a study of lean construction practices in gaza strip · that the lean construction is an...

121
اﻹﺳﻼﻣﻴﺔ اﻟﺠﺎﻣﻌﺔ- ﻏﺰةThe Islamic University of Gaza اﻟﻌﻠﻴﺎ اﻟﺪراﺳﺎت ﻋﻤﺎدةDeanery of Higher Studies اﻟﻬﻨﺪﺳﺔ آﻠﻴﺔFaculty of Engineering اﻟﻤﺪﻧﻴﺔ اﻟﻬﻨﺪﺳﺔ ﻗﺴﻢCivil Engineering Department اﻟﻤﺸﺎرﻳﻊ إدارةConstruction Management A Study of Lean Construction Practices in Gaza Strip دراﺳﺔ ﺗﻄﺒﻴﻖ اﻟﺴﻠﺲ اﻟﺒﻨﺎء ﻏﺰة ﻗﻄﺎع ﻓﻲRamdane M. El-Kourd Supervised by Dr. Salah R. Agha Dr. Mamoun A. Alqedra A Thesis Submitted in Partial Fulfillment of the Requirements for the Degree of Master of Science in Construction Management July, 2009

Upload: others

Post on 14-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

The Islamic University of Gaza غزة-الجامعة اإلسالمية Deanery of Higher Studiesعمادة الدراسات العليا

Faculty of Engineering آلية الهندسة Civil Engineering Department قسم الهندسة المدنية

Construction Management إدارة المشاريع

A Study of Lean Construction

Practices in Gaza Strip

في قطاع غزة البناء السلس تطبيق دراسة

Ramdane M. El-Kourd

Supervised by

Dr. Salah R. Agha Dr. Mamoun A. Alqedra

A Thesis Submitted in Partial Fulfillment of the Requirements for the Degree of Master of Science in Construction Management

July, 2009

Page 2: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction
Page 3: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Dedication

I would like to dedicate this work to my family for

their sacrifice and endless support

Ramdane Mohammed El-Kourd

I

Page 4: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Acknowledgment

I would like to express my deepest appreciation to my

supervisors Dr. Salah R. Agha and Dr. Mamoun A.

Alqedra for their professional guidance, useful advice,

continuous encouragement, and support that made this

thesis possible.

Deepest thanks go for the staff of construction

management at the Islamic University for their

academic and scientific supervision during my study at

the Islamic University.

Gratitude is due to Abu-Shahla consultant office for

their help in providing the required documents.

II

Page 5: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

III

Page 6: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

ABSTRACT

This research deals with the problem of waste in time, materials, resources and

achievement of customer needs. This study has been applied to a contracting company

in the construction of a project located in GAZA. The main objective of this study is to

apply the principles of lean to the construction in the Gaza Strip. The mechanism of

research implementation consists of two stages:

Stage one: Theoretical study of various Arabic and English references and Master

researches from the Islamic University, studies that deal with the waste and the problem

of contractors’ performance. The criteria that have been derived can be applied to

construction projects in the Gaza Strip.

Stage two: The methodology of applying lean construction was represented in 10

points, the standardization tools and the five why tools as described in the current study

in order to achieve the lean construction in reducing the activity and steps, thus

minimizing the duration by the elimination of the non-value added process in the

activity by using arena simulation.

The study of the project has been implemented in the Gaza strip because of the lack of

projects under construction due to the situation in the Gaza Strip. The data of the

project was taken from the daily reports. These reports showed the duration and steps of

the process for executing the project. Measuring the value and the non-value added in

the process that used standardization tools and showed the cause of waste by using the

five why tools. Consequently, defining solution to deal with them.

Using simulation was to measure the effect of non-value added on each process in the

project.

Results showed that using lean construction reduced the number of steps in the whole

project by 57%. The non-value added decreased from 81% to 14% in the duration of the

project. The total cycle time of the project was reduced by 75%.

Lean construction is new in the field of construction in the world in general and in the

Arab countries in particular.

After proving the potential of applying lean, the focus should be on obstacles of lean

implementation.

IV

Page 7: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table of Contents

Dedication ......................................................................................................................... I

Acknowledgment.............................................................................................................II

Arabic Abstract............................................................................................................. III

Abstract.......................................................................................................................... IV

Table of Contents ........................................................................................................... V

List of Abbreviations ................................................................................................. VIII

List of Tables ................................................................................................................. IX

List of Figures............................................................................................................... .XI

Chapter One: Introduction

1. 1 Statement of the problem............................................................................ 2

1. 2 Research aim and objectives....................................................................... 2

1.3 Methodology outline................................................................................... 2

1.4 Thesis contents............................................................................................ 2

Chapter Two: Lean Construction

2.1 The history of Lean Construction ................................................................... 4

2.2 Lean Construction Definition ......................................................................... 5

2.3 Impact of Lean Construction .......................................................................... 6

2.4 Lean Construction Principles...........................................................................6

2.4.1 Value ........................................................... 6

2.4.2 Value Stream ........................................................... 6

2.4.3 Flow ........................................................... 7

2.4.4 Pull ........................................................... 7

2.4.5 Perfection ........................................................... 7

2.5 Criteria of Lean construction ......................................................................... 9

2.5.1 Non Value-Added Activities Reduction .......................................... 9

2.5.2 Increase Output Value ................................................................... 9

2.5.3 Variability Reduction....................................................................... 9

2.5.4 Cycle Time Reduction ................................................................... 10

2.5.5 Simplify by Minimizing the Number of Steps............................... 11

V

Page 8: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

2.5.6 Increase Output Flexibility ............................................................ 12

2.5.7 Increase Process Transparency ...................................................... 12

2.5.8 Focus Control on the Complete Process ........................................ 13

2.5.9 Build Continuous Improvement into the Process .......................... 13

2.5.10 Balance Flow Improvement with Conversion Improvement....... 14

2.5.11 Benchmark ................................................................................... 14

2.6. Tools of Lean Construction

2.6.1 Just in Time (JIT).......................................................................... 15

2.6.2 Last Planner System....................................................................... 16

2.6.3. Increased Visualization................................................................. 18

2.6.4. First Run Studies........................................................................... 19

2.6.5. Daily Huddle Meetings................................................................. 19

2.6.6. The 5s Process .............................................................................. 20

2.6.7. Fail-Safe for Quality ..................................................................... 21

2.6.8 Productivity Standardization.......................................................... 21

2.6.9 The Five Why's ............................................................................... 22

2.7 Construction Waste..................................................................................... 22

2.8 Construction Waste in Gaza Strip............................................................... 25

2.9 Summary ..................................................................................................... 29

Chapter Three: Methodology

3.1 Research Strategy ........................................................................................ 31

3.2 Data Collection ............................................................................................. 31

3.3 Application of Lean Principles in Construction ........................................... 33

Chapter four: Application

4.1 Project Description ....................................................................................... 35

4.2 Project Activities........................................................................................... 36

4.3 Lean criteria Procedure................................................................................. 36

4. 4 Non Value Added Process Identification..................................................... 41

4 .4.1 Mobilization and Excavation Activity............................................. 42

4.4.2 Plain Concrete................................................................................... 42

4.4.3 Foundation Activity.......................................................................... 43

4.4.4 Neck Column Activity...................................................................... 44

VI

Page 9: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.4.5 Isolation ............................................................................................ 45

4.4.6 Backfilling ........................................................................................ 45

4.4.7 Ground Beam ................................................................................... 46

4.4. 8 Ground Floor Column ..................................................................... 46

4.4. 9 Ground Floor ................................................................................... 47

4.4.10 Ground Floor Slab ......................................................................... 48

4.4.11 First Floor Columns ........................................................................ 48

4.4.12 First Floor Slab ............................................................................... 49

4.4.13 Ground Floor Building.................................................................... 50

4.4.14 First Floor Building ........................................................................ 51

4.5 Remove or Reduce the Influence of Waste .................................................. 52

4.5.1 Mobilization and Excavation Activity................................................. 59

4.5.2 Plain Concrete...................................................................................... 59

4.5.3 Foundation ........................................................................................... 60

4.5.4 Neck Column ....................................................................................... 60

4.5.5 Isolation ............................................................................................... 61

4.5.6 Backfilling ........................................................................................... 61

4.5.7 Ground Beam....................................................................................... 62

4.5.8 Column Ground Floor.......................................................................... 62

4.5.9 Ground Floor........................................................................................ 63

4.5.10 Ground Floor Slab ............................................................................. 63

4.5.11 Column First Floor............................................................................. 64

4.5.12 First Floor Slab .................................................................................. 64

4.5.13 Building in Ground Floor .................................................................. 65

4.5.14 Building in First Floor ....................................................................... 66

4.6 Identify the Cause of Wastes ........................................................................ 66

4.7 Finding the Largest Non-Value Added Activity........................................... 69

4.7 Application of Lean Construction for Future Construction Project ............. 79

Chapter Five: Conclusions and Recommendations

5.1 Conclusions................................................................................................... 82

5.2 Recommendations…..................................................................................... 83

References...................................................................................................................... 84

VII

Page 10: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Appendices

Appendix (A): Daily Report

Appendix (B): Arena Simulation

Appendix ( C): Simulation result of the project before applying eight points and after

applying lean tools

Appendix (D): Simulation Result after applying "0" for three biggest non-value added

processes of the project during applying eight points

VIII

Page 11: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

List of Abbreviations

F. Floor First Floor

G. Floor Ground Floor

IGLC International Group of Lean Construction

JIT Just in Time

LC Lean Construction

LPS Last Planner System

NUMMI New United Motor Manufacturing Inc.

NVA Non Value Added

PMI Project Management Institute

PPC Percent Plan Complete

RPS Reverse Phase Scheduling

PS Pilot Study

SN Steps Number

SWLA Six-Week Look Ahead

TMS Toyota Manufacturing System

VA Value Added

VAS Value Added Steps

VSM Value Stream Mapping

IX

Page 12: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

List of Tables Table 2.1: Conceptualization of lean principle in construction ........................................ 8

Table 2.2: 5S Purpose and Goals .................................................................................... 20

Table 3.1: Productivity of resources in Gaza Strip……………………………………..32

Table 4.1: Details of project .......................................................................................... 35

Table 4.2: Productivity of the Project activities ............................................................. 38

Table4.3: NVA and VA activities in mobilization and excavation ................................ 42

Table 4.4: NVA and VA processes in plain concrete ................................................... 42

Table 4.5: NVA and VA processes in foundation ........................................................ 43

Table 4.6: NVA and VA processes in neck column ....................................................... 44

Table 4.7: NVA and VA processes in isolation.............................................................. 45

Table 4.8: NVA and VA processes in Back filling......................................................... 45

Table 4.9: NVA and VA processes for ground beam activity ........................................ 46

Table 4.10: NVA and VA processes for G.Floor column .............................................. 46

Table 4.11: NVA and VA processes for ground floor .................................................... 47

Table 4.12: NVA and VA processes in slab for Ground Floor....................................... 48

Table 4.13: NVA and VA processes in column for F.Floor ........................................... 49

Table 4.14: NVA and VA processes in slab for first Floor ............................................ 49

Table 4.15: NVA and VA processes in building for G.Floor ......................................... 50

Table 4.16: NVA and VA processes in building for F.Floor.......................................... 51

Table 4.17: Simulation result.......................................................................................... 56

Table 4.18: Waste elimination in mobilization and excavation...................................... 59

Table 4.19: Waste elimination in plain concrete ............................................................ 59

Table 4.20: Waste elimination in Foundation................................................................. 60

Table 4.21: Waste elimination in column neck .............................................................. 60

Table 4.22: Waste elimination in isolation ..................................................................... 61

Table 4.23: Waste elimination for backfilling ............................................................... .61

Table 4.24: Waste elimination in ground beam.............................................................. 62

Table 4.25: Waste elimination for ground floor column .............................................. .62

Table 4.26: Waste elimination for ground floor ............................................................ .63

Table 4.27: Waste elimination for G.Floor slab ............................................................ 63

X

Page 13: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.28: Waste elimination for F.Floor column ....................................................... 64

Table 4.29: Waste elimination for F.Floor Slab ............................................................. 64

Table 4.30: Waste elimination processes for building for G.Floor ................................ 65

Table 4.31: Waste elimination in building for F.Floor ................................................... 65

Table 4.31: Difference between activity before and after applying lean........................ 66

Table 4.33: Total project duration ................................................................................ 70

Table 4.34: Activities in a descending order based on duration..................................... 71

Table 4.35: Greatest duration of waste in activity .......................................................... 72

Table 4.36: Project duration without the most wasting activity .................................... .72

Table 4.37: Balancing the process .................................................................................. 74

Table 4.38: Cycle time compared ................................................................................... 78

Table 4.39: Process assigned and process completed..................................................... 80

XI

Page 14: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

List of Figures

Figure 2.1: Reduction of cycle time................................................................................ 11

Figure 2.2: Last Planner planning................................................................................... 18

Figure 2.3: Seven wastes ................................................................................................ 24

Figure 4.1: Procedure of the application of lean principles ................................ …..… 37

Figure 4.2: Application of lean to mobilization and excavation..................................... 52

Figure 4.3: Excavation process data ............................................................................... 53

Figure 4.4: Laboratory process data ............................................................................... 53

Figure 4.5: Application of lean to plain concrete ........................................................... 54

Figure 4.6: Formwork process data ................................................................................ 54

Figure 4.7: Casting plain concrete process data ............................................................. 55

Figure 4.8: Remove form work process data.................................................................. 55

Figure 4.9: Comparing value added steps to value added time ...................................... 68

Figure 4.10: Cause of failure .......................................................................................... 69

Figure 4.11:Simulation model ........................................................................................ 69

Figure 4.12: Duration variability before introducing buffer........................................... 73

Figure 4.13: Duration variability after introducing buffer.............................................. 78

Figure 4.14: Actual PPC of each week ........................................................................... 80

Figure 4.15: Average PPC of each four week ................................................................ 81

XII

Page 15: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Chapter One Introduction

Lean production was originally encapsulated within the Toyota Manufacturing System

and is well articulated by Womack (1990). Lean thinking subsequently became the

generic term to describe universal application beyond manufacturing (Womack and

Jones, 1996). The ideas of lean thinking comprise a complex amalgam of ideas

including continuous improvement, flattened organization structures, teamwork, the

elimination of waste, efficient use of resources and co-operative supply chain

management. Within the UK construction industry, the language of lean thinking has

become synonymous with the best practice. Confidence in these ideas remains so high

that the lean construction is an established component of construction best practice

(Green et al., 2005).

Lean construction much like current practice has the goal of better meeting customer

needs while using less of everything. But unlike current practice, lean construction rests

on production management principles. The result is a new project delivery system that

can be applied to any kind of construction but it is particularly suited for complex,

uncertain, and quick projects (Gregory et al., 1999).

Projects in the Gaza Strip are characterized by: low productivity, errors, poor co-

ordination, bad reputation, high accident rates, insufficient quality and overruns in cost

and schedule…etc.(Yahia, 2004).

The study was applied to a construction company, with wide experience in the field of

construction in Gaza Strip. The craftsmen with more than 10 years experience were met

so as to compare their productivity with that of those working at the Center National of

Animation Enterprises and Treatment of Information for Labor in Algeria. The reason

of lack of percent plan complete of work in the process, which means the rate of the

processes that were applied compared with that which should be applied, was defined

from the engineer in Abu Shahla office by using the five why tools of lean construction.

Finally, the result of applying lean construction, its methodology, and tools were

offered.

1

Page 16: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

1.1 Statement of the Problem Most of the construction projects in the Gaza Strip are characterized by inefficiencies,

large variability and low performance and thus wasting time, money and other resources

(Said, 2006). In this thesis, we will show the expected benefits of using some lean tools

in Gaza construction industry in order to reduce or eliminate waste and eventually

satisfy customer needs.

1. 2 Research Aim and Objectives The aim of this research is to study the status quo of the application of lean construction

practices in the Gaza Strip and their implications on the performance. The aim of this

research can be divided into the following objectives:

1. To identify the criteria of lean as they apply to construction projects.

2. To identify basic lean tools for process improvement.

3. To identify methodology for application lean tools

4. To investigate the impact of lean practices.

1.3 Methodology Outline The methodology used in undertaking the study has consisted of three stages:

1. Literature review including lean principles, lean tools and criteria of lean

construction.

2. A project was selected. Then, the processes and activities of the project were

analyzed using the daily reports. The duration and steps were found out.

3. Standardization and five why tools were applied on the project so as to reduce

the non value added process. Simulation was used to measure the impact of

value added.

Finally, results and recommendations are given.

1.4 Thesis contents This thesis includes five chapters. Chapter One introduces the problem statement,

objectives and methodology outline. Chapter Two introduces literature review including

the history of lean construction, lean construction principles, lean construction criteria,

lean construction tools, and seven wastes. In chapter three, methodology is given in

2

Page 17: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

details. Chapter Four analyzes case study data before and after applying lean tools.

Finally, conclusions and recommendations are given in Chapter Five.

3

Page 18: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Chapter Two Lean Construction

2.1 Lean Construction History The lean construction system initially appeared after the Second World War as

“Toyota system” or “lean manufacturing system”. Japan was defeated in the war, which

caused a lack of financial, physical and human resources thus resulting in the

superiority of American companies for the auto industry over Japanese companies by a

factor of 10 cars in production.

Then, Toyota leaders (Ohno and others), thought about the creation of this system

“Toyota system”.

Taiichi Ohno, who was given the task of developing a system that would

enhance productivity at Toyota, is generally considered to be the primary force behind

his system. Ohno chose some ideas from the west and particularly from Henry Ford’s

book “Today and tomorrow.” Ford’s moving assembly line of continuously flowing

material formed the basis for the Toyota production system. After some

experimentation, the Toyota production system was developed and was called “Just in

Time” between 1945 and 1970. Then the name was changed into “ Lean Production” as

the previous name seemed unsuitable. The system is still growing today all over the

world. The basic underlying idea of this system is to minimize the non value added.

In order to compete in today’s fiercely competitive market, US manufacturers

have come to realize that the traditional mass production concept has to be adapted to

the new ideas of lean manufacturing. A study that was done at the Massachusetts

Institute of Technology of the movement from mass production to world lean

manufacturing. The study underscored the great success of Toyota at NUMMI (New

United Motor Manufacturing Inc.) and brought out the huge gap that existed between

the Japanese and the western automotive industry. The ideas came to be adopted in the

US because the Japanese companies developed, produced and distributed products with

half or less human effort, capital investment, floor space, tools, materials, time, and

overall the expense (Abudallah et al., 2003).

4

Page 19: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

The lean movement in construction started around 1992 with the creation of the

International Group of Lean Construction, which accepted the Ohno’s production

system design criteria as a standard of perfection. Since then, and especially over the

past decade, organizations all over the world have been looking for ways to increase

competitive advantage for the delivery of capital projects through the application of lean

concepts and techniques (Arbulu et al., 2006).

Today, there are an Arabic inclination towards the application of lean system in

the local projects where we find it in many productive projects: military clothing

industry as in Iraq which got a big success and a big production development. A lot

researches, masters and doctoral theses recommended to apply it at the Construction

projects level in the Arabic countries (Sameh, 2008).

