case study - fujitsu_malaga_perth - (tia 942) - 20110722

Post on 12-Jan-2017

297 Views

Category:

Documents

2 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Hitec Diesel Rotary UPS systems

Case Study: The Malaga Data Centre, Perth, WA

A comparison between the original static UPS and standby diesel generator design and the high-voltage Hitec Diesel

Rotary UPS solution installed

Ride through systems DRUPS systems

www.hitec-ups.com

• The Hitec Organisation in APAC

• The Hitec Diesel Rotary UPS System

• Malaga Case Study - Data Centre Design Criteria

- The Original SUPS Scheme

- The HV DRUPS approach

- Reducing CAPEX

- Meeting TIA 942 / Tier III

- Sustainability and efficiency

- The completed facility

- Awards

The Hitec Organisation

in APAC

HITEC + HOTEC, Taiwan

HITEC + Power Partners, Singapore

HITEC Malaysia

Hisec, Japan

Hitec+ Metrowest, Australia + NZ

Hi-Rel, India HPS, South Korea

Matech, Thailand

Hitec in Asia Pacific Wide Regional Presence

PBG Indonesia

DP Consulting, Vietnam

Taiwan: 197

China: 28

Singapore: 46

Malaysia: 9

Australia: 20

India: 8

South Korea: 47

Thailand: 16

Asia Installed Base: 371 units

Hitec in Asia Pacific Large installed based

• Sales and Marketing

• Technical and Design Assistance

• Project Engineering

• Project Management

• After Sales Support

• Service and Maintenance

• Strategic and Consumable Spares

Hitec in Asia Pacific Hitec’s Regional Support

The Hitec

Diesel Rotary UPS system

The Hitec DRUPS system

• A complete solution that utilises

stored mechanical energy

to provide continuous power.

• Combines the functionality of

both a UPS and a Standby Diesel Engine in a single module.

• Provides high quality power to support all types of load,

including critical cooling loads and those with a leading

power factor i.e. Blade Servers.

• Suitable for both HV and LV and 50/60 Hz applications.

• A highly reliable tried and tested design.

Standby Diesel

UPS Inverters

Air Conditioning

Switchboards PFC

Standby Batteries

Spark-proof Lighting Busduct & Cabling

Fire Protection & Security

Static UPS

+

The Hitec DRUPS system Ways in which UPS can be achieved

Hitec DRUPS

The Hitec DRUPS system Ways in which UPS can be achieved

Hitec DRUPS

Standby Diesel

Static UPS

UPS Inverters

Air Conditioning

Switchboards PFC

Standby Batteries

Spark-proof Lighting Busduct & Cabling

Fire Protection & Security

The Hitec DRUPS system Ways in which UPS can be achieved

Case Study:

The Malaga Data Centre,

WA

• Co-location Facility

• Minimal build cost

• UTI Tier III / TIA 942 Certified

• 3000m² of raised floor

• Load to increase over time (3-4 Year Build-out)

• Initial floor loading of 750 Watts/m²

• Ultimate floor loading 1500 Watts/m²

• Pay as you go approach to infrastructure

• Was fully designed around SUPS plus standby generators

Data Centre Criteria

The Original Scheme

LV Switchgear

Standby Generators Static UPS #1

Static UPS #2

Tx Tx

The Original Scheme

Floor plan and plantroom take-up

for the SUPS and diesel generator scheme

Issues with the SUPS and diesel generator scheme:

• Cost and availability of the 22kV to 415V transformers

• Restricted space for up to 5 standby diesel generators

• Cooling (recirculation) issues for the diesel generators

• Very high nominal (In) and short-circuit (Isc) currents

• Reliability, control and cost of the ATS switches

• Capacity, quantity and space required for the reticulation

• LV switchgear expanding beyond the available space

• Space and cooling required for the SUPS and batteries

• Chillers unsported by UPS power

The Original Scheme

The DRUPS challenge!

• Resolve the transformer delivery issue

• Rationalise the distribution scheme, reduce reticulation

• Remove the ATS control and reduce high fault currents

• Support (if possible increase) the avialable UPS power

• Provide continuous power to the chillers

• Reduce the total building load and increase efficiency

• Resolve the spatial and cooling issues with the generators

• If possible increase useable raised floor area

• Deliver a scalable solution – Pay as you Grow!

The DRUPS Approach

A B

A B

A B

The DRUPS approach Removing transformers, simplifying the scheme, reducing reticulation, increase UPS power

SUPS + DG’s DRUPS

Total UPS Load 4161.9 kW 4161.9 kW

Total Cooling Load 1872.9 kW* 1664.8 kW

Total Building Load 187.5 kW 187.5 kW

Grand Total 6222.3 kW 6014.2 kW

*Cooling Load is less for DRUPS as it requires no AC and can operate at ambient

Reducing the Building Load SUPS versus DRUPS

Ventialtion and cooling Reverse the modules, remotely sited radiators and a plantroom approach

Space and Expansion Individual fire rated DRUPS rooms, seperate switchgear rooms, redundant control and rooms

Original SUPS Requirement

• 12 x 500 kVA SUPS Modules 2(4 +1)

• 5 x 2.5 MVA Standby Diesel Generators (N+1)

Alternative DRUPS Requirement

• 5 x 2.3 MVA DRUPS Modules (N+1)

Is this the totality of the comparison?

