addendum #2...2020/06/19 · sheet e101: add note to reinstall light fixtures in ceiling. 2 7....
TRANSCRIPT
1
ADDENDUM #2
June 19, 2020
Project Name: Lake Woodard Annex Renovations
Owner: Raleigh Water City Bid #: MISC-2020-46 HH Project #: 16-097 From: HH Architecture David Carey, Associate AIA, LEED AP [email protected]
To: All plan holders (plan holders list is available on planscope.com)
Message: Bidders are hereby informed that the following additions, deletions, changes and clarifications supersede and supplement the Contract Documents for the above referenced project. It forms a part of the previously issued documents dated May 22, 2020. This addendum may include revised pages and drawings, which shall be inserted before the corresponding page or drawings in the previously issued documents.
REVISIONS TO SPECIFICATIONS
1. Section 081216 Aluminum Frames: ADD entire section with attached section 081216.
2. Section 012100 Allowances: REVISE 3.3 Schedule of Allowances as follows:
a. Allowance No. 1: Lump-Sum Allowance: Include the sum of $2,500 $1,200 for all City of Raleigh Permits and Inspections.
3. Section 267500 Telecommunication Cabling Infrastructure: ADD entire section with attached section 267500.
REVISIONS TO DRAWINGS
1. Sheet D121: REPLACE entirely with revised sheet attached.
2. Sheet A001: REPLACE entirely with revised sheet attached.
3. Sheet A121: REPLACE entirely with revised sheet attached.
4. Sheet ID001: REPLACE entirely with revised sheet attached.
5. Sheet ED101: ADD note to support light fixtures for removal of ceiling.
6. Sheet E101: ADD note to reinstall light fixtures in ceiling.
2
7. Sheet E201: ADD receptacle and data outlet to new wall. Revised Keynote No. 10 to describe breaker as GFCI breaker.
8. Sheet E401: REVISE “2 - CAT 5e data cables in 1-1/4”C” to “2 – CAT 6 data cables in 1-1/4”C”.
CLARIFICATIONS
1. There will be no unit prices listed on the bid form. Price Bid Schedule on page 5 of bid form is to be blank. List as N/A for this project.
2. There will be no elevator access during construction, including material and debris transport.
3. Trash chutes will not be allowed to be installed for this project.
4. COVID-19 Statement:
a. COVID-19 impact: With current impacts due to COVID-19 the Owner will be willing to extend the construction contract duration for issues with material procurement or subcontractor engagement that are beyond the control of the selected Contractor. It is expected that the Contractor will alert the Owner and Architect in advance of such delays to the greatest extent possible. Liquidated Damages will not be assessed nor will the Owner entertain any extended General Conditions costs for such impacts.
5. The total estimated construction cost for this project is $415k.
6. The television work in break room 233 shall be part of the base bid.
7. Training Room is numbered 241 on construction documents; however, it should be noted that the room signage on site labels it as 232.
8. Raleigh Water will remove all existing equipment, furniture, contents, flat files, refrigerator, etc. prior to Notice to Proceed. Existing work stations to be re-used will be removed by Owner and stored off site prior to NTP.
9. Please see the video provided by Raleigh Water in the link below.
a. https://hh-arch.sharefile.com/d-s569002053754bf09
10. General Contractor is responsible for Telecom and AV scope, as well as Equipment located on sheet ID001. Furniture will be by Owner. See project documents for Contractor responsibilities for rough-in and blocking requirements.
11. Deck in open office area 242 does not need to be painted. All new mechanical ceiling items installed in his area shall be painted to match existing.
12. The only work scope in room 241 is installation of acoustical panels. No paint or carpet work is required in this room.
13. Sales tax is excluded from bid but is applicable and required to be reported by contractor in order to be reimbursed.
14. Assume existing ceramic tile floors, tile wall base, and mud bed located in 235, 239 and 242 to be removed along with setting bed and any residue.
15. In open office area 242, casework built into exterior walls shall remain. All other casework to
3
be removed per the documents. See example on attached picture A.
16. System specific manufacturers noted in Section 250100 2.1 A 1 – Operation and Maintenance of Integrated Automation
a. Johnson Controls
17. System specific manufacturers noted in Section 283100 2.1 A 1 - Fire Alarm
a. Match existing fire alarm system manufacturer – MIRCOM
18. TU 2-3 and TU 2-4 are new. All others are existing. These two new units will use the same numbering as the two boxes shown on the demolition drawing. We are trying to keep terminal unit numbering in the control system consistent. TU 2-5 (E) & TU 2-11 (E) are to be relocated.
PICTURE A
END OF ADDENDUM #2
Lake Woodard Annex Renovations Construction Documents
Raleigh Water 05/22/2020
Aluminum Frames 081216 - 1
SECTION 081216 - ALUMINUM FRAMES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and
Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Interior aluminum frames for doors installed in gypsum board partitions.
2. Interior aluminum frames for glazing installed in gypsum board partitions.
1.3 PREINSTALLATION MEETINGS
A. Preinstallation Conference: Conduct conference at Project site.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
1. Include construction details, material descriptions, dimensions of individual components and
profiles, fire-resistance rating, and finishes.
B. Shop Drawings: For aluminum frames:
1. Include elevations, sections, and installation details for each wall-opening condition.
2. Include details for each frame type, including dimensioned profiles and metal thicknesses.
3. Include locations of reinforcements and preparations for hardware.
4. Include details of anchorages, joints, field splices, connections, and accessories.
5. Include details of moldings, removable stops, and glazing.
C. Samples: For each exposed product and for each color and texture specified, in manufacturer's standard
sizes.
D. Product Schedule: For aluminum frames. Use same designations indicated on Drawings. Coordinate with
door hardware schedule and glazing.
1.5 CLOSEOUT SUBMITTALS
A. Maintenance Data: For aluminum frames to include in maintenance manuals.
1.6 QUALITY ASSURANCE
A. Mockups: Build mockups to verify selections made under Sample submittals and to demonstrate aesthetic
effects and to set quality standards for fabrication and installation.
1. Build mockup of each type of aluminum frame in typical wall area as shown on Drawings.
2. Approval of mockups does not constitute approval of deviations from the Contract Documents
contained in mockups unless Architect specifically approves such deviations in writing.
3. Subject to compliance with requirements, approved mockups may become part of the completed
Work if undisturbed at time of Final Acceptance.
Lake Woodard Annex Renovations Construction Documents
Raleigh Water 05/22/2020
Aluminum Frames 081216 - 2
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Basis-of-Design Product: Subject to compliance with requirements, provide Frameworks, Inc.; an
ASSA ABLOY Group company; or comparable product by one of the following:
1. Dual Lock Partition Systems, Inc.; Avalon International Aluminum.
2. RACO Interior Products, Inc.
3. Versatrac Frames; a division of American Door Products Inc.
B. Source Limitations: Obtain aluminum frames from single source from single manufacturer.
2.2 COMPONENTS
A. Aluminum Framing: ASTM B 221, with alloy and temper required to suit structural and finish
requirements, and not less than 0.062 inch thick.
B. Door Frames: Extruded aluminum, knock down frame, reinforced for hinges, strikes, and closers.
C. Glazing Frames: Extruded aluminum, for indicated glass thickness.
D. Door Tracks: Extruded aluminum where exposed, sized to enclose sliding-door hardware, and in finish.
E. Trim: Extruded aluminum, not less than 0.062 inch thick; removable, snap-in casing trim glazing stops
and door stops, without exposed fasteners.
1. Trim Style: Type II, 2" Flush Trim.
F. Doors: As specified in Section 081416 "Flush Wood Doors."
G. Frame and Trim Finish: Clear-anodized aluminum.
2.3 ACCESSORIES
A. Fasteners: Aluminum, nonmagnetic, stainless-steel or other noncorrosive metal fasteners compatible with
frames, stops, panels, reinforcement plates, hardware, anchors, and other items being fastened.
B. Door Silencers: Manufacturer's standard continuous mohair, wool pile, or vinyl seals in black color.
C. Glazing Gaskets: Manufacturer's standard extruded or molded rubber or plastic, to accommodate glazing
thickness indicated; in black.
D. Glass: As specified in Section 088000 "Glazing."
2.4 FABRICATION
A. Provide concealed corner reinforcements and alignment clips for accurately fitted hairline joints at butted
connections.
B. Factory prepare aluminum frames to receive templated mortised hardware; include cutouts,
reinforcements, mortising, drilling, and tapping, according to the Door Hardware Schedule and templates
furnished as specified in Section 087100 "Door Hardware."
Lake Woodard Annex Renovations Construction Documents
Raleigh Water 05/22/2020
Aluminum Frames 081216 - 3
C. Fabricate frames for glazing with removable stops to allow glazing replacement without dismantling
frame.
1. Locate removable stops on the inside of spaces accessed by keyed doors.
D. Fabricate components to allow secure installation without exposed fasteners.
2.5 GENERAL FINISH REQUIREMENTS
A. Appearance of Finished Work: Noticeable variations in same piece are not acceptable. Variations in
appearance of adjoining components are acceptable if they are within the range of approved Samples and
are assembled or installed to minimize contrast.
2.6 ALUMINUM FINISHES
A. Clear Anodic Finish: AAMA 611, AA-M12C22A31, Class II, 0.010 mm or thicker.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for
installation tolerances and other conditions affecting performance of the Work.