2.2 Lean Construction Definition Lean construction presents a coherent synthesis of the most effective techniques for

eliminating waste and delivering significant sustained improvement. in cost, time,

quality and safety simultaneously. In fact, lean construction has many definitions:

Ballard (2004) defines lean "added value by eliminating waste, being responsive to

change, focusing on quality, and enhancing the effectiveness of the workforce.

Typically, 95% of all lead time is non–value added". Ballard and Howell (2004) defined

it as “a temporary production system while delivering the product with maximum value

and minimum waste". whereas the lean construction institute (2003) defines lean

construction as, “a production management based approach to project delivery. Lean

production management has caused a revolution in manufacturing design, supply and

assembly. But Reiser (2000) defines lean construction as, "a project delivery system

based on the lean production management process, originally developed by the Toyota

Motor Company that is aimed at improving value by satisfying customer needs and

improving performance".

Finally, lean construction can be defined as added value by eliminating the waste of

space floor, material and the productivity of resources.

5

Page 20: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

2.3 Impact of Lean Construction According to (Colarelli Construction, 2005; Arbulu et al., 2006; Reiser et al., 2000),

lean construction provides key benefits and its impacts are as follows:

1. It delivers more value to the client with less waste of time and resources.

2. It helps contractors improve processes and overall project delivery.

3. It improves productivity by improving planning.

4. It helps accommodating change.

5. It reduces cost, accelerates delivery, and improves both quality and safety.

6. It delivers products or services on time and within budget.

7. It injects reliability, accountability, certainty, and honesty into the project

environment.

8. It reduces system noise.

9. It promotes continuous improvement in project delivery methods through

lessons learned.

2.4 Lean Construction Principles Lean construction consists of the following five principles:

2.4.1 Value

The first and most critical lean principle as presented in lean thinking is value. Womack

and Jones(2003) emphasize that value can only be defined by the ultimate customer

and only meaningful when it is expressed in terms of a specific product (a good, or a

service, and often both at once) which meets the customer’s needs at a specific price

and specific time.

2.4.2 Value Stream

The second lean principle as presented in lean thinking is value stream, Womack and

Jones(2003) emphasize that value stream can only be defined by specific activities

required to design, order and provide a specific product from concept to launch, order to

delivery, raw material into the hands of the customer.

6

Page 21: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

2.4.3 Flow

The third principle is flow, once all the wasteful activities are eliminated, the remaining

value-added steps need to ‘flow’. Conceptually companies have a difficult time

applying beyond internal departments. True integration of functions and departments in

a company into product teams organized along the value stream enables and promotes

flow of information and materials. Thus construction process is composed of two

different types of flows:

- Material process consisting of the flows of material to the site, including processing

and assembling on site.

- Work processes of construction teams. The temporal and spatial flows of construction

teams on site which are often closely associated with the material processes (koskela et

al., 1992).

2.4.4 Pull

The fourth lean principle as presented in lean thinking is pull, Womack and Jones(2003)

emphasize that pull can only be defined by implying the ability to design and make

exactly what the customer wants just when they want it. Nothing should be made until it

is needed, then it should be made quickly.

2.4.5 Perfection

The fifth lean principle as presented in lean thinking is perfection. Womack and Jones

(2003) emphasize that pull can only be defined by perfection implying the complete

elimination of waste. Important things to envision is the type of product and operating

technologies needed to improve.

The conceptualization of the lean in construction as developed by Björnfot (2006) is

shown in Table (2.1).

7

Page 22: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 2.1 Conceptualization of lean principle in construction (Björnfot, 2006).

No Lean principle Conceptualization in construction

1 Value

a) Define the customer.

b) Define what is value to the customer.

c) Define what is value to the delivery team.

d) Define how value is specified by products.

2 Value stream

a) Define all and activities required for construction b. Define all resources required for construction.

c) Standardize current practice.

d) Define and locate key component suppliers.

3 Flow

a) Identify none-value added activities (waste).

b) Remove or reduce the influence of waste as it is observed

c) Identify key performance indicators.

d) Measure performance.

4 Pull

a) Keep the production system flexible to customer

requirements.

b) Keep the production system adaptable to future customer

requirements.

c) Exercise a conscious effort at shortening lead and cycle

times.

d) Perform work at the last responsible moment.

5 Perfection

a) Keep the production system transparent for all involved

stakeholders.

b) Capture and implement experience from completed

projects.

c) Exercise a conscious effort at improving value for

customers.

d) Exercise a conscious effort at improving the execution of

work.

8

Page 23: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

2.5 Criteria of Lean Construction Koskela (1992) applied lean production in the construction with eleven criteria which

are shown bellow:

2.5.1 Non-value added activities reduction

Reducing the share of non value-added activities is a fundamental guideline. Experience

shows that non value-added activities dominate most processes; usually only 3% to 20

% of steps add value (Ciampa et al., 1991), and their share of the total cycle time is

negligible, from 0.5 to 5 % (Stalk and Hout et al.,1990).

There are three main causes for the presence of non value-added activities:

• Construction Management: Non value-added activities are existed by

traditional management. Every time a task is subdivided into two subtasks

executed by different specialists, This leads to an expansion of the non value-

added activities(such as : inspecting, waiting …etc) .

• Ignorance: Especially, it exists in the administration of construction. The

volume of non value-added activities is not measured. This requires contacting

with a project manager with a wide experience in dealing with the use of lean

tools.

• Seven wastes during construction: There are mistakes in the field or defects in

material. 2.5.2 Increase output value through systematic consideration of customer

This is considered the second criteria. Since value added is achieved according to

customer’s requirements without any exaggeration. Finding, for example the enterprise

companies are clients to the consultant. The consultant engineer’s office has to give the

design without any errors, the quantity of bidding cope with the design, the duration of

project is sensible. Considering the owner is a contractor’s customer, who aims to get a

building complied with specification of bidding, time schedule and costs as in the

contract.

2.5.3 Variability reduction

This is considered the third criteria. Schonberg (1986) says that “the reducing of

variation must be considered an essential aim”. So, having to measure the reasons of the

variation and work on reducing it, can be done by standardization. It works to measure

the rate of standardization of work per hour or day. So this can make master schedule

9

Page 24: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

for measuring the percent plan complete (PPC) and look for the causes of failure. In

addition, PPC also helps to reduce the variation.

2.5.4 Cycle time reduction The cycle time is the time required for executing the process traverse the construction

flow. The cycle time is used to measure the flow processes and it is a more useful than

cost and quality. It can be represented as follows:

Cycle time = Processing time + inspection time + wait time + move time

The new construction philosophy aims to compress the cycle time, which forces the

reduction of inspection, move and wait time.

In addition to the forced elimination of wastes, compression of the total cycle time gives

the following benefits: faster delivery to the customer, reduced need to make forecasts

about future demands, decrease of disruption of the construction process due to change

orders, easier management because there are fewer customer orders to keep track of.

The principle of cycle time compression also has other interesting implications:

1. From the perspective of control, it is important that the cycles of deviation detection

and correction be speedy.

2. In design and planning, there are many open-ended tasks that benefit from an

iterative search for successively better (if not optimal) solutions. The shorter the

cycle time, the more cycles are affordable.

3. From the point of view of improvement, every layer in an organizational hierarchy

adds to the cycle time of error correction and problem solving. This simple fact

provides the new construction philosophy’s motivation to decrease organizational

layers, thereby empowering the persons working directly within the flow.

Practical approaches to cycle time reduction include the following: Eliminating work-

in-progress (this original JIT goal reduces the waiting time and thus the cycle time),

reducing storing time and setting temporary stores so that moving distances are

minimized, thus keeping things moving; smoothing and synchronizing the flows,

reducing variability, changing activities from sequential order to parallel order, and

eventually isolating the main value-added sequence from support work. In general,

solving the control problems and constraints prevents a speedy flow.

10

Page 25: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Figure (2.1) shows that the cycle time can be progressively compressed through

elimination of non value added activities and variability reduction.

Processing time

Processing time

Processing time

Waste time

Waste time

Waste time

Processing time

Figure 2.1 Reduction of cycle time (Berliner and Brimson, 1988 )

2.5.5 Simplify by minimizing the number of steps and parts

The human ability to deal with complexity is restricted. This complexity of a product

increases non value-added activities. Complexity means the increase of the number of

steps in the production process. Reducing the number of steps leads to a reduction of

cost and an increase in reliability in the production process. Simplification can be

understood as, reducing of the number of components in a product, and reducing of the

number of steps in a material or information flow. Simplification can be realized, on the

one hand, by eliminating non value-added activities from the production process, and on

the other hand by reconfiguring value-added parts or steps. Organizational changes can

also bring about simplification. Vertical and horizontal division of labor always brings

about non value-added activities, which can be eliminated through self contained units

(multi-skilled, autonomous teams). Practical approaches to simplification include:

shortening the flows by consolidating activities, reducing the part count of products

through design changes or prefabricated parts, standardizing parts, materials, tools, etc.,

decoupling linkages, and minimizing the amount of control information needed.

11

Page 26: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

2.5.6 Increase output flexibility Flexibility should be limited during the period of construction. We can talk about it

from the duration of the project, for example, by using standardization of works, we can

add the number of resources to reduce the time, while the change in the activity affects

the project.

2.5.7 Increase process transparency

In a theoretical sense, transparency means a separation of the network of information

and the hierarchical structure of order giving, which in the classical organization theory

are identical. The goal is thus to substitute self-control for formal control and related

information gathering.

Transparency reduces errors and increases motivation for improvement. Thus, it is an

objective to make the production process transparent and observable for facilitation of

control and improvement: “to make the main flow of operations from start to finish

visible and comprehensible to all employees” (Stalk and Hout 1989). This can be

achieved by making the process directly observable through organizational or physical

means, measurements, and public display of information.

Practical approaches for enhanced transparency include the following:

Establishing basic housekeeping to eliminate clutter.

Making the process directly observable through appropriate layout and signage

Rendering invisible attributes of the process visible through measurements

Embodying process information in work areas, tools, containers, materials and

information systems

Utilizing visual controls to enable any person to immediately recognize

standards and deviations from them.

Reducing the interdependence of production units (focused factories).

2.5.8 Focus control on the complete process

There are two causes of segmented flow control: the flow traverses different units in a

hierarchical organization or crosses through an organizational border. In both cases,

there is a risk of sub optimization.

There are at least two prerequisites for focusing control on complete processes. First,

the complete process has to be measured. Secondly, there must a controlling authority

for the complete process. Several alternatives are currently used. In hierarchical

12

Page 27: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

organizations, process owners for cross-functional processes are appointed, with

responsibility for the efficiency and effectiveness of that process (Rummler et al.,

1990). A more radical solution is to let self-directed teams control their processes

(Stewart et al., 1992).

For inter-organizational flows, long term co-operation with suppliers and team building

has been introduced with the goal of deriving mutual benefits from an optimized total

flow.

2.5.9 Build continuous improvement into the process

The effort to reduce waste and to increase value is an internal, incremental, and

iterative activity that can and must be carried out continuously. There are several

necessary methods for institutionalizing continuous improvement; these include the

following:

Measuring and monitoring improvement.

Setting stretch targets (e.g. for inventory elimination or cycle time

reduction), by means of which problems are unearthed and their solutions

are stimulated.

Giving responsibility for improvement to all employees; a steady

improvement from every organizational unit should be required and

rewarded.

Using standard procedures as hypotheses of best practice, to be constantly

challenged by better ways.

Linking improvement to control: improvement should be aimed at the

current control constraints and problems of the process. The goal is to

eliminate the root of problems rather than to cope with their effects.

2.5.10 Balance flow improvement with conversion improvement In the improvement of productive activities, both conversions and flows have to be

addressed; however, the question is how these two alternatives should be balanced.

For any production process, the flow and conversion aspects have a different

potential for improvement. This goes as a rule:

The higher the complexity of the production process, the higher the impact

of flow improvement

13

Page 28: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

The more wastes inherent in the production process, the more profitable is

flow improvement in comparison to conversion improvement.

However, in a situation where flows have been neglected for decades, the potential

for flow improvement is usually higher than conversion improvement. On the

other hand, flow improvement can be started with smaller investments, but usually

requires a longer time than a conversion improvement.

The crucial issue is that flow improvement and conversion improvement are

intimately interconnected:

Better flows require less conversion capacity and thus less equipment

investment

More controlled flows make implementation of new conversion technology

easier

New conversion technology may provide smaller variability, and thus flow

benefits.

Therefore, one is tempted to agree with Ohno, who argues that “improvement

adheres to a certain order” (Ohno, 1988). It is often worthwhile to aggressively

pursue flow process Improvement before major investments in new conversion

technology: “Perfect existing processes to their full potential before designing new

ones” (Blaxill et al., 1991). Later, technology investments may be aimed at flow

improvement or redesign.

2.5.11 Benchmark

Unlike technology for conversions, the best flow processes are not marketed to us; we

have to find the world class processes ourselves.

Often benchmarking is a useful stimulus to achieve breakthrough improvement through

radical reconfiguration of processes.

The basic steps of benchmarking include the following (Camp et al., 1989)

Knowing the process; assessing the strengths and weaknesses of sub

processes.

Knowing the industry leaders or competitors; finding, understanding and

comparing the best practices.

Incorporating the best; copying, modifying or incorporating the best

practices in your own sub processes.

14

Page 29: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Gaining superiority by combining existing strengths and the best external

practices.

2.6 Tools of Lean Construction The lean construction tools which can be applied on the construction projects are:

2.6.1. Just in Time (JIT)

It is a philosophy that works in the elimination of waste in all activities and operations.

JIT system is a production cost system in the specified time for certain productivity

within the project; productivity which leads to its development and reduce its costs.

It is an inventory costs system in a timely manner, which works on receiving materials

today and use them tomorrow and this can be effected by adjusting the time of material

receipt at the time we start using it in production and adjusting the time of completion

with the time we delivered to customer. This represents a step in controlling stocks

systems leading to a JIT process.

On this basis, the adjusting time system which is working in production cost reduction

is by reducing the supply periods.

The most important JIT goals:

• Dispensing with all types of stock or reduced to a minimum.

• Reducing the wastage of time and resources in the productive processes.

• Purchasing in the appropriate time and quantities to meet consumer needs in a

timely and quality Occasion.

• The development of trust and relationship between the company and suppliers

through the development of long-term goals that lead to confidence

To deduce the problems and disadvantages of production costs at the time specified as

follows:

1. Difficulty of achieving some assumptions, such as the absence of defects in

production, as well as reaching level units with zero. Fault, along with zero

inventory, means difficulty in achieving it in large-scale company or companies

with seasonal activity.

2. This system requires substantial cooperation among management, workers and

suppliers, and we cannot apply this system without integration among those parties.

15

Page 30: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

3. System requires the need to develop general accounting systems, special cost

system, and general costs concepts System.

4. Some company do not accept the idea of the application of the system of

production costs in time because of its high cost, which occur at the beginning of the

application of this system by the preparation of administrators and workers and by

changing company dealings with both suppliers and customers.

5. Administrators are not convinced about the change from existing systems to a

system of production costs in time because they fear its application failure.

6. Closures is the biggest problem facing the economic side to provide materials as the

stock in this system is equal to zero, and in the case of the closure, we will not find

materials to be used by the contractor and consequently activities are halted.

2.6.2 Last Planner System

Ballard (2000) indicates that Last Planner System (LPS) is a technique that shapes

workflow and addresses project variability in construction. The Last Planner is the

person or group accountable for operational planning, that is, the structuring of product

design to facilitate improved work flow, and production unit control, that is, the

completion of individual assignments at the operational level. In the last planner system,

the sequences of implementation (master schedule, Reverse Phase Schedules (RPS),

six-week look ahead, Weekly Work Plan (WWP), Percent Plan Complete (PPC),

constraint analysis and variances analysis).

The goals of last planner are to pull activities by reverse phase scheduling through team

planning and optimize resources in the long-term. This tool is similar to the Kanban

system and production leveling tools in lean manufacturing.

2.6.2.1 Master Schedule

The master schedule is an overall project schedule, with milestones, that is usually

generated for use in the bid package. RPS is produced based on this master schedule.

2.6.2.2 Reverse Phase Scheduling (RPS)

Ballard and Howell (2003) indicated that a pull technique is used to develop a schedule

that works backwards from the completion date by team planning; it is also called

Reverse Phase Scheduling (RPS). They also state that phase scheduling is the link

between work structuring and production control, and the purpose of the phase schedule

16

Page 31: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

is to produce a plan for the integration and coordination of various specialists’

operations.

The reverse phase schedule is developed by a team consisting of all the last planners. It

is closer to reality than the preliminary optimal schedule which is the master schedule.

However, without considering actual field factors in the RPS, the RPS is less accurate

than the WWP.

2.6.2.3 Six-Week Look Ahead (SWLA)

Ballard (2000) indicated that the tool for work flow control is look ahead schedules.

SWLA shows what kinds of work are supposed to be done in the future. In the look

ahead window, week 1 is next week, the week after the WWP meeting. The number of

weeks of look ahead varies. For the design process, the look ahead window could be 3

to 12 weeks (Ballard 2000). All six-week-look ahead durations and schedules are

estimated based on the results of the RPS, and constraints are indicated in order to solve

the problems before the actual production takes place. SWLA is distributed to all last

planners at WWP meetings. Lean look ahead planning is the process to reduce

uncertainty to achieve possible constraint free assignments (Koskela et al., 2000).

2.6.2.4 Weekly Work Plan (WWP)

Should, Can, and Will are the key terms in WWP (Ballard 2000). Weekly Work Plan

(WWP) is produced based on SWLA, the actual schedule, and the field condition before

the weekly meeting. Along with this plan, manpower from each trade will be adjusted to

the need.

• Should: Indicates the work that is required to be done according to schedule

requirements. • Can: Indicates the work which can actually be accomplished on account of

various constraints on the field.

• Will: Reflects the work commitment which will be made after all the constraints

are taken into account.

The WWP meeting covers the weekly schedule, safety issues, quality issues, material

needs, manpower, construction methods, backlog of ready work, and any problems that

can occur in the field. It promotes two-way communication and team planning to share

information on a project in an efficient and accurate way. It can improve safety, quality,

17

Page 32: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

the work flow, material flow, productivity, and the relationship among team members.

Ballard and Howell (2003) indicates that WWP should emphasize the learning process

more by investigating the causes of delays on the WWP instead of assigning blames and

only focusing on PPC values. Variance analysis is conducted based on the work

performance plan from the previous week. The causes of variance should be

documented within the WWP schedule (Figure 2.2)

LAST PLANNER

PLANNING CAN WILL

SHOULD

Figure 2.2 Last Planner planning

2.6.2. 5 Percent Plan Complete (PPC)

The measurement metric of Last Planner is the Percent Plan Complete (PPC) values. It

is calculated as the number of activities that are completed as planned divided by the

total number of planned activities (Ballard 2000). The positive (upward) slope between

two PPC values means that production planning was reliable and vice versa. According

to Ballard (1999), PPC values are highly variable and usually range from 30% to 70%

without lean implementation. To achieve higher values (70% and above), additional

lean construction tools such as first run studies have to be implemented.

