baart sarkar government of india kond`iya ivavut p ... · kond`iya ivavut p`aiqakrna ......

19
Baart sarkar Government of India kond`Iya ivaVut p`aiQakrNa Central Electricity Authority piScama xao~Iya ivaVut saimait Western Regional Power Committee ef -3, emaAayaDIsaI xao~, AMQaorI (pUva- ), mauMba[- - 400 093 F-3, MIDC Area, Andheri (East), Mumbai - 400 093 Aa[- esa Aao : 9001-2008 ISO: 9001-2008 dUrBaaYa Phone: 022- 28221681; 28250004; 28200195; fO@sa Fax : 022 – 28370193 Website : www.wrpc.gov .in E-mail : [email protected] No. : WRPC/Protection/SPS/2014/4219 Date: 16.05.2014 To As per mailing list Sub : Minutes of Meeting held on 29.04.2014 to discuss the suggested revisions in System Protection Schemes (SPS) for secured operation of the All India grid. Sir, The minutes of meeting held on 29.04.2014 at Mumbai, to discuss the suggested revisions in System Protection Schemes (SPS) for secured operation of the All India grid, is enclosed herewith for information and necessary action please. The MoM is available at our web site www.wrpc.gov.in. Yours’ faithfully, Encl. : As above sd/- ( O. P. Singh) Superintending Engineer (Protection)

Upload: dinhanh

Post on 04-Jun-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Baart sarkarGovernment of India kond`Iya ivaVut p`aiQakrNa

Central Electricity Authority piScama xao~Iya ivaVut saimait

Western Regional Power Committee ef -3, emaAayaDIsaI xao~, AMQaorI (pUva-), mauMba[- - 400 093

F-3, MIDC Area, Andheri (East), Mumbai - 400 093

Aa[- esa Aao : 9001-2008

ISO: 9001-2008

dUrBaaYa Phone: 022- 28221681; 28250004; 28200195; fO@sa Fax : 022 – 28370193 Website : www.wrpc.gov.in E-mail : [email protected]

No. : WRPC/Protection/SPS/2014/4219 Date: 16.05.2014 To

As per mailing list

Sub : Minutes of Meeting held on 29.04.2014 to discuss the suggested revisions in System Protection Schemes (SPS) for secured operation of the All India grid.

Sir, The minutes of meeting held on 29.04.2014 at Mumbai, to discuss the suggested revisions in

System Protection Schemes (SPS) for secured operation of the All India grid, is enclosed herewith for information and necessary action please. The MoM is available at our web site www.wrpc.gov.in.

Yours’ faithfully, Encl. : As above

sd/-

( O. P. Singh) Superintending Engineer (Protection)

Page 2: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Mailing List

1) CE (LD), MSETCL, Kalwa.Fax-27601769/65 2) CE (STU), MSETCL, Bandra. Fax No. 022 26598587 3) CE (W), MSEGCL, 3rd floor, Prakash gad, Mumbai 4) CE (LD), GETCO, Baroda. 0265-2352019, 2356469 5) CE (LD), MPPTCL, Jabalpur. Fax - 0761- 2664343 / 2282632. 6) CE (LD), CSPTCL, Raipur. Fax-0771 – 2574174 7) ED, WR-I, N.T.P.C., Mumbai 022-28259364 8) ED, WR-II, NTPC, Raipur 0771-2259335 9) ED, WRTS-I, PGCIL, Nagpur. 0712-2641471 10)ED, WRTS-II, PGCIL, Baroda 0265-2488564 11) GM, WRLDC, Mumbai Fax: 022- 28235434 12)ED, JPL, Raigarh. Fax. No. Fax: 07767-281995, 281993. 13)Chief Operating Officer, APL, Bodakdev, Ahmedabad. Fax: 079 - 2555 717 14)CEO, IEPL, Nagpur Fax: 0712 - 2295989 15) Project Head, KSK Mahanadi Power Company Limited, Bilaspur. Fax: 040- 23559930 16) Sr. Vice President (Power), DB Power, Nariman Point, Mumbai. Fax: 022-39306008 17)ED, NLDC, Katwaria Sarai, New Delhi Fax: 011-26536901/26524525 18) GM, BALCO, Korba Fax: 07759-241053 19) GM, KWPCL, Raigarh, Fax: 07762 – 251514 20) GM, Lanco Amarkantak Power Limited, New Delhi. Fax: 0124 - 4741024 21) GM, NSPCL, Bhilai. Fax: 0788 – 2282437