B. Verify that wall thickness does not exceed standard tolerances allowed by throat size of indicated
aluminum frame.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Install aluminum frames plumb, rigid, properly aligned, and securely fastened in place; according to
manufacturer's written instructions.
B. Install frame components in the longest possible lengths with no piece less than 48 inches; components
96 inches or shorter shall be one piece.
1. Use concealed installation clips to produce tightly fitted and aligned splices and connections.
2. Secure clips to extruded main-frame components and not to snap-in or trim members.
3. Do not leave screws or other fasteners exposed to view when installation is complete.
C. Glass: Install glass according to Section 088000 "Glazing" and aluminum-frame manufacturer's written
instructions.
D. Door Hardware: Install according to Section 087100 "Door Hardware" and aluminum-frame
manufacturer's written instructions.
3.3 ADJUSTING
A. Inspect installation, correct misalignments, and tighten loose connections.
B. Clean exposed frame surfaces promptly after installation, using cleaning methods recommended in
writing by frame manufacturer and according to AAMA 609 & 610.
Lake Woodard Annex Renovations Construction Documents
Raleigh Water 05/22/2020
Aluminum Frames 081216 - 4
C. Touch Up: Repair marred frame surfaces to blend inconspicuously with adjacent unrepaired surface so
touchup is not visible from a distance of 48 inches as viewed by Architect. Remove and replace frames
with damaged finish that cannot be satisfactorily repaired.
END OF SECTION
Lake Woodard Annex Renovations Addendum No. 2 Raleigh Water 06/17/2020
Telecommunications Cabling Infrastructure 265100 - 1
267500 – TELECOMMUNICATION INFRASTRUCTURE CABLING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions
and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes wire, cable, connecting devices, installation, and testing for wiring systems to be used
as signal pathways high-speed data transmission. This includes cabling designated as “Data” and “Voice
(over IP)”.
B. Structured Cabling System Warranty: The Data Infrastructure Cabling system shall be warranted as a
structured cabling system by the connecting hardware manufacturer. The Contractor shall be a Certified
Installer by the manufacturer. The Contractor shall furnish all labor, supervision, tooling, and
miscellaneous mounting hardware and consumables necessary to qualify for the manufacturer’s system
warranty. The Contractor shall initially have and maintain current status a certified installer with the
warranting manufacturer, including all training requirements, for the duration of the Project. Refer to
Warranty paragraph below for further details.
C. Relevant criteria from the City of Raleigh Network Infrastructures Standards have been incorporated within
this section.
1.3 DEFINITIONS
A. EMI: Electromagnetic interference.
B. IDC: Insulation displacement connector.
C. LAN: Local area network.
D. PVC: Polyvinyl chloride
E. UTP: Unshielded twisted pair.
1.4 REFERENCES
A. EIA/TIA-568-A: Commercial Building Telecommunications Cabling Standard.
B. EIA/TIA-569: Commercial Building Standard for Telecommunications Pathways and Spaces.
C. EIA/TIA-606: Administrative Standard for the Telecommunications Infrastructure of Commercial
Buildings.
D. EIA/TIA-607: Commercial Building Grounding and Bonding Requirements for Telecommunications.
E. NEC: National Electric Code.
Lake Woodard Annex Renovations Addendum No. 2 Raleigh Water 06/17/2020
Telecommunications Cabling Infrastructure 265100 - 2
F. BISCI TDMM: Building Industries Consulting Services, International Telecommunications Distribution
Design Manual.
1.5 SUBMITTALS
A. Product Data: Include data on features, ratings, and performance for ALL components specified.
B. Shop Drawings: Include dimensioned plan and elevation views of each individual component. Show
equipment assemblies, method of field assembly, workspace requirements, and access for cable
connections.
1. Provide bound full size sets of scaled architectural floor plans with Installer’s border sheet depicting
outlet and equipment locations and proposed route of backbone cabling. Label all outlets utilizing
proposed labeling scheme. Electronic copy of architectural floor plans will be provided by Engineer
in format compatible with most recent release of AutoCAD upon request. Copies of Project
Construction Documents or details there from may NOT be part of Shop Drawings.
2. Provide key to labeling scheme with description and multiple examples.
3. All rack elevations depicting manufacturer and model numbers for patch panels, fiber trays, wire
management and rack.
4. Outlet faceplate elevations depicting manufacturer and model numbers for faceplate and jacks.
C. Qualification Data, for Manufacturers: Provide copy of proposed structured cabling system warranty with
appropriate documentation that warranty has been applied for.
D. Qualification Data for Installer: Provide letter documenting personnel, projects, and indicating compliance
with Installer Qualifications as required in paragraph 1.6 QUALITY ASSURANCE.
E. Cabling Test Reports. Provide hard copy and digital files on a compact disk. Include viewing software on
disk.
F. Cabling Schedule: Provide hard copy and digital spreadsheet files on a compact disk. Spreadsheet files
must be Microsoft Excel compatible format.
G. As-built Drawings: Prior to final acceptance, provide three complete bound full size sets of scaled
architectural floor plans with Installer’s border sheet depicting final outlet and equipment locations and
route of backbone cabling. All outlets shall be labeled on As-builts as labeled at project site. Electronic
copy of architectural floor plans will be provided by Engineer in format compatible with most recent release
of AutoCAD upon request. Copies of Project Construction Documents or details there from may NOT be
part of as-builts. As-builts for Intercom System, Data Infrastructure System, and MATV System shall be
bound together. Furnish electronic record of all plan drawings on compact disk, in AutoCad R14 software
format.
H. Operation and Maintenance Data: For voice and data communication cabling to include in
emergency, operation, and maintenance manuals.
I. At Project Completion
1. As-Builts: Prior to final acceptance, provide three complete bound full size sets of scaled
architectural floor plans with Installer’s border sheet depicting final device and equipment
locations and route of backbone cabling. Electronic copy of architectural floor plans will be
provided by Engineer in format compatible with most recent release of AutoCAD upon
request. Copies of Project Construction Documents or details there from may NOT be part of
as-builts. Provide electronic copy of As-builts in submittal.
Lake Woodard Annex Renovations Addendum No. 2 Raleigh Water 06/17/2020
Telecommunications Cabling Infrastructure 265100 - 3
2. Operation And Maintenance Manuals: Prior to final acceptance, provide three complete sets
of operation and maintenance manuals for the system. The operation manual shall contain all
instruction necessary for the proper operation of the installed system and manufacturer’s
instruction. The maintenance manual shall contain all "proof of performance" information as
required in Section 3, and all manufacturer’s maintenance information, and copies of non-
priority computer programs and system set up disks documenting all programmable features
for the installed system.
1.6 QUALITY ASSURANCE
A. Installer Qualifications:
1. System Installer shall be a manufacturer certified installer under the Warranty program listed below
at time of bid and shall possess a NC Specialty Low-voltage License.
2. System Installer must have installed within the last three years a minimum of three projects of
similar scope and complexity.
3. System Installer shall employ a job superintendent or project manager during the course of the
installation to provide coordination of work. This person shall maintain current RCDD®
(Registered Communications Distribution Designer) registration and shall be responsible for quality
control during installation, equipment set-up, and testing.
4. System Installer’s installation personnel shall meet manufacturer’s training and education
requirements to comply with Warranty program.
B. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for
intended use.
C. Surface-Burning Characteristics of Cabling: As determined by testing identical products according
to ASTM E 84 by a qualified testing agency. Identify products with appropriate markings of
applicable testing agency.
a. Flame-Spread Index: 25 or less.
b. Smoke-Developed Index: 50 or less
D. Comply with NFPA 70.
E. 25-Year Performance Warranty
The warranty proposed for this infrastructure must meet the following minimum requirements and
be a total sole source warranty supplied by the General contractor specifying a single point of con-
tact for warranty claims on the copper or fiber installation. The warranty is to be comprised of the
following segmented parts:
1. 25-Year System Performance Warranty (Not Component Only). Includes copper and fiber
optic cabling.
2. Warrant all current and all future network applications designed for a TIA/EIA 568-B
compliant infrastructure.
3. Cover labor and materials for repair or replacement of defective products.
4. Warranty to be issued directly to the end-user (not to the Contractor)
1.7 COORDINATION
A. Coordinate layout and installation of voice and data communication cabling with Owner's
telecommunications and LAN equipment suppliers.
Lake Woodard Annex Renovations Addendum No. 2 Raleigh Water 06/17/2020
Telecommunications Cabling Infrastructure 265100 - 4
1. Meet jointly with telecommunications and LAN equipment suppliers, local exchange carrier
representatives, and Owner to exchange information and agree on details of equipment
arrangements and installation interfaces.
2. Record agreements reached in meetings and distribute to other participants.
B. Pre-Installation Meeting: Electrical Contractor and System Installer shall attend a pre-installation meeting
with Engineer and Owner to discuss issues that pertain to telecom work.
C. Coordinate layout and installation of all equipment and all pathways with other construction, including
conduit, piping, and adjacent surfaces. Maintain proper work space clearances.
1.8 EXTRA MATERIALS
A. Furnish extra materials described below that match products installed and that are packaged with
protective covering for storage and identified with labels describing contents.
