BÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 - 15.12.2018 09 th Dec 15 th Dec HẠNG MỤC THI CÔNG TẦNG F24, F25 ABOVE FLOOR WORK

Upload: others

Post on 31-Dec-2019

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

BÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT

09.12.2018 - 15.12.2018

09th Dec – 15th Dec

HẠNG MỤC

THI CÔNG TẦNG F24, F25

ABOVE FLOOR WORK

Page 2: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

15.12.2018 15th Dec

Toàn cảnh công trường vào ban ngày Overview of construction at day time

Page 3: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

Tiến độ thi công đổ bê tông sàn tầng F24 The casting concrete slab plan for floor F24 progress

13.12.2018 13th Dec

Page 4: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

Tiến độ thi công đổ bê tông cột tầng F23 The casting concrete column plan for floor F23 progress

13.12.2018 13th Dec

Page 5: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

Lắp dựng cốt thép cho san F24 - zone 2 Installing rebar for floor F24 - zone 2

11.12.2018 11th Dec

Page 6: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

12.12.2018 12th Dec

Đổ bê tông cho sàn F24 – zone 2 Casting concrete for floor F24 zone 2

Page 7: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

12.12.2018 12th Dec

Trát tường tầng F4 ~ F9 Plastering wall for floor F4 ~ F9

Page 8: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

Xây tường tầng F15 ~ F19 Brick work for floor F15 ~ F19

13.12.2018 13th Dec

Page 9: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

14.12.2018 14th Dec

Lắp đặt ván khuôn cho sàn F25 – zone 2 Carry out formwork for floor F25 - zone 2

Page 10: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

Lắp dựng cốt thép dầm cho sàn F25 – zone 2 Installing beam rebar for floor F25 - zone 2

15.12.2018 15th Dec

Page 11: BÁO CÁO TIẾN ĐỘ THI CÔNG - Hiyori Garden Towerhiyorigardentower.com/uploads/Tiendo 09_15.12.18.pdfBÁO CÁO TIẾN ĐỘ THI CÔNG CONSTRUCTION PROGRESS REPORT 09.12.2018 -

NGÀY LẬP BÁO CÁO

ĐƠN VỊ LẬP BÁO CÁO

CÔNG TY CP KỸ THUẬT XÂY DỰNG DINCO

Phòng Kinh Doanh – Sun Frontier Đà Nẵng

15.12.2018

NGUỒN THÔNG TIN BÁO CÁO