2.6.3 Increased Visualization

The increased visualization lean tool is about communicating key information

effectively to the workforce through posting various signs and labels around the

construction site. Workers can remember elements such as workflow, performance

targets, and specific required actions if they visualize them (Moser and Dos Santos

2003). This includes signs related to safety, schedule, and quality. This tool is similar to

18

Page 33: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

the lean manufacturing tool, Visual Controls, which is a continuous improvement

activity that relates to the process control

2.6.4 First Run Studies

First Run Studies are used to redesign critical assignments (Ballard and Howell et al.,

1977), part of continuous improvement effort; and include productivity studies and

review work methods by redesigning and streamlining the different functions involved.

The studies commonly use video files, photos, or graphics to show the process or

illustrate the work instruction. The first run of a selected craft operation should be

examined in detail, bringing ideas and suggestions to explore alternative ways of doing

the work. A PDCA cycle (plan, do, check, act) is suggested to develop the study: Plan

refers to select work process to study, assemble people, analyze process steps,

brainstorm how to eliminate steps, check for safety, quality and productivity. Do means

to try out ideas on the first run. Check is to describe and measure what actually happens.

Act refers to reconvening the team, and communicating the improved method and

performance as the standard to meet.

2.6.5 Daily Huddle Meetings (Tool-box Meetings)

Two-way communication is the key of the daily huddle meeting process in order to

achieve employee involvement. With awareness of the project and problem solving

involvement along with some training that is provided by other tools, employee

satisfaction (job meaningfulness, self-esteem, sense of growth) will increase. As part of

the improvement cycle, a brief daily start-up meeting was conducted where team

members quickly give the status of what they had been working on since the previous

day's meeting, especially if an issue might prevent the completion of an assignment

(Schwaber, 1995). This tool is similar to the lean manufacturing concept of employee

involvement, which ensures rapid response to problems through empowerment of

workers, and continuous open communication through the tool box meetings.

2.6.6 The 5s Process (Visual Work Place)

• Sort

The first level of housekeeping consisted of separating material by reference and

placing materials and tools close to the work areas with consideration of safety and

crane movements.

19

Page 34: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

• Straighten

Next, materials were piled in a regular pattern and tools were placed in gang boxes.

Each subcontractor took responsibility for specific work areas on the job site.

• Standardize

The next level included the preparation of a material layout design. The layout

contained key information of each work activity on the job site. The visual

workplace helped locate incoming material, reduce crane movements, and reduce

walking distance for the crews.

• Shine

The next step consisted of keeping a clean job site. Workers were encouraged to

clean workplaces once an activity had been completed. A housekeeping crew was

set to check and clean hidden areas on the job site.

• Sustain

The final level of housekeeping sought to maintain all previous practices throughout

the project. At the end of the project, this level is not fully achieved, in part because

project personnel did not view housekeeping as a continuous effort. They had to be

reminded frequently of housekeeping practices.

Table 2.2 resumes 5S purpose and goals.

Table 2.2 5S Purpose and Goals 5S Elements Purpose Goals

Sort Eliminating what is not needed

• Eliminate unnecessary items. • Create means to keep them out of the

environment. • Regain valuable space. • Eliminate safety hazards caused by

clutter. • Produce more positive environment.

Set in Order Creating the most effective physical layout possible

• Design space that supports work flow.

• Create a structure that supports neatness.

• Organize tools, equipment, and materials in a way that facilitates efficient operations.

Shine

Establish a clean environment

• Remove clutter, debris from environment.

• Identify problems through inspection and initiate a correction process.

20

Page 35: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 2.2 5S Purpose and Goals (cont.)

5S Elements Purpose Goals

Standardization

Creating standard ways of doing/storing things so anyone can di/find anything.

• Establish standards that describe how things should exist.

• Establish communication devices so that everyone may understand how things work.

Sustain

Integrating 5S principles into the culture of the organization

• Form 5S habits. • Integrate 5S into the organization's

culture. become s the way things are done around here.

2.6.7 Fail-Safe for Quality

• Check for Quality

An overall quality assessment was completed at the beginning of the project. Most

quality issues could be addressed by standard practices, and it seemed there was

little room for improvement. During the execution of the project, however, some

critical items appeared such as a new vibration method for shearing walls was

suggested and implemented by the superintendent of the project.

• Check for Safety

Safety was tracked with safety action plans, i.e., lists of main risk items prepared by

each crew. Potential hazards were studied and explored during the job. Most

hazards, such as eye injuries, falls and trips, and hearing loss, have standard

countermeasures; however, in practice, workers have to be reminded of safety

practices (Salem et al., 2006).

2.6.8 Productivity Standardization

Productivity is a measure of how much we produce per unit input. From a client's

perspective, higher productivity leads to lower costs, shorter construction programs,

better value for money and a higher return on investment (Malcolm et al., 2001).

Contractors’ profits from increases in productivity are generally in the range of 2% to

4% of turnover. The increase in labor productivity by 25% would increase their profit

margins from 2% to 8%, or from 4 % to 10%, a two and a half to fourfold increase in

profit.

Partial Productivity = Total Output / (1) Input

Labour Productivity =Total Output / Number of labor

21

Page 36: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Material Productivity = Total Output / Amount of Material

Machine Productivity = Value of production / Amount of work (Yahia, 2004).

2.6.9 The Five Why's:

Five whys as part of lean manufacturing is a problem solving technique that allows you

to get at the root cause of a problem fairly quickly. It was made popular as part of the

Toyota Production System (1970’s.) Application of the strategy involves taking any

problem and asking “Why - what caused this problem”.

The benefits of the 5 Whys are as follows:

• It helps to quickly identify the root cause of a problem.

• It helps determine the relationship between different root causes of a problem.

• It can be learned quickly and does not require statistical analysis to be used.

2.7 Construction Waste A number of definitions of waste are available. In general, Alarcon (1994), Koskela

(1992) and Love et al. (1997) argued that all those activities that produce costs, direct or

indirect, and take time, resources or require storage but do not add value or progress to

the product can be called waste. These waste categories are measured as a function of

their costs, including opportunity costs. Furthermore, other types of waste are related to

the efficiency of process, equipment or personnel.

Non value-added activity (also called waste): Activity that takes time, resources or

space but does not add value.(koskela et al., 1992).

Waste in the construction industry has been the subject of several research projects

around the world in recent years (Formoso et al., 1999). The study by Skoyles (1987) in

the UK also suggested that all those involved in the construction process contributed to

waste. This includes those who design materials, plant and building; those who specify

and communicate, for example, the quantity surveyors and head office staff; and

particularly site managers and site operators.

Therefore, the responsibility for minimizing waste should be shared by all parties

involved in construction projects, including:

• All managers in building organizations, not only site managers,

• Those who design, manufacture and supply merchandise and plant used in

construction,

22

Page 37: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

• Those who design buildings,

• Those who specify, describe and account for the works, and

• Those who provide briefs pay for and use buildings.

Graham and Smithers (1996) believed that construction waste could occur during

different project phases:

• Design (plan errors, detail errors and design changes),

• Procurement (shipping error and ordering error),

• Materials handling (improper storage, deterioration and improper handling on and

off site)

• Operation (human error, trades person, labors, equipment error, accidents and

weather),

• Residual (leftover and irreclaimable non-consumables), and

• Other (theft, vandals and clients actions).

Despite variations in construction projects, potential material waste is caused by similar

inefficiencies in design, procurement, material handling, operation or residual on-site

waste such as packaging (Formoso et al., 1993 and Gavilan and Bernold, 1993).

Research also indicated that clients could be a source of waste through careless

inspection procedures and variation orders during the process. Initially, carelessness at

the design stage can lead to excessive waste which creates a need to over order to avoid

a shortage of materials on site (Graham and Smithers, 1996). Waste in construction is

not only focused on the quantity of waste of materials on-site, but also related to several

activities such as overproduction, waiting time, material handling, processing,

inventories and movement of workers (Formoso et al., 1999; Alarcon, 1994).

Consolidating research from authors (Alarcon, 1995; Alwi, 1995; Koskela, 1993;

Robinson, 1991; Lee et al., 1999; Pheng and Hui, 1999), the main categories of waste

during the construction process can be described as: reworks/repairs, defects, material

waste, delays, waiting, poor material allocation, unnecessary material handling and

material waste. In Chile, a research study from 1990 to 1994, focusing on waste was

conducted to identify the most relevant factors that produce waste of productive time in

building construction works (Serpell et al., 1995). The study concluded that waiting

time, idle time and travelling time, indicated as the main subcategory of non-

contributory work (waste), explained 87% of the total value of waste. Another

23

Page 38: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

investigation showed that 25 percent time savings is achievable in a typical construction

work package without increasing allocated resources (Mohamed et al., 1996).

Lean construction maximizes value and reduces waste and applies specific techniques in

an innovative project delivery approach including supply chain management and Just-

In-Time techniques as well as the open sharing of information between all the parties

involved in the production process. Lean manufacturing is an outgrowth of the Toyota

Production system that was developed by Taichii Ohno in Toyota in the 1950s. Ohno

identified seven wastes in mass production systems (Figure 2.3).

Waiting time

Defects

Over-

processing

Figure 2.3 Seven wastes

Motion

Material

Movement

Overproducing

Inventory

The seven wastes

24

Page 39: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

2.8 Construction Waste in the Gaza Strip According to Said (2006), construction wastes Gaza Strip are classified according to

the seven wastes as follows:

2.8.1 Over-production

Over-production is unnecessarily producing more than demanded or producing it too

early before it is needed. This increases the risk of obsolescence, increases the risk of

producing the wrong thing and increases the possibility of having to sell those items at a

discount or discard them as scrap. However, there are some cases when an extra supply

of semi-finished or finished products is intentionally maintained, even by lean

manufacturers.

Over-production waste of construction in the Gaza Strip is due to:

1. Ordering of materials that do not fulfill project requirements defined on design

documents, and waiting for replacement.

2. Over ordering or under ordering due to mistake in quantity surveys.

3. Over ordering or under ordering due to lack of coordination between warehouse

crews and construction crews.

2.8.2 Defects: (Correction)

In addition to physical defects which directly add to the costs of goods sold, this may

include:

errors in paperwork, provision of incorrect information about the product, late delivery,

production to incorrect specifications, use of too much raw materials or generation of

unnecessary scrap, repair or rework wastes time and resources at every level of the

organization, correction means doing it twice which doubles an employee’s exposure to

risk

Defects waste of construction in the Gaza Strip is due to :

1. Damage materials on site.

2. Unnecessary inventories in site which lead to waste.

3. Manufacturing defects.

4. Poor quality of materials.

5. Use of incorrect material, thus requiring replacement.

6. Equipment frequently breakdown.

25

Page 40: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

7. Poor technology of equipment.

8. Shortage of tools and equipments required.

10. Rework due to workers’ mistakes.

11. Damage to work done caused by subsequent trades.

12. Poor workmanship.

2.8.3 Inventory

Inventory waste means having unnecessarily high levels of raw materials, work-in-

progress and finished products. Extra inventory leads to higher inventory financing

costs, higher storage costs and higher defect rates.

Inventory hides waste and defects as materials that have been fabricated and stored for

various projects, backlog of good work over jobs, a batch of engineering

recommendations, and massive amounts of data being stored for use at a later date or

never used at all.

Inventory waste of construction in the Gaza Strip is due to:

1. Wrong storage of materials.

2. Inadequate stacking and insufficient storage on site.

3. Insufficient instructions about storage and stacking.

4. Inappropriate storage leading to damage or deterioration.

2.8.4 Transportation: (Material Movement)

Transportation includes any movement of materials that does not add any value to the

product, such as moving materials between workstations. The idea is that transportation

of materials between productions stages should aim for the ideal that the output of one

process is immediately used as the input for the next process. Transportation between

processing stages results in prolonging production cycle times, the inefficient use of

labor and space and can also be a source of minor production stoppages. Unnecessarily

moving materials wastes

time, energy, resources, and increases the likelihood of injury such as moving work-in-

process from a site to site, moving an engineering recommendation from one area to

another for review, moving pipe from location to location.

Transportation waste of construction in the Gaza Strip is due to:

1. Damage during transportation

2. Use of inadequate tools and equipments

26

Page 41: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

3. Poor storage

4. Far distance between place of working and storage.

5. Unpacked supply (fragile).

2.8.5 Waiting

Waiting is idle time for workers or machines due to bottlenecks or inefficient

production flow on the factory floor. Waiting also includes small delays between

processing of units. Waiting results in a significant cost insofar as it increases labor

costs and depreciation costs per unit of output are in general known as: waiting for

parts, waiting for decisions or direction, waiting for data or information, waiting for

recommendation and waiting for supplies.

Waiting waste of construction in the Gaza Strip is due to:

1. Waiting for design documents and drawings Motion.

2. Rework that don't comply with drawings and specifications.

3. Rework due to workers’ mistakes.

4. Delays in passing of information to the contractor on products.

5. Waiting for workers or materials or equipments to arrive.

6. Equipment frequently breakdown.

7. Delay in commencement of project.

8. Delay in performing inspection and testing by the consultant engineer.

9. Suspension of work by the owner.

10. Change orders.

2.8.6 Motion

Motion includes any unnecessary physical motions or walking by workers which diverts

them from actual processing work. For example, this might include walking around the

factory floor to look for a tool, or even unnecessary or difficult physical movements,

due to poorly designed ergonomics, which slow down the workers. Unnecessary

movement (walking, reaching, lifting, etc.) wastes time and energy such as walking

back and forth between equipment and a truck to get tools or parts, walking back and

forth between the drawing table and a document storage area to get information, going

to a warehouse to get parts

Motion waste of construction in the Gaza Strip is due to:

1. Poor schedule to procurement the materials.

27

Page 42: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

2. Unnecessary material handling.

3. Tradesmen slow/ineffective.

4. Far distance between place of working and storage.

5. Poor distribution of materials in site.

6. Lack of proper maintained pathways.

7. Difficulty in motion of worker in the site

2.8.7 Over-processing

Over-processing is unintentionally doing more processing work than the customer

requires in terms of product quality or features – such as polishing or applying finishing

on some areas of a product that won’t be seen by the customer. Doing more work tends

to keep people “busy,” but adds no “value” such as writing a comprehensive legal

agreement when a simple agreement would suffice, replacing more parts than necessary,

spending extra time doing more analysis than is really necessary, unnecessary

complexity.

Over-processing waste of construction in the Gaza Strip is due to:

1. Conversion waste from cutting uneconomical shapes.

2. Using excessive quantities of materials more than the required.

3. Wrong handling of materials.

4. Insufficient instructions about handling.

5. Lack of workers or tradesmen or subcontractors’ skill.

6. Difficulty in performance and professional work.

7. Interaction between various specialists.

8. Using untrained labors

28

Page 43: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

2.9 Summary The lean construction takes its idea from the lean manufacturing by making customer’s

needs as the main priority of the company objectives. The application of lean

construction started in 1992 by International Group of Lean Construction. The main

objective of lean construction is to increase the value added activities and remove or

reduce the non-value added activities in the project. The impact of lean construction

gives more value to the client with less waste of time and resources. It helps contractors

improve processes and overall project delivery, improve productivity by improving the

planning. The impact is also an approach well suited to accommodate change, reduces

cost, accelerates delivery, improves both quality and safety, delivers products or

services on time and within budget. It also injects reliability, accountability, certainty,

and honesty into the project environment and reduces system noise, improves project

delivery methods and promotes continuous improvement in project delivery methods

through lessons learned. Lean thinking consist of five points: Value, value stream, flow,

pull and perfection. Koskela (1992) applied lean production in the construction with

eleven criteria which are: non-value-added activities reduction, increase output value,

variability reduction, cycle times reduction, simplifies by minimizing the number of

steps, increase output flexibility, increase process transparency, benchmark, build

continuous improvement into the process, balance flow improvement with conversion

improvement and focus control on the complete process. The lean construction tools

are: Just in time (JIT), last planner system, increased visualization, first run studies,

productivity, the 5S process, fail-safe for quality, the 5 why's and daily huddle meetings.

The seven wastes according to the research thesis of the construction wastes in the

Gaza Strip (Said, 2006) are: over-production (ordering of materials that do not fulfill

project requirements defined on design documents, and waiting for replacement, over

ordering or under ordering due to a mistake in quantity surveys, over ordering or under

ordering due to lack of coordination between warehouse and construction crews),

defects (damage materials on site, unnecessary inventories in site which lead to waste,

poor quality of materials, use of incorrect material, thus requiring replacement,

equipment frequently breakdown, poor technology of equipment, shortage of tools and

equipments required, rework due to workers’ mistakes, damage to work done caused by

subsequent trades, poor workmanship and choice of wrong construction method ),

29

Page 44: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

inventory (Wrong storage of materials. Inadequate stacking and insufficient storage on

site, insufficient instructions about storage and stacking and inappropriate storage

leading to damage or deterioration), transportation (damage during transportation, use

of inadequate tools and equipments, poor storage, far distance between place of working

and storage and unpacked supply), waiting (waiting for design documents and drawings

motion, rework that does not comply with drawings and specifications, rework due to

workers’ mistakes, delays in passing of information to the contractor on products,

waiting for workers or materials or equipments to arrive, equipment frequently

breakdown, delay in commencement of project, delay in performing inspection and

testing by the consultant engineer and suspension of work by the owner and change

orders ), motion (poor schedule to procurement the materials, unnecessary material

handling, tradesmen slow/ineffective, far distance between place of working and

storage, poor distribution of materials in site, lack of proper maintained pathways, and

difficulty in motion of worker in the site ) and over-processing (conversion waste from

cutting uneconomical shapes, using excessive quantities of materials more than the

required, wrong handling of materials, insufficient instructions about handling, lack of

workers or tradesmen or subcontractors’ skill, difficulty in performance and

professional work, interaction between various specialists and using untrained labors).

In this thesis, we shall work on achieving the largest number of lean construction

criteria because the project which was studied was completed. Waste in the value added

process and non-value added process will be eliminated or reduced. These wastes are

particularly found in the project that was studied. Standardization and five why were the

chosen tools to apply and implement lean construction in the Gaza Strip.

30

Page 45: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Chapter Three

Methodology

This chapter presents the methodology which was followed in this research.

3.1 Research Strategy Quantitative and qualitative methods are used in this thesis. Quantitative data has been

collected to measure the proportion of non-value added and the value added for time

and steps in each process. This was measured by standardization tools, while qualitative

data was used in order to understand the reasons of non-value added in the process by

using the five why tools and giving solutions and suggestions for reducing the non-

value added in construction.

3.2 Data Collection To achieve the objectives of the current study, the researcher has used several sources.

These include:

3.2.1 Primary Sources

Productivity data was obtained for Yahia (2004). Moreover 30 crafts men who have

more than 10 years experience were interviewed. The results obtained were compared

with productivity data reported in the Center National of Animation Enterprises and

Treatment of Information for Labor in Algeria Company. Minimum, the most likely and

the maximum productivity of the resources are shown in (Table 3.1). In addition, the 5

why were used to determine the causes of waste.

