client will provide
accomplishments
Deliberation of the
Personnel Board
Recommendation for Approval of the Board
Resolution
Issuance of Order of
Admin Office
Working Committee will preliminarily evaluate
and assess the accomplishment/s
Conversion of Leave
Credits to DPRM
START
END
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
28
1.4.6. NARRATIVE
1.4.6.1. The Client – Division Chief/Key Officers will submit administrative accomplishment to Administrative Office (Working Committee) for preliminary screening and evaluation.
1.4.6.2. The Working Committee will assess and evaluate the accomplishment/s prior deliberation to the Board.
1.4.6.3. The Personnel Board will reevaluate the accomplishment and recommend approval or disapproval of the awards, medals and recognition.
1.4.6.4. The Administrative Office will issue appropriate awards, medals and recognition to the personnel.
1.4.6.5. The Administrative Office will furnish a copy of the issued Medals to DPRM for the conversion of such to leave credits to be enjoyed by concerned personnel from date of conferment onwards but not later than the last day of the next calendar year.
1.4.7 SERVICE STANDARD
Transaction Type Turn Around Time
Average Transaction Time
Submission of Accomplishment Report
Preliminary Screening of Working Committee
1 to 2 days
Deliberation and Recommendation of the Board
2 days
Approval of the TDICTM 1 day
Issuance of Order 1 hour
Total Average Transaction Time 5 days and 1
hour
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
29
1.5. PNP ID Application
1.5.1. OBJECTIVE: Prescribing the guidelines and procedures in the applications of PNP ID. 1.5.2. REFERENCES
1.5.2.1. DPRM Form 1A – 2007.
1.5.3. DEFINITION OF TERMS
1.5.3.1. DPRM Form 1A – 2007 - the revised PNP ID Application Form.
1.5.4. REQUIREMENTS 1.5.4.1. New Applicant
1.5.4.1.1 Endorsement from the Administrative Officer 1.5.4.1.2 Accomplished PNP ID Form 1.5.4.1.3 Appointment Order 1.5.4.1.4 Authenticated Latest Payslip
1.5.4.2. Renewal/Update 1.5.4.2.1. Endorsement from the Admin Officer 1.5.4.2.2. Accomplished PNP ID Form 1.5.4.2.3. Surrender Old/Expired ID 1.5.4.2.4. Promotion Order if newly promoted 1.5.4.2.5. Demotion Order if demoted 1.5.4.2.6. Change Status/Amendment Order if Amended/Changed
1.5.4.3. Retired 1.5.4.3.1. Endorsement from the Admin Officer 1.5.4.3.2. Accomplished PNP ID Form 1.5.4.3.3. Retirement Orders 1.5.4.3.4. Surrender old ID
1.5.4.4. Replacement (loss/dilapidated) 1.5.4.4.1. Endorsement from the Admin Officer 1.5.4.4.2. Accomplished PNP ID Form 1.5.4.4.3. Affidavit of Loss if loss 1.5.4.4.4. Surrender dilapidated ID if dilapidated 1.5.4.4.5. Payment of Php 60.00 for the replacement of ID Card
TITLE Procedure No. No. of Pages
ID Application 1.5 4
INTERFACES DICTM Admin Office and Personnel
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
30
1.5.5. FLOWCHART 1.5.6. NARRATIVE
1.5.6.1. The Client will submit the accomplished ID Application Form
required and required documents to the Administrative Office. 1.5.6.2. The Personnel PNCO will evaluate the submitted requirements
and prepare the Unit Endorsement. 1.5.6.3. The Personnel Officer will verify the documents and countersign
to the ID application form. 1.5.6.4. The Administrative Officer will sign the ID Application Form and
the endorsement. 1.5.6.5. The liaison officer will submit the application to RMD, DPRM for
issuance of PNP ID. 1.5.6.5. Distribution of PNP ID to the concerned Personnel.
Submission of requirements
to Admin Office
Evaluation of the requirements & preparation of the
endorsement
Verification of the
requirements
Signature of the Application Form and Endorsement
Memorandum
Liaison Officer will submit the application to RMD ,
DPRM
Release of PNP ID
START
END
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
31
1.5.7. SERVICE STANDARD
Transaction Type Turn Around Time
Average Transaction Time
Submission of Requirements
Evaluation of the Requirements 2 hours
Verification of the Requirements 1 hour
Countersignature of Admin Officer
30 mins
Command Group 1 hour & 30 mins
Endorsement of the Director 1 hour
Total Average Transaction Time 6 hours
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
32
1.5.8. SAMPLE FORMAT
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
33
1.6. Filing of Leave of Absence
TITLE Procedure No. No. of Pages
Filing of leave of absence for all DICTM personnel.
1.6 6
INTERFACES DICTM Admin Office/Command Group/Personnel
1.6.1. OBJECTIVE
To provide procedures and guidelines in the application of leave of absence for all DICTM personnel. 1.6.2. REFERENCES
1.6.2.1. PNP Circular No.2002-009 dated May 21, 2002 1.6.2.2. Rule XVI of the Omnibus Rules Implementing Book V of the
Administrative Code of 1987 (Executive Order 292)
1.6.3. DEFINITION OF TERMS
1.6.3.1. Leave form (CSC Form No.6) – To be accomplished for filing a Leave of Absence
1.6.3.2. Leave of Absence (LOA) - is a term used to describe a period of time that one is to be away from his/her primary job, while maintaining the status of employment. This term is in contrast to normal periods away from the workplace, such as vacations, holidays, hiatuses, sabbaticals, and “working from home” programs, in that they are considered to be exceptional circumstances, rather than benefits. Generally such an arrangement has a predefined termination at a particular date or after a certain event has occurred.
1.6.4. REQUIREMENTS
1.6.4.1. For vacation/sick leave abroad 1.6.4.1.1. Letter endorsement from unit chief 1.6.4.1.2. Basic letter request, including the number of days,
reason for leave and address while on leave 1.6.4.1.3. Duly accomplished CSC form No.6 1.6.4.1.4. Breakdown of leave credits from RMD, DPRM 1.6.4.1.5. NHQ IAS and Legal Service clearances 1.6.4.1.6. Unit Clearances 1.6.4.1.7. Certificate of non-pending case
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
34
1.6.4.1.8. Certificate of non-money/property accountability 1.6.4.2. For sick leave exceeding five (5) days & maternity leave
1.6.4.2.1. Certificate indicating therein the period and nature of treatment and with license number of the attending physician indicted.
1.6.4.2.2. Duly accomplished CSC form No.6 1.6.4.3. For sick leave not exceeding five (5) days
1.6.4.3.1. Accomplished CSC Form No. 6 1.6.4.3.2. Affidavit
1.6.4.4. For special, mandatory, emergency, & paternity leave 1.6.4.4.1. Duly accomplished CSC form No.6
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
35
1.6.5. FLOWCHART START
END
Client will duly accomplish CSC Form No. 6
and prepare necessary document.
Personnel Clerk receives and checks the completeness of the requirements.
C, Clerk/NUP Supervisor records the dates and countersigns on the leave form.
Personnel Officer signs on the leave form.
Morale & Welfare Staff prepares the Unit Endorsement.
ADMO signs on the leave form.
Command Group - DDA signs the Unit
Endorsement
Liaison Officer transmits the endorsement
to TDPRM, RMD.
TDPRM, RMD issues appropriate implementing order and furnish the unit concerned.
Client will duly accomplish CSC Form No. 6
and prepare necessary document.
Personnel Clerk receives and checks the completeness of the requirements.
C, Clerk/NUP Supervisor records the dates and countersigns on the leave form.
Personnel Officer signs on the leave form.
Morale & Welfare Staff prepares the Unit Endorsement.
ADMO signs on the leave form.
Command Group - DDA signs the Unit
Endorsement
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
36
1.6.6. NARRATIVE
1.6.6.1. The clients duly accomplish CSC Form No. 6 (2 copies) and files leave application at the admin office.
1.6.6.2. The personnel clerk receives the application, check the completeness of the requirements then forward the applications to NUP Supervisor for NUP and to C, Clerk for Uniformed Personnel.
1.6.6.3. NUP Supervisor/C, Clerk record the dates indicated on the leave form then countersigns.
1.6.6.4. The Personnel Officer signs the leave form. 1.6.6.5. The Morale and Welfare Staff prepares unit endorsement. 1.6.6.6. The Administrative Officer signs the leave form. 1.6.6.7. The TDICTM signs the unit endorsement. 1.6.6.8. The Liaison Officer forwards the accomplished leave form and
endorsement to TDPRM, RMD. 1.6.6.9. TDPRM will issue implementing orders and furnish the concerned
unit. 1.6.7. SERVICE STANDARDS
Transaction Type Turn Around Time
Average Transaction Time
Receive /Checking of Documents
20 mins
Recording & countersigning 10 mins
Pers Officer Signature 10 mins
Preparation of Unit Endorsement
20 mins
ADMO Signature 10 mins
DDA Signature 30 mins
Transmittal to TDPRM 30 mins
Issuance of order
Total Average Transaction Time 2 hours 10 minutes
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
37
1.6.8. SAMPLE FORMAT
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
38
1.7. Issuance of Letter of Accommodation
TITLE Procedure No. No. of Pages
Issuance of Letter of Accommodation
1.7 4
INTERFACES DICTM Admin Office/Personnel
1.7.1. OBJECTIVE
Prescribing the guidelines and procedures in the issuance of Letter of Accommodation to a uniformed personnel 1.7.2. REFERENCES
1.7.2.1. PNP MEMO CIRCULAR NO 99 – 016, “Guidelines on the Transfer/Reassignment of PNP Personnel.”
1.7.2.2. Memo from TADPRM dated June 29, 2007 re: Requirements for Transfer of PNP Personnel.
1.7.3. DEFINITION OF TERMS
1.7.3.1. Letter of Accommodation - is a letter given to personnel who
are willing to be assigned to a unit/office which was duly signed by the Director/Chief of Office of the gaining unit/office.
1.7.4. REQUIREMENTS 1.7.4.1. Basic Letter Request 1.7.4.2. Projected Designation to position commensurate to the rank
based on T.O. Position if personnel is a PCINSP to PSSUPT rank.
1.7.4.3. Updated CSC Personal Data Sheet
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
39
1.7.5. FLOWCHART
START
Evaluation of the requirements and
Preparation of the Letter
(Personnel PNCO)
Verification of the requirements and letter
(Personnel Officer)
Recommend approval of the Administrative Officer
Approval of the Director
Releasing of Letter of Accommodation
Submission of requirements
to Admin Office
END
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
40
1.7.6. NARRATIVE
1.7.6.1. The Client will submit the requirements to Administrative Office. 1.7.6.2. The Personnel PNCO will evaluate the submitted requirements
and prepare the Letter of Accommodation. 1.7.6.3. The Personnel Officer will verify the documents and countersign
to the letter. 1.7.6.4. The Administrative Officer may/may not talk to the client then will
recommend approval of the accommodation. 1.7.6.5. The Director will approve or disapprove the letter of
accommodation. 1.7.6.6. Releasing of Letter of Accommodation.
1.7.7. SERVICE STANDARD
Transaction Type Turn Around Time
Average Transaction Time
Submission of Requirements
Evaluation of the Requirements 2 hours
Verification of the Requirements 1 hour
Recommendation of Admin Officer
4 hours
Command Group 3 hours
Approval of the Director 2 hour
Total Average Transaction Time 1 day and 4
hours
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
41
1.7.8. SAMPLE FORMAT
Republic of the Philippines Department of the Interior and Local Government
NATIONAL POLICE COMMISSION NATIONAL HEADQUARTERS PHILIPPINE NATIONAL POLICE
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT Camp Crame, Quezon City
September 15, 2009
A C C O M M O D A T I O N
THIS IS TO CERTIFY that PCI JUAN DELA CRUZ, 0-123456 assigned
at QCPD, NCRPO is granted accommodation to this Directorate.
This certification is issued to subject PCO to facilitate the issuance of
his/her reassignment order.
ATTY MAGTANGGOL B GATDULA, Ph.D/CEO VI Police Director
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
42
1.8. Transfer/Reassignment of Uniformed Personnel
TITLE Procedure No. No. of Pages
Transfer/Reassignment of Uniformed Personnel
1.8 3
INTERFACES DICTM Admin Office/Personnel
1.8.1. OBJECTIVE
Prescribing the guidelines and procedures in the transfer/reassignment of uniformed personnel to other Units. 1.8.2. REFERENCES
1.8.2.1. PNP MEMO CIRCULAR NO 99 – 016, “Guidelines on the Transfer/Reassignment of PNP Personnel.”
1.8.2.2. Memo from TADPRM dated June 29, 2007 re: Requirements for Transfer of PNP Personnel.
1.8.3. DEFINITION OF TERMS
1.8.3.1. Transfer - is a movement from one position to another which is of
equivalent rank, level or salary without break in service involving the issuance of an appointment.
1.8.3.2. Reassignment - is the movement of an employee from one organizational unit to another in the same department or agency which does not involve a reduction in rank, status, or salary and doest not require the issuance of appointment.
1.8.3.3. Availability of Reassignment - is a certificate being given by the losing unit duly signed by its Director/Chief of Office granting the transfer of personnel to another unit.
1.8.3.4. Letter of Accommodation - is a letter given to a personnel who are willing to be assigned to a unit/office which was duly signed by the Director/Chief of Office of the gaining unit/office.
