april 2012 construction update

39
Bensenville School District #2 Addi4ons to Johnson & Tioga Elementary Schools Budget Review April 4, 2012

Upload: terry-ryan

Post on 29-Mar-2016

218 views

Category:

Documents


4 download

DESCRIPTION

Gilbane Building Co. provides an overview of progress on the Tioga School and W.A. Johnson School addition projects

TRANSCRIPT

Page 1: April 2012 Construction Update

Bensenville  School  District  #2  

Addi4ons  to                        Johnson  &  Tioga  

Elementary  Schools    

Budget  Review  April  4,  2012  

Page 2: April 2012 Construction Update

Tioga  &  Johnson  Construc1on  Budget  Update  $  millions   Total  

Johnson  addi1on  &  renova1on   24.8  

Tioga  1st  addi1on  (Includes  Contempla1on  Bridge)   21.8  

Tioga  2nd  addi1on   5.5  

Demoli1on  Costs   0.6  

Total  Es1mate   52.7  

Less  Unallocated  Con1ngencies  and  Possible  Allowance  Recoveries   0.9  

Likely  Range   $51.8-­‐52.7  

Page 3: April 2012 Construction Update

Allowance  &  Con1ngency  Recap  

 Allowances     Johnson  Tioga          

(Current  Phase)  Tioga                

(Next  Phase)   Total  

 Allowances  Awarded     520,000 910,000 1,430,000

 Less  Authorized  to  Date     126,225 479,579 605,804

 Less  Future  Spending  (est.)     343,775 280,421 624,196

 Unspent  allowances     50,000 150,000 200,000

Con4ngencies  Ini4ally  Budgeted   600,000 600,000 200,000 1,400,000

Less  Allocated    To  Date    (Wetlands,  Asbestos,  Bulle4ns)  

400,000 300,000 0 700,000

Remaining  Con4ngencies   200,000 300,000 200,000 700,000

Page 4: April 2012 Construction Update

Bensenville  School  District  #2  

 Addi4ons  to                        

Johnson  &  Tioga  Elementary  Schools  

Page 5: April 2012 Construction Update

Discussion  Overview        -­‐  Review  February  progress  –  WAJ      -­‐  Review  March  Major  AcCviCes      -­‐  Review  February  progress  -­‐  Tioga      -­‐  Review  March  Major  AcCviCes  

   

Page 6: April 2012 Construction Update

W.A.  Johnson  Elementary  School  

   

Page 7: April 2012 Construction Update

March  Major  Ac4vi4es        -­‐  Completed  masonry  interior  CMU  work  –  Café,  Admin      -­‐  Completed  roofing  installaCon  at  Café  &  Gym        -­‐  Started  roofing  at  Learning  Center,  Admin  Area      -­‐  ConCnued  Mech/Elec/Plumb  overhead  Rough-­‐In      -­‐  ConCnued  drywall  framing,  taping  installaCon      -­‐  ConCnued  interior  painCng      -­‐  ConCnued  exterior  glazing  –  classroom  areas      -­‐  Complete  seWng  of  mechanical  equipment        

   

Page 8: April 2012 Construction Update

Exterior  Glazing  –  NE  Classrooms  April  2,    2012  

Page 9: April 2012 Construction Update

Exterior  Glazing  –  Art  Room  April  2,    2012  

Page 10: April 2012 Construction Update

Exterior  Glazing  –  Innova4on  Lab    April  2,    2012  

Page 11: April 2012 Construction Update

Exterior  Glazing  –  Innova4on  Lab  (Interior)      April  2,    2012  

Page 12: April 2012 Construction Update

Cafeteria    April  2,    2012  

Page 13: April 2012 Construction Update

Courtyard  –  Music  Room  Eleva4on  April  2,    2012  

Page 14: April 2012 Construction Update

Roofing  –  Administra4on  Area      April  2,    2012  

Page 15: April 2012 Construction Update

Learning  Center  -­‐  Roofing  April  2,    2012  

Page 16: April 2012 Construction Update

Classroom  Area  Corridor  April  2,    2012  

Page 17: April 2012 Construction Update

Typical  Classroom  –  Light  Fixtures      April  2,    2012  

Page 18: April 2012 Construction Update

Student  Commons  April  2,    2012  

Page 19: April 2012 Construction Update

April  Major  Ac4vi4es        -­‐  Complete  roofing  at  AdministraCon  Area      -­‐  Complete  exterior  glazing  –  classroom  areas      -­‐  ConCnue  exterior  glazing  –  café,  gym      -­‐  ConCnue  Mech-­‐Electrical-­‐Plumbing-­‐Fire  Prot  Rough-­‐in      -­‐  ConCnue  drywall  framing,  installaCon,  taping,  painCng      -­‐  Start  Casework  installaCon      -­‐  Start  ceramic  Cle  work      -­‐  Start  VCT  flooring  installaCon      -­‐  Overall  CPM  schedule  currently  tracking  per  plan  