31

Page 46: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 3.1 Productivity of resources in Gaza Strip

Unit/hours Main Activity

Activity process Unit

Minimum Most likely

Maximum

Mobilization and excavation Excavation work M3 57.69 62.5 68.18

Form work M3 0.625 0.875 1 Cast plain concrete M3 0.75 0.875 1 Plain concrete Remove form work M3 0.58 0.7 0.875 Form work M3 0.625 0.875 1.125 Fix neck column M3 0.648 0.81 1.08 Cast foundation M3 5.77 6.5 12

Foundation work

Remove form work M3 2.62 3.25 4.31 Form work M3 0.072 0.083 0.147 Cast concrete M3 0.083 0.1 0.125 Neck columnRemove form work M3 0.31 0.375 0.46 First layer M3 17.85 20.8 22.3 Second layer M3 25 31.25 41.66 Back filling Final layer M3 25 31.25 41.66 Form work M3 0.28 0.4 0.58 Cast concrete M3 0.083 0.1 0.125 Ground beamRemove form work M3 0.7 0.93 1.125 Fix steel column M3 1.81 2.26 3 Form work M3 0.176 0.2 0.35 Cast concrete M3 0.4 0.48 0.6 Column work

Remove form work M3 1.51 1.81 2.26 Preparation work M2 33.33 36.36 40 Steel work M2 14.28 14.81 15.38 Mechanic work M2 66.7 80 100 Ground floor

Cast concert M2 66.7 80 100 Form work M2 6.55 7.37 8.42 Hollow cement Block work M2 9.83 11.8 14.75

Steel work M2 6.55 7.37 8.42 Electric work M2 6 8 12 Cast concrete M2 8 9 10

Slab work

Remove form work M2 4.91 5.9 7.37

32

Page 47: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 3.1 Case study productivity (Cont.)

Unit/hours Main

Activity Activity process Unit

Minimum Most likely Maximum

Building under the window M2 2.07 2.17 2.38

Lintel work under window ML 15.91 19.1 23.87

Cast lintel under the windows ML 47.75 63.66 95.5

Remove form work ML 23.87 31.83 47.75 Building behind the widows M2 2.65 2.8 3.18

Lintel work behind window ML 15.91 19.1 23.87

Cast lintel up the windows ML 47.75 63.66 95.5

Remove form work ML 47.75 31.83 93.87

Building work

Building up the window M2 2.07 2.17 2.38

3.2.2 Secondary Sources

The secondary sources include books, references, journals and magazines, and papers

related to the research subject.

3.3 Application of Lean Principles in Construction

Standardization was used to reduce the waste in the process by using the data of (Table

3.1). The five why tools were used to identify the causes of waste and reduce the

number of steps. The following ten points were used to define the biggest non- value

added process in the project by using arena simulation in order to reduce non value

added. More details of Arena Simulation are given in appendix (B).

1. Select all non value-added activities in the simulation model (candidates for

improvement). Use the definition provided by (Koskela, 1992) in the previous

section to focus on activities that do not add value to the operation.

2. Set the task durations of the improvement candidates to zero (one at a time).

Although, in many cases, eliminating these activities is not possible or practical,

doing so will allow one to determine their significance on the model output.

3. Produce simulation results (run the simulation).

33

Page 48: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4. Sort the candidates in order of their significance to the simulation model. This will

enable

the improvement process to focus on those activities that have the greatest impact on

model outputs.

5. Look for practical activity reduction solutions for the candidates, starting with the

activity that has the greatest potential for improvement.

6. Edit the simulation model to reflect zero-time delivery the biggest non value added

activities. Although this may not be possible or practical, it will allow one to

determine the effect on the project.

7. Produce simulation results (run the simulation).

8. Look for practical solutions to improve the material delivery processes (if required).

If the material delivery process has a significant impact on model outputs, efforts

should be made to make practical improvements.

9. Look for practical solutions to improve production activities. Only after the lean

concepts (value-added activities and pull-driven flow) have been introduced to the

model should the improvement be focused on production activities.

10. Introduce buffers to compensate for increased model variability and for differing

production rates of linked operations. The lean production improvement process has

generally been shown to introduce significant variability into processes. Buffers

should be introduced as a final step to compensate for this effect (Jack et al., 2004).

34

Page 49: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Chapter Four

Application Lean has been applied on a completed construction project of the construction because

there is a lack of projects under construction. The project data are available and the

project is of a medium size. The lean tools (standardization) are applied on this project

and simulation has been applied to analyze the processes and activities duration.

4.1. Project Description Table (4.1) shows information about the selected project.

Table 4.1 Details of project

No SUBJECT DATA

1 Project name -

2 Location -

3 Owner -

4 Contractor -

5 Sub contractor -

6 Design consultant -

7 Site consultant -

8 Donor The Islamic development bank- Jeddah

9 Project area 3200 m2

10 Basement floor area 2370 m2

11 Ground floor area 2508 m2

12 First floor area 2420 m2

13 Start day 20/05/2004

14 Finish day 20/06/2006

15 Real project duration 750days

16 Contract duration 365 days

17 Estimated cost of project 2,331,834.00 $

35

Page 50: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.2 Project Activities Lean construction has been applied on the following project activities in mobilization,

plain concrete, foundation, neck column, isolation, back filling, ground beam works,

column for ground floor, ground floor, ground floor slab, first floor column, second

floor slab, building for ground floor, and building works for first floor. The execution of

the project is divided into three blocks A, B and C. Appendix (E).

4.3 Lean Criteria Procedure The procedure of applying the lean principles is as follows:

• Defining the customer, the customer value, all resource required for construction,

and all activities required for construction.

• Identify non value added process (steps, time).

• Removing or reducing the wastes in process by using the standardization and the

five why tools to identify the cause of failure.

• Identifying non value added activities by applying the points in figure 4.1 on the

construction of El-Nasser New Pediatric Hospital project.

• Improving the project until reaching perfection.

The above procedures are applied to the project as follows:

The customer is the Ministry of Health. The value of customer is to construct the project

with the same duration and cost and specification of contract.

Only the following eight points in Figure (4.1) from the ten points in section (3.3) were

applied to the project because it is a completed construction project.

36

Page 51: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Setting the process durations of the improvement candidates

to zero (one at a time)

Producing simulation result(run the simulation)

Sorting the candidates in order of their significance to the simulation model

Producing simulation results (run the simulation)

Editing the simulation model to reflect zero-time on the

biggest non value added process.

Looking for practical activity reduction solutions

for the candidates, starting with the activity that has the

greatest potential.

Looking for practical solutions to improve production activities. Only after

the lean concepts (value-adding activities and pull-driven flow) have been

introduced to the model should the improvement be focused on production

activities.

Introduce buffers to compensate for increased model variability and for differing production rates of linked operations.

Conclusion and recommendation

Figure 4.1 Procedure of the application of lean principles

37

Page 52: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.2 represents the resources, the duration for the process and the bill of the

quantities of project by using Table (3.1). The following resources are available

throughout all the project period: Project manager (1), Site engineer (2), Foreman (1),

Surveyor (1).

Calculation in the last column was done as follows:

Duration (hour) = Quantity/ ( Number of resources x Productivity x 8 hours)

Maximum duration of the excavation process = 6000/ (1x 57x 8)= 13 hours.

Most likely duration of the excavation process = 6000/ (1x 62x 8)= 12 hours.

Minimum duration of the excavation process = 6000/ (1x 68x 8)= 11 hours.

The remaining processes were calculated in the same way.

Table 4.2 Productivity of the project activities

Main Activity Process Uni

t

Quantity

No. resource

Productivity/* hour

Duration 1day=8h

Mobilization and

excavation

Excavation work M3 6000 1

Excavator 57, 62, 68 11,12,13 days

Form work M2 140 5 workers 0.6, 0.8, 1 3.5, 4.5.

5.5 days

Cast plain concrete M2 140 5 workers 0.7, 0.8, 1 4,5,6

hours Plain

concrete

Remove form work M2 140 5 workers 0.6, 0.7, 0.9 3, 4, 5

days

Form work M3 935 9 workers 0.6, 0.9, 1 11.5, 15, 21 days

Fix neck column M3 935 9 workers 6, 8, 10 1.5,2, 2.5

days Cast foundation M3 935 9 workers 6 , 7 , 12 12, 16,18

hours

Foundation

Remove form work M3 935 9 workers 2, 3, 4 3, 4, 5

days Form work

M3 60 8 workers 0.07, 0.08, 0.15

51, 90, 103

hours Cast concrete M3 60 8 workers 0.08, 0.1,

0.12 60, 75, 90

minute Neck

column Remove form work M3 60 8 workers 0.3, 0.4, 0.5 16, 20, 24

hours

* This column shows the minimum, most likely and maximum productivities according to the bill quantity of the project.

38

Page 53: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.2 Productivity of the project activities(Cont.)

Main Activity Process Unit

Quantity

No. resource

Productivity/hour

Duration 1day=8h

First layer

M3

1000

2 excavator

s 18, 21, 22 2.5, 3,3.5

days

Second layer M3 1000

2 excavator

s 25, 31, 41 1.5, 2, 2.5

days Back filling

Final layer

M3 1000 2

excavators

25, 31, 41 1.5, 2, 2.5 days

Form work M3 180 8

workers 0.3, 0.4,

0.6 4.5, 7, 10

days Cast concrete M3 180 8

workers 0.08, 0.1,

0,12 60, 75,90

hours Ground beam Remove

form work

M3 180 8 workers 0.7, 0.9, 1 2.5, 3, 4

days

Fix steel column M3 145 4

workers 1.8, 2, 3 1.5, 2, 2.5 days

Form work M3 145 4

workers 0.1, 0.2,

0.3 102, 180, 206 hours

Cast concrete M3 145 4

workers 0.4, 0.5,

0.6 60, 75, 90

minute

Column work

Remove form work

M3 145 4 workers 1.5, 1.8, 2 16, 20, 24

hours

Preparation work M2 2000 5

workers 33, 36, 40 10, 11, 12 hours

Steel work M2 2000 5

workers 14, 15, 16 26, 27, 28 hours

Mechanic work M2 2000 5

workers

60, 80, 100

4, 5 ,6 hours

Ground floor

Cast concrete M2 2000 5

workers 60, 80,

100 4, 5 ,6 hours

39

Page 54: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.2 Productivity of the project activities(Cont.)

Main Activity Process Un

it Quantity

No

resource

Productivity/

1hours

Duration 1day=8h

Form work M2 1180 9 workers 6, 7, 8 (3.5, 4, 4.5)

days Hollow cement block M2 1180 9

workers 10, 12, 15 (2, 2.5, 3) days

Steel work M2 1180 9 workers 6, 7, 8 (3.5, 4, 4.5)

days

Electric work M2 1180 4 workers 6, 8, 12 (6, 8, 12)

hours

Cast concrete M2 1180 9 workers 8, 9, 10 8, 9, 10hour

Slab work

Remove form work M2 1180 9

workers 5, 6, 7 4, 5, 6 days

Building under the window M2 5730 5

workers 2, 2.5 ,3 20, 22, 23 days

Lintel work under window

ML 5730 5

workers 16, 19, 24 2, 2.5, 3 days

Cast lintel under the windows

ML 5730 5

workers 48, 64, 95 4, 6, 8 hours

Remove form work

ML 5730 5

workers 24,32, 48 1, 1.5, 2 days

Building behind the widows M2 5730 5

workers 2.5, 2.8, 3 15, 17, 18 days

Lintel work behind window

ML 5730 5

workers 16, 19, 24 2, 2.5, 3 days

Cast lintel up the windows

ML 5730 5

workers 48, 64, 95 4, 6, 8 hours

Remove form work

ML 5730 5

workers 24, 32, 48 1, 1.5, 2 days

Building work

Building up the window M2 5730 5

workers 2, 2.5 ,3 20, 22, 23 days

40

Page 55: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.4. Non-Value Added and Value Added Process Identification Activities can be classified as:

1. Activity that adds value and can be defined as follows:

• Activity which contributes to the customer's perceived value of the product

or service (Convey et al., 1991).

• Activity that “converts material and/or information towards what is required

by the customer” (Koskela et al., 1992).

2. Activity that does not add value and can be defined as follows:

• Activity which, if eliminated, would not detract from the customer's

perceived value of the product or service (Saukkorriipi et al., 2004).

• Activity which“takes time, resources and space but does not add value”

Koskela et al., 1992).

In the analysis of the project, the value added and non-value added times and steps of

the process can be defined as follows:

• Value added time is the time that increases the value duration of the process

without any waste.

• Non-value added time is the time that does not increase the value added of the

process without waste.

• Value added steps are the steps that increase the value of the work steps without

any kind of waste.

• Non-value added steps are the steps that do not increase the process value

without waste.

• Waste is a kind of seven wastes over- production, defects, inventory,

transportation, waiting, motion and over- processing.

Section 4.4.1 to 4.4.14 show the value and non value added processes of the project

activities. The non value added takes “0” whereas value added takes number “1” or a

fraction according to the number of the steps in a process. For example section (4.4.1)

the excavation process took two steps so the value added steps equal 1/2 +1/2 = 1. If the

excavation was performed in one step, the value added of step takes “1”.

41

Page 56: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.4.1 Mobilization and excavation

Table (4.3) shows seven processes where the number of value added steps is 1 out of 7

steps which corresponds to14% of total steps. The total duration of the mobilization and

excavation in the daily report is 240 hours.

Table 4.3 Value and non-value added processes in mobilization and excavation

Step

Duration

No.

Process

Step number

Value added steps

1day= 8hours

1 Site cleaning, includes removing trees 1 0 48 2 Demolishing the existing walling fence. 2 0 32 3 To setup the site engineer office 3 0 32

4 Excavation of the natural ground to the required levels 4 1/2 96

5 Laboratory 5 0 8 6 Expand the excavation 6 1/2 16 7 Laboratory 7 0 8

Total 7 1

Percentage of value added steps 14%

240

4.4.2 Plain concrete

Table (4.4) shows the five processes that constitute the plain concrete. The number of

value added steps is 1 out of 5 steps (20%) and the total duration in the daily report is 63

hours.

Table 4.4 Non-value added and value added processes in plain concrete

Steps Duration (hours)

No. Process Step

number

Value added steps

1day= 8hours

1 Cheblona work +form work concrete 1 0 24 2 Cast in site 10cm thick plain concrete 2 1/2 16 3 Rework form work for foundation concrete 3 0 8 4 Cast 3M3 plain concrete 4 1/2 5 5 Remove form work 5 0 10

Total 5 1 Percentage of value added steps 20%

63

42

Page 57: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.4.3. Foundation

Table (4.5) shows thirteen processes that constitute the foundation. Where the number

of value added steps is 2 out of 13 steps (15%) and the total duration in the daily report

is 276 hours.

Table 4.5 Non-value added and value added processes in foundation

Duration/

hours

Step

1day=8hours

Value added steps

Step number

Process No.

88 0 1 Form work foundation concrete part "C" 1

80 0 2 Form work foundation concrete part "A and "B" 2

28 1/4 3 Fix steel of neck column part "A" 3

8 1/4 4 Fix neck steel of neck column "B" 4

8 1/4 5 Cast foundation "A" 5

8 0 6 Remove form work part "A"+ form work part "C".6

4 1/4 7 Fix steel neck column part "C" 7

4 1/4 8 Cast foundation part "B" 8

8 1/4 9 Steel work for foundation part "C" 9

8 1/4 10 Cast foundation part "B" 10

8 0 11 Remove form work part "C"+ part "B". 11

16 0 12 Form work for 5 foundation part "c", back filling 12

8 1/4 13 Steel work +cast 5 foundation part "C" + back filling + steel work + Laboratory13

2 13 Total 276

15% Percentage of value added steps

43

Page 58: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.4.4 Neck column

Table (4.6) shows thirteen processes that constitute the neck column. The number of

value added steps is 1 out of 13 steps (7.6%) and the total duration in the daily report is

132 hours.

Table 4.6 Non-value added and value added processes in neck column

Duration (hours)

Step

1day= 8hours

Value added steps

Step number

Process No.

8 0 1 Reinforced concrete basement, remove walls form work

1

54 0 2 Form work neck column , wall concrete2

4 0 3 Justify the defect in the

column. 3

2 0 4 Cast wall concrete "A" 4

8 0 5 Form work "B"5

8 0 6 Remove form work "A" neck

column wall concrete+ "6

16 0 7 Neck column "B".7

2 1/3 8 Cast neck column "B"+ 8

8 0 9 Remove form work wall 9

10 0 10 Form work part " C" 10

2 1/3 11 Cast neck column part B. 11 2 1/3 12 Cast neck column part C12

8 0 13 Remove form work +

Chaining 13

1 13 Total 132 7.6% Percentage of value added steps

44

Page 59: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.4.5 Isolation

Table (4.7) shows two processes that constitute the isolation. The number of value

added steps is 1 out of 2 steps (50 %) and the total duration in the daily report is 48

hours.

Table 4.7 Non-value added and value added processes in isolation processes

Duration (hours)

Steps

1day=8hours Value added steps

Step number

Process No.

8 0 1 Cleaning

1

40 1 2 , isolation work Cleaning 2 1 2 Total

48 50% Percentage of value added steps

4.4.6 Back filling

The six processes that represent backfilling are shown in Table (4.8). The number of

value added steps is three out of six steps (50%) and the total duration in the daily report

is 112 hours.

Table 4.8 Non-value added and value added processes in back filling

Duration

1day=8hours Step

Duration

Of process/ hours

Value added steps

Step number Process No.

48 1 1 Back filling layer1 + cleaning 1

8 0 2 Laboratory2 32 1 3 Back filling layer 23

4 0 4 Laboratory4 16 1 5 Back filling layer 35 4 0 6 Laboratory 6

3 6 Total 112 50% Percentage of value added steps

45

Page 60: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.4.7 Ground beam

The twelve processes that represent ground beam are shown in Table (4.9). The number

of value added steps is 6 out of 12 steps (50%) and the total duration in the daily report

is 192 hours.

Table 4.9 Non-value added and value added processes in ground beam

Duration (hours)

Step

Process No. Step Value added steps

number 1day=8hours

1 Form work for ground beam part A 1 0 16 2 Form work for ground beam part B 2 0 48 3 Back filling 3 1 8 4 Form work for ground beam part C 4 0 60

5 1 8 Steel work 5 8 1 6 Mechanical work 6 8 1 7 Earth electric 7 8 1/2 8 Caste ground part A,C8 16 0 9 Remove form work part A 9 4 1 10 Isolation work10 2 1/2 11 Cast G. beam part B11 6 0 12 Remove form work12

6 12 Total 192 50% Percentage of value added steps

4.4.8 Ground floor column Table (4.10) shows nineteen processes where the number of value added steps is 2 out

of 18 steps (10%) and the total duration of ground floor column in the daily report is

346 hours.

Table 4.10 Non-value added and value added processes for ground floor column

Duration (hours)

Step

1day= 8hours

Value added steps

Step number

Process No.

