bts3900 (ver.d) installation guide(v100r009c00_03)(pdf)-en

Upload: eugene

Post on 01-Jun-2018

410 views

Category:

Documents


34 download

TRANSCRIPT

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    1/175

    BTS3900(Ver.D)

    V100R009C00

    Installation Guide

    Issue 03

    Date 2014-08-30

    HUAWEI TECHNOLOGIES CO., LTD.

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    2/175

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    3/175

    About This Document

    Overview

    This document describes the installation process for the BTS3900 (Ver.D) (shortened to

    BTS3900 in this document) cabinet, boards, modules, and cables. It also provides checklists for

    hardware installation.

    Product Version

    The following table lists the product versions related to this document.

    Product Name Solution Version Product Version

    BTS3900 l SRAN9.0

    l GBSS16.0

    l RAN16.0

    l eRAN7.0

    V100R009C00

    Intended Audience

    This document is intended for:

    l Base station installation personnel

    Organization

    1 Changes in BTS3900 (Ver.D) Installation Guide

    This chapter describes the changes inBTS3900 (Ver.D) Installation Guide.

    2 Overview

    Familiarize yourself with this information as well as the cabinet interior, application scenarios

    of the cabinets, and relevant clearance requirements before installing the cabinets.

    3 Installation Preparations

    BTS3900(Ver.D)

    Installation Guide About This Document

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    ii

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    4/175

    This chapter lists the tools and instruments that must be obtained before the installation. It also

    specifies the skills that the onsite personnel must have.

    4 Unpacking Check

    Unpack and check the delivered equipment to ensure that all the materials are included and intact.

    5 Obtaining the ESN

    The electronic serial number (ESN) is a unique identifier of a NE. Record the ESN of the base

    station beforethe installation for future commissioning.

    6 Installation Process

    Before the BTS3900 cabinets are delivered, boards inside the cabinets have been installed. You

    only need to install the cabinet and cables onsite. Some optional components may also need to

    be installed based on onsite requirements.

    7 Checking Installed Modules and Cables

    Modules and cables in the cabinet have been installed before delivery. You need to check whether

    the modules and cables are installed securely.

    8 Installing a Base

    A BTS3900 cabinet can be installed on a base. The base can be installed either on a concrete

    floor or ESD floor according to the equipment room conditions and customer's requirements.

    9 Installing the Cabinet

    A BTS3900 cabinet can be installed alone, side by side with another BTS3900 cabinet, or stacked

    on another BTS3900 cabinet. This section describes the procedure for installing the BTS3900(Ver.D) cabinets in the preceding modes. The procedures for installing the BTS3900(Ver.B),

    BTS3900(Ver.C), and BTS3900(Ver.D) cabinets are the same.

    10 Installing a PGND Cable and an Equipotential Cable

    A PGND cable connects a PGND screwin a cabinet and a PGND bar to ensure proper grounding

    of the cabinet. An equipotential cable connects PGND screws on different cabinets to ensure the

    equipotential bonding between the cabinets.

    11 Installing Optional Modules and Their Cables

    This chapter describes procedures for installing the optional modules and their cables onsite.

    12 Installing Cables

    Before cabinets are delivered, the boards and cables inside the cabinets have been installed. You

    must install the external cables and cables for optional components onsite.

    13 Installation Checklist

    After the cabinets and devices are installed, you need to check the installation items, installation

    environment,and cable-related items.

    14 Powering On a Base Station

    This section describes how to power on a base station and handle a failure in the power supply

    to the components in a cabinet.

    BTS3900(Ver.D)

    Installation Guide About This Document

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    iii

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    5/175

    Conventions

    Symbol Conventions

    The symbols that may be found in this document are defined as follows.

    Symbol Description

    Indicates an imminently hazardous situation which, if not

    avoided, will result in death or serious injury.

    Indicates a potentially hazardous situation which, if not

    avoided, could result in death or serious injury.

    Indicates a potentially hazardous situation which, if not

    avoided, may result in minor or moderate injury.

    Indicates a potentially hazardous situation which, if not

    avoided, could result in equipment damage, data loss,

    performance deterioration, or unanticipated results.

    NOTICE is used to address practices not related to personal

    injury.

    Calls attention to important information, best practices and

    tips.

    NOTE is used to address information not related to personal

    injury, equipment damage, and environment deterioration.

    General Conventions

    The general conventions that may be found in this document are defined as follows.

