bnfn 521 investment appraisal lecture notes lecture three
TRANSCRIPT
BNFN 521INVESTMENT APPRAISAL
Lecture Notes
Lecture Three
2
DISCOUNTING
AND
ALTERNATIVE INVESTMENT
CRITERIA
3
Project Cash Flow Profile
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Ben
efit
s L
ess
Cos
ts
(-)
(+)
Year of Project Life
Initial Investment Period
Operating StageLiquidation
Project Life
4
Discounting and Alternative Investment Criteria
Basic Concepts:A. Discounting
• Recognizes time value of money
a. Funds when invested yield a return
b. Future consumption worth less than present consumption
PVB = (B o/(1+r)
o
+(B 1/(1+r)1+.…….+(Bn /(1+r)
nPVC = (C
o /(1+r) +(C 1/(1+r)1+.…….+(Cn /(1+r)
o
o
r
rNPV = (B o-Co)/(1+r) o+(B 1-C1)/(1+r) 1+.…….+(B n-Cn)/(1+r) n
o n
o
r
5
Discounting and Alternative Investment Criteria (Cont’d)
B. Cumulative Values
• The calendar year to which all projects are discounted to is important
• All mutually exclusive projects need to be compared as of same calendar year
If NPV = (B o-Co)(1+r) 1+(B1-C1) +..+..+(B n-Cn)/(1+r) n-1 and
NPV = (B o-Co)(1+r) 3+(B1-C1)(1+r) 2+(B2-C2)(1+r)+(B 3-C3)+...(B n-Cn)/(1+r) n-3
Then NPV = (1+r) 2 NPV
1r
3r
3r
1r
6
Year 0 1 2 3 4
Net Cash Flow -1000 200 300 350 1440
Example of Discounting (10% Discount Rate)
25.676)1.1(
1440
)1.1(
350
)1.1(
300
1.1
2001000PV
4320
1.0
88.743)1.1(
1440
)1.1(
350
1.1
300200)1.1(1000PV
321
1.0
26.818)1.1(
1440
)1.1(
350300)1.1(200)1.1(1000PV
2122
1.0
Note: All of the transactions are done at the beginning of the year.
7
C. Variable Discount Rates• Adjustment of Cost of Funds Through Time
•For variable discount rates r1, r2, & r3 in years 1, 2, and 3, the discount factors
are, respectively, as follows:
1/(1+r1), 1/[(1+r1)(1+r2)] & 1/[(1+r1)(1+r2)(1+r3)]
0 1 2 3 4 5
r0r1r2r3
r4r5
r *4
r *3
r *2
r *1
r *0
If funds currently are abnormally scarce
Normal or historical average cost of funds
If funds currently are abnormally abundant
Years from present period
8
Year 0 1 2 3 4
Net Cash Flow -1000 200 300 350 1440
r 18% 16% 14% 12% 10%
Example of Discounting (multiple rates)
55.515)12.1)(14.1)(16.1(
1440
)14.1)(16.1(
350
16.1
300200)18.1(10001 NPV
04.598)12.1)(14.1(
1440
)14.1(
350300)16.1(200)16.1)(18.1(10002 NPV
91.436)12.1)(14.1)(16.1)(18.1(
1440
)14.1)(16.1)(18.1(
350
)16.1)(18.1(
300
18.1
20010000 NPV
Note: All of the transactions are done at the beginning of the year.
9
1. Net Present Value (NPV)
2. Benefit-Cost Ratio (BCR)
3. Pay-out or Pay-back Period
4. Internal Rate of Return (IRR)
ALTERNATIVE INVESTMENT
CRITERIA
10
Net Present Value (NPV)1. The NPV is the algebraic sum of the discounted values of the
incremental expected positive and negative net cashflows over a
project’s anticipated lifetime.
2. What does net present value mean?
– Measures the change in wealth created by the project.
– If this sum is equal to zero, then investors can expect to recover
their incremental investment and to earn a rate of return on their
capital equal to the private cost of funds used to compute the
present values.
– Investors would be no further ahead with a zero-NPV project than
they would have been if they had left the funds in the capital
market.
– In this case there is no change in wealth.
11
First Criterion: Net Present Value (NPV)
• Use as a decision criterion to answer following:a. When to reject projects?
b. Select project(s) under a budget constraint?
c. Compare mutually exclusive projects?
d. How to choose between highly profitable mutually exclusive projects with different lengths of life?