24 1/2 1 Steel work column part A, C.1 96 0 2 Form work column part A,C2 12 0 3 Check column before casting

for part C3

46

Page 61: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.10 Non-value added and value added processes for ground floor column (cont.)

8 1/3 4 Cast column part C. 4 8 0 5 Check column part A 5 8 1/3 6 Cast column part A6 8 0 7 Remove form work part A, C7 12 1/2 8 Steel work for column part B8 24 0 9 Form work column part B 9 8 0 10 Check column part B10 8 1/3 11 Cast column part B11 16 0 12 Remove form work part B12 38 0 13 Remove 7 column(error work13 8 0 14 Steel work part B for the seven column14 16 0 15 Form work part B for the seven column15 8 0 16 Checking the column16 8 0 17 Cast column 17 36 0 18 Remove form work 18

2 18 Total 346 10% Percentage of value added steps

4.4.9 Ground floor

Table (4.11) shows seven processes where the number of value added steps is 3 out of 7

steps (43 %) and the total duration in the daily report is 64 hours.

Table 4.11 Non-value added and value added processes for ground floor

Duration (hours)

Steps

1days= 8hours

Value added steps

Step number

Process No.

8 1 1 for part A,B,C Mechanic work1 4 0 2 Preparation work for part A,B2 12 1/2 3 Steel work for part A,B 3 8 1/2 4 Cast ground floor for part A,B4 16 0 5 Preparation work for part C5 8 1/2 6 Steel work for part C6 8 1/2 7 Cast ground floor for part C7

3 7 Total 64 43% Percentage of value added steps

47

Page 62: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.4.10 Ground floor slab

The eleven processes that represent ground floor slab are shown Table (4.12). We notice

that the number of value added steps is 4 out of 11 steps (36%) and the total duration in

the daily report is 168 hours.

Table 4.12 Non-value added and value added processes in slab

Step

No. Process Step number

Value added

steps

Duration /hours

1 Form work for part A,B 1 0 48

2 Hollow cement block for part A,B 2 1/2 6

3 Electric work for part A,B 3 1/2 6

4 Mechanical work for part A,B 4 1/2 8

5 Cast slab ground floor part A,B 5 1/2 8

6 Form work fort part C 6 0 32

7 Hollow cement bloc for part C 7 1/2 12

8 Electric work for part C 8 1/2 8

9 Mechanical work for part C 9 1/2 6

10 Cast slab for part C 10 1/2 8

11 Remove form work for part A,B,C 11 0 26

Total 11 4

Percentage of value added steps 36% 168

4.4.11 First floor columns

Table (4.13) shows the twelve processes that constitute the first floor columns. The

number of value added steps is 2 out of 12 steps (16 %) and the total duration in the

daily report is 300 hours.

48

Page 63: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.13 Non-value added processes in first floor column

Duration/ hours

Step

1day= 8hours

Value added steps

Step number

Process No.

32 1/2 1 Steel work column part A,C1 88 0 2 Form work column part A,C2

8 0 3 Check column before casting for part C3

7 1/3 4 Cast column part C 4 12 0 5 Check column part A. 5 6 1/3 6 Cast column part A6 12 0 7 Remove form work part A, C7 14 1/2 8 Steel work for column part B8 72 0 9 Form work column part B 9 6 0 10 Check column part B10 6 1/3 11 Cast column part B11 37 0 12 Remove form work part B12

2 12 Total 300 16% Percentage of value added steps (%)

4.4.12 First floor slab

The eleven processes that represent first floor slab are shown in Table (4.14). The

number of value added steps is 4 out of 11 steps (36%) and the total duration in the

daily report is 163 hours.

Table 4.14 Non-value added processes in first floor slab

Step Duration 1day= 8hour

Value added steps

Step number

Process No.

Form work for part A,B 50 0 1 1

5 1/2 2 Hollow cement block for part A,B 2

4 1/2 3 Electric work for part A,B3

6 1/2 4 Mechanical work for part A,B4

6 1/2 5 Cast slab ground floor part A,B5

34 0 6 Form work fort part C6

16 1/2 7 Hollow cement bloc for part C7

4 1/2 8 Electric work for part C8

49

Page 64: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.14 Non-value added processes in first floor slab (cont.)

Step Duration 1day= 8hour

Value added steps

Process Step number No.

8 1/2 9 Mechanical work for part C9

6 1/2 10 Cast slab for part C 10

24 0 11 Remove form work for part A,B,C11

4 11 Total 163

36%

4.4.13 Ground floor building

Table (4.15) shows eighteen processes where the number of value added steps is 5 out

of 18 steps (27%) and the total duration of the ground floor building in the daily report

is 560 hours

Table 4.15 Non-value added and value added processes in building for ground floor

Step

Percentage of value added steps

Duration (hours) Value

added steps

Step number

Steps No.

56 1/2 1 Building work in part A,B for first layer 1 24 0 2 Lintel form work under the windows 2 6 1/2 3 Cast lintel 3 16 0 4 Remove form work 4

72 1/2 5 Building work for part A,B in the second layer 5

24 0 6 Lintel form work up the windows 6 8 1/2 7 Cast lintel for second layer 7 8 0 8 Remove form work 8 48 1/2 9 Building work up the window 9 8 1/2 10 Building work in part C for first layer 10 48 0 11 Lintel form work under the windows 11 8 1/2 12 cast lintel 12 80 0 13 Remove form work 13 56 1/2 14 Building work for part C in the second layer 14 16 0 15 Lintel form work up the windows 15 76 1/2 16 Cast lintel for second layer 16 24 0 17 Remove form work 17 38 1/2 18 Building work up the window 18

5 18 Total 560

Percentage of value added steps 27%

50

Page 65: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.4.14 First floor building

Table (4.16) shows the eighteen processes that represent first floor building. The

number of value added steps is 5 out of 18 steps (27%) and the total duration in the

daily report is 550 hours.

Table 4.16 Non-value added and value added processes in building for first floor

Steps Duration (hours)

Value added steps

Step number

Steps No.

60 1/2 1 Building work in part A,B for first layer 1

16 0 2 Lintel form work under the windows 2 6 1/2 3 cast lintel 3 12 0 4 Remove form work 4

70 1/2 5 Building work for part A,B in the second layer 5

24 0 6 Lintel form work up the windows 6 6 1/2 7 Cast lintel for second layer 7 6 0 8 Remove form work 8 40 1/2 9 Building work up the window 9 12 1/2 10 Building work in part C for first layer 10 32 0 11 Lintel form work under the windows 11 10 1/2 12 cast lintel 12 64 0 13 Remove form work 13

32 1/2 14 Building work for part C in the second layer 14

24 0 15 Lintel form work up the windows 15 64 1/2 16 Cast lintel for second layer 16 32 0 17 Remove form work 17 40 1/2 18 Building work up the window 18

5 18 Total 550 Percentage of value added steps 27%

51

Page 66: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.5 Remove or Reduce the Influence of Waste as it is Observed Simulation has been used in each activity to measure the duration and number of steps.

Productivity data in Table (3.1) was used in the simulation model. Results are shown on

Table (4.17). The full simulation results are shown in appendix (C).

The results that were reached from mobilization and plain concrete are explained as

follows ( the other activities use the same methodology).

Figure (4.2) shows how lean is applied to mobilization and excavation activity. Firstly

by using the five why tool. The steps were reduced from seven (Table 4.3) to three steps

(Table 4.18). The seven steps are cleaning the site, demolishing existing walls, building

engineer's office, excavation work, checking soil, extended excavation and checking the

new extension excavation land.

The first three steps can be reduced to one step by coordinating cleaning, demolition

and building. These three contractors can begin work at the same time. The sixth and

seventh steps can be avoided because there is a design error.

Create 1Cleaning Excavation Laboratory

Dispose 1

0

0 0 0

0 0

Figure 4.2 Arena simulation of mobilization and excavation

Secondly, applying productivity to three processes. Cleaning lasted for 48 hours,

demolition took 32 hours and building engineer's office took 32 hours. These three

processes may start at the same time. Since the project was ready, the duration of

cleaning is supposed to be 48 hours (Table 4.3). This is considered non-value added

process.

52

Page 67: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Excavation data according to Table (4.2) that shows the productivity of one excavator

for 6000m3 can be achieved in eleven days in minimum limit and in twelve days most

likely and in thirteen days maximum. This activity is considered value added process.

The data is shown in Figure (4.3).

Figure 4.3 Excavation process data

Checking soil process is done by contacting the technicians in the material lab. The time

it takes to get the results is six, eight, ten hours. This is also considered a non value

added process. The data is shown as in Figure (4.4).

Figure 4.4 Laboratory process data

53

Page 68: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

The result by using arena simulation replication 30 times is that cleaning took 48 hours.

Non value added duration took 8.06 hours; non-value added process, excavation process

took 95.29 hours a value added process. Results are shown in appendix ( C ).

Figure (4.5) shows how lean is applied to plain concrete activity after applying lean.

The five why tool are used to identify the number of the steps in order to be reduced.

Table (4.4) show five actual steps formwork, casting, removing formwork, cast 3 m3,

remove formwork. Table (4.19) shows that only three steps can be used by eliminating

step four and five because they were owing to a design error.

c reateform work Dispose 1cast

workremove form

0 00

TNO

0 0

W

0 Figure 4.5 Applied lean to plain concrete activity

Using standardization in Table ( 4.2) using 140m2, five craftsmen and ten workers, the

productivity of formwork process was 3.5 days minimum, 4 days most likely and 5.5

days maximum (on eight-hours day work).

Figure(4.6) shows formwork process that is considered non-value added. Average

duration by 30 replications was 34.83 hours.

Figure 4.6 Formwork plain concrete data

54

Page 69: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

The cast concrete data according to Table (3.1) is found in Figure (4.7). This process is

value added. The duration was 3.5 hours minimum, 4 hours most likely, 4.5 hours

maximum. Average duration for 30 replication was 3.97 hours.

Figure 4.7 Casting plain concrete process data

Data of formwork removal process in Table (4.2) is inputted in Figure (4.8). This is a

non-value added process. The average duration of 30 replications was 5.03 hours.

Figure 4.8 Remove formwork process data

55

Page 70: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.17 Simulation results

No. Activity Process V.A.Time1

(hours)

N.V.A.Time2

(hours)

Cleaning 0 48

Excavation 95.29 0 1 Mobilization

Laboratory 0 8.06

Casting 3.97 0

Form work 0 34.83 2 Plain concrete

Remove form work 0 5.03

Fix steel 15.94 0

Form work 0 129.6

Casting 15.55 0 3 Foundation

Remove form work 0 31.34

Form work 0 79.23

Casting 1.26 0 4 Column neck

Remove form work 0 19.92

Cleaning 0 11.86 5

Bitumen isolation

Isolation work 39.86 0

Layer 1 23.47 0 Layer 2 16.46 0 Layer 3 15.82 0 Laboratory 0 7.1

Laboratory 0 3.57

6 Back filling

Laboratory 0 3.51

1. V.A.Time: Value Added Time: Valued added time / hours

2. N.V.A.Time: Non Value Added time/ hours.

56

Page 71: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.17 Simulation results (Cont.)

No. Activity Process V.A.Time

(hours)

N.V.A.Time

(hours)

Form work 0 56.85

Casting 4.19 0

Remove form work 0 25.58

Steel work 14 0

Installation P.V.C 6.21 0

7 Ground Beam

Electrical work 11.76 0

Casting 4.95 0

Mechanical work 4.95 0

Preparation 0 10.99 8 Ground Floor

Steel work 27.03 0

Steel work 15.87 0

Casting 1.23 0

Form work 0 163.82 9

Column Work

.

Remove form work 0 19.68

Casting 8.98 0

Electrical Work 8.69 0

Form work 0 31.58

Hollow cement 19.85 0

Remove form work 0 40.87

10 Slab Work

Steel work 32.86 0

Building 1 173.29 0

Building 2 133.24 0

Building 3 173.69 0

Form work 1 0 19.62

Form work 2 0 19.72

Cast1 5.87 0

Cast2 5.98 0

Remove 1 0 11.72

11 Building Work

Remove2 0 11.88

57

Page 72: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.17 Simulation results (Cont.)

No. Activity Processes V.A.Time

(hours)

N.V.A.Time

(hours)

Steel work 16.56 0

Casting 1.27 0

Form work 0 157.51 12

Column Work

.

Remove form work 0 20.41

Casting 8.9 0

Electrical work 8.92 0

Form work 0 31.51

Hollow cement 20.32 0

Remove form work 0 39.37

13 Slab Work

Steel work 32.23 0

Building 1 172.75 0

Building 2 132.67 0

Building 3 172.21 0

Form work 1 0 20.07

Form work 2 0 20.15

Cast1 5.93 0

Cast2 5.99 0

Remove 1 0 12.44

14 Building Work

Remove2 0 11.88

58

Page 73: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.5.1 Mobilization and excavation

Table (4.18) shows that mobilization and excavation duration is equal to 151.35 hours.

Before applying lean tools, it was 240 hours, and the percentage of value added time

was 63%, the actual percent value added duration was 39%, and value added steps after

applying the five why tools is 33% (before applying lean tools was 14%). Step1 and 3

are merged.

Table 4.18 Waste elimination in mobilization

Step

Duration

No. Process Value

added steps

Duration Step

numberof process

(hours)

Value added time

(hours)

1 Site cleaning, includes removing trees

2 Demolishing the existing walling fence, rooms and any obstructed item existing in the proposed area

1 0

48 0

3 Excavation of the natural ground to the required levels 2 1 95.29 95.29

4 Laboratory 3 0 8.06 0 Total 3 1 151.35 95.29

4.5.2 Plain concrete

Table (4.19) shows that plain concrete duration is equal to 41.09 hours. Before applying

lean tools, it was 63 hours, and the percent of value added time 9%, the actual duration

was 6%, and value added step percent is 33%. It was 20% before applying lean tools.

Table 4.19 Waste elimination in plain concrete

Duration Step Value added time

(hours)

Percentage of value added 33% 63%

Duration of process

(hours)

Value added steps

Step number

Process No.

0 34.83 0 1

formwork concrete for "A-B"

1

3.97 3.97 1 2 Cast plain concrete 2 0 5.037 0 Remove form work 3 3

Total 3 1 43.83 3.97 9% 33% Percentage of value added

59

Page 74: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.5.3 Foundation

Table (4.20) shows that foundation duration is equal to 192.43 hours. Before applying

lean tools, it was 276 hours and the percent of value added time was 16%, the actual

duration was 10%, and value added step percent was 50%. It was 15% before applying

lean tools.

Table 4.20 Waste elimination in foundation

Duration

Step

Value added time

(hours)

Duration of

process (hours)

Value added step

Step number

Process No.

0 129.6 0 1

Form work foundation

concrete "A-B-C" and

steel.

1

15.94 15.94 1 2 fix neck column "A-B-

C"

2

15.55 15.55 1 3 Cast Foundation "A-B-

C"

3

0 31.34 0 Remove form work4 4

Total 4 2 192.43 31.49 16% 50% Percentage of value added

4.5.4 Neck column

Table (4.21) shows that neck column duration is equal to 100.41 hours, before applying

lean tools was 132 hours, and the percent of value added time 1.2%, the actual duration

was 0.8%, and value added step percent is 33 %, It was 8% before applying lean tools.

Table 4.21 Waste elimination in neck column

Duration Step Value Added time / hours

Duration /hours

Value added steps

Step number

Process No.

0 79.23 0 1 Form work neck column 1 1.26 1.26 1 2 cast wall concrete "A" 2

0 19.92 0 Remove form work 3 3 Total 3 1 100.41 1.26

1.2% 33 % Percentage of value added

60

Page 75: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.5.5 Isolation

Table (4.22) shows that isolation duration is equal to 39.86 hours. Before applying lean

tools was 48 hours, and the percent of value added time 100%, the actual duration was

82%, and value added step percent is 100 %. It was 50% before applying lean tools.

Table 4.22 Waste elimination in isolation

Duration Steps

Value added time (days)

Duration (hours)

Value added steps

Step number

Process No.

39.86 39.86 1 1 Isolation work cleaning 1

Total 1 1 39.86 39.86 100 % 100 % Percentage of value added

4.5.6 Back filling

Table (4.23) shows that backfilling duration is equal to 69.93 hours. Before applying

lean tools was 112 hours, and the percent of value added time 79.7%, the actual

duration was 49%, and value added step percent is 100 %. It was 50% before applying

lean tools.

Table 4.23 Waste elimination for back filling

Duration

Step

Value added time (days)

Duration (hours)

Value added step

Step number Process No.

23.47 23.47 1 1 Back filling layer1, cleaning site

1

0 7.1 0 2 Laboratory2 16.46 16.46 1 3 Back filling layer 23

0 3.57 0 4 Laboratory4 15.82 15.82 1 5 Back filling layer 35

0 3.51 0 Laboratory6 6 Total 6 3 69.93 55.75

Percentage of value added 50% 79.7%

61

Page 76: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.5.7 Ground beam

Table (4.24) shows that ground beam duration is equal to 118.59 hours. Before applying

lean tools was 192 hours, and the percent of value added time 30%, the actual duration

was 20%, and value added step percent is 67 %. It was 50% before applying lean tools.

Table 4.24 Waste elimination for ground beam

Duration

Step

Value added time

Duration (hours)

Value added step

Step number

Process No.

0 56.85 0 1 Form work for ground beam "A-B-C"1

14 14 1 2 Steel work2

6.21 6.21 1 3 Install and test UPVC+ earth electric3

11.76 11.76 1 4 Earth electric work

4

4.19 4.19 1 5 Caste ground beam5 0 25.58 0 Remove form work 6 6

Total 6 4 118.59 36.16 30% 67% Percentage of value added

4.5.8 Column ground floor

Table (4.23) shows that column ground floor duration is equal to 200.6 hours. Before

applying lean tools was 346 hours, and the percent of value added time 8.5%, the actual

duration was 4.7%, and value added step percent is 50 %. It was 10% before applying

lean tools.

Table 4.25 Waste elimination for ground floor column

Duration Step Value added

time (hours)

Duration (hours)

Value creation step

Step numb

er

Process No.

15.87 15.87 1 1 Steel work 1 0 163.82 0 2 Form work 2

1.23 1.23 1 3 Cast column 3 0 19.68 0 Remove form work 4 4

4 Total 2 200.6 17.1 8.5% 50% Percentage of value added

62

Page 77: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.5.9 Ground floor Table (4.26) shows that ground floor duration is equal to 47.56 hours. Before applying

lean tools was 64 hours, and the percent of value added time 77%, the actual duration

was 55%, and value added step percent is 75 %. It was 57% before applying lean tools.

Table 4.26 Waste elimination for ground floor

Duration

Step

Value added time

Duration Value added step

Step number

Process No.

0 10.99 0 1 Preparation work1 27.03 27.03 1 2 Steel work 2 4.95 4.95 1 3 Mechanical work3 4.59 4.59 1 Cast concrete 4 4

Total 4 3 47.56 36.57

77% 75% Percentage of value added

4.5.10 Ground floor slab

Table (4.27) shows that slab ground floor duration is equal to 142.83 hours. Before

applying lean tools was 168 hours, and the percent of value added time 49% the actual

duration was 41%, and value added step percent is 67 %. It was 44% before applying

lean tools.

