PALM-3000
Integration and Testing Status
A. Bouchez
Team Meeting #15
10/29/2009
PALM-3000
2
PALM-3000 Testbed
Currently laying out the PALM-3000 testbed in the Caltech lab.
QuickTime™ and a decompressor
are needed to see this picture.
PALM-3000
3
Testbed I&T Schedule
• Purpose– Verify interfaces– Characterize subsystem performance– Debug and optimize software
• Testbed schedule– HOWFS characterization Nov.-Dec.
2009– DM characterization Nov.-Dec.– Test reconstructors, DM control Dec.-Jan. 2010– Close HODM loop - Matlab Jan.– Test DM high-speed interface Jan.– Verify RTC data input/output Feb.– Close HODM loop - RTC Mar.– Integrate new DM cables Apr.
PALM-3000
4
Final I&T
At Palomar, August through December 2010– Align P3K relay (optical bench IPT)– Integrate DM electronics, motor controllers
• Includes testing racks at Cass.
– Integrate RTC– Verify all basic system functions
• Includes installation/removal
– Characterize performance in lab (PHARO & P1640)– Document it all!
2 work-years of effort in 5 months!
PALM-3000
5
Commissioning
Commissioning Plan– Requesting 12 nights (4 x 3 nights) for
commissioning in semester 2011A (Feb.-July 2011).– Expect entire team to participate in most of these!– 10 work-months of labor budgeted.
Optimization Phase– Planning a 6-month period post-commissioning to
fully characterize and optimize system performance.