    Convention Description

    Times New Roman Normal paragraphs are in Times New Roman.

    Boldface Names of files, directories, folders, and users are inboldface. For example, log in as user root.

    Italic Book titles are in italics.

    Courier New Examples of information displayed on the screen are in

    Courier New.

    Command Conventions

    The command conventions that may be found in this document are defined as follows.

    BTS3900(Ver.D)

    Installation Guide About This Document

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    iv

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    6/175

    Convention Description

    Boldface The keywords of a command line are in boldface.

    Italic Command arguments are in italics.

    [ ] Items (keywords or arguments) in brackets [ ] are optional.

    { x | y | ... } Optional items are grouped in braces and separated by

    vertical bars. One item is selected.

    [ x | y | ... ] Optional items are grouped in brackets and separated by

    vertical bars. One item is selected or no item is selected.

    { x | y | ... }* Optional items are grouped in braces and separated by

    vertical bars. A minimum of one item or a maximum of all

    items can be selected.

    [ x | y | ... ]* Optional items are grouped in brackets and separated by

    vertical bars. Several items or no item can be selected.

    GUI Conventions

    The GUI conventions that may be found in this document are defined as follows.

    Convention Description

    Boldface Buttons, menus, parameters, tabs, window, and dialog titles

    are in boldface. For example, click OK.

    > Multi-level menus are in boldfaceand separated by the ">"

    signs. For example, choose File> Create> Folder.

    Keyboard Operations

    The keyboard operations that may be found in this document are defined as follows.

    Format Description

    Key Press the key. For example, press Enterand press Tab.

    Key 1+Key 2 Press the keys concurrently. For example, pressing Ctrl+Alt

    +Ameans the three keys should be pressed concurrently.

    Key 1, Key 2 Press the keys in turn. For example, pressing Alt, Ameans

    the two keys should be pressed in turn.

    Mouse Operations

    The mouse operations that may be found in this document are defined as follows.

    BTS3900(Ver.D)

    Installation Guide About This Document

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    v

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    7/175

    Action Description

    Click Select and release the primary mouse button without moving

    the pointer.

    Double-click Press the primary mouse button twice continuously and

    quickly without moving the pointer.

    Drag Press and hold the primary mouse button and move the

    pointer to a certain position.

    BTS3900(Ver.D)

    Installation Guide About This Document

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    vi

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    8/175

    Contents

    About This Document.....................................................................................................................ii

    1 Changesin BTS3900 (Ver.D) Installation Guide....................................................................1

    2 Overview.........................................................................................................................................3

    2.1 Components of BTS3900 Cabinets................................................................................................................................4

    2.2 BTS3900 (Ver.D) Configured with RFUs but Without RRUs.....................................................................................10

    2.3 BTS3900 (Ver.D) Configured with RFUs and RRUs..................................................................................................15

    2.4 Installation Clearance and Layout Requirements.........................................................................................................21

    3 Installation Preparations............................................................................................................25

    3.1 Documents....................................................................................................................................................................26

    3.2 Tools and Instruments..................................................................................................................................................26

    3.3 Requirements for Onsite Personnel..............................................................................................................................27

    4 Unpacking Check........................................................................................................................28

    5 Obtaining the ESN......................................................................................................................30

    6 Installation Process.....................................................................................................................32

    7 Checking Installed Modules and Cables................................................................................34

    7.1 Checking a BTS3900 DC Cabinet................................................................................................................................35

    7.2 Checking a BTS3900 AC Cabinet................................................................................................................................37

    8 Installing a Base...........................................................................................................................42

    8.1 Installing a Base on the Concrete Floor........................................................................................................................43

    8.2 Installing the Base on the ESD Floor...........................................................................................................................47

    9 Installing the Cabinet.................................................................................................................56

    9.1 Installing a Cabinet Without a Base.............................................................................................................................57

    9.2 Installing a Cabinet on a Base......................................................................................................................................62

    9.3 Installing Cabinets Side by Side...................................................................................................................................64

    9.4 Stacking Two Cabinets.................................................................................................................................................66

    10 Installing a PGND Cable and an Equipotential Cable......................................................68

    11 Installing Optional Modules and Their Cables..................................................................73

    11.1 Installing the GPS Surge Protector.............................................................................................................................75

    BTS3900(Ver.D)

    Installation Guide Contents

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    vii

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    9/175

    11.2 Installing the GATM and Bias-Tee............................................................................................................................78

