atp transfer
TRANSCRIPT
-
8/6/2019 ATP Transfer
1/15
Available to Promise (ATP)
y
y Attachments:23
y
Added by Manu Bhatia, last edited by Manu Bhatia on Mar 08, 2009 (view change)
What do we need to know?
Dates:-OrderDate
Date on which the sales order is entered. System proposes the current date by default.
Material Availability Date
The date on which the material must be available. On the material availability date, the vendor must start the activities
relevant for delivery, such as picking and packing the goods. The material availability date must be sufficiently early
enough so that the goods are prepared by the loading date.
Transportation Planning Date
We must arrange transportation by this date, so that the delivery can be sent to the customer. The date from which the
organization of goods transport must begin. The transportation planning date must be selected early enough so that the
transport is available on the loading date to load the goods.
Loading Date
Picking and packing must be completed by this date so that the goods are ready for loading.
Goods Issue Date
Goods must physically leave the shipping point by this date. The date on which the goods must leave the company to
arrive at the customer location in time.
Delivery Date
Customer should receive delivery of the goods by this date. The date on which goods are to arrive at the customer's
premises. Example: The delivery date can be the delivery date requested by the customer (desired delivery date) or the
date confirmed in the vendor's order acknowledgment or shipping confirmation (confirmed or acknowledged delivery
date).
Times:-Pick/Pack Time
Difference between the material availability date and loading date.
Transportation Lead Time
Number of days required for organizing a shipment for an item to be delivered.
Loading Time
Difference between loading date and goods issue date.
Transit Time
Number of days required for delivering an item from your company to the customer via a certain route.
How do we View Availability Situation?Run Transaction: CO09
-
8/6/2019 ATP Transfer
2/15
Enter Plant & Checking Rule, against which the Availability is to be checked. For Sales Order Checking Rule = A,
Delivery = B, Back Order = BO
In this screen, we can see:
y Availability Checking Group (Avail Check): 02
y Check Rule : A
y End Lead Time Refers to the end of Replenishment Lead Time. If that is not included in the Configuration, then this field
is not visible.
y Totals Display:** Receipts = Sum of all +ve Quantities in Rec./Reqd qty Column
(Leave out the last row, MRP Element 001, since it is a total)
These are all the Planned Incoming Movements
o Issues = Sum of all -ve Quantities in Rec./Reqd qty Column
These are all the Planned Outgoing Movements
o Confirmed issues = Sum of all (+ve) Quantities in Confirmed Column
These are the confirmations against ATP.
When is Availability Check Triggered?While creating a Sales Order, Production Order, Delivery, etc. Below is a screen from Sales Order. At the bottom is a
button for Check Material Availability. Also while creating the order, if the Availability situation cannot meet the
-
8/6/2019 ATP Transfer
3/15
requested delivery date, the system goes to Availability screen automatically. (Discussed later)
Run Transaction: VA01
How we arrive at a Confirmed Delivery Date?Below is the logic the system uses to check availability:
y Using the Scheduling data from Delivery & Transportation Scheduling, the system does the backward calculation from
the Requested Delivery Date. This is used to arrive at Material Availability Date.
y On the Material Availability Date, system checks the Available Qty, as seen in CO09 in column Cum. ATP Qty. If theAvailable Qty is > than Required Qty, Requested Delivery Date is confirmed. Otherwise,
y System moves into the future till it finds the required Available Qty. The new date is then the new Material Availability
Date.
y On getting the confirmed Material Availability Date, system does the Forward Scheduling to arrive at a Confirmed
Delivery date.
Backwards Scheduling
Control of Availability Check
-
8/6/2019 ATP Transfer
4/15
Forward Scheduling
-
8/6/2019 ATP Transfer
5/15
Result of Availability Check: Some Sample Scenarios
-
8/6/2019 ATP Transfer
6/15
Above is the Availability Screen as seen in Sales Order. It has following Buttons:
One-time delivery
In the results of Availability, we have 3 options to choose from. This is Case 1, when we can confirm the Customer's
Requested delivery Date. The details of this are visible in the first sub screen below.