1.8.4. REQUIREMENTS
1.8.4.1. Unit Endorsement 1.8.4.2. Availability of Reassignment 1.8.4.3. Basic Letter Request of the Uniformed Personnel 1.8.4.4. Updated DICTMC Personal Data Sheet 1.8.4.5. Letter of Accommodation
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
43
1.8.4.6. Clearances (Non Money/Property and Non-Pending Case and IAS)
1.8.4.7. Certification that subject personnel is not a witness in admin/criminal case
1.8.4.8. Certificate of no pending case for resolution if he/she is a Summary Hearing Officer
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
44
1.8.5. FLOWCHART 1.8.6. NARRATIVE
1.8.6.1. The Client will submit the requirements to Administrative Office. 1.8.6.2. The Personnel PNCO will evaluate the submitted requirements
and prepare the Certificate of Availability for Transfer. 1.8.6.3. The Personnel Officer will verify the documents and countersign
to the certificate. 1.8.6.4. The Administrative Officer may/may not talk to the client then will
recommend approval of the transfer. 1.8.6.5. The Director will approve or disapprove the reassignment of the
personnel. 1.8.6.6. If approved, the Administrative Office will submit the folder to
DPRM for the issuance of implementing order.
Submission of requirements to Admin Office
Recommend approval of the
Administrative Officer
Approval of the Director
Submission of Folder to DPRM for the issuance of
implementing order
END
START
Evaluation of the requirements and Preparation
of Certificate (Personnel PNCO)
Verification of the requirements and certificate
(Personnel Officer)
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
45
1.8.7. SERVICE STANDARD
Transaction Type Turn Around Time
Average Transaction Time
Submission of Requirements
Evaluation of the Requirements 2 hours
Verification of the Requirements 1 hour
Recommendation of Admin Officer
4 hours
Command Group 3 hours
Approval of the Director 2 hour
Total Average Transaction Time 1 day and 4
hours
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
46
1.8.8. SAMPLE
Republic of the Philippines Department of the Interior and Local Government
NATIONAL POLICE COMMISSION NATIONAL HEADQUARTERS PHILIPPINE NATIONAL POLICE
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
Camp Crame, Quezon City [email protected]
September 15, 2009
AVAILABILITY FOR TRANSFER
Availability for transfer is hereby granted to ________________________
(NAME OF PCO/PNCO) for transfer to: __________________________where he is projected to be designated
(GAINING UNIT) to the position of _______________ at said unit. Subject is cleared of money and property accountabilities from this unit; has no pending administrative/criminal case and is not a witness in an administrative/criminal case as of this date. This is issued upon the request of subject PCO/PNCO to facilitate the issuance of his/her reassignment order.
ATTY MAGTANGGOL B GATDULA, Ph.D/CEO VI Police Director
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
47
1.9. Resignation of Personnel
TITLE Procedure No. No. of Pages
Resignation of Personnel 1.9 3
INTERFACES DICTM Admin Office/Personnel
1.9.1. OBJECTIVE
Prescribing the guidelines and procedures in the processing of resignation of personnel. 1.9.2. REFERENCES
1.9.2.1. Civil Service guideline on resignation of personnel 1.9.2.2. PNP guidelines on resignation of personnel
1.9.3. DEFINITION OF TERMS
1.9.3.1. Resignation - is the formal act of giving up or quitting one's office
or position. A resignation can occur when a person holding a position gained by election or appointment steps down, but leaving a position upon the expiration of a term is not considered resignation. An employee who chooses to leave a position is considered a resignation, as opposed to termination, which occurs when the employee involuntarily loses a job.
19.4. REQUIREMENTS
19.4.1. Unit Endorsement 19.4.2. Basic Letter Request 19.4.3. Service Record 19.4.4. Clearances (Non Money/Property and Non-Pending Case and
IAS) 19.4.5. Latest Statement of Assets, Liabilities and Net worth.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
48
1.9.5. FLOWCHART 1.9.6. NARRATIVE
19.6.1. The Client will submit the requirements to Administrative Office. 19.6.2. The Personnel PNCO will evaluate the submitted requirements
and prepare the Unit Endorsement. 19.6.3. The Personnel Officer will talk to the client regarding his/her
resignation. The documents will also be verified. 19.6.4. The Administrative Officer may/may not talk to the client then will
recommend approval of the resignation. 19.6.5. The Director will approve or disapprove the letter of
accommodation. 19.6.6. Releasing of Letter of Accommodation.
START
Submission of requirements
to Admin Office
Evaluation of the requirements & preparation of the
endorsement (Personnel PNCO)
Verification of the requirements
(Personnel Officer)
Recommend approval of the Administrative Officer
Approval of the Director
Submission of Folder to DPRM for issuance of implementing orders
END
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
49
1.9.7. SERVICE STANDARD
Transaction Type Turn Around Time
Average Transaction Time
Submission of Requirements
Evaluation of the Requirements 2 hours
Verification of the Requirements 1 hour
Recommendation of Admin Officer
4 hours
Command Group 3 hours
Approval of the Director 2 hour
Total Average Transaction Time 1 day and 4 hours
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
50
1.10. Optional Retirement
TITLE Procedure No. No. of Pages
Optional Retirement 1.10 3
INTERFACES DICTM Admin Office/Personnel
1.10.1. OBJECTIVE
Prescribing the guidelines and procedures in the optional retirement of DICTM personnel. 1.10.2. REFERENCES
1.10.2.1. Section 40 of RA 6975, An Act Establishing The Philippine National Police Under A Reorganized Department Of The Interior And Local Government, And For Other Purposes.
1.10.3. DEFINITION OF TERMS
1.10.3.1. Optional Retirement - Upon accumulation of at least twenty
(20) years of satisfactory active service, an officer or non-officer, at his own request and with the approval of the Commission, shall be retired from the service and entitled to receive benefits provided by law.
1.10.4. REQUIREMENTS
1.10.4.1. Unit Endorsement 1.10.4.2. Basic Letter Request 1.10.4.3. NAPOLCOM Approval 1.10.4.4. Service Record 1.10.4.5. Latest Promotion Order 1.10.4.6. PLEB Clearance 1.10.4.7. NAPOLCOM Clearance 1.10.4.8. Unit Clearances ( Non Money/Property and Non-Pending
Case) 1.10.4.9. IAS Clearance 1.10.4.10. DIDM Clearance 1.10.4.11. Latest Statement of Assets, Liabilities and Net worth.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
51
1.10.5. FLOWCHART 1.10.6. NARRATIVE
1.10.6.1. The Client will submit two copies of the requirements to
Administrative Office. 1.10.6.2. The Personnel PNCO will evaluate the submitted
requirements and prepare the Unit Endorsement. 1.10.6.3. The Personnel Officer will talk to the client regarding his/her
optional retirement. The documents will also be verified. 1.10.6.4. The Administrative Officer may/may not talk to the client then
will recommend approval of the resignation. 1.10.6.5. The Director will approve or disapprove the application of
optional retirement. 1.10.6.6. Submission of folder to DPRM for issuance of implementing
order.
Submission of requirements
to Admin Office
Evaluation of the requirements & preparation
of the endorsement (Personnel PNCO)
Verification of the requirements
(Personnel Officer)
Recommend approval of the Administrative Officer
Approval of the Director
Submission of Folder to DPRM for issuance of implementing orders
START
END
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
52
1.10.7. SERVICE STANDARD
Transaction Type Turn Around Time
Average Transaction Time
Submission of Requirements
Evaluation of the Requirements 2 hours
Verification of the Requirements 1 hour
Recommendation of Admin Officer
4 hours
Command Group 3 hours
Approval of the Director 2 hour
Total Average Transaction Time 1 day and 4 hours
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
53
2. BUDGET AND FISCAL OFFICE
2.1. Funding and Procurement of Request from Divisions/Offices
TITLE Procedure No. No. of Pages
Funding/Procurement of Requests from different DICTM Divisions/Offices
2.1 3
INTERFACES DICTM Divisions and Offices
2.1.1. OBJECTIVE
To provide fund for the procurement/purchase of approved request by D,CS for supplies, equipment and other logistics.
2.1.2. REFERENCES
RA 6975 as amended by RA 8551
2.1.3. DEFINITION OF TERMS
2.1.3.1. Funding or financing - is to provide capital (funds), which means money for resources (logistics and personnel) for implementation of project, activity or program.
2.1.4. REQUIREMENTS
2.14.1. Submitted request by DICTM Division and Offices 2.1.4.2. Approval of TDICTM 2.1.4.3. Available source of funding 2.1.4.4. Implementation of project 2.1.4.5. Conduct of an activity based on given scheduled program
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
54
Coordinate / Validate with concerned Divisions/Offices
re Request
For Procurement/ Implementation
Forward to SAO For Recording
Memo Request for Funding/Procurement
(From Different Divisions/Offices)
For Recommendation
For Approval / Notation
of TDICTM
2.1.5. FLOWCHART
START
END
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
55
2.1.6. NARRATIVE
2.1.6.1. Memo request for funding and procurement from different DICTM Division and Office for the purchase of supplies, equipment and other resources for the conduct of their respective tasks. Other purpose of request is with regards to the implementation of specific project or for the conduct of particular activity/program.
2.1.6.2. Validate request based on the requirement of the division and on their monthly-required supplies. Validation includes reference on signed or approved implementation of project. Other aspect of validation includes programmed/scheduled activity of the directorate.
2.1.6.3. Creation of memo for recommendation or comment for the said request. 2.1.6.4. For approval/notation or disapproval of TDICTM. 2.1.6.5. Upon approval, program for procurement requested resources based on
available funds. 2.1.6.6. Forward to SAO procured resources for recording/inventory purpose
and subsequent release of said resources to the requesting division/office.
2.1.7. SERVICE STANDARDS
Transaction Type Turn Around Time
Average Transaction Time
Receipt of request for funds 1 day
Coordination/validation of the fund requirement
1 day
Recommendation/Comment to TDICTM 1 days
Approval/Notation of TDICTM 1 day
Total Average Transaction Time 4 days
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
56
3. PLANS AND PROGRAMS DIVISION
3.1 Formulation of Plans, Programs and Activities of DICTM
TITLE Procedure No. No. of Pages
Formulation of Plans, Programs and Activities of DICTM
3.1 3
INTERFACES DICTM PPD and other PNP Offices
3.1.1 OBJECTIVE:
3.1.1.1 To create action plans, programs and activities pertaining to
Information and Communications Technology which will serve as guidelines for the DICTM and all its units.
3.1.2 REFERENCES
3.1.2.1 Activation of DICTM pursuant to NHQ-PNP General Orders Number DPL-09-08 dated April 1, 2009.
3.1.2.2 PNP Information Systems Strategic Plan 3.1.2.3 PNP Telecommunications System Strategic Plan
3.1.3 DEFINITION OF TERMS
3.1.3.1 Plan – is typically any procedure used to achieve an objective. It is a set of intended actions through which one expects to achieve a goal
3.1.3.2 Program – are plans or schedules to be followed. Programs comprise goals, policies, procedures, rules, tasks, assignments, steps to be taken, resources to be used, and other mediums necessary to carry out a given course of action supported by budgets. A program maybe a minor one formulated by a single supervisor to improve the morale of personnel in the DICTM.
3.1.3.3 Project - is a temporary endeavor undertaken to create a unique product or service. A project usually needs resources to deliver its results. Most of the time project execution is based on detailed plan, which considers also external factors and constraints. Planning, execution and controlling of project is the primary field of project management.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
57
3.1.4 REQUIREMENTS
3.1.4.1 Specific activity based on the DICTM annual schedule of activities. 3.1.4.2 Specific conduct of activity based on the specific function of the
DICTM
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
58
3.1.5 FLOW CHART
START
END
Route the report for review, comments and suggestions
(To: EX-O,DDICTM)
Approval and signature (TDICTM)
Team Building on the creation of plans, programs, projects of DICTM Divisions,
ITMS & CES
Consolidation and finalization on the outcome of the summit
(Plans & Programs Division)
Implementation of the Plan (DICTM Divisions)
Monitoring of compliance (Command Group)
Dissemination of memo to all divisions/offices re formulation of action
plan, programs and activities
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
59
3.1.6 NARRATIVE
3.1.6.1 The Plans and Programs Division shall formulate plans, programs and activities for the Directorate for Information and Communications Technology Management which will act as guidelines for all DICTM units/divisions.
3.1.6.2 The ADMO shall schedule a seminar/workshop for the formulation of plans, programs and activities to be participated in by all DICTM Staff, Chief Plans of ITMS and CES.
3.1.6.3 The output of the workshop shall be consolidated by the Plans and Programs Division.
3.1.6.4 Route of the draft plan to the DICTM Command Group for review, comments and suggestions. Subsequently, revision to finalize the plan.
3.1.6.5 Approval of TDICTM 3.1.6.6 Implementation of the plan by all divisions/offices. 3.1.6.7 Monitoring of the implementation of the plan.
