WCDMA RBS
3101/3202
Installation Verification
(Element Manager 사용법)
2
0. 목차
1. Introduction
2. Network Overview
3. RBS Library Overview
4. RBS Overview
5. Site Equipment Overview
6. RBS On site configuration with wizard
7. Practical exercise
7.1 Connection to the node
7,2 Start the Element Manager
7.3 Configuration the node with XML files or wizard
7.4 Concluding routines
8. Antenna theory
9. Standard antenna system components
10. SWR/DTF tests
11. Practical exercises
12. Theoretical ASP test
3
1. Introduction
• Point out the main components of a RBS 3000 site.
• Prepare and connect a laptop to the RBS 3000 and start the RBS Element Manager
• Execute on-site configuration XML-files with the Element Manager
• Verify the on-site configuration
• Understand the basic antenna system theory
• Perform DTF(Distance To Fault) and SWR(Standing Wave Ratio) antenna tests in active or passive antenna systems
• Describe the concluding routines for installation verification, such as completing the Test Record
1.1 Course의 목적
4
1.2 Training & Assessment 과정 (ASP 자격증 취득과정)
Multimedia Based Learning (MBL)
Instructor Led Training (ILT)
Theoretical Assessment (included in the ILT)
Practical Assessment (done in the real sites:
3-5 RBS sites and 1-2 Switch sites)
1. Introduction
5
WCDMA Radio Access Network
Core Network
RBS Radio Base Station
RNC Radio Network Controller
RXI Radio Access Network Aggregator
OSS-RC Operations Support System
Radio & Core
TEMS TEMS Optimization Solutions
OSS-RC TEMS
Other
Management
Systems
Network
Management
Environment
RBS
Hub
RBS
RNC
Radio Access
Network
2. Network Overview
6
WCDMA Radio Access Network
2. Network Overview
7
USIM
ME
Node B
Node B
: RNC
RNS
Node B
Node B
: RNC
RNS
UTRAN
MSC/VLR
HLR
GMSC
SGSN : GGSN
CN
Uu Iu Iub
Iur
:
External Networks
PLMN, PSTN, ISDN, etc..
Internet
Cu
: Interface ME : Mobile Equipment RNC : Radio Network Controller
RNS : Radio Network Sub-System UTRAN: UMTS Terrestrial Radio Access Network
MSC : Mobile Services Switching Center VLR : Visitor Location Register
GMSC: Gateway MSC HLR : Home Location Register
GPRS: General Packet Radio Service SGSN : Serving GPRS Support Node
GGSN: Gateway GPRS Support Node CN : Core Network
: Route for Circuit Switched Service
: Route for Packet Switched Service
2. Network Overview
8
2. Network Overview
9
IMT-2000 / UMTS Concept
2. Network Overview
10
2.1 WCDMA RAN System Description
2. Network Overview
11
2.1 WCDMA RAN System Description
2. Network Overview
12
2.1 WCDMA RAN System Description
2. Network Overview
13
Description
RANOS
Set of software for handling operation and maintenance tasks for the WCDMA
RAN
Gives information such as alarms, configuration and basic performance.
Provides several interfaces for easy integration with the existing management
environment
TEMS
Gives support for planning, test and performance monitoring of the radio and
transport network
Resulting configuration data can be downloaded to the nodes via RANOS
Ericsson’s WCDMA network components
Description
RBS
Controls the actual radio resources and maintains the radio link
Is connected the user equipment (UE) via the Uu interface (radio interface), to the
RNC via the Iub interface
RNC
Controls a number of RBS’s. Controls mobility functions like Power control,
Handovers, Switching, etc.