Complete dlv.
This is Case 2, when we can confirm the Customer's Requested complete delivery at a future Date. The details of this
are visible in the second sub screen below.
Delivery proposal
-
8/6/2019 ATP Transfer
7/15
This is Case 3, when we can confirm the Customer's Requested delivery in partial quantities at future dates. The details
of this are visible in the third sub screen below.
Continue
If we select one of the above options, the same gets saved in the ATP results. Otherwise, we can sele ct this button. In
that case, system leaves the ATP screen without saving the ATP results.
Case: Confirmation on Requested Delivery Date
-
8/6/2019 ATP Transfer
8/15
Case: Confirmation afterRequested Delivery Date (CompleteDelivery)
Case: Confirmation afterRequested Delivery Date (Partial Delivery)
-
8/6/2019 ATP Transfer
9/15
See the screens below corresponding to this situation.
The first screen shows the Availability (CO09) Overview. We have an incoming PO on 19 Jan.
!image034.jpg!In the second screen
-
8/6/2019 ATP Transfer
10/15
We have created a SO (VA01) on 09 Feb, with requested Delivery date for 09 Feb.
Now we change the Availability situation, by changing the PO Date to 12 Feb. See the screensbelow corresponding to this situation.
The first screen shows the Availability (CO09) Overview. We have an incoming PO on 12 Feb. See the new Cum ATP
qty. date wise accordingly.
!image038.jpg!In the second screen
We have created a SO on 09 Feb, with requested Delivery date for 09 Feb.
See that the Delivery got staggered according to the new Availability situation.
Case: Confirmation afterRequested Delivery Date (Replenishment Lead Time)
-
8/6/2019 ATP Transfer
11/15
In the screens below, we have simulated the RLT.
In the first scenario RLT is not activated, see below: 'Check without RLT'. The system considers only the confirmed
inward movements. So out of 500 only 21 is confirmed.
See IMG Guide > SD > BF > AC & TOR > AC > AC with ATP > Control of Availability Check
-
8/6/2019 ATP Transfer
12/15
See VA01
In the second scenario RLT is activated, but corresponding data in material master is not maintained. Material is
procured In-House (E), but In-house Production time (1st
screenshot) & RLT (2nd
screenshot) are not maintained. The
system assumes both these times as Zero. So, complete 500 are confirmed immediately. See MM01
-
8/6/2019 ATP Transfer
13/15
In the third scenario RLT is activated, corresponding data in material master is maintained. Material is procured In-
House (E), In-house Production time (10 days) & RLT (not maintained). The system confirms 21 on basis of incoming
material. Rest 479 is confirmed after 14 days. This is because 10 working days for in-house production + 4 holidays
(Sat-Sun).
-
8/6/2019 ATP Transfer
14/15
In the fourth scenario RLT is activated, corresponding data in material master is maintained. Material is procured In-
House (E), In-house Production time (10 days) & RLT (20 days). The system confirms 21 on basis of incoming material.
Rest 479 is confirmed after 14 days. This is because 20 working days for in-house production + 8 holidays (Sat-Sun).
-
8/6/2019 ATP Transfer
15/15
What Configuration & Data do we need?Controlling Elements:-
Requirements Type
Requirements Class
Schedule Line Category
Delivery Item Category
Checking Group
Checking Rule
Scope of Check
Strategy Group
Partial Delivery Agreement
Replenishment Lead Time
Material MasterData:-
MRP 1 > MRP Group
MRP 2 > Planned Delivery Time
MRP 2 > GR Processing Time
MRP 3 > Checking Group for Availability Check
MRP 3 > Strategy Group
MRP 3 > Total Replenishment Lead Time
Scheduling Data:-
Transit Time
Loading Time
Pick/Pack TimeTransportation Planning Lead Time