3.1.7 SERVICE STANDARDS
Transaction Type
Turn Around Time
Average Transaction
Time
Dissemination to all divisions/offices re formulation of plans of DICTM
1 day
Team Building on the creation of plans, programs, projects of DICTM Divisions, ITMS & CES
2 days
Consolidation and finalization on the outcome of the summit
5 days
For Review, Comments and approval and dispatch (routing of document)
3 days
Approval and Signature of the Action Plan by TDICTM
1 day
Implementation of the plan Period of the
activity
Monitoring of the implementation Period of the
activity
Total Average Transaction Time
12 days – excluding the
period of implementation
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
60
3.2 Field Inspection at Police Regional Offices
TITLE Procedure No. No. of Pages
Field Inspection at Police Regional Offices
3.2 3
INTERFACES DICTM PPD and other PNP Offices
3.2.1 OBJECTIVE
3.2.1.1 To evaluate the viability of PNP ICT projects that would suit the various needs for ICT services in the different PNP Regional sites;
3.2.2 REFERENCES
3.2.2.1 Activation of DICTM pursuant to NHQ-PNP General Orders Number DPL-09-08 dated April 1, 2009.
3.2.2.2 PNP ITP Action Plan for 2009, Integration of Operational and Administrative database of the PNP.
3.2.2.3 Verbal Instruction of C, PNP to standardize the PNP policies, programs, and projects pertaining to ICT.
3.2.2.4 Verbal Instruction of the C, PNP to integrate the operational and administrative database of the PNP.
3.2.2.5 Memorandum Update on Leaders Q and ICT Capability of PNP Field Units from D, ITMS dated May 13, 2009.
3.2.3 DEFINITION OF TERMS
3.2.3.1 Inspection - is, most generally, an organized examination or
formal evaluation exercise. It involves the measurements, tests, and gauges applied to certain characteristics in regard to an object or activity. The results are usually compared to specified requirements and standards for determining whether the item or activity is in line with these targets.
3.2.3.2 Information Systems (IS) - is the system of persons, data records and activities that process the data and information in a given organization, including manual processes or automated processes.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
61
3.2.3.3 Information Technology (IT) - is "the study, design, development, implementation, support or management of computer-based information systems, particularly software applications and computer hardware."
3.2.3.4 Information Communications Technology (ICT) - is the broader term of IT to explicitly include the field of electronic communications.
3.2.4 REQUIREMENTS
3. 2.4.1 Approved IMPLAN regarding Field Visitations to Police Regional
Offices
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
62
3.2.5 FLOW CHART
START
Designate Tasks
Courtesy call to host RD
Conference Creation of IMPLAN re Field Visitation at
PROs
Coordinate with the host PROs
Prepare Tools/Materials
Jump off
Conduct of Inspection re ICT capability of
the PROs
Render After Activity Report
END
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
63
3.2.6 NARRATIVE
3.2.6.1 The Plans and Programs Division shall prepare an IMPLAN regarding the scheduled visit of DICTM to the PRO.
3.2.6.2 Designation of Tasks. Once the IMPLAN is approved, C,PPD DICTM, C, Plans of CES and C, WSCSD shall prepare their respective reports/briefing manuals.
3.2.6.3 C, Plans of CES and C, WSCSD shall prepare their respective reports/briefing manuals.
3.2.6.4 The ADMO, DICTM shall coordinate with the host PRO for the scheduled visit of the DICTM. C, Budget/Finance shall provide transportation and lodging allowances for the visiting DICTM staff.
3.2.6.5 Upon arrival to the PRO, DICTM staff shall render a courtesy call to the host Regional Director.
3.2.6.6 A conference will be held after the courtesy call. 3.2.6.7 An inspection of the ICT capabilities of the PRO’s will follow to
assess further needs of the Police Regional Office. 3.2.6.8 An after activity report signed by the TDICTM will be made and
passed to C,PNP. 3.2.7 SERVICE STANDARDS
Transaction Type
Turn Around Time
Average Transaction
Time
Creation of IMPLAN re Field Visitation at PROs
1 day
Tasks Designation 1day
Tools/Materials Preparation 1day
Coordination with the host PROs 1 day
Call to host RD, Conference, Conduct of Inspection re ICT capability of the PRO
1-2 days
Render After Activity Report 1 day
Total Average Transaction Time 7 – 8 days
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
64
3.3 Formulates policies in support to PNP thrust on ICT development.
TITLE Procedure No. No. of Pages
Formulates policies in support to PNP thrust on ICT development
3.3 3
INTERFACES DICTM PPD and other PNP Offices
3.3.1 OBJECTIVE
3.3.1.1 To make a policy or review existing policies that are geared towards the enhancement of ICT in the Philippine National Police.
3.3.2 REFERENCES
3.3.2.1 Activation of DICTM pursuant to NHQ-PNP General Orders Number DPL-09-08 dated April 1, 2009.
3.3.2.2 Powers and Functions of DICTM
3.3.3 DEFINITION OF TERMS
3.3.3.1 Plan – is a proposed or intended method of getting from one set of circumstances to another. They are often used to move from the present situation, towards the achievement of one or more objectives or goals.
3.3.3.2 Policy - A specific decision or set of decisions designed to carry out such a course of action
3.3.3. REQUIREMENTS
3.3.3.1 Issues and concerns that need policies
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
65
3.3.4 FLOW CHART
3.3.5 NARRATIVE
START
END
Chief PPD shall develop or revise a
proposed policy regarding a particular issue and concern
Routes the initial proposed policy to D-Staff and Command Group for review, comment and suggestion
(Plans Office)
Disseminate the policy for implementation
(Admin Office/Plans Office)
Implementation Phase
Monitoring of the implementation Check for existing policies for
redundancy
Identify the policy need
Finalizes/revises the policy and prepare recommendation of TDICTM
for final approval of CPNP (Plans Office)
Approval and signature of CPNP
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
66
3.3.5 NARRATIVE 3.3.5.1 Plans and Programs Division of DICTM shall identify issues that
need policies 3.3.5.2 Check for existing policies and procedures to research policy
context and to avoid redundancy and possible conflicts 3.3.5.3 Plans and Programs Division shall develop a new policy or revise
existing policy. PPD shall look for references, state the purpose of the policy, define the terms and state/explain the procedures and guidelines of the policy.
3.3.5.4 Route the initial draft to D-staff and Command Group for review, comments and suggestions to be spearheaded by Plans and Program Division
3.3.5.5 PPD will finalize the revised policy based on the suggestions by D-Staff
3.3.5.6 The final draft will be submitted to CPNP for approval upon recommendation of TDICTM.
3.3.5.7 Policy will then be disseminated to the lateral lower units for implementation.
3.3.5.8 DICTM will monitor the effectiveness of the new policy used by different PNP offices
3.3.6 SERVICE STANDARDS
Transaction Type
Turn Around Time
Average Transaction
Time
Identify the policy need 1 day
Check for existing policies for redundancy 2 days
Chief PPD shall develop or revise a policy 3 days
Route the initial policy to D-staff for review, comments and suggestions
3 days
Finalizes/revises the policy 1 day
Recommendation of TDICTM to CPNP for approval
1 day
Approval and Signature of CPNP 3 days
Disseminate the policy for the implementation
Period of the activity
Monitoring of the implementation Period of the activity
Total Average Transaction Time 14 days – excluding
the period of implementation
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
67
3.4 Review and Updates of existing PNP Information Systems Strategic Plan
3.4.1 OBJECTIVE
3.4.1.1 To create, revise and update the Philippine National Police Information Systems Strategic Plan (ISSP) which is the general and overall Information Systems plan of the PNP covering five (5) years.
3.4.2 REFERENCES 3.4.2.1 Memorandum Circular No. 93-3 prescribing the guidelines for
Information Systems planning for the government. 3.4.2.1Output of ISSP Technical Working Group
3.4.3 DEFINITION OF TERMS
3.4.3.1 Information Systems Strategic Plan (ISSP) – Overall plan for the development and implementation of Information Systems supportive of organizational mission/objectives and the corresponding resources requirements over a five-year period.
3.4.3.2 Information Systems (IS) - is the system of persons, data records and activities that process the data and information in a given organization, including manual processes or automated processes.
3.4.3.3 Information Technology (IT) - is "the study, design, development, implementation, support or management of computer-based information systems, particularly software applications and computer hardware."
3.4.3.4 Information Communications Technology (ICT) - is the broader term of IT to explicitly include the field of electronic communications.
3.4.4 REQUIREMENTS
3.4.4.1 Submitted ICT plans from different PNP offices 3.4.4.2 Submitted ICT resources from different PNP offices. 3.4.4.3 Existing ICT systems being used by different PNP offices for
update/upgrade and revision.
TITLE Procedure No. No. of Pages
Review and Updates of existing PNP Information Systems Strategic Plan
3.4 3
INTERFACES DICTM PPD and other PNP Offices
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
68
3.4.5 FLOW CHART
3.4.6 NARRATIVE
START
Monitoring of ISSP -- Implementation and status of the projects
(ISSP Monitoring Team)
Revision of the initial draft based on the TWG review outputs
(Plans & Programs Division)
Review of the ISSP initial draft by the Technical Working Group (TWG)
(Technical Working Group)
Approval of NCC and submission of the ISSP to
the DBM for funding
Revision of the ISSP regarding outputs/ comments of the NCC and submission back to
NCC – ( Plans & Program Division)
Review of existing Information Systems Strategic Plan
(Plans & Programs Division)
Submission of ISSP to the TWG for final review before endorsement of TDICTM
(Plans & Programs Division)
Creation of Technical Working Committee/Group (DICTM, CES, ITMS)
Research and consolidation of technical details/contents of the ISSP
(Research & Development Division) DEVELOPMENT DIVISION
)
Consolidation of information re different IS being used by the PNP
(Systems Integration & Management Division)
Consolidation of other information that will be included in the ISSP
(Plans & Programs Division)
ISSP Submission to the OCPNP ~ Route through the Command Group for
information/comment (Cc: DPL)
Endorsement by TDICTM for signature of the
Chief, PNP
Review and Evaluation of the ISSP
(NCC)
ISSP Submission to National Computer Center
for review and evaluation - Signed by C, PNP
Encoding, proofreading and finalization of the ISSP as Initial Draft for Review
(Plans & Programs Division)
Consolidation of inventory of all PNP ICT resources
(Plans & Programs Division)
Funding of the ISSP - Release of GAA Appropriation/Fund
Allocation/NCA
END
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
69
3.4.6.1 DICTM creates a Technical Working Committee/Group for the
drafting/update/revision of the PNP ISSP. The Plans and Programs Division shall be the secretariat of the committee and shall initiate the review process.
3.4.6.2 The Systems Integration and Management Division shall be charged for the consolidation of information/description of different IS being used by the PNP. The SIMD is also tasked to evaluate and review PNP offices requirements with regard to the IS needs.
3.4.6.3 Research and Development Division shall research and consolidate technical details/contents of the ISP.
3.4.6.4 Inputs and other information from other PNP offices and DICTM divisions shall be consolidated by the Plans and Programs Division.
3.4.6.5 Inventory of ICT resources from all PNP offices shall also be consolidated by the Plans and Programs Division.
3.4.6.6 After consolidation, Plans and Programs Division shall encode revision, proofread the revised ISSP as an initial draft for further review.
3.4.6.7 The Technical Working Group (TWG) shall review the initial draft and report all updates to the Plans and Programs Division for editing.
3.4.6.8 Plans and Programs Division shall revise/edit the initial draft based on the outputs of the TWG.
3.4.6.9 Plans and Programs Division shall then submit the ISSP to the TWG for final review before endorsement to TDICTM for signature and forwarding to the higher office.
3.4.6.10 Upon approval of the ISSP by the TWG it shall be routed to the command group for information and comments/suggestions.
3.4.6.11 Upon approval and signature of the ISSP by the TDICTM, it shall be forwarded to the Office of the Chief Philippine National Police (OCPNP).
3.4.6.12 Upon approval and signature of the ISSP by the C,PNP, it shall be submitted to the National Computer Center (NCC) for review and evaluation.
3.4.6.13 The PNP ISSP shall be evaluated and reviewed by NCC. Upon review, comments and inputs of NCC shall be reviewed by the TWG and Plans and Programs Division shall make corresponding revision to the ISSP.
3.4.6.14 It shall be submitted back to the NCC for further review, evaluation and subsequent, approval.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
70
3.4.6.15 Upon approval of the PNP ISSP by the NCC, it shall be forwarded to the DBM for further confirmation and funding - GAA appropriation/fund allocation/NCA.
3.4.6.16 The approved PNP ISSP shall be forwarded back to the PNP and to the DICTM for implementation. DICTM shall then form a monitoring team that shall monitor in the implementation and status of projects programmed/planned in the ISSP.
3.4.7 SERVICE STANDARDS
Transaction Type Turn Around Time
Average Transaction Time
Creation of Technical Working Group 1 day
Consolidation of IS by SIMD 1 month
Consolidation of other information and inputs from other divisions by PPD
1 month
Consolidation of inventory of all PNP ICT resources
1 month
Editing and proofreading of the ISSP by PPD
1 month
Review of the TWG 2 weeks
Revision based on the TWG outputs by PPPD
2 weeks
Submission to TWG and final review 2 weeks
Routing of the ISSP to the Command Group and Endorsement of TDCITM
2 weeks
ISSP submission to the OCPNP and endorsement to NCC
2 weeks
ISSP submission to the NCC 1 day
Review and evaluation of the ISSP by the NCC
1 month
Review and revision of the ISSP by the TWG and PPD
1 month
Submission to the NCC for further review and evaluation, and approval
1 month
Submission to the DBM of the approved PNP ISSP
2 weeks
Funding by the DBM – Appropriation of funds
2 months
Total Average Transaction Time 1 year
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
71
3.5 Evaluation of Project Proposal
TITLE Procedure No. No. of Pages
Approved Project Proposal 3.5 3
INTERFACES DICTM PPD and other PNP Offices
3.5.1 OBJECTIVE
Provides support for the development of projects, in accordance with the approved priority areas, for local and foreign funding.