Is connected to the core network via the Iu interface. RNC’s are interconnected via
the Iur interface
2. Network Overview
14
Radio Site Implementation Process Overview
Cell Planning
Radio Network Survey
Acquisition
Site Survey
Site Engineering
Site Installation
Quality Audit
Site installation Test
Site Integration
Site Acceptance
& Commissioning Civil Works
Cable ladder Installation
RBS Cabinet Installation
PBC Installation
EACU Installation
Cabling
Antenna Installation
2. Network Overview
15
• RBS Node ; Verified according to Verification Instruction 1/1532-COH 109 334/1
• Site Basic and External HW configuration files (XML or MO scripts)
• Transmission to RNC installed ; Verified and documented
• RBS Mub configured at the RNC
• MG(Media Gateway), OMINF(Operation & Maintenance Router and Operation &
Maintenance Infrastructure) ; Configured and verified
• IP address of the RBS and its user name and password
• SID(Site Installation Documentation available)
2.1 On Site configuration 을 위한 선수조건
2. Network Overview
16
3.1 RBS 3000 Library overview
3. RBS Library Overview
RBS
Product Data
On-Site
Integration
RBS 3000
Verification
Instruction
RBS
Integration
Report
Site Installation
Document Safety Instruction
17
()
()
4.1 RBS 종류
4. RBS Overview
Model Function
RBS3101 Outdoor Macro
RBS3103 Compact Outdoor
RBS3104 Super Compact
RBS3202 Indoor Macro
RBS3203 Compact Indoor
RBS3303 Micro
RBS3402 Mini Indoor
RBS3501 Mini Outdoor
18
()
()
4.2 RBS 3202
4. RBS Overview
항목 규격
Dimensions 170H x 60W x 40D cm, 200 kg
Carriers 12 Carriers, 6 Sectors
Access Method FDD
Max Tx Power 20/40 W
Power Supply -48 V
19
()
()
4.3 RBS 3101
4. RBS Overview
항목 규격
Dimensions 1614H x 1300W x 710D mm
Carriers 12 Carriers, 6 Sectors
Access Method FDD
Max Tx Power 20/40 W
Power Supply Single phase AC or 3 phase
AC
20
Baseband Subrack
4.2 RBS 3202
4. RBS Overview
Radioband Subrack
Multi
Carrier
Power
Amplifier Subrack
Capacitor Unit
Fan Unit
Interface Connection Field
21
4.2 RBS 3202
4. RBS Overview
위치 이름 구분 기능
Capacitor Unit Control •Stabilizes the -48V distribution
Baseband
Subrack
RAXB Traffic •Demodulator, Random Access and Decoder (이
보드의 숫자에 따라 용량 결정, 128CE/Bd)
TXB Traffic •Channel encoding and digital modulation (단 1
개)
BBIFB Traffic •Interface between BB subrack and RF subrack
(Traffic & Timing)
ETB Control •Interface to the RNC. Up to 4 ETB can be
mounted
GPB Control •The ‘Brain’ of the RBS
TUB Control •Distributes timing signals to the rest of the RBS
(1시간 동안 동기 보장)
SCB Control
•Contains the ATM switch and interfaces the
other units in the subrack via the backplane
•Contains power filtering and distrubution for
each subrack
Radioband
Subrack
RFIFB Traffic •Interface between RF subrack and BB subrack
(Traffic & Timing)
TRXB Traffic •Modulation and demodulation for RX/RX path
AIU Traffic
•Antenna inteface with RF filters, amplifiers,
duplex filters and splitters. Can combine RF
signals from 2 MCPA to one antenna(두꺼운 것)
SCB Control
MCPA Subrack MCPA Traffic •Amplifies one carrier to 20W. Can deliver 40W
if combined
Transmission Mini-WIFT •For PCM connection
External alarm EACU •32 external alarms can be defined
Cooling system Fans •15년 동작
28 slots
22
4.2 RBS 3202
4. RBS Overview
TX
RX
BBIF
RFIF
TRX
AIU
PA
SCB
SCB
ET
TU
MP
CU or PSU/PCU
TMS
EACU
ASC
Power Subrack
BB Subrack
RF Subrack
MCPA Subrack
To/From TMS antenna
To/From RNC (Traffic & O&M)
Main Power
ANT
23
4.2 RBS 3202
5. Site Equipment
이름 구분 기능
AC/DC
Power
System
Battery
Cabinet
External
Alarm
Mini-Wift
24
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
단계 내용 정상상태
Power Up the BSS 시스템 전원 On
Configure the Thin Client RBS 접속을 위한 노트북(Client) 설정
O&M access RBS와 O&M간의 연결을 위한 설정
Verify Synchronization
Status
ATM 링크의 동기가 이루어 졌는지 확인
(약 27분 정도 소요)
Site External Hardware RBS 시스템 기본/형상정보 설정
Mub 인터페이스 설정
Verify LED Status LED 상태 확인 Green On
Veirfy RbsLocalCell RBS Local Cell 의 동작상태 확인 Operational
Verify Mub Connection Ping 과 Trace를 이용하여 Mub 연결상태 확인
Verify External Hardware Alarm 과 battery 장치 확인
Concluding Routines 사이트 정리 및 문서작성
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
25
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
•Site 전원이 Off 되어 있는지 확인
•Capacitor Unit (CU) 전원 스위치를 On
•Baseband (BB) sublack 전원 스위치를 On
•Radio Frequency (RF) sublack 전원 스위치를 On
•Multi Carrier Power Amplifer (MCPA) sublack 전원 스위치를 On
•Site 전원을 On
•LED 확인
CU
Baseband
Radio Frequency
MCPA
<RBS 랙 구성도>
전원 On 순서
26