1. Cable: 250 feet of each size and type used for Project. Furnish on reels.
2. Patch-Panel Units: One of each type for every six (6) installed, but no fewer than one.
3. Connecting Blocks: One of each type for every 25 installed, but no fewer than one.
4. Outlet Assemblies: One of each type for every 25 installed, but no fewer than one.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Structured Cabling System Manufacturers: Subject to compliance with requirements, manufacturers
offering structured cabling systems that may be incorporated into the Work include the following:
1. Berk-Tek, A Nexans Company
2. Hubbell Premise Wiring, Hubbell Incorporated
3. Leviton Manufacturing Co., Inc.
4. SYSTIMAX by CommScope Inc.
5. Ortronics, Inc./Legrand
6. Panduit Corp.
B. It is the intent of the manufacturers listed for Structured Cabling System to denote the quality standard of
product desired and not to restrict bidders to a specific brand, make, manufacturer or specific name. The
manufacturers and products listed below are used only to set forth and convey to bidders the general style,
type, character, and quality of product desired. Substitution of equivalent products will be acceptable
according to the following paragraph.
1. Substitution of Equivalent Products: Substitution of manufacturers and products equivalent to those
below shall be submitted to the Engineer for approval; such approval shall be made by the Engineer
prior to the opening of bids and included in addenda. All substitution requests shall be received by
the Engineer a minimum of 10 days prior to the opening of bids.
2.2 SYSTEM REQUIREMENTS
A. General: Coordinate the features of materials and equipment so they form an integrated system.
Match components and interconnections for optimum future performance.
Lake Woodard Annex Renovations Addendum No. 2 Raleigh Water 06/17/2020
Telecommunications Cabling Infrastructure 265100 - 5
B. Single Source: All copper and fiber termination equipment shall be from a single manufacturer. All
copper cabling shall be from a single manufacturer and fiber cabling shall be from a single
manufacturer.
2.3 TWISTED-PAIR CABLES, CONNECTORS, AND TERMINAL EQUIPMENT
A. Cables: Listed as complying with Category 6 of TIA/EIA-568-A.
B. Conductors: Solid copper.
C. UTP Cable: Comply with TIA/EIA-568-A. Four, thermoplastic-insulated, individually twisted pairs
of conductors; No. 24 AWG, color-coded; enclosed in overall jacket. Jacket Color as follows:
1. Horizontal Voice (Over IP): Blue
2. Horizontal Data: Blue
D. All cable shall be plenum rated (CMP).
E. UTP Cable Connecting Hardware: Comply with TIA/EIA-568-A, using modules designed for
punch-down caps or tools.
1. IDC Terminal Block Modules: Integral with connector bodies, including plugs and jacks
where indicated.
2. IDC Connecting Hardware: Consistent throughout Project.
F. Patch Panel: Modular panels housing multiple jack units with Category 6 compliant IDC-type
connectors at each jack for permanent termination of pair groups of installed horizontal cables.
Jacks shall be configured in replaceable modular groups of six jacks each.
1. Number of Jacks supported per Field/Panel: 48 Port (2U). With number of panels per IDF as
required to terminate all horizontal data cables and provide 15% spare.
2. Provide separate dedicated patch panels for horizontal data, voice (over IP), and security.
3. Mounting: Existing Rack.
G. Workstation Faceplates: Modular style faceplate supporting number of ports/jacks as shown on
plans. Faceplate shall incorporate covered labeling slots at the top and bottom of faceplate.
1. Faceplate: High-impact plastic; color: Shall be approved by architect.
2. Mounting: Flush, unless otherwise indicated.
3. Refer to plans for additional details and types.
H. Surface Outlets: Small form factor housing modular jack assemblies designed for surface mounting
and supporting number of ports shown on plans.
I. Data Jacks and Jack Assemblies for UTP Cable: Modular, color-coded, RJ-45 receptacle units with
integral IDC-type terminals. Listed as complying with Category 6
J. of TIA/EIA-568-B.2.
1. Horizontal Voice (Over IP): Blue.
2. Horizontal Data: Blue.
2.4 WIRE MANAGEMENT PANELS
Lake Woodard Annex Renovations Addendum No. 2 Raleigh Water 06/17/2020
Telecommunications Cabling Infrastructure 265100 - 6
A. Provide vertical wire management for each rack in Telecom room. Provide two per rack. Vertical members
shall have the capacity for 480 Category 6 cables and have metal hinged doors.
B. Provide horizontal wire managements panels, (install one per patch panel).
2.5 IDENTIFICATION PRODUCTS
A. Cable Labels: Vinyl wraparound tape markers, machine printed with alphanumeric cable designations.
Covered with clear shrink wrap. Use of clear tape is unacceptable.
B. Outlet and Patch Panel Labels: Vinyl permanent, non-erasable, stick-on, labeling using a professional
labeling machine.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine pathway elements intended for cables. Check raceways, and other elements for compliance
with space allocations, installation tolerances, hazards to cable installation, and other conditions
affecting installation. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.2 RACEWAY INSTALLATION
A. All 2” or larger conduit and sleeves:
1. A pullbox sized per BICSIs Telecommunications Distributions Methods Manual must be
provided after every 180° of bend or in straight section exceeding 150’ in length.
2. All bends must utilize manufactured sweeping long-radius elbows.
3. Provide bushings and marked pull tape for all.
3.3 APPLICATION OF MEDIA
A. Horizontal Cable for Copper Voice (over IP) Service: Use UTP Category 6 cable for runs between
workstation outlets and Telecom rooms (IDFs). Terminate horizontal cable in dedicated Voice (over
IP) rack-mounted patch panels.
B. Horizontal Cable for Copper Data Service: Use UTP Category 6 cable for runs between workstation
outlets and Telecom rooms (IDFs). Terminate horizontal data cable in rack-mounted patch panels.
3.4 INSTALLATION
A. Each wiring system, Voice (over IP) and Data shall be mounted on separate patch panels within each
rack/cabinet.
B. Data jacks shall be terminated using TIA/EIA 568B color coding.
C. Wiring Method: Install control wiring in raceway where concealed within walls, concealed above
inaccessible ceilings, and where exposed. In accessible ceiling spaces provide Innerduct for fiber
and all copper to be supported by J-hooks. Conceal raceway and cables except in unfinished spaces.
D. Patch cables from wall to VOIP phones or PCs shall be provided by vendor. City of Raleigh IT
Department will advise required length.
Lake Woodard Annex Renovations Addendum No. 2 Raleigh Water 06/17/2020
Telecommunications Cabling Infrastructure 265100 - 7
E. Install cables using techniques, practices, and methods that are consistent with Category 6 rating of
components, and that ensure Category 6 performance of completed and linked signal paths, end to
end.
F. Install cables without damaging conductors, shield, or jacket. Visible jacket stress is considered
damage. Engineer to have final word on cable damage. Damaged cables shall be replaced.
G. Do not bend cables, in handling or in installing, to smaller radii than minimums recommended by
manufacturer.
H. Pull cables without exceeding cable manufacturer's recommended pulling tensions.
1. Pull cables simultaneously if more than one is being installed in same raceway.
2. Use pulling compound or lubricant if necessary. Use compounds that will not damage
conductor or insulation.
3. Use pulling means, including fish tape, cable, rope, and basket-weave wire or cable grips, that
will not damage media or raceway.
I. Install exposed cables parallel and perpendicular to surfaces or exposed structural members and
follow surface contours where possible.
J. Provide 4’ service loop for all copper cables in outlet at conduit stub-up. Provide 10’ service loop
for all copper cables in ladder rack above equipment rack/cabinet in IDF/MDFs.
K. Secure and support cables at intervals not exceeding 60 inches and not more than 6 inches from
cabinets, boxes, fittings, outlets, racks, frames, and terminals.
L. All cables shall be secured using Velcro fasteners. The use of “ty-wraps” is not acceptable.
M. Wiring within Wiring Closets and Enclosures: Provide conductors of adequate length. Train
conductors to terminal points with no excess. Use lacing bars to restrain cables, to prevent straining
connections, and to prevent bending cables to smaller radii than minimums recommended by
manufacturer.
N. Separation of Wires: Comply with TIA/EIA-569-A rules for separating unshielded copper voice and
data communication cabling from potential EMI sources, including electrical power lines and
equipment.
O. Make splices, taps, and terminations only at indicated outlets, terminals, and cross-connect and patch
panels.
P. Use splice and tap connectors compatible with media types.
Q. Contractor to terminate the voice backbone cables on 66 blocks.
3.5 GROUNDING
A. Ground equipment to eliminate shock hazard and to minimize ground loops, common-mode returns,
noise pickup, cross talk, and other impairments.
3.6 INSTALLATION IN EQUIPMENT ROOMS AND WIRING CLOSETS
A. Group connecting hardware for cables into separate logical fields.
B. Use patch panels to terminate cables entering the space, unless otherwise indicated.
Lake Woodard Annex Renovations Addendum No. 2 Raleigh Water 06/17/2020
Telecommunications Cabling Infrastructure 265100 - 8
3.7 INSTALLATION STANDARDS
A. Comply with requirements in TIA/EIA-568-A and TIA/EIA-569-A.
B. Comply with requirements in TIA/EIA-560-A standards.
3.8 IDENTIFICATION
A. System: Per the Labeling Scheme outlined in the City of Raleigh Network Infrastructures Standards
use a unique, alphanumeric designation for each cable, and label cable and jacks, connectors, and
terminals to which it connects with same designation. Use logical and systematic designations for
facility's architectural arrangement.
