Gilbane Building Co. provides an overview of progress on the Tioga School and W.A. Johnson School addition projects

TRANSCRIPT

  • Bensenville School District #2

    Addi4ons to Johnson & Tioga

    Elementary Schools

    Budget Review April 4, 2012

  • Tioga & Johnson Construc1on Budget Update $ millions Total

    Johnson addi1on & renova1on 24.8

    Tioga 1st addi1on (Includes Contempla1on Bridge) 21.8

    Tioga 2nd addi1on 5.5

    Demoli1on Costs 0.6

    Total Es1mate 52.7

    Less Unallocated Con1ngencies and Possible Allowance Recoveries 0.9

    Likely Range $51.8-52.7

  • Allowance & Con1ngency Recap

    Allowances Johnson Tioga (Current Phase) Tioga (Next Phase) Total Allowances Awarded 520,000 910,000 1,430,000

    Less Authorized to Date 126,225 479,579 605,804

    Less Future Spending (est.) 343,775 280,421 624,196

    Unspent allowances 50,000 150,000 200,000

    Con4ngencies Ini4ally Budgeted 600,000 600,000 200,000 1,400,000

    Less Allocated To Date (Wetlands, Asbestos, Bulle4ns)

    400,000 300,000 0 700,000

    Remaining Con4ngencies 200,000 300,000 200,000 700,000

  • Bensenville School District #2

    Addi4ons to

    Johnson & Tioga Elementary Schools

  • Discussion Overview - Review February progress WAJ - Review March Major AcCviCes - Review February progress - Tioga - Review March Major AcCviCes

  • W.A. Johnson Elementary

    School

  • March Major Ac4vi4es - Completed masonry interior CMU work Caf, Admin - Completed roong installaCon at Caf & Gym - Started roong at Learning Center, Admin Area - ConCnued Mech/Elec/Plumb overhead Rough-In - ConCnued drywall framing, taping installaCon - ConCnued interior painCng - ConCnued exterior glazing classroom areas - Complete seWng of mechanical equipment

  • Exterior Glazing NE Classrooms April 2, 2012

  • Exterior Glazing Art Room April 2, 2012

  • Exterior Glazing Innova4on Lab April 2, 2012

  • Exterior Glazing Innova4on Lab (Interior) April 2, 2012

  • Cafeteria April 2, 2012

  • Courtyard Music Room Eleva4on April 2, 2012

  • Roong Administra4on Area April 2, 2012

  • Learning Center - Roong April 2, 2012

  • Classroom Area Corridor April 2, 2012

  • Typical Classroom Light Fixtures April 2, 2012

  • Student Commons April 2, 2012

  • April Major Ac4vi4es - Complete roong at AdministraCon Area - Complete exterior glazing classroom areas - ConCnue exterior glazing caf, gym - ConCnue Mech-Electrical-Plumbing-Fire Prot Rough-in - ConCnue drywall framing, installaCon, taping, painCng - Start Casework installaCon - Start ceramic Cle work - Start VCT ooring installaCon - Overall CPM schedule currently tracking per plan

  • Tioga Elementary

    School

  • March Major Ac4vi4es - Completed interior masonry CMU work - Completed roong - gymnasium - ConCnued exterior glazing classroom wings, Pre-K, Admin - ConCnued Mech/Elec/Plumb/Fire Prot overhead Rough-In - ConCnued classroom area drywall framing, installaCon, taping - ConCnued classroom area painCng - Poured contemplaCon bridge deck - ConCnued ceiling grid installaCon - Started ceramic Cle work and casework installaCon - Completed seWng of mechanical equipment

  • Contempla4on Bridge Deck March 16, 2012

  • Contempla4on Bridge Mechanical Rough-in April 2, 2012

  • Exterior Glazing Classroom Areas March 16, 2012

  • Exterior Glazing Pre-K Classrooms March 22, 2012

  • Exterior Glazing Courtyard Stair March 22, 2012

  • Temporary Walkway April 2, 2012

  • Temporary Walkway April 2, 2012

  • Gymnasium Mechanical Rough-in April 2, 2012

  • Ceramic Tile Student Bathrooms April 2, 2012

  • Ceramic Tile Sta Bathroom April 2, 2012

  • Classroom Area Entrance Ves4bule April 2, 2012

  • Typical Classroom - Interac4on Room April 2, 2012

  • Innova4on Lab April 2, 2012

  • Typical Classroom Radiant Ceiling Panels April 2, 2012

  • Typical Classrooms April 2, 2012

  • Typical Classroom Sliding Markerboard Wall Mock-Up April 2, 2012

  • April Major Ac4vi4es - Complete exterior glazing work classroom areas - ConCnue exterior glazing Admin area, Pre-K, LRC - ConCnue Mech-Electrical-Plumbing-Fire Prot Rough-in - ConCnue drywall framing, installaCon, taping - ConCnue painCng work - ConCnue ceiling grid - ConCnue classroom casework installaCon - Start seWng of light xtures - Start VCT ooring installaCon - Overall CPM schedule currently tracking ~15 days behind

  • Bensenville School District #2

    Addi4ons to

    Johnson & Tioga Elementary Schools