articel

3
Proceedings World Geothermal Congress 2010 Bali, Indonesia, 25-29 April 2010 1 Case Study: Biological Treatment of Geothermal Drilling Cuttings Frydda Sandoval 1 , J.B. Randle 2 Polaris Energy Nicaragua S.A., Ofiplaza El Retiro #723, Rotonda El Periodista, 150 m al sur, Managua, Nicaragua 1 [email protected], 2 [email protected] Keywords: Drilling cuttings, geothermal waste management. Biological treatment. ABSTRACT This paper focuses on the bioremediation technology used for the mud and the drilling cuttings obtained during the drilling of five geothermal wells in the period between August 2007 and May 2008. Polaris Energy Nicaragua S.A. is developing the San Jacinto Tizate geothermal project near to Leon, Nicaragua. The first well drilled reached a depth of 150 meters, but was abandoned after a blowout at 150 m. The other four (reinjection and production) wells were drilled successfully without problems and reached depths of between 1000 and 2000 meters. The geothermal well drilling process may negatively impact the environment, therefore it is necessary to introduce measures in order to prevent, control and mitigate the environmental impacts that they can produce. The mud and the drilling cuttings are a key environmental issue after the process of drilling a well. The biological treatment, also known as biotreatment or bioremediation, uses microorganisms like: bacteria and fungi to biologically degrade waste into nontoxic residues. The objective of biotreatment is to accelerate the natural decomposition process by adding: manures that contribute to the fertility of the waste, nutrients, aeration, moisture, and a small portion of soil. Some advantages of biological treatment are: it is relatively environmentally benign; it generates few emissions; wastes are converted into useful products; and it requires minimal transportation. In this case bioremediation was used as a final disposal step and the waste was used for establishment and growth of vetiver grass for use elsewhere in the project as erosion control planting. 1. INTRODUCTION Polaris Energy Nicaragua S.A. is developing the San Jacinto Tizate geothermal project in the Telica municipality, departament of León. The company drilled five geothermal wells in the August 2007 – May 2008 period. This paper shows the treatment technique employed to treat solid residues obtained during drilling. The liquid (water) component of the drilling mud was re-injected into drilled wells; the process described here refers to: the separation of the liquid and solid phase at the source of generation, transfer of the mud, final treatment. The following figure shows the drilling mud management scheme used in the site. . 1.Transport of sludge to the waterproof sump Drilling Mud's Management Scheme 2. The liquid phase is re-injected into the wells 3. The final disposal zone 4. The bioremediation technique Figure 1: The figure above shows the drilling mud management scheme used on site during and after the drilling process

Upload: tyan-nufutomo

Post on 27-Sep-2015

6 views

Category:

Documents


3 download

DESCRIPTION

articel

TRANSCRIPT

  • Proceedings World Geothermal Congress 2010 Bali, Indonesia, 25-29 April 2010

    1

    Case Study: Biological Treatment of Geothermal Drilling Cuttings

    Frydda Sandoval1, J.B. Randle2

    Polaris Energy Nicaragua S.A., Ofiplaza El Retiro #723, Rotonda El Periodista, 150 m al sur, Managua, Nicaragua [email protected], [email protected]

    Keywords: Drilling cuttings, geothermal waste management. Biological treatment.

    ABSTRACT

    This paper focuses on the bioremediation technology used for the mud and the drilling cuttings obtained during the drilling of five geothermal wells in the period between August 2007 and May 2008. Polaris Energy Nicaragua S.A. is developing the San Jacinto Tizate geothermal project near to Leon, Nicaragua. The first well drilled reached a depth of 150 meters, but was abandoned after a blowout at 150 m. The other four (reinjection and production) wells were drilled successfully without problems and reached depths of between 1000 and 2000 meters.

    The geothermal well drilling process may negatively impact the environment, therefore it is necessary to introduce measures in order to prevent, control and mitigate the environmental impacts that they can produce. The mud and the drilling cuttings are a key environmental issue after the process of drilling a well. The biological treatment, also known as biotreatment or bioremediation, uses microorganisms like: bacteria and fungi to biologically degrade waste into nontoxic residues. The objective of biotreatment is to accelerate the natural decomposition

    process by adding: manures that contribute to the fertility of the waste, nutrients, aeration, moisture, and a small portion of soil.

    Some advantages of biological treatment are: it is relatively environmentally benign; it generates few emissions; wastes are converted into useful products; and it requires minimal transportation. In this case bioremediation was used as a final disposal step and the waste was used for establishment and growth of vetiver grass for use elsewhere in the project as erosion control planting.

    1. INTRODUCTION

    Polaris Energy Nicaragua S.A. is developing the San Jacinto Tizate geothermal project in the Telica municipality, departament of Len. The company drilled five geothermal wells in the August 2007 May 2008 period. This paper shows the treatment technique employed to treat solid residues obtained during drilling. The liquid (water) component of the drilling mud was re-injected into drilled wells; the process described here refers to: the separation of the liquid and solid phase at the source of generation, transfer of the mud, final treatment.

    The following figure shows the drilling mud management scheme used in the site.

    .

    1.Transport of sludge to the waterproof sump

    Drilling Mud's Management Scheme

    2. The liquid phase is re-injected into the wells

    3. The final disposal zone4. The bioremediation technique

    Figure 1: The figure above shows the drilling mud management scheme used on site during and after the drilling process

  • Sandoval and Randle

    2

    2. SOLID EFLUENTS MANAGEMENTS

    Only water-based fluid is used in the project at each of the drilling stages. However, due to the nature of the drilling cuttings, these require special handling to diminish adverse impacts to the environment.

