PENGAWATAN PENGUKURAN TIDAK
LANGSUNG
PLN DISTRIBUSI JAWA TIMUR JL, EMBONG TRENGGULI 19-21
SURABAYA
www.pln.co.id/disjatim
-
2015-03-13
2
TRAFO
SISI PRIMER SISI SEKENDER
R
S
T n
t
s
r
PENGUKURAN TAK LANGSUNG
TM
PENGUKURAN TAK LANGSUNG
TR
-
2015-03-13
3
Primer (TM) Sekunder (TR) R
S
T
r
s
t
n
Trafo Distribusi
-
2015-03-13
4
R
S
T
R
T
S
Phasor primer (TM) Phasor sekender (TR)
-
2015-03-13
5
PENGUKURAN TIDAK LANGSUNG
TEGANGAN RENDAH (TR)
-
2015-03-13
6
1 2 3 4 65 7 8 9 10
WIRING DIAGRAM 3P 4W PENGUKURAN TIDAK LANGSUNG TR
P1 P1 P1 P2P2P2
S2 S2 S2S1 S1 S1
R
S
T
N
-
2015-03-13
7
DIAGRAM PENGAWATAN METER PENGUKURAN TIDAK LANGSUNG TR
CT
-
2015-03-13
8
1 2 3 4 65 7 8 9 10
CT 100/5 A
Cl 0.5 1 VA
Cl 1.0 3 VA
Cl 3.0 -s1 s1 s1s2 s2 s2
P1 P1 P1
P2 P2 P2
CT 100/5 A
Cl 0.5 1 VA
Cl 1.0 3 VA
Cl 3.0 -
CT 100/5 A
Cl 0.5 1 VA
Cl 1.0 3 VA
Cl 3.0 -
R S T N
BEBAN
PENGUKURAN TIDAK LANGSUNG TR S2 CT Disambung dan di bumikan
-
2015-03-13
9
DIAGRAM PENGAWATAN METER PENGUKURAN TIDAK LANGSUNG TR
M
E
T
O
D
E
I
N
J
E
K
S
I
-
2015-03-13
10
PENGUKURAN TIDAK LANGSUNG TR METODE INJEKSI
1 2 3 4 65 7 8 9 10
CT 100/5 A
Cl 0.5 1 VA
Cl 1.0 3 VA
Cl 3.0 -s1 s1 s1s2 s2 s2
P1 P1 P1
P2 P2 P2
CT 100/5 A
Cl 0.5 1 VA
Cl 1.0 3 VA
Cl 3.0 -
CT 100/5 A
Cl 0.5 1 VA
Cl 1.0 3 VA
Cl 3.0 -
R S T N
BEBAN
-
2015-03-13
11
-
2015-03-13
12
M
E
T
O
D
E
I
N
J
E
K
S
I
-
2015-03-13
13
PENGUKURAN TIDAK LANGSUNG
TEGANGAN MENEGAH (TM)
-
2015-03-13
14
TRAFO TEGANGAN (PT)
-
2015-03-13
15
15
20000/3 Volt
100/3 Volt
PT (Potential Transformer)
Bidang Distribusi Metering 2011
PRIMER SEKUNDER
-
2015-03-13
16
Bidang Distribusi Metering 2011
16
KE METER 20000/3 Volt
100/3 Volt
PENGAWATAN PT (Potential Transformer)
-
2015-03-13
17
17
PHASOR TEGANGAN HUBUNGAN BINTANG
Bidang Distribusi Metering 2011
-
2015-03-13
18
Bidang Distribusi
Metering 2011 18
20000 Volt
100 Volt
PT (Potential Transformer)
-
2015-03-13
19
Bidang Distribusi Metering 2011
19
KE METER
-
2015-03-13
20
20000 V
100 V
-
2015-03-13
21
21
PHASOR TEGANGAN HUBUNGAN OPEN DELTA (ARON)
Bidang Distribusi Metering 2011
VR
VT
VS
-
2015-03-13
22
TRAFO ARUS (CT)
-
2015-03-13
23
Current Transformer (CT)
-
2015-03-13
24
24
SERI PARALEL
CT (Current Transformer)
Pengukuran klas 0.5 atau 0.2s
Proteksi
Klas 5P10
Pengukuran klas 0.5 atau 0.2s
Proteksi
Klas 5P10
Proteksi
Klas 5P10 Pengukuran
klas 0.5 atau 0.2s
Kumparan primer
Kumparan sekender
Rasio tunggal
Rasio ganda
-
2015-03-13
25
25
P1 P2
CT MULTI RASIO
1S1 1S2 1S3 1S4 2S1 2S2 2S3 2S4
1S1-1S2 = 50/5 A
1S1-1S3 = 100/5 A
1S1-1S4 = 150/5 A
Kumparan primer
Kumparan sekender