1. Example Label: 2A-24
2. First syllable identifies the building floor and the patch panel designator: (2A).
3. Second syllable identifies port number: (24)
4. Corresponding port number shall match label on end point face plate where terminated: (A-
24)
5. Line wire labeled at both ends, patch panel and face plate.
B. Workstation:
1. Label cables within outlet boxes.
2. Label each port in workstation faceplate. Utilize labeling slots at the top and bottom of
faceplate.
C. Distribution Racks and Frames: Label each unit and field within that unit.
D. Within Connector Fields in Equipment Rooms and Wiring Closets: Label each connector and each
discrete unit of cable-terminating and connecting hardware. Where similar jacks and plugs are used
for both voice and data communication cabling, use a different color for jacks and plugs of each
service.
E. Cables, General: Label each cable within 4 inches of each termination and tap, where it is accessible
in a cabinet or junction or outlet box, and elsewhere as indicated.
1. Labeling of cables at patch panel shall be applied such that label is visible without removing
the bundle support ties. Cables labeled within the bundle, where the label is obscured from
view shall not be acceptable.
F. Cable Schedule: Post in prominent location in each equipment room and wiring closet. List
incoming and outgoing cables and their designations, origins, and destinations. Protect with rigid
frame and clear plastic cover. Furnish an electronic copy of final comprehensive schedules for
Project, in software and format selected by Owner.
G. Cable Administration Drawings: Show building floor plans with cable administration point labeling.
Identify labeling convention and show labels for telecommunications closets, backbone pathways
and cables, terminal hardware and positions, horizontal cables, work areas and workstation terminal
positions, grounding buses and pathways, and equipment grounding conductors. Follow convention
of TIA/EIA-606. Furnish electronic record of all plan drawings, in AutoCad R14 software or newer
versions.
3.9 FIELD QUALITY CONTROL
Lake Woodard Annex Renovations Addendum No. 2 Raleigh Water 06/17/2020
Telecommunications Cabling Infrastructure 265100 - 9
A. Testing Agency: Engage a qualified testing and inspecting agency to perform the following field
tests and inspections and prepare test reports:
B. Perform the following field tests and inspections and prepare test reports:
1. Operational Test: After installation of cables and connectors, demonstrate product capability
and compliance with requirements. Test each signal path for end-to-end performance from
each end of all pairs installed. Remove temporary connections when tests have been
satisfactorily completed.
2. Copper Cable Procedures: Inspect for physical damage and test each conductor signal path
for continuity and shorts. Test according to TIA/EIA-TSB67, "Transmission Performance
Specifications for Field Testing of Unshielded Twisted-Pair Cabling Systems". Link
performance for UTP cables must meet minimum criteria of TIA/EIA-568-A.
3. All cable identifications listed on test data must match the cable identifications of the labels
installed on the face plates and patch panels.
C. Remove malfunctioning units, replace with new units, and retest as specified above. Provide testing
results to the City of Raleigh IT Department for approval upon completion.
D. Reporting: Provide both hard copy and electronic copy of all unacceptable and final acceptable test
results as directed in SUBMITTALS paragraph.
END OF SECTION
1. THE CONTRACTOR SHALL FIELD VERIFY THE DIMENSIONS,
ELEVATIONS, AND OTHER REQUIREMENTS NECESSARY FOR
CONSTRUCTION. ANY DISCREPANCIES SHALL BE BROUGHT TO
THE ATTENTION OF THE ARCHITECT.
2. ALL PARTITIONS ARE TO BE TYPE 'M40A' UNLESS OTHERWISE
NOTED. SEE A-001 FOR WALL PARTITION LEGEND.
3. PROVIDE TEMPERED GLASS AT DOOR AND WINDOW LITES.
4. ALL DIMENSIONS ARE TO THE FACE OF CMU OR FACE OF WALL.
5. ALL DOOR HINGE-SIDE JAMBS TO BE 4" FROM FACE OF THE
PERPENDICULAR WALL TO THE INSIDE FACE OF THE METAL
JAMB, TYP., U.N.O.
6. FOR FINISHES, NEW AND EXISTING, SEE FINISH PLAN SHEETS.
7. GENERAL CONTRACTOR TO VERIFY ALL EXISTING CONDITIONS.
KEYNOTES DO NOT EXCLUDE CONTRACTOR FROM REPAIRING
AND PATCHING ALL FLOORS, WALLS AND CEILINGS AS NEEDED
AS A RESULT OF DEMOLITION WORK. GENERAL CONTRACTOR
TO PREPARE ALL FLOORS AND WALL SUBSTRATES AS REQUIRED
TO APPLY NEW FINISH AS INDICATED IN THE FINISH PLANS
AND SPECIFICATIONS.
GENERAL ARCHITECTURAL
NOTES
PARTITION NOTES:1. ALL RATED WALL ARE TO BE STENCIL PAINTED IN RED AS
FOLLOWS:
"1-HOUR RATED WALL
SMOKE BARRIER; SEAL ALL PENETRATIONS"
WITH THE APPLICABLE RATING NOTED, PER PLANS. LETTERS
TO BE 6" HIGH. STENCILS TO BE 12" ABOVE CEILING AND
SPACED AT 48" O.C. MAX. BOTH SIDES OF WALL.
2. COORDINATE ADJACENT WALLS OF DIFFERENT TYPES SO THAT
GYP. BD. WALL FACES ALIGN. RESILIENT CHANNELS TO BE ON
THE SAME SIDE OF THE WALL, TYP.
3. FACE OF STUD = FACE OF RESILIENT CHANNEL, WHERE
APPLICABLE.
4. ALL INTERIOR PARTITIONS TO BE TYPE 'M40A', U.N.O.
5. SEAL PERIMETER OF ALL WALLS, TYP.
6. PROVIDE FIRE SEALANT AT BASE OF ALL WALLS REQUIRING
FIRE RATING.
7. SEE FINISH SCHEDULE AND FINISH PLANS FOR WALL TILE
AND WALL FINISHES.
8. SEE Mxx SYMBOL ON PLANS FOR PARITION TYPES.
9. ALL RATED WALLS TO BE CONTINUOUS SYSTEMS. GC TO
COORDINATE CORRECT SEQUENCING OF RATED WALL
CONSTRUCTION.
A-000
01
SYMBOL LEGEND
CEILING ELEVATION HT.
ROOM / AREA
DOOR ID.
DETAIL
NORTH ARROW
ELEVATION CALLOUT
WINDOW TYPE
INTERIOR PARTITION TYPE
SECTION CALLOUT
FF&E TYPE
ROOM NAME
101
101
A101
1
N
A
3
A-000
01
A 8' - 0"
CEILING TYPE
P01
DEMOLITION GENERAL NOTES1. CONTRACTOR AND ALL SUB-CONTRACTORS MUST VISIT THE
SITE AND FULLY EXAMINE EXISTING CONDITIONS PRIOR TO
COMMENCING WORK. ANY DISCREPANCIES IN THE EXISTING
CONDITION AND THE WORK MUST BE BROUGHT TO THE
IMMEDIATE ATTENTION OF THE ARCHITECT.
2. GENERAL CONTRACTOR MUST PROTECT ALL EXISTING
MATERIALS TO REMAIN. REPAIR OR REPLACEMENT WILL BE THE
RESPONSIBILITY OF THE CONTRACTOR.
3. ALL DEMOLITION WORK INDICATED ON THESE DRAWINGS
INVOLVING THE REMOVAL OF EXISTING CONSTRUCTION SHALL
BE COORDINATED WITH CORRESPONDING STRUCTURAL,
PLUMBING, MECHANICAL, AND ELECTRICAL DRAWINGS.
REMOVE EXISTING CONSTRUCTION AS INDICATED.
DEMOLITION SHALL BE TO THE LEAST EXTENT POSSIBLE IN
ORDER TO COMPLETE THE WORK. DO NOT PERFORM
DEMOLITION BEYOND THE SCOPE OF CONSTRUCTION.
4. DETAILS OF EXISTING CONDITIONS: ACTUAL FIELD
CONDITIONS WHICH ARE CONCEALED BY EXISTING
CONSTRUCTION MAY VARY FROM THOSE INDICATED. ALL WORK
THAT RELATES TO, OR IS IN ANY WAY AFFECTED BY EXISTING
CONDITIONS WHICH VARY FROM THOSE INDICATED SHALL BE
MODIFIED TO ACHIEVE THE REQUIREMENTS OF THE CONTRACT
DOCUMENTS ACCORDING TO FIELD ASSESSMENTS AND
MEASUREMENTS. REPORT ANY DISCREPANCIES TO THE
ARCHITECT BEFORE PROCEEDING WITH THE ASPECTS OF
DEMOLITION OR CONSTRUCTION.
5. CONTRACTOR TO COORDINATE DEMOLITION WITH ALL
CONSTRUCTION WASTE MANAGEMENT SPECIFICATIONS.
6. PLAN DIMENSIONS ARE TO FACE OF FINISHED WALL U.N.O. ALL
DIMENSIONS INDICATED FOR EXISTING CONSTRUCTION ARE
APPROXIMATE: FIELD VERIFY ALL DIMENSIONS PRIOR TO
COMMENCEMENT OF WORK.