Table 4.27 Waste elimination for ground floor slab

Duration

Step

Value added time

Duration Value added step

Step number

Process No.

0 31.58 0 1 Form work1 19.85 19.85 1 2 Hollow cement block 2 32.86 32.86 1 3 Steel work3

8.69 8.69 1 4 Electric + mechanic work 4

8.98 8.98 1 5 Cast concrete 5 0 40.87 0 Remove form work6 6

Total 6 4 142.83 70.38 67% 49% Percentage of value added

63

Page 78: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.5.11 Column first floor

Table (4.28) shows that column first floor duration is equal to 195.75 hours. Before

applying lean tools was 346 hours, and the percent of value added time 9%, the actual

duration was 4.7%, and value added step percent is 50 %.It was 10 % before applying

lean tools.

Table 4.28 Waste elimination in first floor column

Duration Step Value added

time (hours)

Duration (hours)

Value added step

Step number Process No.

16.56 16.56 1 1 Steel work 1 0 157.51 - 2 Form work column 2

1.27 1.27 1 3 Cast column 3 0 20.41 Remove form work 4 4 -

4 Total 2 195.75 17.83 50% 9% Percentage of value added

4.5.12 First floor slab

Table (4.29) shows that slab first floor duration is equal to 140.53 hours. Before

applying lean tools was 168 hours, and the percent of value added time 50%, the actual

duration was 44%, and value added step percent is 67 %. It was 41% before applying

lean tools.

Table 4.29 Waste elimination for first floor slab

Duration

Step

Value Added

Time (hrs) Duration Value

added step Step

number

Process No.

0 31.51 0 1 Form work1 20.32 20.32 1 2 Hollow cement block 2 32.23 32.23 1 3 Steel work3

8.92 8.92 1 4 Electric, mechanic work

4

8.9 8.9 1 5 Cast concrete 5 0 39.37 0 Remove form work6 6

Total 6 4 140.53 70.37 50% 67% Percentage of value added

64

Page 79: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.5.13 Building in ground floor

Table (4.30) shows that building ground floor duration is equal to 554.91 hours. Before

applying lean tools was 560 hours, and the percent of value added time 88%, the actual

duration was 87%, and value added step percent was 55 %. It was 26% before applying

lean tools.

Table 4.30 Waste elimination for ground floor building Duration Step

Value Added

Time (hrs)

Duration (hours)

Value added step

Step number

Process No.

173.29 173.29 1 1 Building work 1 0 19.62 0 2 Form work2

5.87 5.87 1 3 Cast lintel 3 0 11.72 0 4 Remove form work4

133.24 133.24 1 5 building work 25 0 19.62 - 6 Lintel work form

work 16

5.98 5.98 1 7 Cast lintel 7 0 11.88 Remove form work 8 -8

173.69 173.69 1 9 Building work 3 9 Total 9 5 554.91 492.07

88% 55% Percentage of value added

4.5.14 Building in first floor

Table (4.31) shows that building first floor duration is equal to 553.37 hours. Before

applying lean tools was 560 hours, and the percent of value added time 88%, the actual

duration was 87%, and value added step percent is 55 %. It was 26% before applying

lean tools.

Table 4.31 Waste elimination for first floor building Duration Step

Value Added

Time (hrs)

Duration (hours)

Value added step

Step numb

er

Process No.

172.75 172.75 1 1 Building work 1 0 20.07 0 2 Form work2

5.93 5.93 1 3 Cast lintel 3 0 11.72 0 4 Remove form work4

132.67 132.67 1 5 Building work 25 0 20.1 0 6 Lintel work form work 6

5.99 5.99 1 7 Cast lintel 7 0 11.88 0 8 Remove form work8

172.21 172.21 1 9 Building work 3 9 Total 9 5 553.37 489.55

88% 55% Percentage of value added

65

Page 80: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.6 Identify the Cause of Waste Table (4.32) shows the difference between activity before and after applying lean in

order to demonstrate the effect of lean on the activity and also to identify the activities

that can be improved. The difference column (PVAT) is in descending order.

Table 4.32 Difference between activity before and after lean application

Before applying lean

After applying lean Difference

No. Activity PVAS3

(%) PVAT4

% PVAS

(%) PVAT

% PVAS

(%) PVAT

%

1 Back filling 50 49 50 79.7 0 30.7

2 Mobilization 14 39 33 63 19 24

3 Ground floor 57 57 75 77 18 20

4 Isolation 50 82 100 100 50 18

5 Ground beam 43 18.8 67 30 24 11.2

6 Slab work in first floor 36 41 67 50 31 9

7 Slab work ground floor 36 41 67 49 31 8

8 Foundation 15 11 50 16 35 5

9 Column first floor 10 5 50 9 40 4

10 Column ground floor 10 4.9 50 8.5 40 3.6

11 Plain concrete 20 6 33 9 13 3

12 Building work in ground floor

26 87 55 88 29 1

13 Building work in first Floor

26 87 55 88 29 1

14 Neck column 8 1 33 1 25 0 3. Percent value added time.

4. Percent value added steps.

66

Page 81: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Figure (4.9) is divided into four quarters.

In the first quarter, little improvement in value added steps which produces high

improvement in value added time in the backfilling, ground floor, mobilization and

excavation activities. The backfilling activity was 0% in the value added steps and

30.7% in value added time. This happened by avoiding the delay of the work of the

excavator which stopped for a certain period of time. Stopping was due to an error in

the design. The production of the excavator was not satisfactory because the foremen

were absent. The mobilization and excavator activities increase by 19% in value added

steps and 26% in value added time by avoiding the unclear design. Ground floor activity

increased by 18% in value added steps and 20% in value added time by increasing the

management experience.

In the second quarter, a slight improvement in value added steps led to the same

improvement in value added time. The ground beam activity raised by 17% in value

added steps and 11% in value added time. The plain concrete activity increased by 3%

in value added time because the percentage of non value added activity of the formwork

and removing it, are less than value added activity.

In the third quarter, the big improvement in value added steps gave only a little

improvement in the value added time. The value added steps in the slab activity has

raised by 23% and the value added time raised by 8%. The value added steps for the

columns activity raised by 40% and value added time 3.6%. The number of the steps of

the neck columns improved by 25% and the value added time did not improve. The

number of steps of building activity improved by 29% and value added time by 1%.

This all happened because the non value added processes (form work and removing it)

had a big time value inside the activity.

In the fourth quarter, a big improvement in the value steps produced big improvement in

the value added time. The number of steps in the isolation activity of the value added

steps rose by 50% that also rose the value added time by 18%. These rises happened

because cleaning process was done after removing the formwork. It was done during the

work of the contractor because of the lack of workers and the cleaning material.

67

Page 82: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

0%

5%

10%

15%

20%

25%

30%

35%

0% 10% 20% 30% 40% 50% 60%

Percent of value adding steps

Perc

ent o

f val

ue a

ddin

g tim

e

1

23

4

Figure 4.9 Comparing value added steps to value added time

Regarding the causes of delays of activities, using the five why tools showed the

following results:

• The failure due to design error was 30.7%.

• The failure due to work error was 24%.

• The failure due to lack of experienced management was 20%.

• The failure due to lack of resources was 18% due to lack of permanent

resources.

• The failure due to lack of material formwork was 8% because the contractor

had to divide the project into many stage because of lack of the formwork. The

solution is to save enough formwork. Figure (4.10) shows the percentage of

the causes of a failure as in the diagram.

68

Page 83: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

0

5

10

15

20

25

30

35

Design error Work error Lack ofexperience

Lack of numberof ressources

Lack ofmaterial

Cause of non value added process

Per

cent

of n

on v

alue

add

ed

proc

ess

Figure 4.10 Cause of failure

4.7 Finding the Largest Non-Value Added Process

The eight points that were mentioned in the methodology (4.3) were applied using arena

simulation in order to find the biggest non value added process. The whole non value

added process is shown in Table (4.33) by putting “0” non value added process in turn

and calculating the time period in the end of the project (run the simulation Figure

(4.11)).

MOBILIZATION

Create 2

PLAIN C ON C R ETE FO U N D ATIO N N IC K C O LU MN ISOLATION D EMOLITION

G R O U N D BEAM C O L U M N 1 G R O U N D FL O O R Slab work Column2 SLAB2

building work1 building work2 Dispose 2

TNOW

0

0 Figure 4.11 Simulation model

69

Page 84: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.33 Total project duration

No. Process Non value added

Time =0

Total duration

Site cleaning 0 2951.3 1 Mobilization and excavation Laboratory 0 2991.3

Form work concrete 0 2964.5 2 Plain concrete Remove form work 0 2994.3

Form work concrete 0 2869.7 3 Foundation Remove form work 0 2968

Form work concrete 0 2920.1 4 Neck column Remove form work 0 2979.4

5 Isolation Cleaning 0 2992.2 Laboratory of layer1 0 2995.8 Laboratory of layer2 0 2995.8

6 Back filling

Laboratory of layer3 0 2942.5 Form work concrete 0 2973.8 7

Ground beam Remove form work 0 2835.5

Form work concrete 0 2979.7 8 Column ground floor Remove form work 0 2988.3 9. Ground floor Preparation work 0 2967.8

Form work concrete 0 2958.5 10 Slab work ground floor Remove form work 0 2841.8

Form work concrete 0 2978.9 11 Column first floor Remove form work 0 2967.8 Form work concrete 0 2960 12

Slab work first floor Remove form work 0 2979.7

Form work concrete 0 2987.6 Remove form work 0 2979.6 Form work concrete 0 2987.5

13 Building work in ground floor

Remove form work 0 2979.3 Form work concrete 0 2986.9 Remove form work 0 2979.2 Form work concrete 0 2987.5

14

Building work in first floor

Remove form work 0 2951.3

70

Page 85: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Then the candidates have been sorted out in order of their significance duration based

on simulation results. This enables the improvement process to focus on those activities

that have the greatest impact on model outputs (Table 4.34).

Table 4.34 Activities in a descending order based on duration

No. Activity Non- value added Total

duration(hours)Column ground floor Form work concrete 2835.5 1 Column first floor Form work concrete 2841.8 2 Foundation Form work concrete 2869.7 3 Neck column Form work concrete 2920.1 4 Ground beam Form work concrete 2942.5 5 Mobilization and Site cleaning 2951.3 6 Slab work ground floor Remove form work 2958.5 7 slab work first floor Remove form work 2960 8 Plain concrete Form work concrete 2964.5 9 Slab work ground floor Form work concrete 2967.8 10 slab work first floor Form work concrete 2967.8 11 Foundation Remove form work 2968 12 Ground beam Remove form work 2973.8 13 Column first floor Remove form work 2978.9 14 Building work in first floor Form work concrete 2979.2 15 Building work in first floor Form work concrete 2979.3 16 Neck column Remove form work 2979.4 17 Building work in ground Form work concrete 2979.6 18 Column ground floor Remove form work 2979.7 19 Building work in ground Form Work Concrete 2979.7 20 Building work in first floor Remove form work 2986.9 21 Building work in ground Remove form work 2987.5 22 Building work in first floor Remove form work 2987.5 23 Building work in ground Remove form work 2987.6 24 Ground floor Preparation work 2988.3 25 Mobilization and Laboratory 2991.3 26 Back filling Laboratory of layer1 2992.2 27 Plain concrete Remove form work 2994.3 28 Back filling Laboratory of layer2 2995.8 29 Back filling Laboratory of layer3 2995.8 30

71

Page 86: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Then, the processes with the greatest impact on the project duration are identified and

shown in Table (4.35).

Calculated of the value added percent is as follows:

V.A. Percent=Value added / Total duration

Value added according the appendix (c)=1906.15 hours

V.A.Percent of the form work the ground floor column = 1906.15 / 2835.5 = 67%.

V.A.Percent of the form work the first floor column = 1906.15 / 2841.8 = 67%.

V.A.Percent of the form work the foundation = 1906.15 / 2869.7 = 66%.

Table 4.35 Greatest duration of waste in activity

No. Process

Non value added

Total duration (hours)

V.A Percent

(%)

1 Ground floor column Form work concrete 2835.5 67%

2 First floor column Form work concrete 2841.8 67% Foundation Form work concrete 3 2869.7 66%

In case of putting “0” for the three process, the results are shown in Table (4.36).The

full simulation result is shown in appendix (D).

Calculated of the value added percent is as follows:

Value added percent = 1906.15 / 2563.05 = 74%

Table 4.36 Project duration without the most wasting activity

Process Non- value

added process

Total duration (hours)

V.A Percent No.

(%) Foundation Form work Concrete Ground floor column Form work Concrete

74% 1

2563.05 Form work Concrete First floor column

72

Page 87: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Finally, buffers are introduced to balance the processes duration.

Figure (4.12) shows that duration of the foundation formwork process is 129.6 hours.

This is far from the other processes (shown as number eight). Ground floor columns

formwork process duration are 163.82. First floor columns formwork process duration

was 157.51 hours. These are longer than the other processes (shown as number 34, 53).

The duration of the building processes took 173.29, 133.2, 173.69, 172.75, 132.67,

172.21 hours. These numbers correspond to 42, 43, 44, 61, 62, 63. These duration are

larger than those in the other processes.

0

20

40

60

80

100

120

140

160

180

200

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67

Process

Dur

atio

n (h

ours

)

Non value added process Value added process

Figure (4.12) Duration variability before introducing buffers and after applying lean

tools

Table (4.37) shows the balance improvement into the process by decreasing the duration

of processes. Foundation formwork process duration decreased from 129.6 hours to

42.6 hours by increasing the number of resources from 9 to 27 workers shown as

number eight in Figure (4.13). The duration of excavation process decreased from 95.29

to 45 hours by using 2 excavators shown as number three. The duration of the ground

floor columns formwork decreased from 163.82 hours to 56.49 hours by increasing the

number of workers to12 workers shown as number 34. The first floor columns

formwork duration decreased from 157.51 hours to 56.49 hours by increasing the

73

Page 88: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

number of workers to 12 workers shown as number 53. The ground floor building

duration decreased from 173.29, 133.24, 173.96 hours to 65.9, 66.07, 66.37 hours by

increasing the number of workers to 13, 10, 13 workers shown as number 42, 43, 44.

The first floor building duration decreased from 172.75, 132.67, 172.21 hours to 65.9,

66.07, 66.37 hours by increasing the number of workers to 13, 10, 13 workers shown as

number 61, 62, 63.

The result of introducing buffer is that the non-value added time decreased by 55%

(from 1906.15 hours to 846.5 hours).

Table 4.37 Balancing the process

Before introducing buffers After introducing buffers

Activity Process New

resources

number

VA

hours

NVA

hours

New

resources

number

New

V.A.

New

NVA

Check - 0 8.06 - 0 8.06

Cleaning - 0 48 - 0 48 Mobil.

Excavation 1

Excavator95.29 0

2

Excavator 45 0

Casting 5 3.97 0 5 3.97 0

Form Work 5 0 34.83 5 0 34.83 Plain

concret. Remove

form 5 0 5.03 5 0 5.03

Fix steel 9 15.94 0 9 15.94 0

Form work 9 0 129.6 27 0 42.6

Casting 9 15.55 0 9 15.5 0 Found.

Remove

Formwork 9 0 31.34 9 0 31.3

Formwork 8 0 79.23 14 0 67.29

Casting 8 1.26 0 8 1.26 0 Neck

Column Remove

formwork 8 0 19.92 8 0 19.9

74

Page 89: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.37 Balancing the process (cont.)

Before introducing buffers After introducing

buffers

Activity Process

NRN

VA

hours

NVA

hours

NRN

New

V.A.

New

NVA

Cleaning 2 0 11.86 2 0 11.8

Isolation Isolation

work 2 39.86 0 2

39.8

6 0

Layer 1

2

Excavato

r

23.47 0 2 Excav.

23.47 0

Layer 2 2

Excavat. 16.46 0 2

Excav.16.4

6 0

Layer 3 2

Excavat. 15.82 0 2

Excav.15.8

2 0

Laboratory 1 - 0 7.1 - 0 7.1

Laboratory 2 - 0 3.57 - 0 3.57

Backfilling

Laboratory 3 - 0 3.51 - 0 3.51

Form Work 8 0 56.85 16 0 29.85

Casting 8 4.19 0 8 4.19 0

Remove form 8 0 25.58 8 0 25.58

Steel work 8 14 0 8 14 0

Install. PVC 8 6.21 0 8 6.21 0

Ground

beam

11.7

6 Electrical 8 11.76 0 8 0

75

Page 90: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.37 Balancing the process (cont.)

Before introducing buffers After introducing buffers

Activity Process

NRN

VA

hours

NVA

hours

NRN

New

V.A.

New

NVA

Casting 5 4.95 0 5 4.95 0

Mechanical

work 5 4.95 0 5 4.95 0

Preparation 5 0 10.99 5 0 10.99

Ground

floor

Steel work 5 27.03 0 5 27.03 0

Steel work 4 15.87 0 4 15.87 0

Casting 4 1.23 0 4 1.23 0

Form work 4 0 163.82 12 0 56.49

Column

work

Remove form

Work 4 0 19.68 4 0 19.68

Casting 9 8.98 0 9 8.98 0

Electrical

work 9 8.69 0 9 8.69 0

Form work 9 0 31.58 9 0 31.58

Hollow

cement 9 19.85 0 9 19.85 0

Remove form

work 9 0 40.87 11 0 32.47

Slab

work

ground

floor

Steel work 9 32.86 0 9 32.86 0

Building 1 5 173.29 0 13 65.9 0

Building 2 5 133.24 0 10 66.07 0

Building 3 5 173.69 0 13 66.37 0

Form work 1 5 0 19.62 5 0 19.62

Form work 2 5 0 19.72 5 0 19.72

Cast1 5 5.87 0 5 5.87 0

Cast2 5 5.98 0 5 5.98 0

Remove 1 5 0 11.72 5 0 11.72

Building

ground

floor

Remove2 5 0 11.88 5 0 11.88

76

Page 91: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.37 Balancing process (Cont.)

Before introducing buffers After introducing buffers

Activity Process

NRN

VA

hours

NVA

hours

NRN

New

V.A.

New

NVA

Steel work 5 16.56 0 5 16.56 0

Casting 5 1.27 0 5 1.27 0

Form work 5 0 157.51 12 0 56.49

Column

work first

floor

. Remove

form 5 0 20.41 5 0 20.41

Casting 9 8.9 0 9 8.9 0

Electrical

work 9 8.92 0 9 8.92 0

Form work 9 0 31.51 9 0 31.51

Hollow

cement 9 20.32 0 9 20.32 0

Remove

form work 9 0 39.37 11 0 32.47

Slab work

first floor

Steel work 9 32.23 0 9 32.23 0

Building 1 5 172.75 0 13 65.9 0

Building 2 5 132.67 0 10 66.07 0

Building 3 5 172.21 0 13 66.37 0

Form work 1 5 0 20.07 5 0 20.07

Form work 2 5 0 20.15 5 0 20.15

Cast1 5 5.93 0 5 5.93 0

Cast2 5 5.99 0 5 5.99 0

Remove 1 5 0 12.44 5 0 12.44

Building

work

first floor

Remove2 5 0 11.88 5 0 11.88

77

Page 92: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Actual project duration was 6000 hours.