3.5.2 REFERENCES
3.5.2.1 RA 6975 as amended by RA 8551 3.5.2.2 PNP Computerization/ISSP
3.5.3 DEFINITION OF TERMS
3.5.3.1 Project – a research or design, that is carefully planned to achieve a particular aim, reaching of which is considered necessary for the achievement of planned benefits.
3.5.3.2 Project Management - is the discipline of planning, organizing, and managing resources to bring about the successful completion of specific project goals and objectives
3.5.3.3 Proponent – a person who puts forward a proposition or proposal.
3.5.3.4 Project Preparation – consists of the entire social, technical and financial work required to ensure that a project is feasible and can be successfully and appropriately implemented. The process ensures the identification and elimination of key risks at the earliest possible time and maximizes development opportunities.
3.5.3.5 Project Identification – is a repeatable process for documenting, validating, ranking and approving candidate projects within an organization.
3.5.3.6 Proposal Evaluation – is an assessment of the proposal and the proponent ability to perform the prospective contract successfully (according to technical feasibility, administrative / managerial capability, acceptability and other prescribed criteria).
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
72
3.5.4 REQUIREMENTS 3.5.4.1 Memorandum/HWI or routine slip from Higher Office 3.5.4.2 Proponent Project Proposal and the Proponent Company
profile.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
73
3.5.5 Flowchart
DICTM Admin
ADMO courses the final project proposal to TDICTM
END
START
Project Management Section, PPD reviews project preparation, project identification, proposal evaluation
Memorandum/HWI/Routine Slip from NHQ
ITMS/CES review and recommendation of the
approved project
Consolidation of ITMS/CES after activity report
Project Management Section, PPD makes final
recommendation and after activity report for signature of
TDICTM for C, PNP’s information and reference
Proponent’s assessment of the proposal and their ability to
perform the prospective contract successfully.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
74
3.5.6 NARRATIVE
3.5.6.1 Received Memorandum/HWI or routine slip from higher office to DICTM admin office regarding the approved project proposal.
3.5.6.2 Reviews the project proposal, the initial budget proposal, the technical aspect, resources, the timeline of the project and the risk management.
3.5.6.3 Proponent’s assessment of the proposal and their ability to perform the prospective contract successfully.
3.5.6.4 Forward the project proposal to ITMS/CES for review and recommendation.
3.5.6.5 Consolidation of the after activity report from ITMS/CES. 3.5.6.6 A final recommendation and after activity report for signature of
TDICTM for C, PNP’s information and reference.
3.5.7 SERVICE STANDARDS
Transaction Type Turn Around Time
Average Transaction Time
Receipt of memo/HWI or routine slip from NHQ
1 day
Review of the project proposal, identifying all risk, assessment of the proponent ability and prospective
2 weeks
Endorsement letter and project proposal to ITMS/CES for review and recommendation
1 days
Consolidation of the after activity report from ITMS/CES
1 day
Final recommendation and after activity report for signature of TDICTM for C, PNP’s information and reference
1 day
Total Average Transaction Time 18 days
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
75
3.6 Formulation of plan for monitoring and evaluation of ICT projects for the PNP.
3.6.1 OBJECTIVE - Creation of plans for monitoring and evaluation of
Information and Communications Technology Projects of the PNP.
3.6.2 REFERENCES 3.6.2.1 Activation of DICTM dated April 1, 2009 3.6.2.2 Functions of the Monitoring and Evaluation Section (MES),
Plans and Programs Division, DICTM.
3.6.3 DEFINITION OF TERMS 3.6.3.1 Plans – specifically refers to the plans for monitoring and
evaluation of the different ICT projects of the PNP. 3.6.3.2 Project Monitoring – (see definitions) 3.6.3.3 Project Evaluation –(see definitions)
3.6.4 REQUIREMENTS
3.6.4.1 Directives/Policies/Guidelines 3.6.4.2 Project Plan/Proposal
TITLE PROCEDURE NO. No. of Pages
Formulation of Plan for Monitoring and Evaluation of ICT Projects
3.6
3
INTERFACES DICTM, ITMS, CES
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
76
3.6.5 FLOWCHART
Start
Receipt of Project Activity Report (PPD, DICTM)
Evaluation of Reports (MES,PPD)
Review of the project plan, related policies, timeline, costing, etc.
of the project (MES)
Formulation of Action/Implementation Plan for monitoring and evaluation of the project
(MES)
Choose appropriate monitoring tool/system for the project. Design
one if needed. (MES)
Route/Request for comment/approval
of the plan (DICTM Staff)
YES COMMENT
NO Approval of the Plan for
Monitoring and Evaluation of the Project
(TDICTM)
End
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
77
3.6.6 NARRATIVE 3.6.6.1 Reports on ICT projects are submitted to/received by the PPD,
DICTM. 3.6.6.2 Project activity reports are evaluated by the MES, PPD, DICTM 3.6.6.3 The MES, PPD reviews project plans, polices, timelines, costing
and other pertinent matters relevant to the project. 3.6.6.4 The MES chooses the appropriate monitoring and evaluation
tools/system that have already been proven effective elsewhere or designs a new one, if needed.
3.6.6.5 The MES formulates appropriate Plan for Monitoring and Evaluation of the Project and submits them to the Chief, PPD.
3.6.6.6 The PPD routes the formulated plan for comment of the DICTM Staff.
3.6.6.7 When there are comments, there might be a need to go back to earlier processes of evaluation, review, amendment or reformulation of plan, go back then to whichever process is required, reroute until comments/suggestions are satisfied.
3.6.6.8 When there is no comment, proceed to the next process. 3.6.6.9 Submit the formulated plan for approval of the TDICTM.
3.6.7 PLAN FORMULATION STANDARD
TURN-AROUND TIME
Average Period for the Formulation of Plan for
Monitoring and Evaluation of ICT
Projects.
Receipt of the Activity Report 1 day
Evaluation of Project Reports 1 day
Review of the plan, polices, etc. 1 day
Choose/Design monitoring tools 1 day
Formulation of plan 2 days
Request for comment 1 day
Approval of the plan 1 hour
Total Average Period 7 days and 1 hour
When there is comment, allow time to reprocess accordingly
6 days
Total Average Period when reprocessing is done 13 days and 1 hour
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
78
3.7 Implementation of plan for monitoring and evaluation of plan for ICT projects of the PNP.
3.7.1 OBJECTIVE - To see that effective procedures are put in place to ensure
the optimum use of PNP resources and to enable realization of priority projects on time.
3.7.2 REFERENCES
3.7.2.1 Directives/Policies/Guidelines; 3.7.2.2 Functions of the Monitoring and Evaluation Section (MES), Plans
and Programs Division, DICTM. 3.7.2.3 Action Plan/Monitoring Tools and Systems; and 3.7.2.4 Plan for Monitoring and Evaluation of ICT Project
3.7.3 DEFINITION OF TERMS
3.7.3.1 Action Plan (see definitions) 3.7.3.2 Project Monitoring Tools (see definitions)
3.7.4 REQUIREMENTS
3.7.4.1 Directives/Policies/Guidelines 3.7.4.2 Approved Plan for Monitoring & Evaluation of ICT Projects
TITLE PROCEDURE NO. No. of Pages
Implementation of Plan for Monitoring and Evaluation of Plan of ICT Projects
3.7
3
INTERFACES DICTM, ITMS, CES , POs, PMEOs,
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
79
3.7.5 FLOWCHART Start
End
Preparation of directive for implementation
(MES, PPD)
Delegation/Tasking of responsibilities
(Project Monitoring and Evaluation Officer/s)
Dissemination of directives/Coordination with Project Officer/s (POs, DICTM, ITMS,
CES & other PNP Units)
Documentation of the Findings
(Project Monitoring & Evaluation Officer/s)
Submission of Project Monitoring and Eval. Report to the C, MES (Project Monitoring & Evaluation Officer/s)
Evaluation of the achievements using
performance indicators/ appropriate monitoring
systems (PMEOs)
Evaluation, preparation and submission of
report and recommend-dations to the C, PPD and TDICTM (MES)
(C, MES)
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
80
3.7.6 NARRATIVE 3.7.6.1 Directives for the implementation of the Plan for Monitoring and
Evaluation of ICT project is prepared by the MES, DICTM
3.7.6.2 Tasking and responsibilities are delegated to the Project
Monitoring and Evaluation Officers of the DICTM.
3.7.6.3 Directives are disseminated and coordination is conducted with
PNP Units/Personnel involved in the project.
3.7.6.4 The Project Monitoring and Evaluation Officers (PMEO)
establishes the project activity and performance tracking using
key performance indicator systems and other operational
measures.
3.7.6.5 The PMEOs documents the related findings to support report to
the C, MES.
3.7.6.6 The Chief, MES evaluates the findings, draws recommendations
and submit them to the Chief, PPD for further evaluation.
3.7.6.7 The Chief, MES evaluates the reports submitted by the PMEOs
then prepares/submit related report and recommendations for the
information/ signature of the Chief, PPD for the information of
TDICTM.
3.7.7 PLAN IMPLEMENTATION STANDARD
TURN-AROUND TIME
Average Period
for the Implementation
of Plan for Monitoring and Evaluation of ICT Projects.
Preparation of directives for implementation of plan.
2 hours
Delegation/Tasking of responsibilities to PMOEs
1 hour
Dissemination of Directives/ Coordination with PNP Units/ Personnel involved in the project.
2 days
Evaluation of the achievements of the project objectives.
1 day
Documentation of the findings 1 day
Submission of report to the C, MES 2 hours
Evaluation, submission of report/ recommendations to the C, PPD and TDICTM
1 day
Total Average Period 5 days and 5 hours
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
81
3.8 Evaluation of Plan for Monitoring of ICT Project
3.8.1 OBJECTIVES
3.8.1.1 To develop the findings and recommendations made by the
PMEOs/MES regarding resource management, practices and the requirements of the project specialists;
3.8.1.2 To develop/improve monitoring and evaluation methods; and 3.8.1.3 To document lessons, experience and management/operational
issues relative to project implementation.
3.8.2 REFERENCES 3.8.2.1 Directives/Policies/Guidelines;
3.8.3 DEFINITION OF TERMS
3.8.3.1 Resource Management – is the efficient and effective deployment
for an organization's resources when they are needed. Such resources may include financial resources, inventory, human skills, production resources, or information technology (IT).
3.8.3.2 IT Governance Practices – The Responsible Management of IT resources, including mitigation of risks, in order to realize the value of IT investments.
3.8.4 REQUIREMENTS
3.8.4.1 Monitoring and Evaluation Tools and Systems; 3.8.4.2 Plan for Monitoring and Evaluation of ICT Project; and 3.8.4.3 Project Monitoring and Evaluation Reports and related
documents.
TITLE PROCEDURE NO. No. of Pages
Evaluation of Plan for Monitoring of ICT Project
3.8
3
INTERFACES DICTM, ITMS, CES
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
82
3.8.5 FLOWCHART
Legend : MES – Monitoring and Evaluation Section PMEO – Project Monitoring and Evaluation Officer
Receipt of Monitoring & Evaluation Reports from the
PMEOs (MES, PPD)
Evaluation of Reports and documents relative to the Monitoring & Eval. Plan
implemented (MES)
Evaluation of the effectiveness of the plan and the mechanisms used for monitoring
and evaluation of the project. (MES)
Review of existing Monitoring tools and systems.
(MES)
Preparation of Proposal for the improvement of Project
Monitoring and Evaluation mechanisms
(MES)
Submission of Proposal to the C, PPD
(MES)
Route for comment/ recommendations of the
DICTM Staff (PPD)
Approval of the Recommendation/ Proposal (TDICTM)
Needs Improvement
COMMENT
Submission of Recommendation (PPD)
YES
NO
NO
YES
END
START
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
83
3.8.6 NARRATIVE 3.8.6.1 The MES, PPD receives monitoring and evaluation reports from
the Project Monitoring Officers.
3.8.6.2 The MES evaluates the monitoring and evaluation reports
relative to the monitoring and evaluation plan.
3.8.6.3 The MES reviews existing monitoring tools/systems to ensure
that the best monitoring and evaluation mechanism applies to
the plan.
3.8.6.4 The need for improvement is determined by the MES, PPD
3.8.6.5 When there is no need for improvement of the plan, the MES
submits recommendation/proposal to the Chief, PPD
3.8.6.6 The PPD routes the recommendation for comment of the
DICTM Staff, then forwards to the TDICTM for final approval.
3.8.6.7 When a need for improvement is deemed necessary, the MES
prepares recommendation/proposal.
3.8.6.8 The MES then submits proposal to the C, PPD.
3.8.6.9 The PPD routes the proposal for comments/recommendations
of the DICTM Staff.