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
HyperTerminal 등의
텔넷 프로그램 이용
<시리얼 포트를 이용한 연결: 비상시에만 사용>
RJ-45 시리얼포트
27
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
169.254.1.1 (default) 169.254.1.2
<이더넷을 이용한 연결: 일반적인 방법>
RJ-45 RJ-45
Cross 케이블
28
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
직접연결 (Locally) 원격연결 (Remote)
사용
프로그램
Element Manager (EMAS라고도 함)
시리얼통신
Element Manager
RANOS
<연결방식 비교 : Local vs. Remote>
Element Manager 시리얼 통신
용도 일반적일 경우 사용 비상시 사용
사용
프로그램
Element Manager
-JAVA Plug-in 1.3.1_09 필요
-최초 접속시 RBS로부터 다운받음
터미널 프로그램
(ex. Hyper Terminal)
연결방식 이더넷 시리얼 통신
케이블 RJ-45 to RJ-45 (Cross) 시리얼 to RJ-45
<연결방식 비교 : Element Manager vs. 시리얼 통신>
29
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<JAVA Plug-in 설치>
JAVA Plug-in : Java 2 Runtime Environment, Standard Edition 1.3.1_09
※ 나머지 항목은 기본설정 유지
•Element Manager가 실행이 안될 경우 확인할 사항
1. 제어판 \ Java Plug-in 설정 확인
2. Documents and Settings \ 사용자이름 \ Ericsson 폴더를 삭제
30
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<JAVA Plug-in 설치>
\Program Files\JavaSoft\JRE\1.3.1_09 \lib\security\java.policy
31
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<JAVA Plug-in 설치>
grant { permission java.security.AllPermission; };
이 줄을 삽입 (모두 허용)
32
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Element Manager 실행>
169.254.1.1 (default) 169.254.1.2
RJ-45 RJ-45
Cross 케이블
33
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Element Manager 실행>
<Element Manager 메인화면>
34
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Configuration Version>
CV (Configuration Version) 란? => RBS의 설정(Configuration)을 저장하고 있는 파일
Mub Configuration (mo)
Site External Hardware
Configuration (xml)
O&M Configuration (xml)
Basic Configuration
(공장 출하시 기본 설정) Basic CV
OAM CV
SITE CV
XX CV
•위로 갈수록 내용이 추가되는 것임
•Rollback 하고 싶으면 하위 버전의 CV를 Load
35
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Configuration Version>
•RBS에 저장되어 있는 CV 들
36
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<CV 생성>
•XML files (2개)
•MO scripts (1개) •CV 3개 생성
xml 파일
xml 파일 mo 파일
•총 2개의 xml 파일과 1개의 mo 파일을 이용해 3개의 CV 생성
•설정시 Automatic 방법과 Wizard 방법이 있는데, Wizard 방법을 권장
(Automatic 방법은 xml/mo 파일을 읽어서 한번에 변환하는 방식
Wizard 방법은 xml/mo 파일을 읽어서 step by step으로 설정내용을 보여줌)
37
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<RBS Configuration 개요>
O&M access
Site External Hardware
Site External
Hardware
Config file
executor
설정내용
RBS IP address
RNC와의 연결방식
(E1/T1/J1)
IP over ATM 설정
O&M으로의 경로설정 (static route)
시스템 기본설정 (날짜, 시간, 위치 정보 등)
시스템 형상정보
(TMA/ASC 장착여부,
안테나, 주파수, 안테나
feeder관련 파라미터:attenuation, delay,
Cell_ID, Carrier 설정)
Mub 인터페이스
설정
입력파일
xml xml mo
CV
자동생성여부
Yes Yes No (수동생성 필요)
38
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<RBS Configuration 개요>
RBS RNC
MGW
O&M Router
Mub 인터페이스 (RBS관리)
Mub 인터페이스 => Management 인터페이스
Mur 인터페이스 (RNC관리)
39
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<O&M access>
단계 내용 주의사항
1/7 xml 파일 입력
2/7 xml 파일 로딩
3/7 Location ET-M1 standard : E1
4/7 IP over ATM
Configuration VP Ingress/egress PCR : 4500
5/7 Router Configuration
Get default values for : Any route
Destination IP address : 0.0.0.0
Route Metric : 2
(Metric 낮을수록 우선순위 높다)
6/7 DHCP/DNS 서버 설정
7/7 설정내용 확인 후 저장
40
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<O&M access>
•툴바 \ Configuration \ O&M access…
41
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<O&M access - Automatic>
Automatic
42
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<O&M access>
•Xml 파일 입력 (1/7)
43
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<O&M access>
•Xml 파일 입력 (1/7)
44
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<O&M access>
• IP over ATM configuration (4/7)
45
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<O&M access>
•Router Configuration (5/7)
46
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<O&M access>
•설정내용 확인 (7/7)
47
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Verify Synchronization Status>
•풀다운메뉴 \ ATM \ Network Synchronization \ 마우스 오른쪽 버튼
Properties \ System Clock A = locked mode 인지 확인
48
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
단계 내용 주의사항
1/14 xml 파일 입력
2/14 xml 파일 로딩
3/14 Site Information data
4/14 Alex Server Configuration
5/14 Sector data configuration Antenna height : 안테나의 중간 높이
6/14 Time setting
7/14 TMA/ASC configuration
8/14 Antenna branch
configuration
9~11/14 Sector X, antenna cables
configuration
Feeder 케이블 delay 및 attenuation 값
입력