Actual non-value added duration of total process was 4892.17 hours.

Total duration, before introducing buffer, was 3013.98 hours.

Value added duration of total process before introducing buffer was1906.15.

Total duration after introducing buffer was 1503.43 hours.

Non value added duration of total process after introducing buffer was 846.5 hours.

01020

30405060

7080

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69

Process

Non value added processes Value added processes

Figure (4.13) Duration variability after Introducing buffers

The contracting time duration was 2920 hours. After applying lean tools the total

duration was 1503.15.

Table (4.38) shows the cycle time decrease from 6000 hours to 1503.43 hours

(reduction by 75%).

Table 4.38 Cycle time compared

Application

of lean tools Cycle time after

introducing buffer Activity Actual

duration hours

Duration (hours) % Duration(hours) %

Total duration 6000 3013.98 50%

1503.43 75%

78

Page 93: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

4.8 Application of Lean Construction for Future Construction Project In order to apply lean construction on future projects, we have to apply the following

points:

1. To improve master schedule of the project by using standardization tool

2. To hold a weekly meeting and to determine percent plan complete (PPC) of

the process of the assignment by evaluation of the steps. Advancement of the

project can be measured every 4 weeks or 6 weeks according to the size of

the project. The average must be more than 80%. Later on the change of

average may become very simple.

3. To apply the 5 why tool to identify the main reasons of failure.

4. Correcting and avoiding any previous failure in the following week.

5. To measure the average of the percent plan complete in each 4 weeks, the

weekly meeting will be good if the percent plan complete is more than 80%.

6. To identify, remove or reduce the non-value added process

7. To make a continuous improvement.

Applying the above points to the mobilization and excavation activity described in

project studied: cleaning work, cutting trees, demolition existing wall in the site,

building an engineering office, excavation work first layer, excavation second layer, and

excavation third layer. Table 4.39 shows the process completed and the process

assigned in the master schedule of a real project. In the 1st, 2nd, 3rd week there are two

assigned process (cleaning, cutting trees) and only one was completed. In the 4th and 5th

week there are three assigned (cleaning, cutting trees, demolition) and only two

processes were completed. In the 6th and 7th week there are four assigned and only

three processes were completed. In the 8th and 9th week, there are five assigned and only

four processes were completed. In the 10th week, there are 6 assigned and only 5

processes were completed. In the 11th week there are 7 assigned and only 5 processes

were completed.

79

Page 94: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table 4.39 Process assigned and process completed

Date 1st

Week

2nd

Week

3rd

Week

4th

Week

5th

Week

6th

W.

7th

W.

8th

W.

9th

W.

10th

W.

11th

W.

Process

Assigned 2 2 2 3 3 4 4 5 5 6 7

Process

Completed 1 1 1 2 2 3 3 4 4 5 5

Figure (4.14) shows the real percentage plan complete of each week.

PPC=(Number of processes completed / Number of processes assigned) X 100

In the 1st, 2nd, 3rd weeks, the PPC=1/2 x100=50%. In the 4th week, 5th week the PPC =

2/3 x100 = 66%, in the 6th week, 7th week the PPC= 3/4x100= 75%. %. In the 4th week,

5th week the PPC = 2/3 x 100 = 66%, in the 8th week, 9th week the PPC= 4/5 x 100

=80%. In the 10th week the PPC = 80%, in the 11th week the PPC= 70%. This needs to

determine the main reasons of failure.

Using the five why tool, the cause of failure is the lack of experienced management and

the lack of number of resources.

0

0 .1

0 .2

0 .3

0 .4

0 .5

0 .6

0 .7

0 .8

0 .9

Week 1 Week2

Week3

Week4

Week5

Week6

Week7

Week8

Week9

Week10

Week11

Figure 4.14 Actual percent plan complete of each week (PPC)

80

Page 95: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Figure (4.15) shows the average of percent plan complete is smaller than 80% which

requires finding out failure reasons in each week. By the application of the five why

tools and the 10 points described in part (3.3).

00 .1

0 .2

0 .30 .40 .50 .6

0 .70 .80 .9

Week 1 Week2

Week3

Week4

Week5

Week6

Week7

Week8

Week9

Week10

Week11

w eekly percent plan complete Average percent plan complete

Figure 4.15 Average percent plan complete of each four week

81

Page 96: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Chapter Five

Conclusion and Recommendations 5.1 Conclusion

This study of Lean Construction Practices in the Gaza Strip shows the influence of

applying the lean construction. This study was conducted by identifying criteria of lean

construction and applying standardization tools, 5 why tools, 10 point to achieve the

lean principle in reducing the activity steps and duration by eliminating the non value

added process in the activity by using the arena simulation. The following consequences

have been reached:

1. Value added time increased from 49% to 63% as a result of applying lean tools.

2. The used lean tools decrease the cycle time from 6000 hours to 1503.43 hours

(decreased by 75%).

3. The value added can be enhanced to 74% by improving the form work material in

foundation (using prefabricated) and column activities ( steel form work).

4. The number of steps decreased from 161 to 69 (a reduced by 57%).

5. Non -value added duration of total process was 4892.17 hours (81%) ; it decreased

to 846.5 hours ( 14% decrease).

6. Lean construction through standardization tools reduces the variability of the

process, example the excavation work for one hour (57m3, 62m3, 68m3).

7. The rate of no value added process related to the design error was 30.7%. This has

been considered the biggest value of the no value added in the process since it

happens during the stage of design, therefore, we must apply the lean in the design

to avoid waste during the construction.

8. The percentage of the no value added in the process due the above mentioned

reasons were as follow: Rework 24% lack of experience management 20%, lack of

number of resources 18%, lack of material 8%. This requires training workers.

Engineers, other managers, supervisors should begin suitable courses in

management. It is favorable to work with a permanent technical staff in the

company. Efficient resources, sufficient materials should be provided and saved for

the project.

82

Page 97: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

5.2 Recommendations In order to apply lean construction tools and achieve its benefits successfully, the

following recommendations should be considered:

1. Using standardization tool in companies.

2. Training the workers in the company in order to reach the needed productivity

which has big effects on the improvement of work.

3. Using the 5 why tools to identify the errors and their causes to avoid them and not

looking for the mistaken people.

4. Focusing on this study as a first step to use the lean in construction projects.

5. Applying the methodology used in the current study to all companies in the Gaza

Strip.

6. Improving the master schedule of the project by standardization tools and measuring

the percent plan complete for each process to deal with errors weekly.

7. Process evaluation and project progress should be measured every 4 weeks as

mentioned in the last planner tools.

8. The percent plan complete average of lean project must be more than 80%.

9. After proving the potential application, lean studies should focus on obstacles of

lean implementation.

83

Page 98: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

References

1. Abudallah Fawaz , (2003),"Lean Manufacturing Tools in the Process Industry With a Focus Industry," PhD dissertation, University of Pittsburg.

2. Alarcón, L.F., (1994), “Training Fielwd Personnel to Identify Waste and

Improvement Opportunities,” Lean Construction, Alarcón, L.F. (ed.), A.A. Balkema, Rotterdam, The Netherlands.

3. Alarcon, L.F., (1994), "Tools for the Identification and Reduction Waste in

Construction Projects". In Alarcon, Luis, (Ed.) Lean Construction, A.A.Balkema, Netherlands.

4. Alwi, S., (1995), "The Relationship Between Rework and Work Supervision of

Upper Structure in The Reinforced Concrete Building Structure," Unpublished Master Thesis, University of Indonesia, Jakarta.

5. Arbulu,R. and Todd, Z., (2006), "Implementing Lean In Construction: How To

Succeed," Proceedings IGLC-14, Santiago, Chile. 6. Arbulu R. J., and Tommelein I. D., (2006), “Value stream analysis of

construction supply chains: Case study on pipe supports used in power plants”, Construction Engineering and Management Program, Civil and Environmental Engineering Department, University of California.

7. Ballard, G. and Howell, G., (1997), "Shielding production: an essential step in

production control,".ASCE, J. Constr., Eng. and Mgmt, 124(1), 11-17.

8. Ballard, G., (1999), “The Last Planner System of Production Control.” Proc. Seventh Annual conference of the International Group for Lean Construction (IGLC-7), Berkeley.

9. Ballard,G., (2000), "The last planner system of production control", PhD thesis,

University of Birmingham.

10. Ballard, G. 2000 a.,“The last planner system of production control.” Ph.D. thesis, Univ. of Birmingham, U.K., http:// www.leanconstruction.org. Access date 5/15/08.

11. Ballard, G., 2000b.,“Lean project delivery system.” LCI White Paper8, Lean,

Construction Institute, http://www.leanconstruction.org. Access date 5/1/09. 12. Ballard, G., and Howell, G., (2003), “An update on last planner.” Proc., Int.,

Group for Lean Construction 11th Annual Conf. ,(IGLC-11), IGLC, Blacksburg, Va., 11–23, http://strobos.cee.vt.edu. IGLC11 Access date 15/5/ 2009.

84

Page 99: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

13. Ballard, G., and Howell, G.,( 2003), “An update on last planner.” Proc., Int. Group for Lean Construction 11th Annual Conf. (IGLC-11), IGLC, Blacksburg, Va., 11–23, http://strobos.cee.vt.edu. IGLC11 Access date 15/5/ 2009.

14. Ballard, G. and Howell, G., (2004), “Competing Construction Management

Paradigms”. Lean Construction Journal, 1 (1), 38-45.

15. Berliner, C. and Brimson, J., (1988), “Cost Management for Today’s Advanced Manufacturing”. Harvard Business School Press, Boston.

16. Björnfot A., (2006), “An exploration of lean thinking for multi-storey timber

housing construction – Contemporary Swedish practices and future opportunities”, Doctoral Thesis, University of Technology, Luleå.

17. Blackerby, p.,(2004), "Lean Practices for the Construction Industry" Fountain

Hills Association of Licensed Contractors Fountain Hills, Arizona.

18. Blaxill, M.F. and Hout, T.M., (1991), "The Fallacy of the Overhead Quick Fix," Harvard Business Review, July- August, 93 - 101.

19. Bendell, A., Disney, J., Pridmore, W.A., (1989), "Taguchi Methods:

Applications in World Industry," IFS Publications/Springer, Bedford.

20. Child, Peter, (1991), "The Management of Complexity". Sloan Management Review, fall.

21. Center National d’Animation des enterprise et de traitement des information du

sector a labore (2003), “Condition general d’execution des travaux,” Algeria

22. Ciampa, Dan, ( 1991), "The CEO’s Role in Time-Based Competition. In: Blackburn," J.D. (ed.). 1991. Time- Based Competition, Business One Irwin, Homewood, IL. 273 - 293.

23. Emmitt, S., Sander, D. and Christoffersen, A. K., (2005), “The value universe: Defining a value based approach to lean construction,” lean construction theory, Denmark.

24. Formoso, C.T.; Franchi, C. and Soibelman, L. (1993), "Developing a Method for

Controlling Material Waste on Building Sites. Economic Evaluation and the Built Environment," CIB, Lisbon.

25. Formoso, C.T.; Isatto, E.L.and Hirota, E.H., (1999), "Method for Waste Control

in the Building Industry," Proceedings of the Seventh Annual Conference of the International Group for Lean Construction, Berkeley-USA.

26. Gavilan, R.M, and Bernold, L., (1993), "Source Evaluation of Solid Waste in

Building and Construction," Draft Report for ASCE Journal of Construction Engineering and Management, 120 (3), 536-52.

85

Page 100: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

27. Graham, P. and Smithers, G., (1996), "Construction Waste Minimisation for Australian Residential Development," Asia Pacific Building and Construction Management Journal, 2 (1), 14-19.

28. Jack M., Farrar, Simaan M., AbouRizk, Xiaoming Mao, (2004) "Generic

Implementation of Lean Concepts in Simulation Models," Lean Construction Journal, 1(1), 1-23.

29. Joachim Gustafsson., Master Thesis 2007, "Value Stream Mapping – A Case

Study Of Construction Supply Chain Of Prefabricated Massive Timber Floor Element," Växjö University, Faculty of Humanities and Social Sciences, School of Management and Economics.

30. Koskela, L., (1992) "Application of the New Production Philosophy to

Construction," Technical Report No. 72, CIFE, Stanford University. 29. Koskela, L., (1993) "Lean Production in Construction," The 10th International

Symposium on Automation and Robotics in Construction (ISARC), Elsevier, USA, 47-54.

30. Koskela, L., (2000) "An Exploration Towards a Production Theory and Its

Application to Construction,” VTT Publications schmenner, R. 1993. Production/operations management: From the inside out, Maxwell Macmillan, New York, 1–29.

31. Koskela, L., ( 2000) "An exploration towards a production theory and its

application to construction," PhD. Thesis. University of Technology of Spoon - Finland.

32. Lee, S.H., Diekmann, J.E., Songer, A.D. and Brown, H., (1999) "Identifying

Waste: Applications of Construction Process Analysis," Proceedings of the Seventh Annual Conference of the International Group for Lean Construction, USA, 63-72.

33. Leticia, Soto, (2007)" Construction Design as a Process for Flow:Applying Lean

Principles to Construction Design" Master of Science in Engineering and Management at the Massachusetts Institute of Technology.

34. Lean Construction, Building, Institute,(2003) "knowledge in design and construction," International Group of Lean Construction.

35. Love, P.E.D.; Mandel, P. and Li, Heng, (1997a) "A Systematic Approach to

Modelling the Causes and Effects of Rework in Construction, ” The First International Conference on Construction Industry Development: Building the Future Together, National University of Singapore, Singapore, 347-355

36. Mohamed, S. and Tucker, S.N., (1996) "Construction Process Re-engineering:

Potential for Time and Cost Savings," The International Journal of Project Management, 14 (6), 321- 403.

86

Page 101: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

37. Monden, Yasuhiro (1998) "Toyota production system: an integrated approach to

just-intime," Engineering and Management Press. Norcross, GA. 3rd ed.

38. Moser, L., and dos Santos, A., (2003) “Exploring the role of visual controls on mobile cell manufacturing: A case study on drywall technology.” Proc., Int. Group for Lean Construction 11th Annual Conf. (IGLC-11), IGLC, Blacksburg, Va., 11–23, _http://www.strobos.cee.vt.edu. Access date 1/5/ 2008.

39. Ohno, T., (1988)," Just-in-Time for Today and Tomorrow", in T. Ohno with S.

Mito, trans. J. P. Schmelzeis, Productivity Press.

40. Owell, G. (1999) “What is lean construction?” Proc., Int. Group for Lean Construction 7th Annual Conf. (IGLC-7), IGLC, Berkeley, Calif., 1–10.

41. Pheng, L.S. and Hui, M.S., (1999), "The Application of JIT philosophy to

construction: a case study in site layout," Journal of Construction Management and Economics, 17(5), 657-668.

42. Pritsker, A. B.,(1986), “Introduction to Simulation and SLAMM II”. Systems

Publishing Corporation, West Lafayette, Indiana.

43. Rummler, Geary A. and Brache, Alan P., (1990),"Improving Performance," Jossey-Bass Publishers, San Francisco. 227 p.

44. Robinson, A., (1991), "Continuous Improvement in Operations; A systematic

Approach to Waste Reduction," Productivity Press, USA.

45. Said, S. (2006), "Manging and Minimizing Construction Waste in the Gaza Strip", Thesis for the Degree of Master of Science in Construction Management at Islamic University of Gaza.

46. Salem, O., Solomon, J., and Genaidy, A., (2006), “Lean Construction: From

theory to implementation”, Journal of Management in Engineering, 22( 4)168-176.

47. Sameh M., (2008), “ Toyota Manufacturing System”, Researches,

http://samehar.wordpress.com. Access date 1/11/2008.

48. Saukkoriipi L., (2004), “Perspectives on no-value added activities: The case of piece-rate in the Swedish construction industry”, Building Economics and Management, Chalmers University of Technology, Göteborg.

49. Schonberger, Richard J., (1986), "World class manufacturing," The Free Press, New

York.

50. Schwaber, K., (2002), "Agile Software Development with Scrum," Prentice Hall. Upper Saddle River, NJ.

87

Page 102: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

51. Serpell, A.; Venturi, A. and Contreras, J., (1995), "Characterization of Waste in Building Construction Projects,” In Alarcon, Luis (1997, Ed.) Lean Construction, A.A. Balkema, Netherlands.

52. Skoyles, E.R. and Skoyles, J.R., (1987), "Waste Prevention on Site. The

Mitchell Publishing Company Limited," London.

53. Stalk, G. jr. and Hout, T.M., (1989), "Competing against time" Free Press, NY.

54. Stewart, Thomas A., (1992),"The Search for the Organization of Tomorrow". Fortune, May 18, 92 - 98.

55. Stuart D. Green and Susan C., (2005), "Lean construction: arenas of enactment,

models of diffusion and the meaning of ‘leanness," Building Research and Information , 33(6), 498–511.

56. Womack, J. and Jones D., (1990), "The Machine that Changed the World,

Campus Pres.

57. Womack, J.P. and Jones, D.T., (1996),"Lean Thinking", Simon and Schuster, New York, NY.

58. Yahia, A., (2004), "Time Schedule Preparation by Predicting Production Rate

Using Simulation", Thesis for the Degree of Master of Science in Construction Management at Islamic University of Gaza.

88

Page 103: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

List of Appendices

Appendix A Daily Report.

Appendix B Arena Simulation.

Appendix C Simulation result of the project before applying eight points and after

applying lean tools.

Appendix D Simulation Result after applying "0" for three biggest non-value added

processes of the project during applying eight points.

89

Page 104: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Appendices (A)

Daily report Date Activity

26/06/2003 Site cleaning, includes removing trees 27/06/2003 Site cleaning, includes removing trees

28/06/2003Site cleaning, includes removing trees, demolishing the existing walling fence, rooms and any obstructed item existing in the proposed area

29/06/2003Site cleaning, includes removing trees, demolishing the existing walling fence, rooms and any obstructed item existing in the proposed area and building engineer office

30/06/2003Site cleaning, includes removing trees, demolishing the existing walling fence, rooms and any obstructed item and existing in the proposed area and building engineer office

01/07/2003 Site cleaning, includes removing trees, demolishing the existing walling fence, rooms and any obstructed item and existing in the proposed area and building engineer office.