3.8.6.10 3.6.5. When there is comment from the DICTM Staff, the PPD
returns to previous processes until it reaches the office of
TDICTM for final approval.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
84
3.8.7 Evaluation of Plan for Monitoring Standard
TURN-AROUND TIME
Average Period for the Evaluation of Plan for Monitoring and Evaluation of ICT Projects.
Receipt of Monitoring Report 1 day
Evaluation of Report 1 day
Review of existing monitoring tools 1 day
Evaluation of the Effectiveness of The Plan & Monitoring mechanism
2 days
Preparation, submission of Recommendation
1 day
Approval of the Recommendation 1 hour
Total Average Period when no improvement is recommended
6 days and 1 hour
Preparation of Proposal when improvement is needed 2 days
Submission of proposal to the C, PPD 1 hour
Request for comments 1 day
When there is no comment, submit for approval 1 hour
When there is comment, allow time to process accordingly 4 days and 1 hour
Total Average Period when improvement is proposed 11 days and 2 hrs.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
85
3.9 Formulation of project and activities consonant to project monitoring and evaluation of ICT projects of the PNP.
3.9.1 OBJECTIVE
3.9.1.1 To monitor the effectiveness of the project, its plan and the
mechanisms/ tools being utilized for reviewing and maintaining project development strategies.
3.9.1.2 Use of performance indicators and other effective monitoring tools/systems based on progress and output; and
3.9.1.3 Review and maintain project strategies to ensure that it meets the requirements of all stakeholders and that it is adjusted to reflect the changing priorities of time and external events.
3.9.2 REFERENCES
3.9.2.1 Directives/Policies/Guidelines; 3.9.2.2 Functions of the Monitoring and Evaluation Section (MES), Plans
and Programs Division, DICTM; and 3.9.2.3 Existing Monitoring Mechanism/s
3.9.3 DEFINITION OF TERMS 3.8.3.1 Evaluation Mechanism – is a toolkit of evaluation methodologies and specific techniques to facilitate the decision-making process in deriving an evaluation plan appropriate to the project and needs of the evaluation.
3.9.4 REQUIREMENTS 3.9.4.1 Project Monitoring and Evaluation Tools and Systems; 3.9.4.2 Project Monitoring and Evaluation Plan; and 3.9.4.3 Project Implementation Plan
TITLE PROCEDURE NO. No. of Pages
Formulation of Projects and Activities consonant to Project Monitoring and Evaluation of ICT Projects of the PNP
3.9
3
INTERFACES DICTM, ITMS, CES
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
86
3.9.5 FLOWCHART
Start
COMMENT
Approval of the Proposal for Project and Activity
(TDICTM)
End
Receipt of the Directives and Requirements
(PPD)
Evaluation of the Requirements (MES, PPD)
Adopt/Design/Formulate monitoring and
evaluation mechanism/s for particular project/s
(MES, PPD)
Prepare Proposal for Project/Activity
(MES,PPD)
Route/Proposal for Comments/
Recommendations Of DICTM Staff
YES
Route for comment/ approval of the D-Staff
NO
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
87
3.9.6 NARRATIVE
3.9.6.1 Requirements in the formulation of Projects Monitoring and
Activities are forwarded to/received by the PPD from PMEOs
and PNP Units.
3.9.6.2 Requirements are thoroughly evaluated by the MES, PPD.
3.9.6.3 The MES decides to adopt monitoring and evaluation
mechanism that is most suitable for the particular project or may
opt to design/formulate one if necessary.
3.9.6.4 The PPD then prepares a proposal for the Project/Activity for
the monitoring and evaluation of the project and routes it for
comments and recommendations of the DICTM Staff.
3.9.6.5 When the DICTM Staff approves of the proposal, it is then
forwarded to the office of the TDICTM for approval.
3.9.6.6 The proposal is then forwarded to the D-Staff for comment/
recommendations/ approval.
3.9.7 MONITORING PROJECT AND ACTIVITY FORMULATION STANDARD
TURN-AROUND TIME
Average Period for the Formulation of Projects and Activities consonant to Project Monitoring and Evaluation of ICT Projects of the PNP
Receipt of requirements and directives
1 day
Evaluation of the requirements 1 day
Formulation of Monitoring and Evaluation mechanism
2 days
Preparation of Proposal for the Project/Activity for monitoring
2 days
Routing of the proposal for comment/ recommendations of the DICTM Staff
1 day
When there is no comment, submit to TDICTM for approval
2 hours
Total Average Period 7 days and 2 hours
When there is comment allow time to reprocess accordingly 6 days
Total Average Period when reprocessing is done. 13 days and 2 hours
The average period when routed for comment of the D-Staff is not included.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
88
3.10 Submission of reports of the output of monitoring and evaluation of ICT projects of the PNP.
3.10.1 OBJECTIVE
3.10.1.1 To document and disseminate lessons, experiences and
management/operational issues relative to project implementation.
3.10.2 REFERENCES
3.10.2.1 Directives/Policies/Guidelines; 3.10.2.2 Action Plan/Monitoring Tools and Systems; 3.10.2.3 Plan for Monitoring and Evaluation of ICT Project; and 3.10.2.4 Functions of the Monitoring and Evaluation Section (MES), Plans
and Programs Division, DICTM.
3.10.3 DEFINITION OF TERMS
3.10.4 REQUIREMENTS
3.10.4.1. Directives/Policies/Guidelines 3.10.4.2 Reports /Documents gathered /submitted by PMEOs
TITLE PROCEDURE NO. No. of Pages
Submission of Reports of the Output of Monitoring and Evaluation of ICT projects.
3.10
3
INTERFACES DICTM, ITMS, CES
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
89
3.10.5 FLOWCHART Start
Receipt of monitoring and evaluation reports
from PMEOs (PPD)
Exploitation of knowledge, experiences, lessons from the report
(MES)
Evaluation of the reports and related documents
(MES)
Preparation of report of the Output of Monitoring
Activities (PPD)
Dissemination of information to all concerned units
(Mssg Ctr.)
End
Submission of report to TDICTM
(PPD)
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
90
3.10.6 NARRATIVE 3.10.6.1 The PPD receives Monitoring and Evaluation Reports of ICT
Projects from the PMEOs.
3.10.6.2 The MES evaluates the reports and related documents.
3.10.6.3 The MES analyses the documents to gather lessons, knowledge,
experiences and adjustments that could be used to other ICT
projects.
3.10.6.4 The MES, PPD prepares report of the output of monitoring and
evaluation activities.
3.10.6.5 The PPD submits report for the information of the TDICTM.
3.10.6.6 The DICTM through its Message Center disseminates reports to
all concerned units.
3.10.7 OUTPUT REPORTING STANDARD
TURN-AROUND TIME
Average period for the Submission of Reports of the Output of Monitoring and Evaluation of ICT projects.
Receipt of Monitoring and Evaluation Report
1 day
Evaluation of the reports, documents 1 day
Exploitation of knowledge 1 day
Preparation of report of the output 6 hours
Submission of report 2 hours
Dissemination of information 2 hours
Total Average Period 3 days and 10 hours
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
91
4. SYSTEM INTEGRATION AND MANAGEMENT DIVISION
4.1 System Integration and Management
TITLE PROCEDURE
NUMBER NUMBER OF
PAGES
System Integration and Management 4.1 4
INTERFACES SIMD-DICTM AND OTHER PNP OFFICES
4.1.1 OBJECTIVE
4.1.1.1 To provide assessment and recommendations on all Information
Systems utilized by the PNP.
4.1.2 REFERENCES
4.1.2.1 Creation of the Directorate for Information and Communications Technology Management (DICTM)
4.1.2.2 PNP Information Systems Strategic Plan (ISSP) 4.1.3 DEFINITION OF TERMS
4.1.3.1 Information Systems Strategic Plan (ISSP) – is an Information
and Communications Technology (ICT) blueprint that supports both the short-term and long-term Information System needs of the PNP that is aligned with its strategic thrust and programs.
4.1.3.2 Policy - a deliberate plan of action to guide decisions and achieve rational outcome(s).
4.1.3.3 System - is a set of interacting or interdependent entities forming an integrated whole.
4.1.3.4 Information System (IS) - a system of people, data records and activities that process the data and information in an organization, and it includes the organization's manual and automated processes. In a narrow sense, the term information system (or computer-based information system) refers to the specific application software that is used to store data records in a computer system and automates some of the information-processing activities of the organization.
4.1.3.5 Information and Communications Technology (ICT) - is an umbrella term that covers all advanced technologies in
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
92
manipulating and communicating information. The term is sometimes used in reference to information technology (IT), particularly in these two communities: education and government. The common usage ICT is synonymous assumed the fact that IT or ICT encompasses all mediums, to record information (magnetic disk/tape, optical disks (CD/DVD), flash memory etc. and arguably also paper records); technology for broadcasting information - radio, television; and technology for communicating through voice and sound or images - microphone, camera, loudspeaker, telephone to cellular phones. It includes the wide varieties of computing hardware (PCs, servers, mainframes, networked storage).
4.1.3.6 System Integration - the process by which smaller pieces of software are brought together to form a larger piece of software that was designed to solve a problem.
4.1.3.7 System Management – is the management of the information technology systems in an enterprise. This includes gathering requirements, purchasing equipment and software, distributing it to where it is to be used, configuring it, maintaining it with enhancement and service updates, setting up problem-handling processes, and determining whether objectives are being met.
4.1.3.8 Information - is a stimulus that has meaning in some context for its receiver. When information is entered into and stored in a computer, it is generally referred to as data. After processing (such as formatting and printing), output data can again be perceived as information.
4.1.4 REQUIREMENTS
4.1.4.1 Consolidated report of all IS developed and maintained by ITMS. 4.1.4.2 Audit of other outsourced IS used by the PNP. 4.1.4.3 Evaluation reports generated from PNP end-users for system
capability and limitation of IS being utilized by their unit.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
93
4.1.5 FLOWCHART
Start
Reviews assessment report received from PNP concerned units on system capability and limitations.
Consolidate reports of all PNP IS.
Submit assessment report and recommendations to ITMS and CES for information and implementation.
Review ITMS plans and programs and system updates for IS (from ITMS and other PNP units maintaining IS).
Prepare assessment report and recommendations.
Finalize and revise the proposed
Monitoring of implementation and
compliance of all PNP offices
(DICTM).
End
Route assessment report and recommendations to TDICTM for approval.
Request feedback upon implementation of the above recommendation.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
94
4.1.6 NARRATIVE
4.1.6.1 Reviews assessment report received from PNP concerned units on system capability and limitations.
4.1.6.2 Consolidate reports of all PNP IS. 4.1.6.3 Review ITMS plans and programs and system updates for IS
(from ITMS and other PNP units maintaining IS). 4.1.6.4 Prepare assessment report and recommendations. 4.1.6.5 Route assessment report and recommendations to TDICTM for
approval. 4.1.6.6 Submit assessment report and recommendations to ITMS and
CES for information and implementation. 4.1.6.7 Request feedback upon implementation of the above
recommendation.
4.1.7 SERVICE STANDARD
Transaction Type Time
System audit and assessment of deployed information systems
3 days
Preparation of guidelines for implementation 2 days
Route draft copy of the proposed circular for comments and suggestions.
3 days
Revision of the circular for approval and signature of TDICTM.
1 day
Route proposed circular to the D-Staff and Command Group for comment.
5 days
Finalization of the circular and approval of CPNP. 1 day
Dissemination of the approved circular for implementation.
1 day
Total Average Transaction Time 16 days
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
95
4.2 Policy Formulation and Updates for the Integration and Management of Information Systems
TITLE PROCEDURE NUMBER NUMBER OF
PAGES
Policy Formulation and Updates for the Integration and Management of Information Systems
4.2 4
INTERFACES SIMD-DICTM AND OTHER PNP OFFICES
4.2.1 OBJECTIVE
4.2.1.1 To provide a procedure in the formulation of policy on the
integration and management of information and telecommunications system. Modification of policy for the integration and management of information system shall contribute to the information systems’’ effectiveness and efficiency as to the needs of the PNP.
4.2.2 REFERENCES
4.2.2.1 Creation of the Directorate for Information and Communications
Technology Management (DICTM) 4.2.2.2 PNP Information Systems Strategic Plan (ISSP)
4.2.3 DEFINITION OF TERMS
4.2.3.1 Information Systems Strategic Plan (ISSP) – is an Information and Communications Technology (ICT) blueprint that supports both the short-term and long-term Information System needs of the PNP that is aligned with its strategic thrust and programs.
4.2.3.2 Policy - a deliberate plan of action to guide decisions and achieve rational outcome(s).
4.2.3.3 System - is a set of interacting or interdependent entities forming an integrated whole.
4.2.3.4 Information System (IS) - a system of people, data records and activities that process the data and information in an organization, and it includes the organization's manual and automated processes. In a narrow sense, the term information system (or computer-based information system) refers to the specific application software that is used to store data records in a
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
96
computer system and automates some of the information-processing activities of the organization.
4.2.3.5 Information and Communications Technology (ICT) - is an umbrella term that covers all advanced technologies in manipulating and communicating information. The term is sometimes used in reference to information technology (IT), particularly in these two communities: education and government. The common usage ICT is synonymous assumed the fact that IT or ICT encompasses all mediums, to record information (magnetic disk/tape, optical disks (CD/DVD), flash memory etc. and arguably also paper records); technology for broadcasting information - radio, television; and technology for communicating through voice and sound or images - microphone, camera, loudspeaker, telephone to cellular phones. It includes the wide varieties of computing hardware (PCs, servers, mainframes, networked storage).