Page 3: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Minutes of the meeting held on 29.4.14 to discuss the suggested revisions in System Protection Schemes(SPS) for secured operation of the All India Grid 

  

A meeting was held on 29.4.14 at WRLDC, Mumbai to discuss the revisions proposed by NLDC in the System Protection Scheme  (SPS)  related with  synchronization  of  Southern  grid with NEW  grid  and  its  implementation  process.   NLDC communication dt 11.4.14  is enclosed as Annex‐I.   The  list of participants  is enclosed  in Annex‐II.   Following are  the discussion proceedings.  

Member Secretary, WRPC welcomed all participants to the meeting. In his opening remarks, he stated that the objective of  this meeting  is  to  deliberate  and  implement  the  revised  schemes  suggested  by  NLDC  based  on  the  operational experience  of  the  All  India  grid  post  synchronization      of  NEW  grid  with  Southern  grid  on  31.12.13.  For  smooth synchronization of Southern grid with NEW grid several System Protection Schemes (SPS) were formulated by NLDC and implemented  by  all  concerned  in Western  Region  before  synchronization.    It  was  also  decided  that  based  on  the experience of operation of All India grid the schemes would be reviewed.   

He mentioned that the concerns raised by participating generating status regarding frequent operation of SPS leading to generation loss had been taken up with NLDC and CEA and also discussed in the WRPC forum. The revisions have been suggested considering more number of generators in the W3 area so as to provide required relief during SPS operation. He informed that NLDC have has taken cognizance of the WR Concerns and in view of the operational experience with SR they have suggested revisions which have increased the number of utilities taking part and reducing the relief also for individual generating utilities.  

He requested WRLDC to briefly summarize the SPS operations in the last 4 months and also elaborate the SPS proposed by NLDC.  

GM, WRLDC stated that   though oscillations of 0.2 Hz could be observed in Raichur‐ Sholapur in the event of tripping of units  in  Southern  Grid,  these  were  getting  damped  also.    The  first  swing  was  generally  observed  to  be  of  higher magnitude (115‐125% of the lost generation) and subsequently the oscillations were getting damped.  It was stated that the proposed scheme suggests a time delay of 2.5sec, so as avoid SPS operation at the first half cycle of oscillation.    WRLDC made a presentation on the performance of the SPS during the last 3 months along with  the suggested revisions as proposed by NLDC.    It has been observed  that SPS‐1, 2 and SPS‐5 have operated  frequently during  the  last  three months while the others have not operated. Details of SPS operation is summarised below:‐  Period  SPS 

Name SPS Criteria  No. of 

operation Reason 

31.12.13‐31.3.14 

SPS‐1  Sholapur‐Raichur>800MW 

29  Unit tripping in SR/ Demand ramp up in SR 

  SPS‐2  dP/dt of Sholapur‐Raichur>400MW/sec 

13  ‐do‐ 

  SPS‐5  Wardha‐Parli >750MW  27  Unit tripping in SR/ demand ramp up in SR or Maharashtra 

  The following issues  were also  emphasized for reliable operation of SPS:‐ 

1. Improving reliability of SPS through redundant measurements, logic, communication path and end terminals. 2. Use of metering core of CTs and PTs for analog measurements used in the SPS logic, particularly where the same 

is based on steady state flows crossing a particular value. 3. Need to cover more generators in the NEW grid so that adequate relief is available as in many instances, the 

antecedent generation in many of the generators selected remain already very low. 4. Wiring of each SPS operation to the local substation Event Logger. 5. Triggering of each SPS action and the receipt of signal at each point to be recorded in SLDC/RLDC/NLDC SCADA 6. Prompt submission of data to RLDCs regarding SPS action in the prescribed format. 