7. THE GENERAL CONTRACTOR IS TO PROVIDE SHORING AND
BRACING FROM DEMO THROUGHOUT FINAL COMPLETION OF
NEW CONSTRUCTION AS NECESSARY TO ACHIEVE THE INTENT
OF THE CONTRACT DOCUMENTS.
8. PATCH AND RESTORE ALL AREAS AFFECTED BY DEMOLITION
WORK TO NEW CONDITION / MATCH ADJACENT CONDITION,
IRRESPECTIVE OF NEW WORK.
INTERIOR WALL TYPES
4 7/8"
6"
DECK ABOVE
M30A3-5/8" METAL STUD PARTITION
4 1/4"
@ 16" O.C.
M30B3-5/8" METAL STUD PARTITION
6"
092900.01
05 41 00.A5
092900.01
@ 16" O.C.
092900.01
05 41 00.A5
BASE AS SCHEDULED FINISH SLAB
DECK ABOVE
BASE AS SCHEDULED FINISH SLAB
CEILING AS
SCHEDULED
CEILING AS
SCHEDULED
M 6 0 A
MATERIAL
STUD/BLOCK SIZE
MODIFIER
FIRE RATING
(M) METAL
(W) WOOD
(B) BLOCK
(C) CONCRETE
NAMING LEGEND:
1
F
(TYP.)
ASSCHED.
(TYP.)
AS S
CH
ED
ULED
FG
T
8"
7 1/2" 7 1/2"
8"
2"
(TYPIC
AL)
DO
OR H
EIG
HT
I II
T
WIDTH
DOOR
DO
OR H
EIG
HT
WIDTH
DOOR 2' - 8"
DOOR & FRAME NOTES
1. SEE DETAILS FOR HEAD, JAMB, AND THRESHOLD DETAILS FOR
DOORS.
2. ALL HOLLOW METAL FRAMES TO BE 2" WIDE FACE FRAME, U.N.O.
3. ALL WALL-TO-WALL FRAMES, FIELD VERIFY DIMENSIONS.
4. ALL GLASS IN DOORS AND SIDELITES TO BE TEMPERED, TYP.
VERIFY FRAME DEPTH AT ALL EXISTING WALL CONDITIONS.
T = TEMPERED GLASS
TYPICAL INTERIOR METAL DOOR FRAME
JAMB AND HEADER
5/8" GYPSUM BOARD
METAL STUD,
DRAWN AS 6" STUD
MATCH STUD WITH
WALL TYPE
1/2
"VARIE
S1/2
"
1 1
/2"
2"
5/8" GYPSUM BOARD
TYPICAL INTERIOR METAL DOOR FRAME
TRANSITION
INTERIOR DOOR
3/4"
CENTER FLOOR
FINISH CHANGE
UNDER DOOR
WALL BEYOND
KR
S
TEMARIE
ES
SH
RALEIGH, NC
E
9290
TERED
R
ARCHITE CT
O
C
N
IG
IS
N
RTH AROLINA
HH
A
RCHITECTURE
PA
..
,
s
RALEIGH, NC
ge
51670
tere
dR
Architectural Co rpo ratio
n
Nor t h Ca rolin
a
i
KEY PLAN
APPROVED BY
CHECKED BY
REVISIONS
SHEET NO.
TITLE
DRAWN BY
DATE
PROJECT NO.
SCALE
SEAL
REVISIONS
50116214
RE
NO
VA
TIO
NS
LA
KE
WO
OD
AR
D A
NN
EX
RA
LE
IGH
WA
TE
R
3324 L
AK
E W
OO
DA
RD
DR
IVE
RA
LE
IGH
, N
OR
TH
CA
RO
LIN
A 27604
Dewberry Engineers Inc.2610 WYCLIFF ROADSUITE 410
FAX: 919.881.9923PHONE: 919.881.9939RALEIGH, NC 27607
FULL SIZE SHEET: 30"x42"
NCBELS #F-0929
1100 Dresser Court
Raleigh, NC 27609
Office 919.828.2301
Email [email protected]
MPC
DC
05/22/2020
A001
GENERAL
ARCHITECTURAL NOTES
RM ROOM
S.C. SOLID CORE
S.S. STAINLESS STEEL
SHT SHEET
SIM SIMILAR
SPEC SPECIFICATION
SQ. FT. SQUARE FEET
SQ. IN. SQUARE INCH
STD STANDARD
STL STEEL
STRUC STRUCTURAL
T.O.S. TOP OF STEEL
TELE TELEPHONE
THR'LD THRESHOLD
TYP TYPICAL
U.N.O. UNLESS NOTED OTHERWISE
V.C.T. VINYL COMPOSITION TILE
V.W.C. VINYL WALL COVERING
VERT VERTICAL
W.C. WATER CLOSET
W.G. WIRE GLASS
W.W.F. WELDED WIRE FABRIC
W/ WITH
WD WOOD
LAV LAVATORY
M.O. MASONRY OPENING
MAT'L MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MFR MANUFACTURER
MIN MINIMUM
MISC MISCELLANEOUS
MTL METAL
N.I.C. NOT IN CONTRACT
N.T.S. NOT TO SCALE
NOM NOMINAL
O.C. ON CENTER
O.D. OUTSIDE DIAMETER
O.H. OVERHEAD
OPP OPPOSITE
P.L. PLASTIC LAMINATE
P.S.F. POUNDS PER SQ. FOOT
P.S.I. POUNDS PER SQ. INCH
PART PARTITION
PLY PLYWOOD
PROP PROPERTY
PT PAINT
PVC POLYVINYL CHLORIDE
Q.T. QUARRY TILE
R RADIUS
R.D. ROOF DRAIN
R.D.L. ROOF DRAIN LEADER
R/A RETURN AIR
REBAR REINFORCING BAR
REF REFERENCE
REINF REINFORCING
REQ'D REQUIRED
REV REVISION
EXT EXTERIOR
F.D. FLOOR DRAIN
F.E. FIRE EXTINGUISHER
F.F.E. FURNITURE, FIXTURES,EQUIPMENT
F.O.E.W. FACE OF EXISTING WALL
F.O.M. FACE OF MASONRY
F.O.S. FACE OF STUD
F.P.H.B FREEZE-PROOF HOSE BIB
FACT FACTORY FINISH
FE (SM) SURFACE MOUNTED
FE (SR) SEMI-RECESSED
FIN FINISH
FLR FLOOR
FLUOR FLUORESCENT
FRP FIBERGLASS REINFORCEDPANELS
FTG FOOTING
G.C. GENERAL CONTRACTOR
G.D.S. GUTTER DOWNSPOUT
GA GAUGE
GALV GALVANIZED
GWB GYPSUM WALL BOARD
H.D. HEAVY DUTY
H.M. HOLLOW METAL
HDW HARDWARE
HT HEIGHT
I.D. INSIDE DIAMETER
INSUL INSULATION
INT INTERIOR
JT JOINT
K KIPS
LAM LAMINATE
A.C.T. ACOUSTICAL TILE
A.F.F. ABOVE FINISHED FLOOR
A.R.A. AREA OF RESCUEASSISTANCE
ADJ ADJACENT
ALUM ALUMINUM
APPROX APPROXIMATE
BD BOARD
BLDG BUILDING
BOT BOTTOM
BSMT BASEMENT
C.J. CONTROL JOINTS
C.O. CLEAN OUT
C.T. CERAMIC TILE
CLG CEILING
CLR CLEAR
CMU CONCRETE MASONRY UNIT
COL COLUMN
CONC CONCRETE
CONST CONSTRUCTION
CONT CONTINUOUS
CPT CARPET
DEPT DEPARTMENT
DIA DIAMETER
DIM DIMENSION
DWG DRAWING
E.J. EXPANSION JOINT
E.W.C. ELECTRIC WATER COOLER
EA EACH
ELEC ELECTRICAL
ELEV ELEVATION
EQ EQUAL
EQUIP EQUIPMENT
EXIST EXISTING
ABBREVIATIONS
05 41 00.A5
072500 WEATHER BARRIERS
092216.M4 STEEL STUD FRAMING, 4"
092900.01 5/8" GYPSUM WALLBOARD (TYPE X)
095113 ACOUSTICAL PANEL CEILINGS
KEYNOTES - MASTER
DOOR SCHEDULE
DOOR
NUMBERROOM
DOOR
TYPE
FRAMEHDW COMMENTS
ELEV. WIDTH HEIGHT THICK MAT'L FINISH MAT'L FINISH
209 STOR. F 3' - 0" 7' - 0" 1 3/4" WD FACT I HM PT-1 4 ADD ALTERNATE NUMBER 2
236 OFFICE F 3' - 0" 7' - 0" 1 3/4" WD FACT I HM PT-1 1
237 OFFICE FG 3' - 0" 7' - 2" 1 3/4" GLASS/ALUM
ALUM 1
238 OFFICE FG 3' - 0" 7' - 2" 1 3/4" GLASS/ALUM
ALUM 1
243 STORAGE F 3' - 0" 7' - 0" 1 3/4" WD FACT I HM PT-1 4
244 OFFICE F 3' - 0" 7' - 0" 1 3/4" WD FACT I HM PT-1 1
245 WELLNESS F 3' - 0" 7' - 0" 1 3/4" WD FACT I HM PT-1 3
1/4" = 1'-0"A001
01 DOOR ELEVATIONS
1/4" = 1'-0"A001
02 DOOR FRAME ELEVATIONS
3" = 1'-0"A001
03 ID-1 INTERIOR DOOR CONDITIONS - DETAILS
NO. DATE BY REVISION
1 06/18/20 Rev 1 - Addendum #2
REF.