4.2.3.6 System Integration - the process by which smaller pieces of software are brought together to form a larger piece of software that was designed to solve a problem.
4.2.3.7 System Management – is the management of the information technology systems in an enterprise. This includes gathering requirements, purchasing equipment and software, distributing it to where it is to be used, configuring it, maintaining it with enhancement and service updates, setting up problem-handling processes, and determining whether objectives are being met.
4.2.3.8 Information - is a stimulus that has meaning in some context for its receiver. When information is entered into and stored in a computer, it is generally referred to as data. After processing (such as formatting and printing), output data can again be perceived as information.
4.2.4 REQUIREMENTS
4.2.4.1 Situation of subjected PNP Information System. 4.2.4.2 Inventory of ICT resources from the end user / client / IS recipient. 4.2.4.3 Compliance level of the IS recipient.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
97
4.2.5 FLOWCHART
Start
Conduct system audit on the subjected PNP Information System.
Assess and identify deployment status and situation of subjected
PNP IS.
Approval and signature of the cover Memo by TDICTM.
Prepare guidelines on the implementation and management
of the IS in the form of Memorandum Circular.
Routes to DICTM Divisions, ITMS and DICTM Command Group for
comments and suggestions.
Finalize and revise the proposed Memo Circular with cover Memo
(SIMD).
Routes the proposed Memorandum Circular to the Directorate Offices
and PNP Command Group for comment
Re-route the final copy of the proposed memo circular for
approval and signature of the C, PNP.
For widest dissemination.
Monitoring of implementation and compliance of all PNP offices
(DICTM).
End
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
98
4.2.6 NARRATIVE 4.2.6.1 Conducts systems audit on the current situation of the deployed
Information System. 4.2.6.2 Assess and identify the deployment situation of the Information
System and determine problems encountered or technical difficulties during implementation.
4.2.6.3 Prepare guidelines on the implementation and management of the IS in the form of Memorandum Circular (MC) to resolve difficulties and issues encountered by the end user or recipient.
4.2.6.4 SIMD routes the draft copy of the proposed circular to DICTM Divisions, ITMS and DICTM Command Group for review, comments and suggestions.
4.2.6.5 Based on the comments / suggestions, SIMD revises the proposed circular and re-route the final draft copy with cover memo to DICTM Command Group.
4.2.6.6 Signature and approval of the cover Memo by TDICTM. 4.2.6.7 Routes the proposed Memorandum Circular to the Directorate
Offices and PNP Command Group for comment. 4.2.6.8 Based on the comments, DICTM revises and finalizes the
proposed Memorandum Circular and re-route the final copy for approval and signature of the C, PNP.
4.2.6.9 For widest dissemination and guidance of all PNP offices. 4.2.6.10 DICTM shall monitor the implementation and compliance of the
approved Memorandum Circular.
4.2.7 SERVICE STANDARD
Transaction Type Time
System audit and assessment of deployed IS 3 days
Preparation of guidelines for implementation 2 days
Route draft copy of the proposed circular for comments and suggestions.
3 days
Revision of the circular for approval and signature of TDICTM.
1 day
Route proposed circular to the D-Staff and Command Group for comment.
5 days
Finalization of the circular and approval of CPNP. 1 day
Dissemination of the approved circular for implementation. 1 day
Total Average Transaction Time 16 days
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
99
4.3 Evaluation and Supervision of Plans and Programs of ITMS and CES
TITLE PROCEDURE
NUMBER NUMBER OF
PAGES
Evaluation and supervision of Plans and Programs of ITMS and CES
4.3 4
INTERFACES SIMD-DICTM, ITMS AND CES
4.3.1 OBJECTIVE
4.3.1.1 To evaluate and supervise plans and programs set by Information
Technology Management Service (ITMS) and Communications and Electronic Service (CES). It shall assess the effectiveness and efficiency of plans and programs as to the mandated functions of DICTM and the needs of the PNP as well.
4.3.2 REFERENCE
4.3.2.1 Creation of the Directorate for Information and Communications
Technology Management (DICTM) 4.3.2.2 PNP Information Systems Strategic Plan (ISSP) 4.3.2.3 PNP Telecommunications System Strategic Plan (TSSP)
4.3.3 DEFINITION OF TERMS
4.3.3.1 Information Systems Strategic Plan (ISSP) – is an Information
and Communications Technology (ICT) blueprint that supports both the short-term and long-term Information System needs of the PNP that is aligned with its strategic thrust and programs.
4.3.3.2 Policy - a deliberate plan of action to guide decisions and achieve rational outcome(s).
4.3.3.3 System - is a set of interacting or interdependent entities forming an integrated whole.
4.3.3.4 Information System (IS) - a system of people, data records and activities that process the data and information in an organization, and it includes the organization's manual and automated processes. In a narrow sense, the term information system (or computer-based information system) refers to the specific application software that is used to store data records in a computer system and automates some of the information-processing activities of the organization.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
100
4.3.3.5 Information and Communications Technology (ICT) - is an umbrella term that covers all advanced technologies in manipulating and communicating information. The term is sometimes used in reference to information technology (IT), particularly in these two communities: education and government. The common usage ICT is synonymous assumed the fact that IT or ICT encompasses all mediums, to record information (magnetic disk/tape, optical disks (CD/DVD), flash memory etc. and arguably also paper records); technology for broadcasting information - radio, television; and technology for communicating through voice and sound or images - microphone, camera, loudspeaker, telephone to cellular phones. It includes the wide varieties of computing hardware (PCs, servers, mainframes, networked storage).
4.3.3.6 System Integration - the process by which smaller pieces of software are brought together to form a larger piece of software that was designed to solve a problem.
4.3.3.7 System Management – is the management of the information technology systems in an enterprise. This includes gathering requirements, purchasing equipment and software, distributing it to where it is to be used, configuring it, maintaining it with enhancement and service updates, setting up problem-handling processes, and determining whether objectives are being met.
4.3.3.8 Information - is a stimulus that has meaning in some context for its receiver. When information is entered into and stored in a computer, it is generally referred to as data. After processing (such as formatting and printing), output data can again be perceived as information.
4.3.4 REQUIREMENTS
4.3.4.1 CES Plans and Programs 4.3.4.2 Situation of subjected PNP Information System 4.3.4.3 Inventory of ICT resources from the end user / client / IS recipient 4.3.4.4 Inventory of ICT resources future plans and programs 4.3.4.5 Status of Communication Infrastructure and Equipment 4.3.4.6 Accomplishment Report of ITMS and CES
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
101
4.3.5 FLOWCHART
NO
YES
Start
Review ITMS and CES accomplishment report, situation of subjected PNP IS, inventory of ICT resources from the end user / client / IS recipient and future plans and programs, status of communication infrastructure and equipment.
End
Recommend revision of current plans and programs to adhere to PNP ISSP and TSSP.
Evaluate requirements in consonance with the PNP ISSP and TSSP.
Is the requirements
are in consonance with
the PNP ISSP and TSSP?
Monitoring of Implementation-Procedure No.
4.2
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
102
4.3.6 NARRATIVE
4.3.6.1 Review ITMS and CES accomplishment report, situation of subjected PNP IS, inventory of ICT resources from the end user / client / IS recipient and future plans and programs, status of communication infrastructure and equipment.
4.3.6.2 Evaluate above requirements in consonance with the PNP ISSP and TSSP.
4.3.6.3 If the above requirements adhere to the PNP ISSP and TSSP, monitoring of its implementation shall follow using Procedure 4.2.
4.3.6.4 Prepare recommendations for the revision of current plans and programs if the above requirement does not adhere to PNP ISSP and TSSP.
4.3.6.5 Submit report to TDICTM on above recommendations and approval.
4.3.6.6 Submit recommendations to ITMS and CES for appropriate action.
4.3.6.7 DICTM shall monitor the implementation and compliance of the approved recommendations.
4.3.7 SERVICE STANDARD
Transaction Type Time
Review ITMS and CES accomplishment report, situation of subjected PNP IS, inventory of ICT resources from the end user / client / IS recipient and future plans and programs, status of communication infrastructure and equipment
5 days
Evaluation of the requirements in consonance with the PNP ISSP and TSSP
3 days
Prepare recommendations for the revision of current ITMS and CS plans and programs for TDICTM information and approval
4 days
Route recommendations to ITMS and CES for implementation
1 day
Monitor implementation compliance
Total Average Transaction Time 13 days
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
103
4.4. Communications and Electronics System Section
TITLE PROCEDURE
NUMBER NUMBER OF
PAGES
Communications and Electronics System Section
4.4 4
INTERFACES SIMD-DICTM AND OTHER PNP OFFICES
4.4.1 OBJECTIVE
4.4.1.1 To supervise, assess and recommend on all Communications
and Electronics System utilized by the PNP.
4.4.2 REFERENCES
4.4.2.1 Creation of the Directorate for Information and Communications Technology Management (DICTM)
4.4.2.2 PNP Information Systems Strategic Plan (ISSP)
4.4.3 DEFINITION OF TERMS
4.4.3.1 Electronic Communication - the science and technology of transmitting information electronically by wires or radio signals with integrated encoding and decoding equipment.
4.4.3.2 Electronics - field of engineering and applied physics dealing with the design and application of devices, usually electronic circuits, the operation of which depends on the flow of electrons for the generation, transmission, reception, and storage of information. The information can consist of voice or music (audio signals) in a radio receiver, a picture on a television screen, or numbers and other data in a computer.
4.4.3.3 Communications - process of sharing ideas, information, and messages with others in a particular time and place. Communication includes writing and talking, as well as nonverbal communication (such as facial expressions, body language, or gestures), visual communication (the use of images or pictures, such as painting, photography, video, or film), and electronic communication (telephone calls, electronic mail, cable television, or satellite broadcasts).
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
104
4.4.3.4 Communication System - is a collection of individual communications networks, transmission systems, relay stations, tributary stations, and data terminal equipment (DTE) usually capable of interconnection and interoperation to form an integrated whole. The components of a communications system serve a common purpose, are technically compatible, use common procedures, respond to controls, and operate in unison. Telecommunications is a method of communication (e.g., for sports broadcasting, mass media, journalism, etc.).
4.4.4 REQUIREMENTS
4.4.4.3.1 Consolidated report of all Communication System
developed and maintained by CES. 4.4.4.3.2 Evaluation reports generated from PNP end-users for
system capability and limitation being utilized by their unit.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
105
4.4.5 FLOWCHART
Start
Reviews assessment report received from CES on system capability and limitations.
Consolidate reports of all PNP Communication System.
Submit assessment report and recommendations to CES for information and implementation.
Review CES plans and programs and system updates for Communication System (from CES and other PNP units maintaining Communication System).
Prepare assessment report and recommendations.
Monitoring of implementation and
compliance of all PNP offices
End
Route assessment report and recommendations to TDICTM for approval.
Request feedback upon implementation of the above recommendation.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
106
4.4.6 NARRATIVE
4.4.6.3 Reviews assessment report received from CES on system capability and limitations.
4.4.6.4 Consolidate reports of all PNP Communication System. 4.4.6.5 Review CES plans and programs and system updates for
Communication System (from CES and other PNP units). 4.4.6.6 Prepare assessment report and recommendations. 4.4.6.7 Route assessment report and recommendations to TDICTM for
approval. 4.4.6.8 Submit assessment report and recommendations to CES for
information and implementation. 4.4.6.9 Request feedback upon implementation of the above
recommendation.
4.4.7 SERVICE STANDARD
Transaction Type Time
System audit and assessment for communication systems 3 days
Preparation of guidelines for implementation 2 days
Route draft copy of the proposed circular for comments and suggestions.
3 days
Revision of the circular for approval and signature of TDICTM.
2 days
Route proposed circular to the D-Staff and Command Group for comment.
5 days
Finalization of the circular and approval of CPNP. 2 days
Dissemination of the approved circular for implementation. 1 day
Total Average Transaction Time 18 days
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
107
4.5. Formulation of Policies, Plans and Programs and Updates for the Integration of PNP wide Communication System
TITLE PROCEDURE
NUMBER NUMBER OF
PAGES
Policy Formulation and Updates for the Integration and Management of Information Systems
4.5 4
INTERFACES SIMD-DICTM AND OTHER PNP OFFICES
4.5.1 OBJECTIVE
4.5.1.1 To provide a procedure in the formulation of policy on the
integration of PNP-wide telecommunications system.
4.5.2 REFERENCES
4.5.2.1 Creation of the Directorate for Information and Communications Technology Management (DICTM)
4.5.2.2 PNP Information Systems Strategic Plan (ISSP)
4.5.3 DEFINITION OF TERMS
4.5.3.1 Information Systems Strategic Plan (ISSP) – is an Information and Communications Technology (ICT) blueprint that supports both the short-term and long-term Information System needs of the PNP that is aligned with its strategic thrust and programs.
4.5.3.2 Policy - a deliberate plan of action to guide decisions and achieve rational outcome(s).
4.5.3.3 System - is a set of interacting or interdependent entities forming an integrated whole.
4.5.3.4 Electronic Communication - the science and technology of transmitting information electronically by wires or radio signals with integrated encoding and decoding equipment.