-
2015-03-13
26
26
KE METER
PENGAWATAN 3CT (3P-4W) METERING
-
2015-03-13
27
27
OCR
PENGAWATAN 3CT (3P-4W) PROTEKSI / PEMBATAS DAYA
-
2015-03-13
28
P1 P2 C1 C2
1S1 1S2 2S1 2S2
P1 P2 C1 C2
1S1 1S2 2S1 2S2
P1 P2 C1 C2
1S1 1S2 2S1 2S2
Pengukuran Proteksi
Pengawatan CT
-
2015-03-13
29
29
PHASOR ARUS 3P 4W
Bidang Distribusi Metering 2011
-
2015-03-13
30
Bidang Distribusi Metering 2011
30
KE METER
PENGAWATAN 2CT (3P-3W) METERING
-
2015-03-13
31
31
KE OCR
PENGAWATAN 2CT (3P-W) PROTEKSI / PEMBATAS DAYA
-
2015-03-13
32
32
PHASOR ARUS (3P 3W)
Bidang Distribusi Metering 2011
-
2015-03-13
33
Pengawatan CT, PT dan Meter Sistem 3P -4W
3 CT - 3 PT
-
2015-03-13
34
1 2 3 4 5 6 7 8 9 10
R S T
P1
P2
S1
S2
P1
P2
S1
S2
P1
P2
S1
S2
A
A
A N
a
a
a
n
n
n N
N
-
2015-03-13
35
CT
PT
20000/3 V
100/3 V
-
2015-03-13
36
PHASOR PADA PENGUKURAN METER 3P-4W
-
2015-03-13
37
Pengawatan CT, PT dan Meter Sistem 3P -3W (Aron)
2 CT - 2 PT
-
2015-03-13
38
1 2 3 4 5 6 7 8 9 10
R S T
P1
P2
S1 P1
P2
S1
S2
A
A
a
a
b
S2
B
B
b
-
2015-03-13
39
PT
20000/3 V
100/3 V
CT
-
2015-03-13
40
PHASOR PADA PENGUKURAN METER 3P-3W
-
2015-03-13
41
1 2 3 4 65 7 8 9 10
P1 P1 P1 P2P2P2
S2 S2 S2S1 S1 S1
R
S
T
A
B
A
B
A
B
a a a
b b b 20000/
100/PT CT CT CT
METER ELEKTRONIK TM
DI SETTING 3P 4WMENGGUNAKAN 3 CT 3 PT
-
2015-03-13
42
1 2 3 4 65 7 8 9 10
P1 P1 P2P2
S2 S2S1 S1
R
S
T
A
B
A
B
A
B
a a a
b b b 20000/
100/PT CT CT
METER ELEKTRONIK TM
DI SETTING 3P 4W MENGGUNAKAN 2 CT 3 PT
-
2015-03-13
43
1 2 3 4 65 7 8 9 10
P1 P1 P1 P2P2P2
S2 S2 S2S1 S1 S1
R
S
T
ABA B
aa b b
20000 V
VPT
CT CT CT
METER ELEKTONIK TM
DI SETTING 3P 4W MENGGUNAKAN 3 CT 2 PT
Nol meter tidak
boleh disambung
-
2015-03-13
44
1 2 3 4 65 7 8 9 10
P1 P1 P2P2
S2 S2S1 S1
R
S
T
ABA B
aa b b
20000 V
VPT
CT CT
METER ELEKTRONIK TM
DI SETTING 3P 3WMENGGUNAKAN 2 CT 2 PT
-
2015-03-13
45
1 2 3 4 65 7 8 9 10
P1 P1 P2P2
S2 S2S1 S1
R
S
T
A
B
A
B
A
B
a a a
b b b 20000/
100/PT CT CT
METER ELEKTRONIK TM
DI SETTING 3P 3WMENGGUNAKAN 2 CT 3 PT
-
2015-03-13
46
MACAM PENGAWATAN METER ELEKTRONIK
-
2015-03-13
47
Bidang Distribusi Metering 2011
47
Boleh tidak disambung
-
2015-03-13
48
Bidang Distribusi Metering 2011
48
-
2015-03-13
49
Bidang Distribusi Metering 2011
49
-
2015-03-13
50
Bidang Distribusi Metering 2011
50
-
2015-03-13
51
Bidang Distribusi Metering 2011 51
-
2015-03-13
52
ANALISA DAN EVALUASI KESALAHAN PENGAWATAN
-
2015-03-13
53
METER 3P 4WPENGAWATAN METER NORMAL
METER 3P 3WPENGAWATAN METER NORMAL
P1 = VS-R * IR * Cos ( IR VS-R)
P2 = VS-T * IT * Cos ( IT VS-T)
IRVR
IS
VS
VT
IT
P1
P2
P3
(0o)
(240o)
(120o )