Mic
row
ave
1
1
2
2
3
3
1.1 2.5 4
4
AA
A.1A.1
BB
B.5B.5
CC
DD
EE
FF
GG
HH
Z
C.1C.1
OPEN TO BELOW
OFFICE
221
OFFICE
220
JAN.
208
STOR.
209
WELLNESS
209A
WOMEN
207
MEN
206
STOR.
204
MECH.
203
ELEV.
E1
CONFERENCE
205
CONFERENCE
234
BREAK
233
CONFERENCE
235
OFFICE
236
OFFICE
237
OFFICE
238
TRAINING ROOM
241
OFFICE
244
STORAGE
243
OPEN OFFICE
242
CIRCULATION
232
STAIR
A
ALIG
N
9' - 7"
11"
11"
3' - 0"
WELLNESS
245
244
243
236
245
209
6"
8' -
8 1
/4"
03
01
02
01
01
A121
05 3' -
0"
A12103
06
06
06
05
ADD ALT NO. 1
ADD ALT NO. 2
A12104
A12104
237
238
06
M60A
06
1
FURNITURE, ETC. BY OWNER;
NOT IN CONTRACT
1-HR RATED FIRE BARRIER
EXISTING CONSTRUCTION TO REMAIN
NEW WALL CONSTRUCTION
RENOVATION PLAN LEGEND
2-HR RATED FIRE BARRIER
PLAN KEYNOTES01
02
xx
03
DENOTES AREA EXCLUDED FROM PROJECT OR
PHASE. FOR EXCEPTIONS, SEE PLUMBING,
MECHANICAL, AND ELECTRICAL DRAWINGS.
PROJECT AREA
ALIGN CENTER OF WALL WITH CENTER OF MULLION. GC TO
PROVIDE ALUM. VERTICAL TRIM ENCLOSURE; PAINTED BLACK.
ALIGN EDGE OF WALL WITH EDGE OF CURTAIN WALL WINDOW
UNDERCOUNTER ICEMAKER TO BE INSTALLED IN PREVIOUS
BASE CABINET BETWEEN REFRIGERATOR AND SINK. (ADD
ALT NO. 1)
04 NEW ACOUSTIC CEILING PANELS ATTACHED TO BOTTOM OF
DECK. CONTRACTOR TO COORDINATE WITH EXISTING
DUCTWORK/HANGERS.
05 NEW TV LOCATION. TV AND MOUNTING DEVICE BY OWNER.
CONTRACTOR TO PROVIDE WALL BLOCKING AND
ELECTRICAL/DATA AS NOTED ON ELECTRICAL SHEETS.
06 PATCH AND REPAIR WALL TO MATCH EXISTING FINISH
1 2 3
1.1
2.5
4
A
A.1
B
B.5
C
D
E
F
G
H
Z
C.1
244
243
242
238
237 245
236239
209A
209
205 206 207
233234
235
220
208
A 9' - 6"
A 10' - 0"
A 10' - 0"
A 10' - 0"
A 10' - 0"
A 9' - 6"
A 8' - 0"
A 10' - 0"
A 10' - 0"
9' - 4"A
A 9' - 4"
A 8' - 0"
A 9' - 6"
04
04
04
04
ADD ALT NO. 2
OS
OS
OS
OS
OS
EQ
EQ3' -
0"
3' - 0"
3' - 6" 4' - 0"
OS
1
NEW 2x2 ACOUSTICAL
CEILING TILE AND GRID
RCP LEGEND
RELOCATED RECESSED LIGHT
FIXTURE; SEE ELECTRICAL DRAWINGS
1. GC IS REQUIRED TO PROVIDE COORDINATION DRAWINGS FOR ALL
MEP SYSTEMS OVERHEAD AND IN CEILINGS.
2. SEE MEP SHEETS FOR ADDITIONAL CEILING NOTES.
3. ALL NEW CEILING TILE ARE TO BE TYPE ACP-1 UNLESS
OTHERWISE NOTED.
RCP GENERAL NOTES
SUPPLY DIFFUSER; SEE
MECHANICAL DRAWINGS
RETURN DIFFUSER; SEE
MECHANICAL DRAWINGS
CEILING-MOUNTED OCCUPANCY
SENSOR; SEE ELECTRICAL
DRAWINGS
EXISTING EXIT SIGNS TO
REMAIN; SEE ELECTRICAL
DRAWINGS
OS
EXISTING ACOUSTICAL
CEILING TILE & GRID TO
REMAIN
EXISTING CONSTRUCTION TO REMAIN
NEW WALL CONSTRUCTION
EXISTING 2-HR RATED FIRE BARRIER
NEW 2-HR RATED SHAFT WALL CONSTRUCTION
SPRINKLER HEAD; SEE FIRE
PROTECTION DRAWINGS
EXISTING RECESSED LIGHT FIXTURE;
SEE ELECTRICAL DRAWINGS
2nd FLOOR14' - 0"
3' - 6"2' - 6"1' - 6"1' - 6"
9' - 2" VERIFY
2' -
10"
PL-1
SS-1
RB-1
04
ID001
03
ID001
06
ID001
2nd FLOOR14' - 0"
A.1 B
ICEMAKER BY GCSEE EQUIPMENT SCHEDULE ON ID001
1' - 3"
2' -
10"
1' - 0"
FILLER PANEL AS NECESSARY
NEW CABINET AND ANY FILLER PANELS
TO MATCH EXISTING PLAM (PL-1)
COORDINATE SIZE OF DRAWER STACK
WITH ICE MAKER REQUIRED CLEARANCES
03
ID001
T TT
GLZ-1 APPLIED TO
GLASS OFFICE
FRONTS AND DOOR
3' - 0"
9' - 6 1/2"
7' -
2"
EQ EQ
1-1/2" X 1-1/2"
FRAMING ANGLE
092216.M4
092900.01
095113
SEE R
CP
VARIE
S
1
KR
S
TEMARIE
ES
SH
RALEIGH, NC
E
9290
TERED
R
ARCHITE CT
O
C
N
IG
IS
N
RTH AROLINA
HH
A
RCHITECTURE
PA
..
,
s
RALEIGH, NC
ge
51670
tere
dR
Architectural Co rpo ratio
n
Nor t h Ca rolin
a
i
KEY PLAN
APPROVED BY
CHECKED BY
REVISIONS
SHEET NO.
TITLE
DRAWN BY
DATE
PROJECT NO.
SCALE
SEAL
REVISIONS
50116214
RE
NO
VA
TIO
NS
LA
KE
WO
OD
AR
D A
NN
EX
RA
LE
IGH
WA
TE
R
3324 L
AK
E W
OO
DA
RD
DR
IVE
RA
LE
IGH
, N
OR
TH
CA
RO
LIN
A 27604
Dewberry Engineers Inc.2610 WYCLIFF ROADSUITE 410
FAX: 919.881.9923PHONE: 919.881.9939RALEIGH, NC 27607
FULL SIZE SHEET: 30"x42"
8 16 241242 6
1/8" = 1'-0"
0
NCBELS #F-0929
1100 Dresser Court
Raleigh, NC 27609
Office 919.828.2301
Email [email protected]
MPC
DC
05/22/2020
A121
2nd FLOOR RENOVATION
PLANS
N
1/8" = 1'-0"A121
01 2nd FLOOR PLAN1/8" = 1'-0"A121
02 2nd FLOOR - REFLECTED CEILING PLAN
3/8" = 1'-0"A121
05 ELEVATION- COFFEE BAR3/8" = 1'-0"A121
03 BREAKROOM 214 - CASEWORK ALTERATION (ADD ALTERNATE NO. 1)3/8" = 1'-0"A121
04 TYPICAL ELEVATION OF ALUMINUM GLASS PARTITION
NO. DATE BY REVISION
1 06/18/20 Rev 1 - Addendum #2
3" = 1'-0"A121
6 TYPICAL BULKHEAD CONDITIONS
Mic
row
ave
1
1
2
2
3
3
1.1 2.5 4
4
5
5
AA
A.1A.1
BB
B.5B.5
CC
DD
EE
FF
GG
HH
Z
C.1
C.1
OPEN TO BELOW
01
01
02
020202
02
02 02
02
02
02
02
02
02
02
0202
02
03
03
03
03
03
03
03
03
03
03
03
03
03
03
03
03
03
041' -
3"
OPEN OFFICE
242
TRAINING ROOM
241
CORRIDOR
239
MECH.
203
CONFERENCE
235
STOR.
204
CONFERENCE
205
MEN
206
WOMEN
207
JAN.
208
STOR.
209
OFFICE
220
OFFICE
221
BREAK
233
CONFERENCE
234
CORRIDOR
239
STAIR
A
01
07
08
ADD ALTERNATE
NO. 1
ADD ALT NO. 2
09
09
09
09
03
1
DEMO PLAN NOTES
01
02
DEMOLITION LEGEND
xx
03
04
05
DENOTES AREA EXCLUDED FROM PROJECT OR
PHASE. FOR EXCEPTIONS, SEE PLUMBING,
MECHANICAL, AND ELECTRICAL DRAWINGS.