4.5.3.5 Electronics - field of engineering and applied physics dealing with the design and application of devices, usually electronic circuits, the operation of which depends on the flow of electrons for the generation, transmission, reception, and storage of information. The information can consist of voice or music (audio signals) in a radio receiver, a picture
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
108
on a television screen, or numbers and other data in a computer.
4.5.3.6 Communications - process of sharing ideas, information, and messages with others in a particular time and place. Communication includes writing and talking, as well as nonverbal communication (such as facial expressions, body language, or gestures), visual communication (the use of images or pictures, such as painting, photography, video, or film), and electronic communication (telephone calls, electronic mail, cable television, or satellite broadcasts).
4.5.3.7 Communication System - is a collection of individual communications networks, transmission systems, relay stations, tributary stations, and data terminal equipment (DTE) usually capable of interconnection and interoperation to form an integrated whole. The components of a communications system serve a common purpose, are technically compatible, use common procedures, respond to controls, and operate in unison. Telecommunications is a method of communication (e.g., for sports broadcasting, mass media, journalism, etc.).
4.5.3.8 Frequency - is the number of complete cycles per second in alternating current direction. The standard unit of frequency is the hertz, abbreviated Hz. If a current completes one cycle per second, then the frequency is 1 Hz; 60 cycles per second equals 60 Hz (the standard alternating-current utility frequency in some countries).
4.5.4 REQUIREMENTS
4.5.4.1 Status or situation report of Communication System. 4.5.4.2 Inventory Reports on Communication Equipments. 4.5.4.3 Compliance report on the plans and programs CES.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
109
4.5.5 FLOWCHART
4.5.6 NARRATIVE
Start
Conduct system audit/inspection on the subjected PNP Communication System.
Assess and identify deployment status and situation of subjected PNP Communication
System.
Approval and signature of the cover Memo by TDICTM.
Prepare guidelines on the implementation and management of the Communication System in the form of Memorandum Circular.
Routes to DICTM Divisions, CES and DICTM Command Group for comments
and suggestions.
Finalize and revise the proposed Memo Circular with cover Memo (SIMD).
Routes the proposed Memorandum Circular to the Directorate Offices and PNP Command Group for comment
Re-route the final copy of the proposed memo circular for approval and signature
of the C, PNP.
For widest dissemination.
Monitoring of implementation and compliance of all PNP offices
(DICTM).
End
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
110
4.5.6.1 Conducts systems audit/inspection on the current situation of the
deployed Communication System. 4.5.6.2 Assess and identify the deployment situation of the
Communication System and determine problems encountered or technical difficulties during implementation.
4.5.6.3 Prepare guidelines on the implementation and management of the Communication System in the form of Memorandum Circular (MC) to resolve difficulties and issues encountered by the end user or recipient.
4.5.6.4 SIMD routes the draft copy of the proposed circular to DICTM Divisions, CES and DICTM Command Group for review, comments and suggestions.
4.5.6.5 Based on the comments / suggestions, SIMD revises the proposed circular and re-route the final draft copy with cover memo to DICTM Command Group.
4.5.6.6 Signature and approval of the cover Memo by TDICTM. 4.5.6.7 Routes the proposed Memorandum Circular to the Directorate
Offices and PNP Command Group for comment. 4.5.6.8 Based on the comments, DICTM revises and finalizes the
proposed Memorandum Circular and re-route the final copy for approval and signature of the C, PNP.
4.5.6.9 For widest dissemination and guidance of all PNP offices. 4.5.6.10 DICTM shall monitor the implementation and compliance of the
approved Memorandum Circular.
4.5.7 SERVICE STANDARD
Transaction Type Time
System audit and assessment of deployed IS 3 days
Preparation of guidelines for implementation 2 days
Route draft copy of the proposed circular for comments and suggestions.
3 days
Revision of the circular for approval and signature of TDICTM. 2 days
Route proposed circular to the D-Staff and Command Group for comment.
5 days
Finalization of the circular and approval of CPNP. 2days
Dissemination of the approved circular for implementation. 1 day
Total Average Transaction Time 18 days
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
111
5. RESEARCH AND DEVELOPMENT DIVISION
5.1 Procedure in the Formulation of ICT Trainings
TITLE PROCEDURE NO. NO. OF PAGES
Procedure in the Formulation of ICT Trainings
5.1 3
Interfaces Research and Development Division
5.1.1 OBJECTIVE
This is to determine if the formulated ICT Trainings to be conducted by ITMS/CES for their personnel can be accommodated or not.
5.1.2 REFERENCES
5.1.2.1 Memo from RDD
5.1.2.2 Instructions from TDICTM
5.1.2.3 Memo from CES and ITMS
5.1.3 DEFINITION OF TERMS
5.1.3.1 Information and Communications Technology (ICT) – is the totality of the electronic means employed to systematically collect, process, store, present and share information to end-users in support of their activities. It consists of computer systems, office systems, consumer electronics and telecommunications technologies, as well as networked information infrastructure the components of which include the telephone system, the Internet, fax machines, computers and its accompanying methodologies, processes, rules and conventions. A combination of computer technology, microelectronics applications, and communications information techniques and methods. It encompasses the use of computers, data communications, office systems technologies, as well as any technology that deals with modern day application of computing and/or communication. It can also be seen as the marriage of information technology and data communication.
5.1.3.2 RDD- Research and Development Division 5.1.3.3 TDICTM – The Director, Directorate for Information and
Communications Technology Management.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
112
5.1.3.4 ITMS – Information Technology Management Service 5.1.3.5 CES – Communications and Electronics Service
5.1.4 REQUIREMENT
5.1.4.1 Approval of TDICTM 5.1.4.2 ICT Trainings to be offered periodically
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
113
5.1.5 FLOWCHART
START
RDD
Review and Research of ICT Training
RDD Endorsement of ICT Training
CES ITMS
Evaluation/Comments Evaluation / Comments
DICTM Ex-O For Consolidation of Comments
TDICTM Approval/
Recommendation of ICT Training
RDD Accommodation/
Non Accommodation of ICT Training
END
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
114
5.1.6 NARRATIVE 5.1.6.1 The Research and Development Division (RDD) will conduct
review and research re proposed ICT Trainings (Requirements,
Detailed Program of Instruction (POI), Training Directives and
Lectures).
5.1.6.2 RDD will prepare memo for the proposed detailed ICT Trainings
to be forwarded to TDICTM for endorsement to AD, CES and D,
ITMS.
5.1.6.3 The memo will be forwarded to AD, CES and D, ITMS for
evaluation and comments of the proposed ICT Trainings.
5.1.6.4 CES and ITMS shall prepare memo (reply) of their evaluation
and comments to be forwarded to DICTM Ex-O (Attn: RDD).
5.1.6.5 TDICTM either approve or disapprove the proposed ICT
trainings based on the evaluation and recommendation of the
consolidated data from ITMS and CES.
5.1.6.6 RDD will prepare for the accommodation/non accommodation of
the proposed ICT Trainings as per instruction from TDICTM.
5.1.7 SERVICE STANDARDS
TRANSACTION TYPE TURN AROUND TIME
Procedure in the Formulation of ICT Trainings
Review and Research 1 Day
Evaluation and Comments
2 Days
Preparation of the Recommendation for Accommodation/Non Accommodation of ICT Trainings
1 Day
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
115
5.2 Procedure in the Processing of the Request for Product Presentation
TITLE PROCEDURE NO.
NO. OF PAGES
Procedure in the processing of the Request for Product Presentation 5.2 3
Interfaces Research and Development Division
5.2.1 OBJECTIVE
This is to determine if the Request for Product Presentation by requesting company/ corporation can be accommodated or not. 5.2.2 REFERENCES
5.2.2.1 Request Letter/Letter of Intent/Memo from requesting Company/Corporation
5.2.2.2 Instructions from TDICTM 5.2.2.3 Memo from RDD 5.2.2.4 Memo from ITMS and CES
5.2.3 DEFINITION OF TERMS
5.2.3.1 Presentation - is the process of presenting the content of a
topic/information to an audience.
5.2.4 REQUIREMENT 5.2.4.1 Approval of TDICTM 5.2.4.2 Memo from requesting company/corporation indicated therein
the product’s name, proposed schedule (date/time) and attendees.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
116
5.2.5 FLOWCHART
Requesting Company/Corporation for
Product Presentation
AdmO Endorsement to RDD of Request Letter/
Letter of Intent/Memo
RDD
Verification/Coordination/Scheduling of Product Presentation
TDICTM
Signature for Accommodation/ Non Accommodation of
Product Presentation
Product Presentation by Requesting Company/Corporation
CES ITMS
Evaluation/Comments Evaluation/Comments
RDD Preparation of After Product
Presentation Report
TDICTM For Signature of After Product
Presentation Report C, PNP Submission of After Product Presentation Report
END
START
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
117
5.2.6 NARRATIVE 2.6.1. The Request Letter/Letter of Intent/Memo from requesting
company/corporation to conduct product presentation shall be
received by the Message Center at Administrative Office and will
be endorsed to AdmO/Personnel Officer.
2.6.2. Admo shall forward/ endorse the Request Letter/Letter of
Intent/Memo to Research and Development Division (RDD).
2.6.3. RDD shall verify the company’s/corporation’s profile and shall make
a coordination on the requesting company/corporation. RDD will
check on the availability of venue and attendees for scheduling of
the product presentation.
2.6.4. RDD shall prepare a Memo for approval of TDICTM regarding the
accommodation or non-accommodation of the said request. Once
approved, the memo shall be sent to the requesting
company/corporation for their scheduled product presentation.
2.6.5. RDD shall facilitate product presentation.
2.6.6. A memo will be forwarded to CES and ITMS for necessary
evaluation and comments on the product presentation.
2.6.7. CES and ITMS shall prepare memo (reply) of their evaluation and
comments to be forwarded to Research and Development
Division.
2.6.8 RDD will prepare an After Presentation Report to be submitted to
TDICTM, further to C, PNP.
5.2.7 SERVICE STANDARDS
TRANSACTION TYPE TURN AROUND TIME
Procedure in the processing of the Request for Product Presentation
Processing of Request 1 Days
Preparation of the Recommendation for Accommodation/Non Accommodation of ICT Trainings
2 Days
After Presentation Report 1 Day
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
118
5.3 Procedure in the processing of the Request for ICT Training by other PNP Unit/Office
TITLE PROCEDURE NO. NO. OF PAGES
Procedure in the processing of the Request for ICT Training by other PNP Units/Offices
5.3 3
Interfaces Research and Development Division
5.3.1 OBJECTIVE
This is to determine if the request of other PNP Unit/Office to conduct an ICT Training exclusively for their personnel can be accommodated or not.
5.3.2 REFERENCES
5.3.2.1 Memo from the requesting PNP Unit/Office 5.3.2.2 Instructions for TDICTM 5.3.2.3 Memo from RDD 5.3.2.4 Memo from ITMS and CES
5.3.3 DEFINITION OF TERMS
5.3.3.1 Training - refers to the acquisition of knowledge, skills, and competencies as a result of the teaching of vocational or practical skills and knowledge that relates to specific useful skills.
5.3.4 REQUIREMENT
5.3.4.1 Approval of TDICTM 5.3.4.2 Memo from the requesting PNP Unit/Office indicated therein the
title/contents of training course, proposed schedule (Date/Time) and number and profile of the participants.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
119
TDICTM Approval/Disapproval of ICT Training
5.3.5 FLOWCHART START
ITMS Coordination with Concerned PNP Unit/Office for the Conduct of ICT Trainings/
Submission of After Activity Report
ITMS Memo (Reply) to conduct ICT Trainings
CES Memo (Reply) to conduct ICT Trainings
CES Coordination with Concerned PNP Unit/Office for the Conduct of ICT Trainings/
Submission of After Activity Report
Requesting PNP Unit/Office Memo Request for ICT
Trainings AdmO Forward the Memo
Request to RDD
Memo Request for ICT Trainings
RDD Memo for Endorsement of Request to ITMS and CES
RDD Memo for Recommendation to TDICTM to conduct ICT Trainings
RDD Memo (Reply) to Requesting PNP Unit/Office Memo to CES and
ITMS for accommodation of ICT Trainings
TDICTM For Signature of After Activity Report
C, PNP Submission of After
Activity/Training Report
END
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
120
5.3.6 NARRATIVE 5.3.6.1 The Memo from other PNP Unit/Office requesting to conduct an
ICT Training exclusively for their personnel shall be received by the Message Center and shall endorse it to AdmO.
5.3.6.2 AdmO shall forward the Memo/Request to Research and Development Division (RDD).
5.3.6.3 RDD shall prepare a Memo endorsing the request of other PNP Unit/Office to conduct an ICT Training to ITMS (Attn: C, TRD) and CES (Attn: CDTD).
5.3.6.4 ITMS and CES shall prepare a Memo (Reply) regarding the accommodation /non-accommodation of the said request.
5.3.6.5 RDD shall prepare a Memo for Recommendation to TDICTM to conduct ICT Training for the requesting PNP Unit/Office.
5.3.6.6 TDICTM either approve or disapprove the request for ICT Training.
5.3.6.7 RDD shall prepare a Memo (Reply) to be forwarded to the requesting PNP Unit/Office and a Memo to CES (Attn: CDTD) or ITMS (Attn: C, TRD) for the accommodation of ICT Training.