   

Page 20: April 2012 Construction Update

Tioga  Elementary  School  

   

Page 21: April 2012 Construction Update

 March  Major  Ac4vi4es        -­‐  Completed  interior  masonry  CMU  work      -­‐  Completed  roofing  -­‐  gymnasium      -­‐  ConCnued  exterior  glazing  –  classroom  wings,  Pre-­‐K,  Admin      -­‐  ConCnued  Mech/Elec/Plumb/Fire  Prot  overhead  Rough-­‐In      -­‐  ConCnued  classroom  area  drywall  framing,  installaCon,  taping      -­‐  ConCnued  classroom  area  painCng      -­‐  Poured  contemplaCon  bridge  deck      -­‐  ConCnued  ceiling  grid  installaCon      -­‐  Started  ceramic  Cle  work  and  casework  installaCon      -­‐  Completed  seWng  of  mechanical  equipment      

 

   

Page 22: April 2012 Construction Update

Contempla4on  Bridge  Deck  March  16,  2012  

Page 23: April 2012 Construction Update

Contempla4on  Bridge  –  Mechanical  Rough-­‐in  April  2,  2012  

Page 24: April 2012 Construction Update

Exterior  Glazing  –  Classroom  Areas  March  16,  2012  

Page 25: April 2012 Construction Update

Exterior  Glazing  –  Pre-­‐K  Classrooms  March    22,  2012  

Page 26: April 2012 Construction Update

Exterior  Glazing  –  Courtyard  Stair    March  22,  2012  

Page 27: April 2012 Construction Update

Temporary  Walkway  April  2,  2012  

Page 28: April 2012 Construction Update

Temporary  Walkway  April  2,  2012  

Page 29: April 2012 Construction Update

Gymnasium  –  Mechanical  Rough-­‐in  April  2,  2012  

Page 30: April 2012 Construction Update

Ceramic  Tile  –  Student  Bathrooms  April  2,  2012  

Page 31: April 2012 Construction Update

Ceramic  Tile  –  Staff  Bathroom  April  2,  2012  

Page 32: April 2012 Construction Update

Classroom  Area  –  Entrance  Ves4bule  April  2,  2012  

Page 33: April 2012 Construction Update

Typical  Classroom  -­‐  Interac4on  Room  April  2,  2012  

Page 34: April 2012 Construction Update

Innova4on  Lab  April  2,  2012  

Page 35: April 2012 Construction Update

Typical  Classroom  –  Radiant  Ceiling  Panels  April  2,  2012  

Page 36: April 2012 Construction Update

Typical  Classrooms  April  2,  2012  

Page 37: April 2012 Construction Update

Typical  Classroom  –  Sliding  Markerboard  Wall  Mock-­‐Up  April  2,  2012  

Page 38: April 2012 Construction Update

 April  Major  Ac4vi4es        -­‐  Complete  exterior  glazing  work  –  classroom  areas      -­‐  ConCnue  exterior  glazing  –  Admin  area,  Pre-­‐K,  LRC      -­‐  ConCnue  Mech-­‐Electrical-­‐Plumbing-­‐Fire  Prot  Rough-­‐in      -­‐  ConCnue  drywall  framing,  installaCon,  taping      -­‐  ConCnue  painCng  work      -­‐  ConCnue  ceiling  grid      -­‐  ConCnue  classroom  casework  installaCon      -­‐  Start  seWng  of  light  fixtures      -­‐  Start  VCT  flooring  installaCon      -­‐  Overall  CPM  schedule  currently  tracking  ~15  days  behind  

   

Page 39: April 2012 Construction Update

Bensenville  School  District  #2  

 Addi4ons  to                        

Johnson  &  Tioga  Elementary  Schools