12/14 Initiate sectors 섹터별 output power, carrier 수 설정
13/14 RBS local cell
configuration Cell ID, frequency plane, Cell range
14/14 설정정보 확인
49
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•툴바 \ Configuration \ Site Equipment…
50
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•툴바 \ Configuration \ Site Equipment…
51
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•Xml 파일 입력 (1/14)
52
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•Xml 파일 로딩 (2/14)
53
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•Site information data (3/14)
54
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•Sector data configuration (5/14)
55
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•Tma/Asc configuration (7/14)
56
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•Antenna branch configuration (8/14)
57
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•Sector x, Antenna cables configuration (9/14)
58
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•Sector x, Antenna cables configuration (11/14)
59
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•Rbs Local Cell Configuration (13/14)
60
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Site Equipment>
•설정정보 확인 (14/14)
61
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Config file executor>
•툴바 \ Configuration \ Config file executor…
62
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Config file executor>
•CV 생성
풀다운메뉴 \ Software \ Configuration Version \ 마우스 오른쪽 버튼
Create…
63
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Config file executor>
•CV 생성
풀다운메뉴 \ Software \ Configuration Version \ 마우스 오른쪽 버튼
Create…
64
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Config file executor>
CV 상태 내용
Grey Loaded (지금 돌고 있는 것)
Yellow Saved on the node
Blue Startable
Purple Loaded and startable
65
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Verify LED status>
•각 보드별 LED가 아래의 상태를 유지하고 있는지 확인
Board 명 Green Red Yellow
SCB Steady off Off
ETB Steady off Off
TUB Steady off Flashing
BBIFB Steady off Off
RAXB Steady off Off
GPB Steady off Off
TXB Steady off Off
RFIFB Steady off Flashing
TRXB Steady off Off
AIU Steady off Flashing
MCPA Steady off Flashing
CU Steady off Off
BBSF Steady off
RFSF Steady off
MCPASF Steady off
PSF Steady off
PCU Steady off Off
PSU Steady off Off
ACCU Steady off Off
Climate Unit Steady off Off
XALM steady off Off
LED 상태 Red (fault) Green
(operation)
Yellow
(information)
Off No faults Power loss
Unlocked,
resource
missing
Flickering Initial boot
test Busy
Quickly Load test
Slowly Resource
missing
Shutdown in
process
On H/W fault running Locked
F
O
I
66
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Verify RbsLocalCell>
•풀다운메뉴 \ Radio Network \ RbsLocalCell-STC1
=> Operational State 가 Enabled 인지 확인
67
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Verify RbsLocalCell>
•풀다운메뉴 \ IP \ IP system \ 마우스 오른쪽 버튼 Ping and Trace
68
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<Verify External Hardware>
Power Off
Power On
LED 상태확인
원하는 CV가 로딩되었는지
확인
1 min
•풀다운메뉴 \ Radio Network
=> NBAP Common/dedicated, Node Sync, Cell 이 unlocked / enabled 인지 확인
=> Cell의 FACH, PCH, RACH 가 unlocked / enabled 인지 확인
•CV 를 새로 저장
69
6.1 On-Site Configuration, step by step
6. RBS On site configuration with wizard
Power Up the BSS
Configure the Thin Client
O&M access (Integrate IP over ATM)
Verify Synchronization Status
Site External Hardware
Verify LED Status
Verify RbsLocalCell
Verify Mub Connection (IP over ATM)
Verify External Hardware
Concluding Routines
<마무리>
•Close the Element Manager
•Complete the RBS Integration Report
•Clean the site
•Update the site documentation if changes has occurred
•Give the updated site documentation to the responsible
person
•Lock all doors to the site
70
1. Equipment Installation – Radio cabinet jumpers connection
2. Dist.Unit and PCM/PDH-magazine – Labeling
3. Antenna feeders and distribution cables – Earthing kits on outdoor feeders
4. Antenna feeders and distribution cables – Feeder markings
5. Equipment Installation PCM cabling 75/100/120 Ohm connection
6. Earthing – Earthing principles
7. Equipment Installation – Fastening of cabinet and magazine
8. Backup battery – All cables and connectors correctly labeled
9. Site safety, general and civil works – site appearance
10. Antenna feeders and distribution cables – Antenna jumpers fixing and
clampings
Top ten Failure RBS-Sites
71
Alarm 확인
top related