Page 4: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

7. Each instance of inadequate relief through SPS to be thoroughly analysed and remedial actions taken so as to have increased confidence on the SPS reliability 

 The proposed revisions were agreed by members and the revised settings along with backing down quantum by WR generators is given in detail in Table‐I.   A  detailed  discussion was  held  on  SPS  setting  of Wardha  Parli  400kV D/C  corridor which  is  heavily  loaded  post commissioning  of  number  of  generators  within  central  part  of  Western  Grid.  Representative  of  Maharashtra stressed the need of transmission system at Sholapur. It was stated that back end network including following lines be completed at the earliest. 1. 765kV Wardha‐Aurangabad D/C 2.765kV Pune‐ Sholapur(PG) D/C 3. 765kV Aurangabad‐Sholapur  The  representative  from  GETCO  SLDC  also  supported  the  need  for  completion  of  the  associated  transmission network as above.   WRLDC  has  pointed  out  that  the  SPS  for  Wardha‐Parli  S/C  loading>750MW  has  operated  10  times  due  to Maharashtra load ramp up  and 9 times due to SR load ramp up in the month of March’14. It has been observed that this SPS operates  irrespective of  increase  in flow of Sholapur‐Raichur  line and has operated even when power was being imported from Raichur(SR) to Sholapur(WR).  Further during outage of 400kV Akola‐Aurangabad D/C from 25‐27th April’14, there was very frequent operation of this SPS and as a precautionary measure, the SPS setting of 400kV Wardha‐Parli   S/C  flow was  increased  to 800MW  to avoid  frequent operation of SPS beside safe operation of  the units.     Since Wardha‐Parli  loading  is sensitive to Western Maharashtra  load as well as SR  load,  it was emphasised that    load  shedding  in  Western  Maharashtra    is  also  essential.    SLDC,  MSETCL  expressed  their  concerns  for implementing load shedding and hence assured to immediately pick up generation at Koyna whenever the flow on Wardha  flowgate  crossed  2480MW.   MSETCL  also  agreed  to  implement  generation  reduction  in  the  identified generators in Maharashtra as per the revised SPS.  Further, disarming of SPS by NTPC,Mauda on its own and not participating in automatic generation reduction in case of  SPS  triggering  due  to Wardha‐Parli  overloading   was  viewed  seriously  and MS,WRPC    informed  that  this  is  a serious violation of the decision of WRPC and all the SPS actions have to be automatic.  NTPC Mauda agreed to arm the SPS for automatic generation reduction. Power Grid  expressed  that  they would  require  at  least  a month  time  as  the  revised  scheme  involve  process  of hardwire  procurement.      In  view  of  high  summer  demand    in Maharashtra  vis‐a‐vis  anticipated  frequent  SPS  in Wardha Parli ,it was also decided to continue with the changed SPS setting of 800MW for Wardha‐Parli S/C loading till the revised scheme is implemented. It was also suggested that revision as regards to introduction of time delay setting of 2.5 sec could be  implemented  immediately,  till other  revision such as  inclusion of more generators are implemented. 

 Summarily  it was decided  that,  all  control  actions by  generators  in Western Region   under  various  cases of  SPS would  be backing down by 800MW in proportion to their capacity under commercial operation .  POWERGRID was requested to extend communication signals   for  implementation of the revised schemes wherever required. It was decided  that  the  whole  action  for  implementing  revised  SPS  has  to  be  completed  within  one month  and  any difficulty/delay faced by concerned agency may be addressed to WRPC for further action.  Meeting ended with vote of thanks to chair and participants.        

Page 5: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Table‐I  

Revisions in System Protection Scheme(SPS)‐ NEW grid‐SR synchronisation  SPS Name  Triggering Criteria  Load shedding by 

SR/Backing down in WR in MW 

Contribution by generators 

SPS‐1: Sholapur Raichur Power flow 

i) When flow on 765kV Sholapur‐Raichur S/C line crosses  1000 MW and remains above  this value for 2.5 sec in the direction Sholapur to Raichur. ii) Power flow crosses 1500 MW in direction Sholapur to Raichur (instantaneous) 

500/800   JPL‐150MW, JPL extn‐150MW, KSK‐100MW, LANCO‐100MW, DBPOWER‐100MW KWPCL‐100MW BALCO‐50MW NSPCL‐50MW 

SPS‐2: Rate of change of power flow in Sholapur‐ Raichur>400MW/sec 

Temporarily blocked  NA  NA 

SPS‐3: Loss of Sholapur‐ Raichur line carrying 800 MW towards SR 

Loss of 800MW import by SR due to tripping of 765kV Sholapur‐Raichur line  

500/Nil  Load Generation balance in NEW grid to be achieved by  governor action of generators 

SPS‐4: 400kV Raipur‐ Wardha Power flow 

) Antecedent flow on either of the 400kV Raipur‐Wardha line crossing 850 MW and remaining above this value for 2.5 sec. OR ii) tripping of any circuit when the flow is greater than  700 MW (instantaneous)  

800/800  Same as for SPS‐1  

SPS‐5: 400kV Wardha‐ Parli Power Flow 

i)Flow crossing 850 MW on each circuit with a time delay of 2.5 sec           OR ii) tripping of S/C carrying 750 MW (instantaneous) sensed at Wardha end.  