    Drilling cuttings are small rock fragments (clay, sands, lutites, etc.) that are generated due to the cutting and grinding action of the drill bit. These cuttings are transported to the surface by means of the drilling mud, which is impregnated in their surface area. Due to this impregnation, the degree of contamination will depend on the nature of the drilling fluid and the characteristics of the drilled zone. Drilling cuttings management practices referenced in this paper are Louisiana Statewide Order 29-BRegulation 29B of Louisiana, USA.

    2.1 Mud Volume

    Based on the design of the wells we had a total of 844.63 m of drilling mud to treat. The estimate volume of drilling cuttings from one well, SJ6-2, is shown by way of an example in the table below.

    Table 2. Estimated Volume of Drilling Cuttings from SJ6-2 Well.

    Well SJ6-2

    Directional Well. Large Diameter. Depth 2,000 meters Diamete

    r (Inches)

    From to (Meters)

    Depth (Meters)

    Theoretical Volume

    (m3)

    Expansion

    Factor

    Return to surface

    Expected Volume (m3)

    32 0 39 39 20.23 2 100.00% 40.46 24 39 159.5 120.5 35.16 2 100.00% 70.31

    17.5 159.5 600.5

    441 68.41 2 100.00% 136.81

    12.25 600.5 1473

    872.5 66.32 2 35.00% 46.42

    8.75 1473 2000 527 20.44 2 0.00% 0.00 Total 294.00

    The theoretical expansion factor taken refers to the capacity of minerals to absorb water and expand; their volume is greater than the theoretical but not all minerals have that property. The return to surface refers to the mud losses that take place in geological fractures; note that there is no longer total return of mud in the target zone of the well.

    2.2 Collection System

    A gabion filter was built on the projects drill pads at the exit of the mud discharge system (metal trays called shakers [temblorinas]), with the purpose of separating the liquid or aqueous phase from the solid phase. The solids that have been collected in the gabion filter, are mixed with lime to accelerate the drying process. A backhoe is then used to load the solids onto a dump truck, which takes them to the final disposal zone. The dump truck has a built-in lid to avoid any type of spill.

    The liquid phase is sent to the platforms mud sump. Once the wells target zone is found (losses are encountered), this liquid phase is injected into the well, and thereafter drilling is done with water, not mud.

    3. TREATMENT

    Land-farming is a bio-remediation technique that is used to decontaminate in situ as well as ex situ, and consists of provoking biological oxidation of contaminating agents contained in the soil, by means of stimulating natural microorganisms found in the soil (yeasts, fungi or bacteria) by the addition of fertilizers, aeration and surface irrigation.

    This is a bio-stimulation of the necessary populations we are interested in activating. The land-farming process has a series of advantages that are: low cost, does not leave residues, does not cause (if performed in controlled conditions) contamination risks.

    The effectiveness of this methodology depends on countless factors such as contaminant type and concentration, nutrients, aeration, environmental conditions, presence of inhibitors, concentration of microorganisms, etc. (EPA, 2001; Ercolli et al., 2001, Marn et al., 2006). The capacity to control and optimize all these variables mentioned above is what will determine the efficiency of the land-farming process.

    3.1 Mix Procedure

    Two basins were prepared to receive the drilling mud. The first one, the one with the smaller volume, already existed and only required the addition of a geo-membrane: the second basin, with a greater volume, was built before discharging the material. The treatment process was carried out in two phases that consist of the disposal of the mud in the small basin until it reached its volume and then in the re-location of these into the second basin.

    At this stage, work was only the first phase of the biological treatment. Mixing the mud with the materials that intervene in the bioremediation technique.

    In this manner, the mud discharged in this larger basin was mixed in proportional percentages with fresh manure, plus soil and Triple 15 fertilizer, in approximate proportions of ten full shovels of mud with 5 full shovels of manure and another 5 full shovels of soil plus fertilizer. In other occasions, the bucket of a backhoe was used and the ratio was, in that case, one bucketful of mud plus another one of soil and manure, plus fertilizer.

    The mud mix, along with the other components was aerated by overturning and was irrigated for several weeks. After two months of overturning, plots were established for sowing vetiver (rustic tropical grass, originally from India but broadly used in Asia and Africa for building live hedges to control erosion, apart from being used for fodder for beasts of burden and construction material). Fito-remediation technique: Vetiver has not been reported as accumulating contaminants, nonetheless it has been adapted to the mud mix. Also, even though it does not accumulate contaminants, it may count with positive aspects in its rhizosphere that contribute to the elimination of toxic elements.

    Likewise, with the establishment of Vetiver plots, we were able to establish a reserve bank of this plant to be used in other vulnerable areas around the project that require erosion control.

    The bioremediation technique was chosen for the treatment of the drilling mud because this is a suitable technique to be used in processes for the degradation of organic contaminants in the soil, existing microbial populations are increased and, at the same time, the activity of autochthonous microbial populations will be stimulated, the concentration of enzymes in the media will be increased, which will help to maintain the humidity and improve the characteristics of the same.

    4. RESULTS

    Up to date, two heavy metals analyses have been performed on the materials; the first one was performed in February

  • Sandoval and Randle

    3

    2008. The goal of this was to establish a baseline to determine the initial concentrations in the mix before being treated with the bioremediation technique. The second round of analyses was performed in June 2008, four months after the treatment had begun.

    Concentration limits for these types of residues have been compared with Order 29-B, which is applicable for all oil filed pools, including unlined earth pools (reservoirs) employed for drilling operations throughout the State of Louisiana, United States.

    Table 2. Limits for Waste Confinement According with Order 29-B, State of Louisiana, USA.

    Parameter Maximum concentration

    PH 6 9 Electric conductivity (mmhos/cm)