Alternative Investment Criteria
12
Net Present Value Criterion
a. When to Reject Projects?Rule: “Do not accept any project unless it generates a positive net present value when discounted by the opportunity cost of funds”
Examples:
Project A: Present Value Costs $1 million, NPV + $70,000
Project B: Present Value Costs $5 million, NPV - $50,000
Project C: Present Value Costs $2 million, NPV + $100,000
Project D: Present Value Costs $3 million, NPV - $25,000
Result:
Only projects A and C are acceptable. The country is made worse off if projects B and D are undertaken.
13
Net Present Value Criterion (Cont’d)
b. When You Have a Budget Constraint?Rule: “Within the limit of a fixed budget, choose that subset of the available projects which maximizes the net present value”
Example:
If budget constraint is $4 million and 4 projects with positive NPV:
Project E: Costs $1 million, NPV + $60,000
Project F: Costs $3 million, NPV + $400,000
Project G: Costs $2 million, NPV + $150,000
Project H: Costs $2 million, NPV + $225,000
Result:
Combinations FG and FH are impossible, as they cost too much. EG and EH are within the budget, but are dominated by the combination EF, which has a total NPV of $460,000. GH is also possible, but its NPV of $375,000 is not as high as EF.
14
c. When You Need to Compare Mutually Exclusive Projects?
Rule: “In a situation where there is no budget constraint but a project must be chosen from mutually exclusive alternatives, we should always choose the alternative that generates the largest net present value”
Example:
Assume that we must make a choice between the following three mutually exclusive projects:
Project I: PV costs $1.0 million, NPV $300,000
Project J: PV costs $4.0 million, NPV $700,000
Projects K: PV costs $1.5 million, NPV $600,000
Result:
Projects J should be chosen because it has the largest NPV.
Net Present Value Criterion (Cont’d)
15
Benefit-Cost Ratio (R)
• As its name indicates, the benefit-cost ratio (R), or what is sometimes referred to as the profitability index, is the ratio of the PV of the net cash inflows (or economic benefits) to the PV of the net cash outflows (or economic costs):
)(
)(
CostsEconomicorOutflowsCashofPV
BenefitsEconomicorInflowsCashofPVR
Alternative Investment Criteria
16
Basic rule:
If benefit-cost ratio (R) >1, then the project should be undertaken.
Problems?
Sometimes it is not possible to rank projects with the Benefit-Cost Ratio
• Mutually exclusive projects of different sizes
• Mutually exclusive projects and recurrent costs subtracted out of
benefits or benefits reported gross of operating costs
• Not necessarily true that RA>RB that project “A” is better
Benefit-Cost Ratio (Cont’d)
17
First Problem:The Benefit-Cost Ratio Does Not Adjust for Mutually Exclusive Projects of Different Sizes. For example:Project A: PV0of Costs = $5.0 M, PV0 of Benefits = $7.0 M
NPV0A = $2.0 M RA = 7/5 = 1.4
Project B: PV0 of Costs = $20.0 M, PV0 of Benefits = $24.0 M
NPV0B = $4.0 M RB = 24/20 = 1.2
According to the Benefit-Cost Ratio criterion, project A should be chosen over project B because RA>RB, but the NPV of project B is greater than the NPV of project A. So, project B should be chosen
Second Problem: The Benefit-Cost Ratio Does Not Adjust for Mutually Exclusive Projects and Recurrent Costs Subtracted Out of Benefits or Benefits Reported As Gross of Operating Costs. For example:Project A: PV0 Total Costs = $5.0 M PV0 Recurrent Costs = $1.0 M
(i.e. Fixed Costs = $4.0 M) PV0 of Gross Benefits= $7.0 MRA = (7-1)/(5-1) = 6/4 = 1.5
Project B: Total Costs = $20.0 M Recurrent Costs = $18.0 M(i.e. Fixed Costs = $2.0 M) PV0 of Gross Benefits= $24.0 MRB = (24-18)/(20-18) = 6/2 =3
Hence, project B should be chosen over project A under Benefit-Cost Criterion.Conclusion: The Benefit-Cost Ratio should not be used to rank projects
Benefit-Cost Ratio (Cont’d)
18
Pay-out or Pay-back period
• The pay-out period measures the number of years it will take for the undiscounted net benefits (positive net cashflows) to repay the investment.
• A more sophisticated version of this rule compares the discounted benefits over a given number of years from the beginning of the project with the discounted investment costs.
• An arbitrary limit is set on the maximum number of years allowed and only those investments having enough benefits to offset all investment costs within this period will be acceptable.