800/800+  generation pick up at Koyna immediately. 

Tiroda‐200MW, Mauda‐100MW, Koradi‐70MW, Khaperkhada‐150MW, Chandrapur‐250MW Indiabulls‐30MW   

SPS Name  Triggering Criteria  Load shedding by SR/Backing down in WR in MW 

Contribution by generators 

SPS‐6: 400kV Parli ‐Sholapur Power Flow 

i) Flow crossing  850 MW on each circuit with a time delay of 2.5 sec OR 

800/800  Same as for SPS‐1 

Page 6: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

ii) tripping of any circuit when flow is > than 600 MW sensed at Sholapur.(instantaneous)  

SPS‐7: 765kV Raichur‐ Sholapur line current exceeding 800Amp (1000MW) in either direction 

Current exceeding 800Amp (1000MW )in Sholapur to Raichur  direction. Reverse direction ie., SR to NEW grid  may be blocked.  

Tripping of 765kV Sholapur‐Raichur line with 10 sec delay.  

 

SPS‐8: 400kV Hiriyur Neelmangala Power Flow 

Tripping of one line and other line loading going up to 850 MW (instantaneous) 

500/800  Same as SPS‐1 

SPS‐9: Gooty Neelmangala/Gooty Somanahalli  Power Flow 

Tripping of one of the 400kV Gooty‐ Nelamangala SC line or 400kV Gooty‐Somanahalli SC line and Flow on other line > 850 MW (instantaneous)  

500/800  Same as SPS‐1 

SPS‐10: Talcher‐Kolar SPS 

In case of single pole or bipole outage or blocking of Talcher‐kolar HVDC  sensed at Talcher HVDC terminal.  

LS in SR‐600MW Gen.B/d by ER‐600MW 

Sterlite,GMR,JITPL  

***********

Page 7: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe
Page 8: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe
Page 9: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Page 1 of 10

Revisions in System Protection Schemes(SPS)-NEW & SR grid synchronisation

(part of NLDC communication NLDC/SR_synch_SPS/ dated 11th April 2014)

S. no 

Triggering criteria for SPS(implemented) SPS  action implemented Proposed revision in SPS Remarks

1  765kV Sholapur‐Raichur flow > 800 MW: SPS‐1  Total flow on 765 kV Sholapur‐Raichur 2 x 765  kV  S/C  lines  crossing  a  preset  value, say  800  MW  in  Sholapur  to  Raichur direction  sensed  both  at  Sholapur  and Raichur.  

Western Region  500MW Gen Back down JPL ‐ 350MW KSK ‐  150MW DB power=0  Southern Region 500 MW Load Shedding Tamilnadu‐            146MW Kerala ‐                   125MW Karnataka‐             104MW Andhra Pradesh    125MW 

Suggestion:  SPS  should trigger when   flow on 765 kV Sholapur‐Raichur  S/C  line crosses  1000  MW  and remains  above  1000 MW  for 2.5 seconds.  It  should  also  act instantaneously  when  the power  flow  crosses  1500 MW.  Western Region  800 MW Gen Back down More  generators  such  as Lanco  Amarkantak,  KWPCL, BALCO,  JPL  Ext,  NSPCL  etc. must  be  covered  in W3  area so  that  800  MW  relief  is available under all conditions. Southern Region  No Change 

 Rationale:  SPS  should  not operate  for  the  first  swing arising  out  of  generating  unit trip  in  Southern  Region  and antecedent  flows  from Sholapur  to  Raichur  is  less than,  say  400‐500  MW, towards  Southern  Region.  It has  been  observed  from synchrophasor  data  that  the first  spike  is  typically  115‐125% of the generation  lost  in Southern  Region  and oscillations  of  the  order  of 0.20 Hz are observed.  Further,  one  argument  cited by  generators  towards inadequate  relief  is  the  low antecedent  generation  on these units. As this would be a highly  probable  scenario,  SPS wiring may be done  for more quantum  so  that  800  MW 

Page 10: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Page 2 of 10

S. no 

Triggering criteria for SPS(implemented) SPS  action implemented Proposed revision in SPS Remarks

relief is always available.   

