alkek expansion

24
Alkek Expansion Pre-Submittal Conference October 5, 2006

Upload: paloma

Post on 11-Feb-2016

38 views

Category:

Documents


0 download

DESCRIPTION

Alkek Expansion. Pre-Submittal Conference October 5, 2006. Team Members. Jim Waters, Project Director, Shell and Core Janet Sisolak, Project Director, Interior Build-out Pam Redden, Project Director, Clinical Operations Dan Butterwick, Chief Architect Greg Hudgins, Project Manager. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Alkek Expansion

Alkek Expansion

Pre-Submittal ConferenceOctober 5, 2006

Page 2: Alkek Expansion

Team Members

• Jim Waters, Project Director, Shell and Core• Janet Sisolak, Project Director, Interior Build-out• Pam Redden, Project Director, Clinical Operations• Dan Butterwick, Chief Architect• Greg Hudgins, Project Manager

Page 3: Alkek Expansion

Project Organization

Facilities Steering Committee

Executive Steering Committee

Core Team

Project Directors Jim Waters, Core and Shell

Janet Sisolak, Interior Buildout

Page 4: Alkek Expansion

Feasibility Study

Conducted from December 2005 through July 2006

Page 5: Alkek Expansion

Impacts Evaluated

• Construction Impacts

• Design Impacts

• Operational Impacts

• Downstream Impacts

Page 6: Alkek Expansion

Construction Impacts

• Site Logistics/Staging• Construction Access• Construction Supply - Bates and Bertner• Crane Placement & Removal• Vibration/Noise • Waterproofing• Infection Control - dust• Safety-dropped loads

Page 7: Alkek Expansion

Construction Impacts• Site Logistics/Staging

o Create Contractor’s Entrance to Rotunda

o Removal of Canopieso Closing West

Entrance to Rotunda

Page 8: Alkek Expansion

Construction Access

• Allow for emergency exits

• Keep reception desk open

• Keep construction traffic out of the main lobby

• Maintain access to Physical Therapy

Page 9: Alkek Expansion

Construction Impacts• Construction Supply - Bates and Bertner

Intermittent Lane

Closures along

Bertner and Bates will

be required

Page 10: Alkek Expansion

Construction Impacts• Crane Placement & Removal

In existing empty staff elevator shafts

Page 11: Alkek Expansion

Construction Impacts

• Site Logistics/Staging• Construction Access• Construction Supply - Bates and Bertner• Crane Placement & Removal• Vibration/Noise • Waterproofing• Infection Control - dust• Safety-dropped loads

Page 12: Alkek Expansion

Design Impacts

• Structure – continuation of concrete frame • Use of lighter weight wall panels – fiber reinforced

concrete• HVAC Issues• Electrical Issues• Plumbing Issues• Wind Tunnel Study

Page 13: Alkek Expansion

Impacts to Number of Beds per Floor

Changes to Codes and Standards

• Increased Room Size

• Increased Toilet Size – all fully accessible

Operational Improvements

• Additional space to accommodate Murphy Beds and to allow appropriate circulation for nursing

• Flexible Acuity Room Design

Page 14: Alkek Expansion

Current 52-Bed Floorplate

Page 15: Alkek Expansion

Proposed Floorplate – 40 – 44 beds

Page 16: Alkek Expansion

Design Impacts

• Maximize footprint by eliminating deep recesses at windows, put square footage back into patient room

• Overall appearance of the tower can be preserved

Page 17: Alkek Expansion
Page 18: Alkek Expansion

Design Impacts• Shift stairs and major mechanical chases

closer to elevator core, creating more support space directly adjacent to nursing unit

• Transition can happen at Level 13, the new mechanical floor

Page 19: Alkek Expansion

Elevators

• Infill two existing shafts for staff

• Create 6 new passenger cabs

Page 20: Alkek Expansion

Design Impacts

• Optimal sequence for future build-out

o Growth model may drive recommendation for build out (Inpatient vs. Outpatient vs. support)

o Sequence should minimize disruption to occupants as shell floors are built out.

Page 21: Alkek Expansion

Proposed StackingFloor Proposed Alkek Beds Proposed Lutheran Beds

21 Shell20 Shell19 Shell18 1/2 Shell - 1/2 Med/Surg 2017 Med/Surg 4016 Med/Surg 4015 Med/Surg 4014 Med/Surg 4013 Mechanical GMP Lab12 Med/Surg

Consider full remodel for 20 rooms or 1/2 for 46 40 Med Surg 3211 Med Surg 52 Med Surg 3210 Med Surg 52 Med Surg 329 Pediatrics

Children's Hospital incl ICU 52 Med Surg 328 Mechanical Med Surg 327 ICU 54 Med Surg 326 Interstitial Med Surg 325 ORs/Frozen Section,

Stage 1 PACU Stage 2 PACU4 Interstitial Med Surg 323 DI, Cytopathology, FNA, Procedure

Suite2 Interstitial/Park Emergency Center1 Pathology, PT/OT

B Sterile ProcessingRadiation Oncology

430 256Total Beds Lutheran + Alkek 686

Projected Need 673

2012

Vacant during construction

Shell

Page 22: Alkek Expansion

Operational Impacts

• Closing of Rotunda drive and west entrance • Visitors - Garage 2• Valet Operations• Access• Flooding Exposure• Discharges• Patient Advocacy/Visitor Center/Porcelain Bird

Collection• 12th Floor/protected environment rooms • PT/OT – Closure of gardens used for gait

training and pet therapy

Page 23: Alkek Expansion

• Alkek Drive and West Entrance –How can the duration be mitigated?

• G12 must be vacated–Potential staging area for contractor, but space must be preserved

Operational ImpactsKey Issues

Page 24: Alkek Expansion

Questions?