Page 1: BL13 — XALOC

Kappa group Meeting | Sep 20-21, 2010XALOC - BL13 at ALBA 1

BL13 — XALOC

Guifré Cuní

on behalf of the XALOC team

Page 2: BL13 — XALOC

Kappa group Meeting | Sep 20-21, 2010XALOC - BL13 at ALBA 2

ALBA

offices

Tech. build

ing

warehouse

Page 3: BL13 — XALOC

Kappa group Meeting | Sep 20-21, 2010XALOC - BL13 at ALBA 3

Synchrotron light in Booster: Jan 2010

Page 4: BL13 — XALOC

Kappa group Meeting | Sep 20-21, 2010XALOC - BL13 at ALBA 4

2.7 GeV with 0.7 mA: 22 Jan 2010

Page 5: BL13 — XALOC

Kappa group Meeting | Sep 20-21, 2010XALOC - BL13 at ALBA 5

Status of XALOC at September 2010

• Optics almost all completed

• End-station under installation

• Commissioning with beam just after installing undulator

Page 6: BL13 — XALOC

Kappa group Meeting | Sep 20-21, 2010XALOC - BL13 at ALBA 6

XALOC optics layout

Monochromator

Vert. Foc. Mirror (VFM)

Hor. Foc.Mirror (HFM)

Ring

XBPMs

Page 7: BL13 — XALOC

Kappa group Meeting | Sep 20-21, 2010XALOC - BL13 at ALBA 7

End-Station

DetectorStatus: Awarded

DiffractometerStatus: To be integrated

Beam condit. el’sStatus: Designing

Diffractometer tableStatus: Motor tests

Sample changerStatus: To be commiss.Detector table

Status: Design finished

in-house

commercial

Procurement

mixed

Page 8: BL13 — XALOC

Kappa group Meeting | Sep 20-21, 2010XALOC - BL13 at ALBA 8

End-Station: diffractometer• MD2M

First mini-diffractometer out of ESRF

Full metrology done

Received and tested

To be integrated into the BL control

Not included in the contract

XYZ movable beamstop• In-house design

Viewing system• on-axis• software available

Omega axis• air bearing• run-out 1 m, accuracy < 1 mdeg

Mini-kappa • Removable• sphere of confusion ~5m

Page 9: BL13 — XALOC

Kappa group Meeting | Sep 20-21, 2010XALOC - BL13 at ALBA 9

End Station: Automatic sample changer

Model CATS (FIP-IRELEC)

Name CATS

Repeatability ± 30m

Final install. June 2010

Grippers SPINE pins

Greiner plates (96 wells)

automatically exchangeable gripper

Flexible 6-axis arm

Page 10: BL13 — XALOC

Kappa group Meeting | Sep 20-21, 2010XALOC - BL13 at ALBA 10

Controls

CATS with Custom I/O signals 3 regions: Free, 1, 2 SW allow MOVE/PIN/PLATE

Cryostream: 3 positions IN, OUT, FAR Motion: SW / Icepap Security: PLC

Omega: ETEL/Icepap's slave + metrology Monitoring + batch for operating CATS