 2  Rate of change of flow >400 MW/Sec: SPS‐2 Rate  of  change  of  flow  crossing  400 MW/second  in  the  Sholapur  to  Raichur direction.  

   

Same as above 

Suggestion:  Pending  a clarification  by  POWERGRID as  to  how  dP/dt  is  actually computed  at  field  level,  this setting  may  be  blocked temporarily.  

The  logic  for computing dP/dt needs  to  be  clarified  by PowerGrid  as  it  is  observed from  synchrophasor  data,  it appears  to  have  been activated at lower values also.  

3  SPS for Loss of 800 MW import by SR: SPS‐3 Loss of import on 765 kV Sholapur‐Raichur by more  than 800 MW due  to  tripping of these lines. 

   

Same as above 

 Suggestion:  In case of  loss of import  on  765  kV  Sholapur‐Raichur  by  more  than  800 MW due  to  tripping of  these lines,  only  load  shedding should  occur  in  SR.  Tripping or  backing  down  of generators may therefore be blocked.   

 Rationale:  Load  Generation balance  in  NEW  grid may  be taken care by governor action. In  SR,  to  arrest  a  sharp frequency  fall,  load  shedding through SPS is required.  

Page 11: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Page 3 of 10

S. no 

Triggering criteria for SPS(implemented) SPS  action implemented Proposed revision in SPS Remarks

4  400 kV Raipur‐Wardha :   SPS‐4

Flow on 400 kV Raipur‐Wardha any circuit crossing  800  MW  sensed  at  Raipur  OR tripping  of  any  one  circuit  of  400  kV Raipur‐Wardha  carrying  650  MW  or above. 

Western Region  800MW Gen Back down JPL ‐ 600MW KSK ‐  200MW DB Power – 0 MW  Southern Region  800MW Load Shedding (Kudankulam group) Tamilnadu‐            290MW Kerala ‐                   135MW Karnataka‐             195MW Andhra Pradesh    230MW 

Suggestion:   Triggering  point  may  be modified as  ‘antecedent  flow on  either  of  the  400  kV Raipur‐Wardha  circuit crossing  850  MW  and remaining  above  this  value for 2.5 seconds OR tripping of any  circuit  when  the antecedent  flow  is  greater than 700 MW.  Western Region  800 MW Gen Back down More  generators  such  as Lanco  Amarkantak,  KWPCL, BALCO,  JPL  Ext,  NSPCL  etc. must  be  covered  in W3  area so  that  800  MW  relief  is available under all conditions.  Southern Region  No change  

  Rationale:  To  take  care  that there  is  no  SPS  action  in  the first  spike  following  a  large event.  Further,  one  argument  cited by  generators  towards inadequate  relief  is  the  low antecedent  generation  on these units. As this would be a highly  probable  scenario,  SPS wiring may be done  for more quantum  so  that  800  MW relief is always available.  

Page 12: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Page 4 of 10

S. no 

Triggering criteria for SPS(implemented) SPS  action implemented Proposed revision in SPS Remarks

5  400kV Wardha‐Parli  line  : SPS‐5 

Flow  on  400  kV Wardha‐Parli  any  circuit crossing  750 MW  or  tripping  of  any  one circuit  of  400  kV  Wardha‐Parli  section carrying  600  MW  or  above.  Sensed  at Wardha. 