Alternative Investment Criteria
19
• Project with shortest payback period is preferred by this criteria
Comparison of Two Projects With Differing Lives Using Pay-Out Period
Bt - Ct Ba
Bb
ta
tbCa = Cb Payout period for
project aPayout period for
project b
0
Time
20
• Assumes all benefits that are produced by in longer
life project have an expected value of zero after the
pay-out period.
• The criteria may be useful when the project is
subject to high level of political risk.
Pay-Out or Pay-Back Period
21
Internal Rate of Return (IRR)
• IRR is the discount rate (K) at which the present value of benefits are just equal to the present value of costs for the particular project
Bt - Ct
(1 + K)t
Note: the IRR is a mathematical concept, not an economic or financial criterion
= 0t
i=0
Alternative Investment Criteria
22
Common uses of IRR:
(a) If the IRR is larger than the cost of funds then the
project should be undertaken
(b) Often the IRR is used to rank mutually exclusive
projects. The highest IRR project should be chosen
• An advantage of the IRR is that it only uses
information from the project
23
First Difficulty: Multiple rates of return for project
Solution 1: K = 100%; NPV= -100 + 300/(1+1) + -200/(1+1)2 = 0
Solution 2: K = 0%; NPV= -100+300/(1+0)+-200/(1+0)2 = 0
Difficulties With the Internal Rate of Return Criterion
+300
Bt - Ct
-200-100
Time
24
Second difficulty: Projects of different sizes and also mutually exclusive
Year 0 1 2 3 ... ... ҐProject A -2,000 +600 +600 +600 +600 +600 +600
Project B -20,000 +4,000 +4,000 +4,000 +4,000 +4,000 +4,000
NPV and IRR provide different Conclusions:Opportunity cost of funds = 10%
NPV : 600/0.10 - 2,000 = 6,000 - 2,000 = 4,000
NPV : 4,000/0.10 - 20,000 = 40,000 - 20,000 = 20,000
Hence, NPV > NPV
IRRA : 600/K A - 2,000 = 0 or K A = 0.30
IRRB : 4,000/K B - 20,000 = 0 or K B = 0.20
Hence, K A>KB
0B
0A
0B
0A
Difficulties With The Internal Rate of Return Criterion (Cont’d)
25
Third difficulty:Projects of different lengths of life and mutually exclusive
Opportunity cost of funds = 8%Project A: Investment costs = 1,000 in year 0
Benefits = 3,200 in year 5
Project B: Investment costs = 1,000 in year 0
Benefits = 5,200 in year 10
NPV : -1,000 + 3,200/(1.08) 5 = 1,177.86
NPV : -1,000 + 5,200/(1.08)10= 1,408.60
Hence, NPV > NPV
IRRA : -1,000 + 3,200/(1+KA)5 = 0 which implies that KA = 0.262
IRRB : -1,000 + 5,200/(1+KB)10 = 0 which implies that KB = 0.179
Hence, KA>KB
0B
0A
0B
0A
Difficulties With The Internal Rate of Return Criterion (Cont’d)
26
Fourth difficulty: Same project but started at different times
Project A: Investment costs = 1,000 in year 0
Benefits = 1,500 in year 1
Project B: Investment costs = 1,000 in year 5
Benefits = 1,600 in year 6
NPV A : -1,000 + 1,500/(1.08) = 388.88
NPV B : -1,000/(1.08) 5 + 1,600/(1.08) 6 = 327.68
Hence, NPV > NPV
IRR A : -1,000 + 1,500/(1+K A) = 0 which implies that KA= 0.5
IRRB : -1,000/(1+K B) 5 + 1,600/(1+K B) 6 = 0 which implies that KB = 0.6
Hence, K B >KA
0B
0A
Difficulties With The Internal Rate of Return Criterion (Cont’d)
0
0
27
Year 0 1 2 3 4
Project A 1000 1200 800 3600 -8000
IRR A 10%
Compares Project A and Project B ?
Project B 1000 1200 800 3600 -6400
IRR B -2%
Project B is obviously better than A, yet IRR A > IRR B
Project C 1000 1200 800 3600 -4800
IRR C -16%
Project C is obviously better than B, yet IRR B > IRR C
Project D -1000 1200 800 3600 -4800
IRR D 4%
Project D is worse than C, yet IRR D > IRR C
Project E -1325 1200 800 3600 -4800
IRR E 20%
Project E is worse than D, yet IRR E > IRR D
IRR FOR IRREGULAR CASHFLOWSFor Example: Look at a Private BOT Project from the perspective of the
Government