5.3.6.8 CES (Attn: CDTD) and/or ITMS (Attn: C, TRD) will make coordination to the requesting PNP Unit/Office for the conduct of the ICT Training and shall submit an After Activity Report to TDICTM of the said training.
5.3.6.9 TDICTM shall sign on the After Activity Report submitted by CES and/or ITMS, further, to be forwarded to C, PNP.
5.3.7 SERVICE STANDARDS
TRANSACTION TYPE TURN AROUND TIME
Procedure in the processing of the Request for ICT Training by Other PNP Units/Offices
Processing of Request 1 Day
Preparation of the Recommendation for Accommodation/Non-Accommodation of ICT Training
2 Days
After Activity Report 1 Day
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
121
5.4 Procedure in the Conduct of Research and Development on Latest ICT Products and Services
TITLE PROCEDURE NO
NO. OF PAGES
Procedure in the conduct of research and development on latest ICT products and services.
5.4 3
Interfaces Training and Research Div
5.4.1 OBJECTIVE
This is to determine the procedures in the conduct of research and
development on the latest ICT products that are applicable and advantageous to the PNP. 5.4.2 REFERENCES
5.4.2.1 Memo from RDD 5.4.2.2 Instruction from TDICTM 5.4.2.3 Memo from AD, CES and D, ITMS
5.4.3 DEFINITION OF TERMS
5.4.3.1 Research – it is a careful, systematic, patient study and
investigation in some field of knowledge, undertaken to discover or establish facts or principles.
5.4.3.2 Development – systemic use of scientific and technical
knowledge to meet specific objectives or requirements. 5.4.3.3 Information Communications Technology (ICT) – it is the
broader term of IT to explicitly include the field of electronic communications.
5.4.4 REQUIREMENT
5.4.4.1 Memo from the RDD indicated therein the proposed ICT products
to be researched.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
122
5.4.5 FLOWCHART
START
END
RDD conduct Research latest ICT products
Check product for Competitiveness
Coordinate to concern Division
ITMS Review/Recommendation
CES Review/Recommendation
RDD Consolidate, Evaluate and Propose
Ex-O, DICTM For Comments
DICTM For Approval
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
123
5.4.6 NARRATIVE
5.4.6.1 RDD will conduct research through the use of internet and other sources such as product demonstration on the latest ICT products and services that are applicable to the needs of and are advantageous to the PNP.
5.4.6.2 Part of the research is to check the product for its competitiveness and usefulness to the PNP
5.4.6.3 After the conduct of product research, RDD will coordinate with the different divisions of DICTM about the product for their comments.
5.4.6.4 D, CES and D, ITMS thru a written memorandum will also be requested to review the product and give their recommendations if any.
5.4.6.5 RDD will then consolidate and evaluate the reviewed product, then gave a proposal based on the recommendations made by D, ITMS/ D, CES as the case maybe and then forward said proposal to Ex-O, DICTM for comments.
5.4.6.6 The TDICTM approves/disapproves the proposal.
5.4.7 SERVICE STANDARDS
TRANSACTION TYPE
Turn Around Time
Procedure in the conduct of research on the latest ICT product
Conduct of research on ICT 1-5 days
Preparation of the memorandum for recommendation
15-30 mins
Consolidation of the recommendations and submission of the proposal to TDICTM
30 mins
INSTALL the PNP SALARY
SYSTEM
CONNECT INSTALL MAGIC 7.1E SOFTWARE
1. LOAD THE PNP SS MAGIC.INI FILE
2. CREATE USER/CLIENT PNP SS USER ACCOUNT
3. TEST/RUN (Designated NAS Staff)
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
124
III. GLOSSARY OF TERMS
A. ADMINISTRATIVE OFFICE
1. Availability of Reassignment - is a certificate being given by the losing unit duly signed by its Director/Chief of Office granting the transfer of personnel to another unit.
2. Certification – the act of certifying a person, thing or document; or state of being certified. Certification maybe valid for a certain period of time or lifetime.
3. Commutation Order - is an order that certifies the unused leave credits of
the personnel.
4. Compulsory Retirement – is the automatic retirement of officer and non-officer, upon attainment of age fifty-six (56): Provided, that, in case of any officer with the rank of Chief Superintendent, Director or Deputy Director general, the Commission may allow his retention in the service for an unextendible period of one (1) year.
5. DICTM Personnel Board- is the panel headed by Deputy Director created
to evaluate, assess and/or deliberate DICTM personnel matters such as personnel procurement, movement, development and maintenance prior recommendation to the Director, DICTM for his approval.
6. DICTM Working Committee - is the team from Admin Office created to
assists the Board administratively and shall be responsible for the initial screening and evaluation of personnel matters prior deliberation of the Board.
7. DPRM Form 1A – 2007 – refers to the revised PNP ID Application Form.
8. Leave form (CSC Form No.6) – is a form to be used in filing a Leave of Absence of personnel.
9. Leave of Absence (LOA) - is a term used to describe a period of time
that one is to be away from his/her primary job, while maintaining the status of employee. This term is in contrast to normal periods away from the workplace, such as vacations, holidays, hiatuses, sabbaticals, and “working from home” programs, in that they are considered to be exceptional circumstances, rather than benefits. Generally such an
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
125
arrangement has a predefined termination at a particular date or after a certain event has occurred.
10. Letter of Accommodation - is a letter given to personnel who are willing
to be assigned to a unit/office which was duly signed by the Director/Chief of Office of the gaining unit/office.
11. Optional Retirement - Upon accumulation of at least twenty (20) years of satisfactory active service, an officer or non-officer, at his own request and with the approval of the Commission, shall be retired from the service and entitled to receive benefits provided by law.
12. Reassignment - is the movement of an employee from one organizational unit to another in the same department or agency which does not involve a reduction in rank, status, or salary and doest not require the issuance of appointment.
13. Resignation - is the formal act of giving up or quitting one's office or position. A resignation can occur when a person holding a position gained by election or appointment steps down, but leaving a position upon the expiration of a term is not considered resignation. An employee who chooses to leave a position is considered a resignation, as opposed to termination, which occurs when the employee involuntarily loses a job.
14. Transfer - is a movement from one position to another which is of equivalent rank, level or salary without break in service involving the issuance of an appointment.
B. BUDGET AND FISCAL OFFICE
1 Funding or financing - is to provide capital (funds), which means money for
resources (logistics and personnel) for implementation of project, activity or program.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
126
C. PLANS AND PROGRAMS DIVISION
1. Action plan –An organized, step-by-step reference for action towards
attainment of specific goal within specific measure of time.
2. Evaluation Mechanism – is a toolkit of evaluation methodologies and specific techniques to facilitate the decision-making process in deriving an evaluation plan appropriate to the project and needs of the evaluation.
3. Information Communications Technology (ICT) - is the broader term of IT to explicitly include the field of electronic communications.
4. Information Systems (IS) - is the system of persons, data records and activities that process the data and information in a given organization, including manual processes or automated processes.
5. Information Systems Strategic Plan (ISSP) – refers to the overall plan for the development and implementation of Information Systems supportive of organizational mission/objectives and the corresponding resources requirements over a five-year period.
6. Information Technology (IT) - is the study, design, development, implementation, support or management of computer-based information systems, particularly software applications and computer hardware.
7. Inspection – is most generally, an organized examination or formal evaluation exercise. It involves the measurements, tests, and gauges applied to certain characteristics in regard to an object or activity. The results are usually compared to specified requirements and standards for determining whether the item or activity is in line with these targets.
8. IT Governance Practices – The Responsible Management of IT resources, including mitigation of risks, in order to realize the value of IT investments.
9. Plan – is typically any procedure used to achieve an objective. It is a set of intended actions through which one expects to achieve a goal. Also, is a proposed or intended method of getting from one set of circumstances to another. They are often used to move from the
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
127
present situation, towards the achievement of one or more objectives or goals.
10. Performance Indicator or Key Performance Indicator (KPI) is a measure of performance that are commonly used to help an organization define and evaluate how successful it is, typically in terms of making progress towards its long-term organizational goals.
11. Policy – a specific decision or set of decisions designed to carry out such a course of action.
12. Program – are plans or schedules to be followed. Programs comprise goals, policies, procedures, rules, tasks, assignments, steps to be taken, resources to be used, and other mediums necessary to carry out a given course of action supported by budgets. A program maybe a minor one formulated by a single supervisor to improve the morale of personnel in the DICTM.
13. Project - is a temporary endeavor undertaken to create a unique product or service. A project usually needs resources to deliver its results. Most of the time project execution is based on detailed plan, which considers also external factors and constraints. Planning, execution and controlling of project is the primary field of project management. Also, a research or design, that is carefully planned to achieve a particular aim, reaching of which is considered necessary for the achievement of planned benefits.
14. Project Evaluation is a step-by-step process of collecting, recording and organizing information about project results, including short-term outputs (immediate results of activities, or project deliverables), and immediate and longer-term project outcomes (changes in behavior, practice or policy resulting from the project).
15. Project Identification – is a repeatable process for documenting, validating, ranking and approving candidate projects within an organization.
16. Project Management - is the discipline of planning, organizing, and managing resources to bring about the successful completion of specific project goals and objectives.
17. Project Monitoring – provides information for project activities being implemented by concerned offices with the use of project tracking
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
128
systems and monitoring indicators such as: Input, Output, Outcome and Impact Indicators.
18. Project Monitoring Tools – the means, machinery or entity used to interface between the project and the project implementers to facilitate effective actions from the project implementer/s and ideal output from the project design.
19. Project Preparation – consists of the entire social, technical and financial work required to ensure that a project is feasible and can be successfully and appropriately implemented. The process ensures the identification and elimination of key risks at the earliest possible time and maximizes development opportunities.
20. Proponent – a person who puts forward a proposition or proposal.
21. Proposal Evaluation – is an assessment of the proposal and the proponent ability to perform the prospective contract successfully (according to technical feasibility, administrative / managerial capability, acceptability and other prescribed criteria).
22. Resource Management - is the efficient and effective deployment for an organization's resources when they are needed. Such resources may include financial resources, inventory, human skills, production resources, or information technology (IT).
C. SYSTEM INTEGRATION AND MANAGEMENT DIVISION
1. Information - is a stimulus that has meaning in some context for its receiver. When information is entered into and stored in a computer, it is generally referred to as data. After processing (such as formatting and printing), output data can again be perceived as information.
2. Information System (IS) - a system of people, data records and activities that process the data and information in an organization, and it includes the organization's manual and automated processes. In a narrow sense, the term information system (or computer-based information system) refers to the specific application software that is used to store data records in a computer system and automates some of the information-processing activities of the organization.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
129
3. Information Systems Strategic Plan (ISSP) – is an Information and Communications Technology (ICT) blueprint that supports both the short-term and long-term Information System needs of the PNP that is aligned with its strategic thrust and programs.
4. Information and Communications Technology (ICT) - is an umbrella term that covers all advanced technologies in manipulating and communicating information. The term is sometimes used in reference to information technology (IT), particularly in these two communities: education and government. The common usage ICT is synonymous assumed the fact that IT or ICT encompasses all mediums, to record information (magnetic disk/tape, optical disks (CD/DVD), flash memory etc. and arguably also paper records); technology for broadcasting information - radio, television; and technology for communicating through voice and sound or images - microphone, camera, loudspeaker, telephone to cellular phones. It includes the wide varieties of computing hardware (PCs, servers, mainframes, networked storage).
5. Policy - a deliberate plan of action to guide decisions and achieve rational outcome(s).
6. System - is a set of interacting or interdependent entities forming an integrated whole.
7. System Integration - the process by which smaller pieces of software are brought together to form a larger piece of software that was designed to solve a problem.
8. System Management – is the management of the information technology systems in an enterprise. This includes gathering requirements, purchasing equipment and software, distributing it to where it is to be used, configuring it, maintaining it with enhancement and service updates, setting up problem-handling processes, and determining whether objectives are being met.
9. RESEARCH AND DEVELOPMENT DIVISION
1. CES – Communications and Electronics Service
2. Development – systematic use of scientific and technical knowledge
to meet specific objectives or requirements.
DIRECTORATE FOR INFORMATION AND COMMUNICATIONS TECHNOLOGY MANAGEMENT
130
3. Information Communications Technology (ICT) – is the broader term of IT to explicitly include the field of electronic communications.
4. Information and Communications Technology (ICT) – is the totality of the electronic means employed to systematically collect, process, store, present and share information to end-users in support of their activities. It consists of computer systems, office systems, consumer electronics and telecommunications technologies, as well as networked information infrastructure the components of which include the telephone system, the Internet, fax machines, computers and its accompanying methodologies, processes, rules and conventions. A combination of computer technology, microelectronics applications, and communications information techniques and methods. It encompasses the use of computers, data communications, office systems technologies, as well as any technology that deals with modern day application of computing and/or communication. It can also be seen as the marriage of information technology and data communication.
5. ITMS – Information Technology Management Service
6. Presentation - is the process of presenting the content of a topic/information to an audience.
7. RDD- Research and Development Division
8. Research – is a careful, systematic, patient study and investigation in some field of knowledge, undertaken to discover or establish facts or principles.
9. TDICTM – The Director, Directorate for Information and Communications Technology Management
10. Training - refers to the acquisition of knowledge, skills, and competencies as a result of the teaching of vocational or practical skills and knowledge that relates to specific useful skills.