Western Region APL Tiroda ‐ 600MW NTPC Mauda ‐  200MW IEPL – 0 MW   Southern Region  800 MW Load Shedding (Kudankulam group) Tamilnadu‐            290MW Kerala ‐                   135MW Karnataka‐             195MW Andhra Pradesh    230MW 

Suggestion:  The  triggering  point  for steady  state  loading may  be revised  to  the  flow  crossing 850 MW  each  circuit  with  a delay  of  2.5  seconds  OR tripping  of  any  circuit  when the  antecedent  flow  is greater  than  750  MW.  Flow may  be  sensed  at  Wardha end.  Western Region  800 MW Gen Back down More  generators  such  as Koradi,  Khaperkheda, Chandrapur,  Indiabulls  need to  be  covered  so  that  800 MW relief is always available.  250 MW load shedding in Maharashtra west of Sholapur.  Southern Region  No change; however position can  be  reviewed  once 

 Rationale:  Time  delay required  to  take  care  of  the first  spike.  Further,  Wardha‐Parli  line despite having Quad Moose  conductor  is  334  kms. long  and  any  tripping  of  one line when the antecedent flow is more than 750 MW leads to the  angular  separation between  Wardha  and  Parli crossing  30  degrees.  Without automatic  corrective  action, oscillations will not subside as per simulations.  The second unit at Mauda and the  fourth unit at Tiroda have been  synchronized  and declared  under  COD  recently. These  had  not  been  assumed in the initial studies.   SLDC  Maharashtra  shall regulate  load/generation  in Maharashtra  whenever  total power  flow  on  Wardha flowgate  (400  kV  Wardha‐Akola  D/C  +  400  kV Wardha‐

Page 13: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Page 5 of 10

S. no 

Triggering criteria for SPS(implemented) SPS  action implemented Proposed revision in SPS Remarks

Maharashtra  implements 250  MW  load  shedding suggested above  

Parli D/C) crosses 2480 MW.  Power  order  on  HVDC Chandrapur‐Padghe  bipole shall also be maximized.  Further,  to  ensure  that  800 MW reduction in generation is achieved,  more  generators need to be covered  in eastern Maharashtra.  NTPC  Mauda relief  is  generally  negligible and  the  station  schedule  is also generally low.   The loading on Wardha‐Parli is sensitive  to  both  western Maharashtra  load  as  well  as Southern  Region  load;  hence load  shedding  is also  required to  be  done  in  western Maharashtra.  

6  400 kV Parli‐Sholapur : SPS‐6 

 Antecedent  flow  on  any  circuit  crossing 800 MW or  tripping of any one  circuit of Parli‐Sholapur carrying 600 MW or above. 

Load shedding by Maharashtra to be implemented.  300 MW generation pick up at Koyna  

Suggestion:  The  triggering  point  for steady  state  loading may  be revised  to  the  flow  crossing 800 MW  each  circuit  with  a delay  of  2.5  seconds  OR 

Rationale:  2.5  seconds  delay to  take  care  of  the  first  spike not leading to SPS action.   

Page 14: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Page 6 of 10

S. no 

Triggering criteria for SPS(implemented) SPS  action implemented Proposed revision in SPS Remarks

Sensed at Sholapur. 

800 MW Gen Back down JPL ‐ 600MW KSK ‐  200MW DB Power – 0 MW  Southern Region 800 MW Load Shedding (Kudankulam group) Tamilnadu‐            290MW Kerala ‐                   135MW Karnataka‐             195MW Andhra Pradesh    230MW 

tripping  of  any  circuit  when the  antecedent  flow  is greater  than  600  MW.  Flow may  be  sensed  at  Sholapur end.  Western Region 800 MW Gen Back down More  generators  such  as Lanco  Amarkantak,  KWPCL, BALCO,  JPL  Ext,  NSPCL  etc. must  be  covered  in W3  area so  that  800  MW  relief  is available under all conditions. 250  MW  load  shedding  in Maharashtra  west  of Sholapur.   Southern Region No change; however position can  be  reviewed  once Maharashtra  implements 250  MW  load  shedding suggested above 

 

Page 15: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Page 7 of 10

S. no 

Triggering criteria for SPS(implemented) SPS  action implemented Proposed revision in SPS Remarks

7  765kV  Raichur‐Sholapur  line current  exceeding  800  Amp (1000 MW  on  either  direction): SPS‐7 

 

Tripping  of  765kV  Raichur‐Sholapur  line  with  10  seconds delay. 

No  change  suggested  for  the Sholapur  to Raichur direction which is retained at 1000 MW with ten (10) seconds delay.  Ordinarily SPS‐1 action should prevent  this  situation  from arising. In the eventuality that SPS‐1  does  not  act  and  this SPS  operates,  SPS‐3  above should act.  Tripping  of  765  kV  Sholapur Raichur  on  SPS  due  to  the >1000  MW  flowing  in  the reverse  direction  i.e.,  SR  to NEW grid may be blocked.  This  setting  would  be reviewed  with reinforcements  in  the upstream  and  downstream network.  