EXISTING CONSTRUCTION TO REMAIN.
LIMITS OF EXISTING WALLS, DOORS, FLOORS TO BE
PROTECTED DURING CEILING/MEP WORK
1-HR RATED FIRE BARRIER
2-HR RATED FIRE BARRIER
EXISTING CONSTRUCTION, ETC. TO BE DEMOLISHED.
REFER TO KEY NOTES FOR SPECIFIC INFORMATION.
DEMO EXISTING FLOOR FINISHES - GC TO INSTALL FULL-
HEIGHT PLASTIC PROTECTION AS SPECIFIED.
DEMO EXISTING CASEWORK.
DEMO EXISTING WALL/DOOR CONSTRUCTION.
DEMOLISH CEILING TILE AND GRID
DEMO PORTION OF EXISTING WALL TO RECEIVE NEW DOOR.
(SEE RENOVATION PLANS.) (ADD ALTERNATE NO. 2)
06 REMOVE AND RELOCATE EXISTING LIGHT FIXTURE. SEE
ELECTRICAL SHEETS.
DENOTES AREA OF FLOOR FINISH DEMOLITION
07 EXISTING WORKSTATIONS TO BE REMOVED AND RETURNED
TO OWNER IN GOOD CONDITION.
08 EXISTING CABINETS TO BE REMOVED CAREFULLY AND AS
NECESSARY, ACCORDING TO THE ELEVATIONS WITHOUT DAMAGING
OTHER PARTS OF CABINET. (ADD ALT. NO. 1)
LIGHT FIXTURE TO BE RELOCATED; SEE
ELECTRICAL SHEETS.
EXIT SIGN; SEE ELECTRICAL SHEETS.
09 DEMOLISH EXISTING GYP BOARD WHERE NEW ELECTRICAL, DATA,
AND PLUMBING IS LOCATED
10 REMOVE AND TURN EXISTING LIGHT FIXTURE OVER TO OWNER IN
GOOD CONDITION
11 EXISTING BULKHEAD TO REMAIN - REPAIR AND PATCH GYPSUM
BOARD IF NECESSARY
1 2 3
1.1
2.5
4 5
A
A.1
B
B.5
C
D
E
F
G
H
Z
C.1
05
0606
10
05
05
05
05
OPEN OFFICE
242
CORRIDOR
239
STOR.
204
MEN
206
WOMEN
207
JAN.
208
STOR.
209
OFFICE
220
BREAK
233
CONFERENCE
234
CONFERENCE
235
CONFERENCE
205
CORRIDOR
239
CIRCULATION
232
OFFICE
221
STAIR
A
06
05
05
05
ADD ALTERNATE NO. 2
06
06
10
05
11
11
11
1
KR
S
TEMARIE
ES
SH
RALEIGH, NC
E
9290
TERED
R
ARCHITE CT
O
C
N
IG
IS
N
RTH AROLINA
HH
A
RCHITECTURE
PA
..
,
s
RALEIGH, NC
ge
51670
tere
dR
Architectural Co rpo ratio
n
Nor t h Ca rolin
a
i
KEY PLAN
APPROVED BY
CHECKED BY
REVISIONS
SHEET NO.
TITLE
DRAWN BY
DATE
PROJECT NO.
SCALE
SEAL
REVISIONS
50116214
RE
NO
VA
TIO
NS
LA
KE
WO
OD
AR
D A
NN
EX
RA
LE
IGH
WA
TE
R
3324 L
AK
E W
OO
DA
RD
DR
IVE
RA
LE
IGH
, N
OR
TH
CA
RO
LIN
A 27604
Dewberry Engineers Inc.2610 WYCLIFF ROADSUITE 410
FAX: 919.881.9923PHONE: 919.881.9939RALEIGH, NC 27607
FULL SIZE SHEET: 30"x42"
8 16 241242 6
1/8" = 1'-0"
0
NCBELS #F-0929
1100 Dresser Court
Raleigh, NC 27609
Office 919.828.2301
Email [email protected]
MPC
DC
05/22/2020
D121
2nd FLOOR DEMOLITION
PLANS
N
1/8" = 1'-0"D121
01 2nd FLOOR - DEMOLITION PLAN
0'
GRAPHIC SCALE
8' - 0" 16' - 0" 32' - 0"4' - 0"N
1/8" = 1'-0"D121
02 2nd FLOOR - DEMO REFLECTED CEILING PLAN
1
NO. DATE BY REVISION
1 06/18/20 Rev 1 - Addendum #2
1
REF.
FINISH LEGEND
MANUFACTURER:COLLECTION:PATTERN:COLOR:TYPE/SIZE:INSTALL METHOD:
BASIS OF DESIGN:
FLOORINGCPT-1CARPET
EQUAL 1: EQUAL 2:
[LOCATION]
MANUFACTURER:COLOR:TYPE/SIZE:
BASE
RB-1RUBBER BASE
JOHNSONITE37 PEBBLE4"
MANUFACTURER:COLOR:TYPE/SIZE:
TR-1TRANSITION
MANUFACTURER:COLOR:SHEEN:
PT-1PAINT
SHERWIN WILLIAMSSW7042 SHOJI WHITEEGGSHELL
MANUFACTURER:COLOR:SHEEN:
PT-2PAINT
SHERWIN WILLIAMSSW0073 CHARTREUSEEGGSHELL
MANUFACTURER:COLOR:SHEEN:
PT-3PAINT
SHERWIN WILLIAMSSW6171 CHATROOMEGGSHELL
MANUFACTURER:COLOR:SHEEN:
PL-1PLASTIC LAMINATE
MILLWORK
MANUFACTURER:COLOR:SHEEN:
SS-1SOLID SURFACECOUNTERTOP
MANUFACTURER:STYLE:COLOR:SIZE:GRID:
ACP-1ACOUSTICAL CEILING PANEL
ARMSTRONGOPTIMA OPEN PLAN - 3152WHITE (WH)24" X 24"EXISTING TO REMAIN
CEILINGS
ROPPETBD4"
MANNINGTONTBD4"
MANUFACTURER:STYLE:COLOR:SIZE:GRID:
ACP-2ACOUSTICAL CEILING PANEL
ARMSTRONGDUNE SQUARE LAY-IN - 1772WHITE (WH)24" X 24"EXISTING TO REMAIN
PERFORMANCESPEC
MOHAWK GROUPEXPEDITIONLITHOSPHERE TILE - GT334TBD-BRICK ASHLAR
NEVAMAR WK0017T VENERABLE OLD OAK-
CORIANSILVER BIRCH-
TARKETT-----
PATCRAFT-----
WALLS
SCHLUTERSELECTED BY ARCHITECTSEE 3/ID000
TARKETTSELECTED BY ARCHITECTSEE 3/ID000
PEMKOSELECTED BY ARCHITECT-
MANUFACTURER:COLOR:SHEEN:
PT-4PAINT
SHERWIN WILLIAMSSW7006 EXTRA WHITEFLAT
OVERALL
ACCENT
ACCENT
COFFEE BAR
COFFEE BAR
BASIS OF DESIGN:
CEILINGS + SOFFITS
ENCLOSED OFFICES
OPEN OFFICES
WILSONARTSELECTED BY ARCHITECT-
SWANSTONESELECTED BY ARCHITECT-
USG INTERIORS CERTAINTEED CORP.
USG INTERIORS CERTAINTEED CORP.
MANUFACTURER:STYLE:COLOR:SIZE:GRID:
ACP-3ACOUSTICAL CEILING PANEL
ARMSTRONGCAPZOPTIMA WHITE (WH)36" X 36"NONE
OPEN OFFICES USG INTERIORS CERTAINTEED CORP.
MANUFACTURER:COLOR:TYPE/SIZE:
GLASS FINISH
GLZ-1GLAZING
3MDUSTED CRYSTAL
SOLYXSELECTED BY ARCHITECT
GC TO RECOMMENDSELECTED BY ARCHITECT
SELECT OFFICE DOORS & WALLS
PANOLAMSELECTED BY ARCHITECT-
WILSONARTSELECTED BY ARCHITECT-
NOT USED
1 2 3
1.1
2.5
4
A
A.1
B
B.5
C
D
E
F
G
H
Z
C.1
OFFICE
244
STORAGE
243
OPEN OFFICE
242
TRAINING ROOM
241
OFFICE
238
OFFICE
237
OFFICE
236
CORRIDOR
239
WELLNESS
245
WELLNESS
209A
STOR.
209
CONFERENCE
235
ADD ALTERNATE
NUMBER 2
02
ID001
COORDINATE TRANSITION
AT EXISTING GROUT
LINE. DO NOT CUT
CERAMIC TILE.
PT-3
PT-3
PT-3
PT-3
PT-3
PT-3
1
ADD ALTERNATE
NUMBER 1
FINISH PLAN KEY
NEW CARPET TILE, CPT-1
ICE MAKER - U-LINE - MODEL UANP115-SS01A
EQUIPMENT
DENOTES AREA EXCLUDED FROM PROJECT OR
PHASE. FOR EXCEPTIONS, SEE PLUMBING,
MECHANICAL, AND ELECTRICAL DRAWINGS.
