acometida media tension

Post on 12-Dec-2015

2 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

DESCRIPTION

construccion e instalacion de camaras de media tencion

TRANSCRIPT

CAMARA 1

TIEMPO TAREA % AVANCE1 MOLDAJE EXTERIOR 6%1 ENFIERRADURA 6%2 HORMIGONADO LOZA 13%1 MOLDAJE INTERIOR 6%3 HORMIGONADO TOTAL 19%3 CONFECCION LOZA SUPERIOR 19%5 CONFECCION DE ACCESO 31%

TOTAL 16 TOTAL DE AVANCES 100%TOTAL DE AVANCE REAL 13%

TOTAL FALTANTE 88%DIAS FALTANTES 14

CAMARA 1 13% SUMA DIAS FALTANTESCAMARA 2 6%CAMARA 3 0%

TOTAL 6%

CAMARA 1

PORCENTAJE DE AVANCE TOTAL POR TAREA

100% 6%100% 6%

0% 0%0% 0%0% 0%0% 0%0% 0%

TOTAL

45

CAMARA 2

TIEMPO TAREA % AVANCE1 MOLDAJE EXTERIOR 6% 0%1 ENFIERRADURA 6% 100%2 HORMIGONADO LOZA 13% 0%1 MOLDAJE INTERIOR 6% 0%3 HORMIGONADO TOTAL 19% 0%3 CONFECCION LOZA SUPERIOR 19% 0%5 CONFECCION DE ACCESO 31% 0%

16 TOTAL DE AVANCES 100%TOTAL DE AVANCE REAL 6%

TOTAL FALTANTE 94%DIAS FALTANTES 15

CAMARA 2

PORCENTAJE DE AVANCE TOTAL POR TAREA TIEMPO0% 0% 1

100% 6% 10% 0% 20% 0% 10% 0% 30% 0% 30% 0% 5

TOTAL 16

CAMARA 3

TAREA % AVANCEMOLDAJE EXTERIOR 6% 0%

ENFIERRADURA 6% 0%HORMIGONADO LOZA 13% 0%

MOLDAJE INTERIOR 6% 0%HORMIGONADO TOTAL 19% 0%

CONFECCION LOZA SUPERIOR 19% 0%CONFECCION DE ACCESO 31% 0%

TOTAL DE AVANCES 100%TOTAL DE AVANCE REAL 0%

TOTAL FALTANTE 100%DIAS FALTANTES 16

PORCENTAJE DE AVANCE TOTAL POR TAREA

0%0%0%0%0%0%0%