Rationale:   This  setting  was  decided considering  that  SR  could safely withstand the 1000 MW loss of import or export.  Sustained  operation  above 1000 MW  in  the  Sholapur  to Raichur  direction  would indicate  that  the  upstream and  downstream  systems  are stressed  and  therefore  SR system needs  to be separated through  tripping  of  765  kV Sholapur‐Raichur.  For  the  reverse  direction,  the possibility  of  S1  and  S2  areas getting  separated  due  to  a contingency  is  credible.  There would be a sudden increase in flow from Raichur to Sholapur. Tripping  765  kV  Sholapur‐Raichur  under  these circumstances  may  further worsen  the  situation  in  S1. Hence  this  is  proposed  to  be blocked. 

Page 16: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Page 8 of 10

S. no 

Triggering criteria for SPS(implemented) SPS  action implemented Proposed revision in SPS Remarks

 

8  400  kV  Hiriyur‐Neelamangala:SPS‐8 Tripping  of  one  of  the  400kV  Hiriyur‐ Neelamangala DC  line and  Flow on other line > 850 MW  

Western Region  500 MW Gen Back down JPL ‐ 350MW KSK ‐  150MW DB power=0  Southern Region  500 MW Load Shedding Tamilnadu‐            146MW Kerala ‐                   125MW Karnataka‐             104MW Andhra Pradesh    125MW  

 Western Region  800 MW Gen Back down More  generators  such  as Lanco  Amarkantak,  KWPCL, BALCO,  JPL  Ext,  NSPCL  etc. must  be  covered  in W3  area so  that  800  MW  relief  is available under all conditions.. Southern Region  No change 

Rationale: One argument cited by  generators  towards inadequate  relief  is  the  low antecedent  generation  on these units. As this would be a highly  probable  scenario,  SPS wiring may be done  for more quantum  so  that  800  MW relief is always available.  

 9 

400kV  Gooty‐Neelmangala:SPS‐9  Tripping  of  one  of  the  400kV  Gooty‐Nelamangala  SC  line  or  400kV  Gooty‐ 

Western Region  500MW Gen Back down JPL ‐ 350MW KSK ‐  150MW Southern Region  

 Western Region  800 MW Gen Back down More  generators  such  as Lanco  Amarkantak,  KWPCL, BALCO,  JPL  Ext,  NSPCL  etc. 

Rationale: One argument cited by  generators  towards inadequate  relief  is  the  low antecedent  generation  on these units. As this would be a highly  probable  scenario,  SPS wiring may be done  for more 

Page 17: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Page 9 of 10

S. no 

Triggering criteria for SPS(implemented) SPS  action implemented Proposed revision in SPS Remarks

Somanahalli  SC  line  and  Flow  on  other line > 850 MW  

500MW Load Shedding Tamilnadu‐            146MW Kerala ‐                   125MW Karnataka‐             104MW Andhra Pradesh    125MW 

must  be  covered  in W3  area so  that  800  MW  relief  is available under all conditions.. Southern Region  No change 

quantum  so  that  800  MW relief is always available.  

10  Talcher‐Kolar SPS‐10 In case of single pole or bipole outage or blocking of Talcher‐Kolar HVDC sensed at Talcher HVDC terminal,  

Trip signal be extended to nearby generators  such  as  Sterlite, GMR, JITPL  and  Talcher  Stage‐I  for  gen reduction of 600 MW  so  that  the injection  into  NEW  grid  is restricted to 450 MW. Eastern Region:‐ Sterlite  = 350MW GMR      = 250MW JITPL      = 0  This would be in addition to SPS 1000 already in operation at Talcher‐II. 

 Eastern region:  JITPL  unit  also  needs  to  be connected.  Further  relief from GMR was  not  available on  25th  March  2014  when one  pole  of  Talcher‐Kolar HVDC  bipole  tripped;  so  the unit  selection  logic  at  GMR needs to checked.   600  MW  relief  must  come from  Sterlite, GMR  and  JITPL under all conditions.     