P1 = VR * IR * Cos ( IR VR)
P2 = VS * IS * Cos ( IS VS)
P3 = VT * IT * Cos ( IT VT)
V R
V T
IR
IT
(0o)
(330o)
(270o)
(240o)
P1
P2
-
2015-03-13
54
METER 3P 3WPOLARITAS ARUS FASE R TERBALIK
P1 = VS-R * IR * Cos ( IR VS-R)
P2 = VS-T* IT * Cos ( IT VS-T)
METER 3P 4WPOLARITAS ARUS FASE R TERBALIK
P1 = VR * IR * Cos ( IR VR)
P2 = VS * IS * Cos ( IS VS)
P3 = VT * IT * Cos ( IT VT)
IR VR
IS
VS
VT
IT
P1
P2
P3
0o
120o
240o
180o
V R
V T
IR
IT
(180o)
(330o)
(270o)
(240o)
P1
P2
-
2015-03-13
55
P1 = VR * IR * Cos ( IR VR)
P1 = VS * IS * Cos ( IS VS)
P1 = VT * IT * Cos ( IT VT)
METER 3P 4WPOLARITAS ARUS FASE S TERBALIK
IRVR
IS
VS
VT
IT
P1
P2
P3
0o
240o
120o
300o
METER 3P 3WFASE S TIDAK ADA CT
P1 = VS-R * IR * Cos ( IR VS-R)
P2 = VS-T * IT * Cos ( IT VS-T)
V R
V T
IR
IT
(0o)
(330o)
(270o)
(240o)
P1
P2
-
2015-03-13
56
IRVR
IS
VS
VT
IT
P1
P2
P3
0o
240o
120o
60o
P1 = VR * IR * Cos ( IR VR)
P2 = VS * IS * Cos ( IS VS)
P3 = VT * IT * Cos ( IT VT)
METER 3P 4W POLARITAS ARUS FASE T TERBALIK
METER 3P 3WPOLARITAS ARUS FASE T TERBALIK
P1 = VS-R * IR * Cos ( IR VS-R)
P2 = VS-T * IT * Cos ( IT VS-T)
V R
V T
IR
IT
(0o)
(330o)
(270o)
(60o)
P1
P2
-
2015-03-13
57
IR VR
IS
VS
VT
IT
P1
P2
P3
0o
240o
120o
60o (360
o + 60)
P1 = VR * IR * Cos ( IR VR)
P2 = VS * IS * Cos ( IS VS)
P3 = VT * IT * Cos ( IT VT)
METER 3P 4W POLARITAS ARUS FASE R, S DAN T TERBALIK
METER 3P 3WPOLARITAS ARUS FASE R DAN T TERBALIK
P1 = VS-R * IR * Cos ( IR VS-R)
P2 = VS-T * IT * Cos ( IT VS-T)
V R
V T
IR
IT
(180o)
(330o)
(270o)
(60o)
P1
P2
-
2015-03-13
58
1 2 3 4 5 6 7 8 9 10
R S T
P1
P2
S1
S2
P1
P2
S1
S2
P1
P2
S1
S2
A
A
A N
a
a
a
n
n
n N
N
-
2015-03-13
59
Phasor primer (TM) Phasor sekender (TR)
VT 240o
VR 0o
VS 120o
VS 240o
VR 0o
VT 120o
IS 120o
IR 0o
IT 240o
IT 120o
IS 0o
IR240o
-
2015-03-13
60
P1 = VR * IR * Cos ( IR (240o) - VR (0
o))
P2 = VS * IS * Cos ( IS (0o) - VS(240
o))
P3 = VT * IT * Cos ( IT (120o) - VT(120
o))
Q1 = VR * IR * Sin (IR (240o) - VR (0
o))
Q2 = VS * IS * Sin (IS (0o) - VS (240
o))
Q3 = VT * IT * Sin (IT (120o) - VT (120
o))
Daya Aktif (Watt)
Daya Reaktif (Var)
Ptotal = P1 + P2 + P3
Qtotal = Q1 + Q2 + Q3
-
2015-03-13
61
1 2 3 4 5 6 7 8 9 10
R S T
P1
P2
S1
S2
P1
P2
S1
S2
P1
P2
S1
S2
A
A
A N
a
a
a
n
n
n N
N
-
2015-03-13
62
IS 180o
Phasor primer (TM) Phasor sekender (TR)
IR 60o
VS 240o
VR 0o
IT 120o
VT 120o
VT 240o
VR 0o
VS 120o
IS 120o
IR 0o
IT 240o
-
2015-03-13
63
P1 = VR * IR * Cos ( IR (60o)- VR (0
o))
P2 = VS * IS * Cos ( IS (180o) - VS(240
o))
P3 = VT * IT * Cos ( IT (120o) - VT(120
o))
Q1 = VR * IR * Sin (IR (60o) - VR (0
o))