Reducing CAPEX Power Equipment Summary

Reducing CAPEX Removal of the ‘Big Ticket’ items

• 22kV/415V Transformers

• Main LV Switchboards

• Diesel Generators

• Paralleling Switchboard

• SUPS Modules + Batteries

• SUPS Output Switchboard

X X X

X X

X X

X X X

Reducing CAPEX Simplify distribution, reduce In and Isc

• 7000A Busduct

• 20 x 1C 400mm²

• 20 x 1C 500mm²

• 4000A Mains/Gen ATS’s + Controls

One SUPS String

• 20 x 1C 500mm²

• 4000A Mains/Gen ATS + Controls

• 4 x 3C 300mm² + 3 x 1C 400mm² N+PE

• 5+1 500 kVA SUPS

• 4 x 3C 300mm² + 3 x 1C 400mm² N+PE

• 6000A rated SUPS O/P switchboard

Reducing CAPEX Rationalise reticulation, remove ATS’

Reducing CAPEX Comprehensive evaluation of approaches

SUPS Equipment Removed

• 22kV/415V Transformers

• Main LV Switchboards

• Diesel Generators

• Paralleling Switchboard

• SUPS Modules + Batteries

• SUPS Output Switchboard

• ATS Switches and Controls

• High Current LV Busduct

• High Current LV Cabling

Reducing CAPEX Comprehensive evaluation of approaches

Addition of:

• Up to 5No 2.3 MVA Hitec DRUPS Modules

• Ancillary DRUPS Equipments

• 22kV UPS Input / Output Switchgear

• Low-current high-voltage cabling

• 22kV to 415 power transformers

• Dual Redundant Control Scheme (Tier III)

Reducing CAPEX Comprehensive evaluation of approaches

Tier Classification: • System component redundancy:

N+1 requirement: for both UPS and Generation equipment, as site Generation is considered to be the primary power source.

• Multiple distribution paths, enabling…

• Concurrent Maintainability: “Any component necessary to support the IT processing environment can be maintained without impact on the IT environment.”

But… • System not ‘Fault Tolerant’:

“The site is susceptible to disruption from unplanned activities.”

UTI Tier III Concurrent Maintainabililty

DRU

PS 2

DRU

PS 5

DRU

PS 3

DRU

PS 4

DRU

PS 1

• System Component Redundancy (N+1)

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

DRU

PS 2

DRU

PS 5

DRU

PS 3

DRU

PS 4

DRU

PS 1

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

• Multiple Distribution Paths

DRU

PS 2

DRU

PS 5

DRU

PS 3

DRU

PS 4

DRU

PS 1

• Concurrent Maintainability

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

DRU

PS 2

DRU

PS 5

DRU

PS 6

DRU

PS 3

DRU

PS 4

DRU

PS 1

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

• Concurrent Maintainability

DRU

PS 2

DRU

PS 5

DRU

PS 3

DRU

PS 4

DRU

PS 1

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

• Concurrent Maintainability

DRU

PS 2

DRU

PS 5

DRU

PS 3

DRU

PS 4

DRU

PS 1

UPS Input Switchboard

Separate UPS Output Switchboards

System ‘A’ System ‘B’

22kV ‘A’

22kV ‘B’

LV Loads ‘A’

LV Loads ‘B’

The DRUPS Approach Concurrent Maintainability

• Concurrent Maintainability

Bypass Control Panel

Q3

Q4

Dual Redundant Modbus+ Networks

Unit Control Panel PLC

Bypass Control Panel

Dual PLCs

To other modules

Modbus+ N

etwork

Bypass Control Panel

Dual PLCs

Unit Control Panel PLC

Modbus+ N

etwork

Fibre Optic

Unit Control Panel

Unit Control Panel

Bypass Control Panel

The DRUPS Approach Dual Redundant Control Scheme (Tier III)

Increasing lettable space Reducing Total Plantroom Area

LV Switchgear

Standby Generators Static UPS #1

Static UPS #2

Tx Tx

Increasing lettable space The Static UPS approach

• 9MVA Static UPS and Diesel Generator arrangement

• Total space required =1,762m²

DRUPS Modules, HV Switchgear and Controls

SwGr ‘A’

SwGr ‘B’

• 9 MVA Diesel Rotary UPS solution

• Total space required = 1,228m² • Total Space saved = 534m² (30% Space Saving)

Data Centre Expansion

Increasing lettable space The Diesel Rotary UPS approach

Calculating Carbon Footprint Operating efficiency is the key to calculating a ‘systems’ Carbon Footprint

Increasing Effiency

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

1 2 3 4 5 6 7 8 9 10

DRUPS Static UPS

$1,939K

$895K

High Efficiency = Low Life Cost Comparative running costs at 50% load based

on 9.5 cents/kWhr (AIR 2.5%) for a UPS requirement of 1600kW

Cost

€’s

Year

Saving of $1,044K over a 10 Year Period

Increasing Effiency

• Reduced CAPEX

• Simplified the reticulation and reduced fault current

• Used fewer components increased the lettable area

• Reduced the connections between supply and Load

• Provided continuous support to the total facility

• Lowered the overall building load

• Increased environmental and operating efficiency

• Reduced the carbon footprint and OPEX

• Increases the overall system reliability

• Considered as the ‘GREEN’ sustainable power approach

So why HV Hitec DRUPS?

The Completed Installation

The Completed Installation

The Completed Installation

Awards Excellence in Energy Efficiency

Awards Best Building Fit Out Over $20M

Questions

top related