02/07/2003 Building engineer office03/07/2003 Building engineer office04/07/2003 Building engineer office05/07/2003 Building engineer office06/07/2003 Excavation of the natural ground to the required levels 07/07/2003 Excavation of the natural ground to the required levels08/07/2003 Excavation of the natural ground to the required levels09/07/2003 Excavation of the natural ground to the required levels10/07/2003 Excavation of the natural ground to the required levels 12/07/2003 Excavation of the natural ground to the required levels13/07/2003 Excavation of the natural ground to the required levels14/07/2003 Excavation of the natural ground to the required levels15/07/2003 Excavation of the natural ground to the required levels16/07/2003 Excavation of the natural ground to the required levels17/07/2003 Excavation of the natural ground to the required levels18/07/2003 Excavation of the natural ground to the required levels20/07/2003 Laboratory 21/07/2003 Expand the excavation 22/07/2003 Expand the excavation 23/07/2003 Laboratory

A1

Page 105: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Activity Date Cheblona work 24/07/2003 Cheblona work and Form work concrete 26/07/2003 Cheblona work and Form work concrete 27/07/2003 Cast in site 10cm thick plain concrete (B200) for "A-B" 28/07/2003 Cast in site 10cm thick plain concrete (B200) for "C" 29/07/2003 Form work foundation concrete "c" and steel work 30/07/2003 Form work foundation concrete "c", steel and cast 3M3 plain concrete 31/07/2003

Form work foundation concrete "c" and steel 02/08/2003 Form work foundation concrete "A-B-C" 03/08/2003 Form work foundation concrete "A-B-C "and steel 04/08/2003 Form work foundation concrete "A-B" steel work and fix neck column "A-B" 05/08/2003

Form work foundation concrete "A-B-C" and steel 06/08/2003 Fix neck column "B" and cast foundation "A-B" 07/08/2003 Remove form work part "A", form work for foundation "c-b", steel work and neck column 09/08/2003

Steel work for foundation part "B", fix steel neck column and cast foundation part 10/08/2003

Form work foundation concrete "A "and steel work. 11/08/2003 Cast ready mix concrete (B300) for reinforced concrete ground beams "B". 12/08/2003 Remove form work and steel work and cleaning 13/08/2003 Remove and reinforced concrete basement walls form work 14/08/2003 Form work neck column and wall concrete 16/08/2003 Form work neck column A-B and wall concrete and adjust of column 17/08/2003 Form work neck column A-B and wall concrete and adjust of column 18/08/2003 Form work wall concrete and cast wall concrete "A" and form work "B" 19/08/2003 Remove form work "A" neck column, form work wall concrete and neck column "B" 20/08/2003 Cast neck column "B", form work "B" wall and neck column 21/08/2003 Form work neck column "A,B" and remove form work wall 23/08/2003 Form work part "B-C" and cast neck column part B 24/08/2003 Cast A-C 25/08/2003 Remove form work and cleaning foundation. 26/08/2003 Isolation work and Cleaning site 27/08/2003 Form work for wall and neck column part "c", isolation work and Cleaning site 28/08/2003 Form work for wall and neck column , isolation work and cleaning site 30/08/2003 Isolation work and cleaning site 31/08/2003 Back filling and cleaning site 01/09/2003 Back filling , laboratory and cleaning site 02/09/2003 Back filling 25cm , laboratory and cleaning site 03/09/2003

A2

Page 106: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Back filling 25 cm , laboratory and cleaning site 04/09/2003 Form work for 5 foundation part "c", back filling work and steel work06/09/2003 Form work for 5 foundation, back filling second layer25 cm 07/09/2003 Form work for 5 foundation part "c", back filling , steel work and laboratory 08/09/2003 Back filling 25 cm 09/09/2003 Form work for wall part "c" and Back filling 25 cm 10/09/2003 Form work for wall, neck column part "c" and back filling 25 cm 11/09/2003 Form work neck column part "c" and back filling part "A-B" 13/09/2003 Cast neck column part "c" and back filling 14/09/2003 Remove form work neck column and Back filling 15/09/2003 Back filling work 25 cm 16/09/2003 Back filling work 25 cm, form work for ground beam and isolation work 17/09/2003 Back filling work 25 cm and form work for ground beam 18/09/2003 Form work for ground beam "A-B-C" 20/09/2003 Form work for ground beam "A-B-C" 21/09/2003 Form work for ground beam " B " 22/09/2003 Form work for ground beam " B " 23/09/2003 Form work for ground beam " B " 24/09/2003 Form work for ground beam " B " 25/09/2003 Form work for ground beam " B " 26/09/2003 Form work for ground beam " B " 27/09/2003 Form work for ground beam "A-B-C" 28/09/2003 Steel work , excavation under ground beam part "B" 29/09/2003 Steel work "A-B" 30/09/2003 Form work ground beam "A-C", steel work for part "B", Supply, install and test UPVC and earth electric.. 01/10/2003 form work for ground beam "A-B-C" , sanitary work and earth electric 02/10/2003 Form work ground beam "B" and earth electric 04/10/2003 Caste ground part "C" 08/10/2003 Caste ground part "A" 09/10/2003 Remove form work "A", Form work wall and column "c" 11/10/2003 Remove form work "A", Form work wall and column "c", steel work ground beam "c" 12/10/2003 Form work G. beam, Form work column "c" and mechanical work 13/10/2003 Form work G.beam , Wall "B", Steel work "c", Isolation work 14/10/2003 Form work G. beam, Steel work column, isolation work 15/10/2003 Form work wall , Column" ABC" 16/10/2003 Form work wall and Column "ABC" 18/10/2003 Cast G. Beam "B", form work wall and column "AC" 19/10/2003 Remove form wall"B",Form work "AC" 20/10/2003 Remove form wall"B"and form work "AC" 21/10/2003 Remove form wall"B"and form work "AC" 22/10/2003 Form work "ABC" 23/10/2003 Form work "ABC" 25/10/2003 Finishing work and isolation 26/10/2003 Isolation work and cleaning 27/10/2003

A3

Page 107: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Form work wall "c" and column "B" 28/10/2003 Column and wall "c" and manhole work "B" 30/10/2003 Cast column and wall "c" and manhole work "B" and cleaning work 01/11/2003 Manhole work "BC" and remove form work "C" 02/11/2003 Manhole work "BC" and remove form work "C" 03/11/2003 Back filling between ground beam and mechanic work and steel work" wall B" 04/11/2003 Back filling between ground beam and Form work "B" and Mechanical work 05/11/2003 Back filling and mechanic work 06/11/2003 Back filling and mechanic work and steel work for column A" 08/11/2003 Steel work and Mechanic work and Column and wall "B" 09/11/2003 Column and wall 'AB" and Mechanic work 10/11/2003 Column and wall 'AB" and Mechanic work 11/11/2003 Column and wall 'AB" and Mechanic work and ground floor steel work 12/11/2003 Cast "A" Column and wall and steel ground floor "AB" and formwork wall and column and mechanical work 13/11/2003 Remove form work "A" column and wall and Ground floor "B" and Form work wall and column "B" and Mechanical work 15/11/2003 Cast "c" ground floor and Form work column " B" remove form work wall and column "A" 16/11/2003 Form work column "B”, ground floor work "B" and remove form work column "A" 17/11/2003 Form work column, ground floor AB and Mechanical work and ground floor slab form work 18/11/2003 Form work column "B", ground floor work AB and mechanical work and Slab form work "c" 19/11/2003 Cast ground floor " AB" and Form work column "B" and Form work slab "c" 20/11/2003 Cast column "c", electric work "b", slab work "c" and Ground floor "B" 22/11/2003 Column "B", slab "c" and Ground floor "B" 23/11/2003 Cast column "B" and Remove 7 column and Ground floor work 24/11/2003 Steel wall and column , slab work "c" and ground floor "B" 29/11/2003 Slab "c 'and Wall "B" 30/11/2003 Cast ground floor 550m2 "B', slab "c" and wall work "B" 01/12/2003 Cast wall "B" 04/12/2003 Remove form work band steel work slab "c" and form work "A" slab 07/12/2003 Remove form work for wall "B", slab "CA "and column work "B" 08/12/2003 Cast column "B", Slab steel, mechanic work "CA" and Remove form work wall "B". 09/12/2003

Slab "AC" 10/12/2003 Slab Work "AC" and Cast column "A" 11/12/2003 Slab work "AC" 13/12/2003 Slab work "AC" 14/12/2003 Slab work "AC" 15/12/2003 Cast slab "c"and Slab work "AC"and Wall work 16/12/2003 Slab work "A"and Column work "c" 17/12/2003

A4

Page 108: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Slab work "A"and Column work "c" 18/12/2003 Slab work "AB"and Column work "c" 20/12/2003 Slab work "AB" 21/12/2003 Slab work "AB" and Column work "c" 22/12/2003 Slab work "AB" and Column work "c" 23/12/2003 Slab work "AB" and Column work "c" 24/12/2003 Slab work "AB" and Column work "c" 25/12/2003 Cast column "c" and slab "AB" 27/12/2003 Slab work "AB" 29/12/2003 Cast slab "A" and Work in slab "B" 30/12/2003 Slab electric work "B" 31/12/2003 Slab work "B" 01/01/2004 Slab work "B" 03/01/2004 Cast Slab work "B"1670m2andform work second floor slab "c" 04/01/2004 Form work second floor slab "c" and Column axes "AB" 06/01/2004 Form work second floor slab "c" and Column "AB" 11/01/2004 Form work second floor slab "c" and Column "AB" 12/01/2004 Form work second floor slab "c" and Column "AB" 13/01/2004 Form work second floor slab "c" and Column "AB" 14/01/2004 Form work second floor slab "c" and Column "AB" 15/01/2004 Form work second floor slab "c" and Column "AB" 17/01/2004 Column work "AB" 18/01/2004 Form work second floor slab "c", column "AB" and Cast column "A"19/01/2004 Form work second floor slab "AC" and Column "B" 20/01/2004 Cast slab "c" and Cast 16 column in part "B" 21/01/2004 Work slab " AB' and Work column "B" and 22/01/2004 Work slab " AB and Work column "B" and electric work 24/01/2004 Slab "AB" and Electric slab "A" and column "B" 25/01/2004 Cast column "B" and Slab work AB 26/01/2004 Remove form work" B" and slab A B 27/01/2004 Cast slab "A" and Work in slab "B". 28/01/2004 Work in slab "B" 29/01/2004 Work in slab "B" 05/02/2004 Slab "B" and Column "AC 07/02/2004 Slab "B" and Column "AC" 08/02/2004 Cast column "C" and slab eclectic "B" and column "A" 09/02/2004 Slab "c", cleaning, first floor column A and Slab B 10/02/2004 Slab "c", building work and first floor column A and Slab B 11/02/2004 Slab "c" and building work and First floor column A and Slab B 12/02/2004 Cast column "A" and Building work and Finishing work in slab "B" 16/02/2004 Slab "c" and Cast slab "B" and building work 17/02/2004 Slab A C and Building work 18/02/2004 Slab A C and Building work 19/02/2004 Slab A, electric slab C and Building work 21/02/2004 Slab A and Electric slab C and Lintel work 22/02/2004 Slab A C and Building work 23/02/2004 Slab A C and Building work 24/02/2004 Slab A C and Building work and Column "B" 25/02/2004

A5

Page 109: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Slab A C and Building work and Column "B" 26/02/2004 Cast slab "C' and Slab work A and Building work 27/02/2004 Slab A and Building work and Column "B" 29/2/2003 Stop work because there are Conflict between the contractor and the consultant. 01/03/2004 Stop work because there are Conflict between the contractor and the consultant. 02/03/2004

Slab A and Building work AC and electric work in wall 03/03/2004 Slab A and Building work AC and electric work in wall 04/03/2004 Slab A and Building work and Column "B" 06/03/2004 Slab A and Building work and Column "B" 07/03/2004 Slab A and Building work and Column "B" and lintel work 08/03/2004 Slab A and Building work and Column "B" 09/03/2004 Slab A and Finishing Building work and Column "B" 10/03/2004

11/03/2004 Cast column ground floor "B" and Slab electric "A" and Lintel AC 13/03/2004 Building ground floor BC and Lintel A and Column first floor "B"

Cast column ground floor "B" and check slab "A" and Lintel A and Building ground floor "B"

15/03/2004

Cast first slab "B" and cast lintel" A" and Building "B" and Electric work and Slab first floor "B' 16/03/2004

Column first floor "B" and Slab first floor AB and building work and Electric wall 17/03/2004

Cast column first floor "B" and slab work "B' and Lintel ground floor "A" and Electric wall and Slab "A" and Back filling column 18/03/2004

Remove form work for column "B" and slab first floor "BC" and Building 20/03/2004

Building ground floor "B" and lintel and slab first floor "B" and Form work7 column "B" 26/03/2003

Building ground floor "AB" and cast "B" and slab first floor "B" 27/03/2004 Building ground floor "B" and slab first floor "B" 28/03/2004 Building ground floor "B" and slab first floor "B" 29/03/2004 Building ground floor "ACB and Slab first floor "B" and lintel ground floor "B" 30/03/2004

Slab first floor "B" and Building first floor "c" and Lintel ground floor "B" 31/03/2004

Slab first floor "B" and building AC and lintel "B" 01/04/2004 Slab first floor "B" and Building first floor "C" 02/04/2004 Slab first floor "B" and Lintel ground floor "B' 04/04/2004 Slab first floor "B" and lintel ground floor "B and building first floor "A" 05/04/2004

Slab first floor "B" and lintel ground floor "B and building first floor "B" 06/04/2004

Slab first floor "B" and lintel ground floor "B and building first floor "A" 07/04/2004

Cast lintel "B" and lintel ground floor "C" and building up lintel "B" and slab first floor "B" 08/04/2004

Cast lintel "B" and lintel ground floor "C" and building up lintel "B" and s lab first floor "B" and electric floor "B" and electric ground floor "A"

10/04/2004

A6

Page 110: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Cast lintel "BC" and Slab first floor "B" 11/04/2004 Slab first floor "B" and lintel AB 12/04/2004 Slab first floor "B" 13/04/2004 Column first floor27"B"andBuiding "B" and lintel Ground floor A 14/04/2004 Slab floor "B" and Building up lintel "B" 15/04/2004 Cast lintel ground floor "B" and Electric slab work and Building ground floor "B" 17/04/2004

Remove form work for lintel and Electric work 18/04/2004 Remove form work for lintel and Electric work and slab floor "B" 19/04/2004 Slab first floor "B" and Lintel Ground floor BC 20/04/2004 Slab first floor "B" and Lintel Ground floor ABC and building "B" 21/04/2004 Cast Slab first floor "B" and Lintel Ground floor ABC and building "B" 22/04/2004

Plastering work and Start remove form work for slab first floor and Electric work and Lintel AC 24/04/2004

Plstering and Lintel floor "AC" and electric ground floor. 25/04/2004 Plastering and Form work G.Floor" and Electric ground floor 26/04/2004 Column roof and Plastering work. 27/04/2004 Form work lintel ground floor and column roof and Plastering and electric ground floor 28/04/2004

Form work lintel ground floor and column roof and Plastering and Electric G.F. 29/04/2004

Column roof and Plastering and Electric G.F. 01/05/2004 Column roof and Plastering and Electric G.F. 02/05/2004 Plastering work 03/05/2004 Stop work because of a conflict between the contractor and consultant 04/05/2004

Stop work because of a conflict between the contractor and consultant 05/05/2004

Stop work because of a conflict between the contractor and consultant 06/05/2004

Remove slab "B" and open window in wall and Form work 08/05/2004 Remove slab "B" and Open window in wall and Electric work 09/05/2004 Plastering work and Lintel and Remove form work slab 10/05/2004 Roof slab and building work 11/05/2004 Roof slab and Plastering work 12/05/2004 Stop work because there are defect in works. 13/05/2004 Slab work and Building work and plastering 15/05/2004 Slab work and Open window in wall and Plastering 16/05/2004 Column roof and Plastering 17/05/2004 Cast column roof 18/05/2004 Remove form work column roof 19/05/2004 Building work 26/05/2004 Open window in wall 29/05/2004 Electric wall 21/06/2004 Slab roof and Building roof in first floor 07/07/2004 Building in first floor and Stop work in roof slab 08/07/2004 Cast roof slab 09/07/2004 Building first floor 11/03/2004

A7

Page 111: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Building first floor 12/07/2004 Building first floor 13/07/2004 Building first floor 14/07/2004 Building first floor 15/07/2004 Slab roof 17/03/2004 Building first floor "B" and slab roof 18/07/2004 Form work lintel first floor "B" 19/07/2004 Slab roof 20/07/2004 Slab roof 21/07/2004 Building first floor "BC" 22/011/2004 Form work roof slab and building work 24/07/2005 Cast lintel first floor and electric roof slab work 25/07/2005 Slab roof 26/07/2005 Lintel first floor and building first floor 31/07/2005 Slab roof and lintel first floor 01/08/2005 Finishing slab roof and form work lintel in first floor 02/08/2005 Building first floor and electric slab roof and lintel first floor 03/08/2005 Slab roof and lintel first floor 04/08/2005 Slab roof and lintel first floor 05/08/2005 Slab roof and building first floor 07/08/2005 Slab roof 08/08/2005 Lintel first floor cast slab roof. 09/08/2005 Building first floor and lintel first floor 10/08/2005

11/08/2005 Building first floor and lintel first floor 12/08/2005 Building first floor and lintel first floor 0412/2005 Building work

A8

Page 112: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Appendix (B)

Arena Simulation

Computer simulation is defined by Pristker (1986) as the process of designing a

mathematical-logical model of a real world system and experimenting with the model

on a computer. Simulation has proved to be a valuable analytical tool in many fields.

Particularly, it is powerful when studying resource-driven processes since it provides a

Fast and economical way to experiment with different alternatives and approaches.

Furthermore, key factors in the process can be identified through an in-depth

understanding of the interactions of resources and processes. Construction operations

include many processes. The flow between processes and the resource utilization at

every step thus determines the performance of the whole project. To understand the

interaction of construction processes and the impact of resource supply, the construction

project planner can experiment with different combinations of construction processes

and varying levels of resource supply in a simulation environment to seek the best

performance for their construction operation.

Arena software (Rockwell Software Manual, 2000) is used to simulate and represent the

real system which allows the planners to observe the behavior of the system when

changes are made in the system. Also Arena enables the planners to bring the power of

modeling and simulation to their planning.

Objectives of arena are:

1. It has good ability for the interface.

2. It has good ability to build scenarios.

3. Data entry is easy.

4. Output reports are more comprehensive.

5. It has good animation for the real system.

The following table show the basic elements of arena simulation.

B1

Page 113: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Table B1: The basic elements of arena simulation

No. Name Symbol Description

1. Create Module

Starting point for entities in a Simulation model

2. Process Module

The main processing method in the simulation

3. Decide Module

Decision-Making processes in the system

4. Assign Module Assigning new values to variables

5. Batch Module

The grouping mechanism within the simulation model.

6. Separate Module

Split a previously batches entity.

7.

Record Module

Collect statistics in the simulation model.

8.

Dispose Module

Ending point for entities in a simulation model.

B2

Page 114: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Appendix (C ) Simulation result of the project before applying eight points and after

applying lean tools

C1

Page 115: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

C2

Page 116: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

C3

Page 117: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

C4

Page 118: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

D1

Page 119: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

D2

Page 120: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

D3

Page 121: A Study of Lean Construction Practices in Gaza Strip · that the lean construction is an established component of construction best practice (Green et al., 2005). Lean construction

Non value added time processes

D4