Q2 = VS * IS * Sin (IS (180o) - VS (240
o))
Q3 = VT * IT * Sin (IT (120o) - VT (120
o))
Daya Aktif (Watt)
Daya Reaktif (Var)
Ptotal = P1 + P2 + P3
Qtotal = Q1 + Q2 + Q3
-
2015-03-13
64
1 2 3 4 5 6 7 8 9 10
R S T
P1
P2
S1
S2
P1
P2
S1
S2
P1
P2
S1
S2
A
A
A N
a
a
a
n
n
n N
N
-
2015-03-13
65
Phasor primer (TM) Phasor sekender (TR)
VT240o
VR0o
VS120o
VT240o
VR0o
VS120o
IS120o
IR0o
IT240o
IS0o
IR240o
IT120o
-
2015-03-13
66
P1 = VR * IR * Cos ( IR (120o)- VR (0
o))
P2 = VS * IS * Cos ( IS (240o) - VS(120
o))
P3 = VT * IT * Cos ( IT (0o) - VT(240
o))
Q1 = VR * IR * Sin (IR (120o) - VR (0
o))
Q2 = VS * IS * Sin (IS (240o) - VS (120
o))
Q3 = VT * IT * Sin (IT (0o) - VT (240
o))
Daya Aktif (Watt)
Daya Reaktif (Var)
Ptotal = P1 + P2 + P3
Qtotal = Q1 + Q2 + Q3
-
2015-03-13
67
1 2 3 4 5 6 7 8 9 10
R S T
P1
P2
S1
S2
P1
P2
S1
S2
P1
P2
S1
S2
A
A
A N
a
a
a
n
n
n N
N
-
2015-03-13
68
Phasor primer (TM) Phasor sekender (TR)
VT240o
VR 0o
VS120o
VT240o
VR0o
VS120o
IS120o
IR0o
IT240o
IT0o
IS240o
IR120o
-
2015-03-13
69
P1 = VR * IR * Cos ( IR (240o)- VR (0
o))
P2 = VS * IS * Cos ( IS (0o) - VS(120
o))
P3 = VT * IT * Cos ( IT (120o) - VT(240
o))
Q1 = VR * IR * Sin (IR (240o) - VR (0
o))
Q2 = VS * IS * Sin (IS (0o) - VS (120
o))
Q3 = VT * IT * Sin (IT (120o) - VT (240
o))
Daya Aktif (Watt)
Daya Reaktif (Var)
Ptotal = P1 + P2 + P3
Qtotal = Q1 + Q2 + Q3
-
2015-03-13
70
1 2 3 4 5 6 7 8 9 10
R S T
P1
P2
S1
S2
P1
P2
S1
S2
P1
P2
S1
S2
A
A
A N
a
a
a
n
n
n N
N
-
2015-03-13
71
Phasor primer (TM) Phasor sekender (TR)
VS240o
VR0o
VT120o
VT240o
VR0o
VS 120o
IS120o
IR0o
IT240o
IR0o
IT270o
IS90o
-
2015-03-13
72
P1 = VR * IR * Cos ( IR (0o)- VR (0
o))
P2 = VS * IS * Cos ( IS (90o) - VS(120
o))
P3 = VT * IT * Cos ( IT (270o) - VT(240
o))
Q1 = VR * IR * Sin (IR (0o) - VR (0
o))
Q2 = VS * IS * Sin (IS (90o) - VS (120
o))
Q3 = VT * IT * Sin (IT (70o) - VT (240
o))
Daya Aktif (Watt)
Daya Reaktif (Var)
Ptotal = P1 + P2 + P3
Qtotal = Q1 + Q2 + Q3
-
2015-03-13
73
1 2 3 4 5 6 7 8 9 10
R S T
P1
P2
S1
S2
P1
P2
S1
S2
P1
P2
S1
S2
A
A
A N
a
a
a
n
n
n N
N
-
2015-03-13
74
Phasor primer (TM) Phasor sekender (TR)
VT 240o
VR 0o
VS 120o
VT 240o
VR 0o
VS 120o
IS 120o
IR 0o
IT 240o
IS 120o
IR 180o
IT 240o
-
2015-03-13
75
P1 = VR * IR * Cos ( IR (180o)- VR (0
o))
P2 = VS * IS * Cos ( IS (120o) - VS(120
o))
P3 = VT * IT * Cos ( IT (240o) - VT(240
o))
Q1 = VR * IR * Sin (IR (180o) - VR (0
o))
Q2 = VS * IS * Sin (IS (120o) - VS (120
o))
Q3 = VT * IT * Sin (IT (240o) - VT (240
o))
Daya Aktif (Watt)
Daya Reaktif (Var)
Ptotal = P1 + P2 + P3
Qtotal = Q1 + Q2 + Q3
-