1
FINISH PLAN GENERAL NOTES1. ALL MATERIALS TO BE FIELD VERIFIED PRIOR TO ORDERING. DO
NOT SCALE FROM DRAWINGS.
2. ALL MATERIALS SHALL BE INSTALLED PER MANUFACTURER'S
RECOMMENDATIONS WITH APPROVED ADHESIVES.
3. IF THERE ARE QUESTIONS ABOUT THE DESIGN INTENT OF ANY
PATTERN OR MATERIAL TO BE INSTALLED, THE GC SHALL SUBMIT
A REQUEST FOR INFORMATION TO THE DESIGNER FOR
CLARIFICATION PRIOR TO ORDERING THE MATERIALS.
4. THE GC SHALL PROVIDE ALL FINISHING PIECES AND
TRANSITIONS WHERE DIFFERENT FLOORING THICKNESSES
MEET, U.N.O. THE GC SHALL SUBMIT A SAMPLE OF THE
COLOR/FINISH TO THE DESIGNER FOR APPROVAL.
5. ALL WALLS TO BE FIELD PAINT, PT-1, U.N.O. ALL GYP. BD.
PARTITIONS TO RECEIVE A LEVEL 4 FINISH.
6. ALL INTERIOR DOOR FRAMES TO RECEIVE PAINT IN GLOSS
FINISH, PT-1, U.N.O.
7. GC TO PROVIDE SHOP DRAWINGS FOR ALL FLOOR PATTERN
TYPES FOR APPROVAL, PRIOR TO ORDERING MATERIALS.
8. ALL INTERIOR GYP. BD. PARTITIONS TO RECEIVE RUBBER BASE,
RB-1, U.N.O.
9. CASEWORK NOTES:
A. CASEWORK SHALL BE CONSTRUCTED FROM MDF OR PARTICLE
BOARD. SHOP DRAWINGS OF CASEWORK TO BE SUBMITTED
TO DESIGNER FOR APPROVAL.
B. ALL CASEWORK TO COMPLY WITH AWI STANDARDS.
C. PROVIDE CONCEALED HINGES FOR ALL DOORS.
D. ON COMPUTER DESKING, PROVIDE GROMMETS WHERE
NEEDED. GC TO COORDINATE GROMMET LOCATIONS WITH
OWNER.
E. ALL DOOR AND DRAWER PULLS TO BE 4” U-SHAPED PULL
WITH BRUSHED ALUMINUM FINISH.
F. PROVIDE SILENCERS FOR ALL CABINET DRAWERS.
G. WOOD GRAIN LAMINATE, PL-1 SHALL RUN IN VERTICAL
DIRECTION.
H. ALL EXPOSED EDGES TO RECEIVE 3MM PVC EDGEBANDING TO
MATCH COORDINATING LAMINATE SURFACE.
10. GENERAL CONTRACTOR TO SUPPLY 10% ADDITIONAL STOCK OF
ACOUSTIC CEILING TILE, CARPET TILE AND VINYL TILE TO
OWNER.
SOLID SURFACE COUNTERTOP &
BACKSPLASH ON 1" PARTICLE
BOARD BACKER;1 1/2" FRONT
PROFILE
INTEGRAL SOLID SURFACE
BACKSPLASH, CAULK AT WALL
INTERSECTION
SOLID SURFACEWITH BACKSPLASH:
1" MAX.
2' - 0"
2' - 1 1/2"
2' -
10"
4"
09
04
05
06
01
08
10
12
11
13
ALL EXPOSED INSIDE SURFACES TO BE MELAMINE
LAMINATE
P. LAM. DOOR WITH 3MM MATCHING EDGEBANDING
1" FIXED SHELF, MELAMINE LAMINATE ALL EXPOSED
SURFACES, U.N.O., 3MM MATCHING EDGEBANDING, TYP.
MELAMINE LAMINATE; 3/4" ADJUSTABLE SHELF
WITH 3MM PVC EDGEBANDING
SHELF CLIPS
32MM LINE-BORING CENTERS
1/2" HARDBOARD BACK, TYP.
1/4" HARDBOARD BACK
PULL HANDLE (4" SS WIRE PULL MATTE)
DRAWER WITH 3MM MATCHING EDGEBANDING
COUNTERTOP SYSTEM, SEE COUNTERTOP DETAILS FOR
MATERIAL VARIATIONS; SEE ELEVATION FOR MATERIAL
3/4" PLYWOOD SUBCOUNTER
BASE (RUBBER) AS SCHEDULED
THICKNESS OF BACKSPLASH TO BE 1/2" (IF QUARTZ:
2CM)
TRASH RECEPTACLES TO BE PROVIDED BY GC
CASEWORK KEYNOTES01
02
xx
03
04
05
06
07
08
09
10
11
12
13
14
15
CARPET TO TILE TRANSITION
EXISTING CERAMIC TILE
CPT - SEE FINISH
SCHEDULE
1/4" HARDBOARD BACK
DRAWER WITH 3MM PVC
EDGEBANDING
3/4" PLYWOOD SUBCOUNTER
SOLID SURFACE COUNTERTOP AND
BACKSPLASH ON 1" PARTICLE BOARD
BACKER; 1 1/2" FRONT PROFILE
BASE
MELAMINE LAMINATE
4"
2' - 0"
1" MAX
2' - 1 1/2"
3"
4"
4"
2' -
10"
3/4"
15
01
02
09
12
11
14
08
13
KR
S
TEMARIE
ES
SH
RALEIGH, NC
E
9290
TERED
R
ARCHITE CT
O
C
N
IG
IS
N
RTH AROLINA
HH
A
RCHITECTURE
PA
..
,
s
RALEIGH, NC
ge
51670
tere
dR
Architectural Co rpo ratio
n
Nor t h Ca rolin
a
i
KEY PLAN
APPROVED BY
CHECKED BY
REVISIONS
SHEET NO.
TITLE
DRAWN BY
DATE
PROJECT NO.
SCALE
SEAL
REVISIONS
50116214
RE
NO
VA
TIO
NS
LA
KE
WO
OD
AR
D A
NN
EX
RA
LE
IGH
WA
TE
R
3324 L
AK
E W
OO
DA
RD
DR
IVE
RA
LE
IGH
, N
OR
TH
CA
RO
LIN
A 27604
Dewberry Engineers Inc.2610 WYCLIFF ROADSUITE 410
FAX: 919.881.9923PHONE: 919.881.9939RALEIGH, NC 27607
FULL SIZE SHEET: 30"x42"
8 16 241242 6
1/8" = 1'-0"
0
NCBELS #F-0929
1100 Dresser Court
Raleigh, NC 27609
Office 919.828.2301
Email [email protected]
MPC
DC
05/22/2020
ID001
FINISH PLAN, LEGEND,
SCHEDULE & DETAILS
FINISH SCHEDULE
ROOM
NO.ROOM NAME BASE FLOOR
NORTH
WALL
EAST
WALL
SOUTH
WALL
WEST
WALLCEILING
2nd FLOOR
242 OPEN OFFICE RB-1 CPT-1 PT-1 PT-1 PT-1 PT-1 ACP-1
241 TRAINING ROOM NA NA NA NA NA NA NA
235 CONFERENCE RB-1 CPT-1 PT-1 PT-1 PT-1 PT-1 ACP-2
209 STOR. RB-1 EXST PT-1 PT-1 PT-1 PT-1 EXST
239 CORRIDOR RB-1 CPT-1 PT-1 PT-1 PT-1 PT-1 ACP-1
244 OFFICE RB-1 CPT-1 PT-1 PT-3 PT-1 PT-1 ACP-2
236 OFFICE RB-1 CPT-1 PT-1 PT-3 PT-1 PT-1 ACP-2
243 STORAGE RB-1 CPT-1 PT-1 PT-1 PT-1 PT-1 ACP-2
237 OFFICE RB-1 CPT-1 PT-1 PT-3 PT-1 PT-1 ACP-2
238 OFFICE RB-1 CPT-1 PT-1 PT-3 PT-1 PT-1 ACP-2
209A WELLNESS RB-1 CPT-1 PT-1 PT-1 PT-3 PT-1 ACT-2
245 WELLNESS RB-1 CPT-1 PT-1 PT-1 PT-3 PT-1 ACP-2
N
1/8" = 1'-0"ID001
01 2nd FLOOR - FINISH PLAN
1 1/2" = 1'-0"ID001
05 TYP. COUNTER TOP DETAILS
1 1/2" = 1'-0"ID001
04 TYP. LOWER CABINET w/ SOLID SURFACE COUNTERTOP3" = 1'-0"ID001
02 EXISTING TILE TO CARPET TRANSITION DETAIL
1 1/2" = 1'-0"ID001
03 CW-4 TYP. LOWER CABINET w/ SOLID SURFACE COUNTERTOP
1 1/2" = 1'-0"ID001
06 TYP. BASE CABINET W/ PULL OUT TRASH/RECYCLE
1
1
NO. DATE BY REVISION
1 06/18/20 Rev 1 - Addendum #2
1
DocuSign Envelope ID: AD111053-8CF1-4C53-8427-053436C98F5E
6/17/2020
DocuSign Envelope ID: AD111053-8CF1-4C53-8427-053436C98F5E
6/17/2020
DocuSign Envelope ID: AD111053-8CF1-4C53-8427-053436C98F5E
6/17/2020