Rationale: Even after Southern region  is  synchronized,  the system  is  still not planned  for single  pole  of  Talcher‐Kolar HVDC bipole going out. 

Page 18: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Page 10 of 10

S. no 

Triggering criteria for SPS(implemented) SPS  action implemented Proposed revision in SPS Remarks

11  Kudankulam : SPS‐11 SPS  of  Kudankulam  Unit  and  SPS  of Talcher‐Kolar  Pole  trip  at  Kolar  end  are having  the  same  group  of  loads  for shedding  and  these  needs  to  be segregated  at  the  earliest  by  identifying separate loads for Kudankulam SPS.  

    

 

Note: SPS-1, 2 and SPS-5 have operated frequently during the last three months while the others have either not operated or operated infrequently. Notwithstanding the above revisions suggested, the following are also important. o Improving reliability of SPS through redundant measurements, logic, communication path and end terminals. o Use of metering core of CTs and PTs for analog measurements used in the SPS logic, particularly where the same is based on

steady state flows crossing a particular value. o Need to cover more generators in the NEW grid so that adequate relief is available as in many instances, the antecedent

generation in many of the generators selected is already very low. o Wiring of each SPS operation to the local substation Event Logger. o Triggering of each SPS action and the receipt of signal at each point to be recorded in SLDC/RLDC/NLDC SCADA o Prompt submission of data to RLDCs regarding SPS action in the prescribed format. o Each instance of inadequate relief through SPS to be thoroughly analysed and remedial actions taken so as to have increased

confidence on the SPS reliability.

Page 19: Baart sarkar Government of India kond`Iya ivaVut p ... · kond`Iya ivaVut p`aiQakrNa ... Wardha‐Parli S/C flow was increased to 800MW to avoid frequent operation of SPS beside safe

Annexure-II

Sl.No. Organisation, Name & Designation E-mail Mobile

I WRPC1 Shri S.D. Taksande, M.S. [email protected] 98208783842 Shri Satyanarayan S. [email protected] 92233999383 Shri M.M. Dhakate, S.E. [email protected] 81087877784 Shri P.D. Lone [email protected] 98676228235 Shri D.N. Gawali [email protected] 99306667656 Shri Shiva Suman [email protected] 9869910968

II MSETCL / MSEDCL/MahaGenco7 Shri D.K. Rokade, S.E. [email protected] 91678315518 Shri N.R. Sonkavday, S.E. [email protected] 99877839249 Shri V.D. Pande [email protected] 9820741941

III MPPTCL / MPPGCL10 Shri R.C. Sharma, E.E. [email protected] 9425804970

IV GETCO / GSLDC/ GSECL11 Shri B.B. Mehta, C.E. [email protected] 9879200736

V WRLDC / POWERGRID12 Shri P. Mukhopadhyay, G.M. [email protected] 986943807313 Shri V.K. Shrivastav, A.G.M. [email protected] 986945022114 Smt. Pushpa Seshadri, C.M. [email protected] 986940448215 Smt. Sachala Mishra, C.M. [email protected] 986945022316 Shri Vivek Pandey [email protected] Shri V.B. Bhandarkar, Mgr. [email protected] 9422303129

VI NTPC18 Shri Manas Pratem Deb, A.G.M. [email protected] 900449714119 Shri M. Jauhari, A.G.M. [email protected] 8275045109

VII APL 20 Shri Uday Trivedi [email protected] 909905505421 Shri C.P. Sahoo [email protected] 9765494068

VIII KSK Mahanadi22 Shri S.K. Prasad, Sr. D.G.M. [email protected] 963002020323 Shri C. Narasimha [email protected] 9959444903

IX JPL 24 Shri R.C. Gupta, C.P.C. [email protected] 7898905010

X DB Power 25 Shri V.A. Murty, Advisor [email protected] 986945020726 Shri Sanjay Jadhav, Dy. G.M. [email protected] 9769190360

XI IEPL 27 Shri G.V. Sant, Dy.G.M. [email protected] 8975754507

XII VEDANTA28 Shri Sangeet Kumar Sahu, Mgr. [email protected] 9893592588

LIST OF PARTICIPANTS OF A SPECIAL MEETING ON SPS OF SR-NEW SYNCHRONIZATION HELD ON 29.04.2014 AT MUMBAI