    11.3 Installing a DCDU-12B..............................................................................................................................................84

    11.4 Installing the BBU......................................................................................................................................................89

    11.5 Installing Boards in the BBU and surge protection boards........................................................................................97

    11.6 Installing the RFU....................................................................................................................................................100

    11.7 Installing the EMU...................................................................................................................................................106

    11.8 Installing the RRU....................................................................................................................................................108

    12 Installing Cables......................................................................................................................109

    12.1 Cabling Requirements..............................................................................................................................................110

    12.2 Cable Holes...............................................................................................................................................................116

    12.3 Installing Power Cables............................................................................................................................................120

    12.3.1 Installing Power Cables for AC Cabinets..............................................................................................................120

    12.3.2 Installing Power Cables for DC Cabinets..............................................................................................................13112.4 Installing Transmission Cables.................................................................................................................................137

    12.4.1 Installing the E1/T1 Cables...................................................................................................................................137

    12.4.2 Installing the FE/GE Ethernet Cables....................................................................................................................139

    12.4.3 Installing FE/GE Fiber Optic Cables.....................................................................................................................140

    12.5 Installing Signal Cables............................................................................................................................................142

    12.5.1 (Optional) Installing a Monitoring Signal Cable Between Cascaded FAN 03C Assemblies................................142

    12.5.2 (Optional) Installing Inter-BBU Signal Cables.....................................................................................................144

    12.5.3 Installing a BBU Alarm Cable...............................................................................................................................148

    12.6 InstallingRF Jumpers...............................................................................................................................................14912.7 (Optional) Installing CPRI Electrical Cables...........................................................................................................151

    12.8 (Optional) Installing CPRI Fiber Optic Cables........................................................................................................154

    13 Installation Checklist..............................................................................................................158

    14 Powering On a Base Station..................................................................................................161

    BTS3900(Ver.D)

    Installation Guide Contents

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    viii

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    10/175

    1Changes in BTS3900 (Ver.D) InstallationGuide

    This chapter describes the changes inBTS3900 (Ver.D) Installation Guide.

    03 (2014-08-30)

    This is the third commercial release.

    Compared with Issue 02 (2014-07-30), this issue includes the following changes.

    Topic Change Description

    The whole document Changed information about the appearance of

    the BTS3900 cabinet.

    02 (2014-07-30)

    This is the second commercial release.

    Compared with Issue 01 (2014-04-30), this issue includes the following changes.

    Topic Change Description

    8.2 Installing the Base on the ESD Floor Changed installation information of the

    support for an ESD floor.

    01 (2014-04-30)

    This is the first commercial release.

    Compared with issue draft B (2014-02-28), no information is changed.

    Draft B (2014-02-28)

    This is a draft.

    BTS3900(Ver.D)

    Installation Guide 1 Changes in BTS3900 (Ver.D) Installation Guide

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    1

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    11/175

    Compared with issue draft A (2014-01-20), no information is added or deleted.

    Compared with issue draft A (2014-01-20), this issue incorporates the following changes:

    Topic Change Description

    14 Powering On a Base Station Added descriptions of the status of the

    indicators for CPRI ports.

    Draft A (2014-01-20)

    This is a draft.

    Compared with the issues for the multimode base station version V100R008C00 and the single-

    mode base station versions WCDMA-NodeB V200R015C00, GSM-BTS V100R015C00, and

    eNodeB V100R006C00, this issue includes the following new information:l 7.2 Checking a BTS3900 AC Cabinet

    l (Optional) Installing RRU Power Cables

    l Installing EPU05A-02 Power Cables

    Compared with the issues for the multimode base station version V100R008C00 and the single-

    mode base station versions WCDMA-NodeB V200R015C00, GSM-BTS V100R015C00, and

    eNodeB V100R006C00, this issue includes the following changes.

    Topic Change Description

    The whole document l Added the information about installation

    of BTS3900 AC cabinets.

    l Renamed all EPC6 connectors in this

    document EPC4 connectors.

    l Added the interconnection mode about

    UMPT + UMPT for the inter-BBU signal

    cable.

    l Added the description of UBBP.

    Compared with the issues for the multimode base station version V100R008C00 and the single-mode base station versions WCDMA-NodeB V200R015C00, GSM-BTS V100R015C00, and

    eNodeB V100R006C00, no topic is deleted from this issue.

    BTS3900(Ver.D)

    Installation Guide 1 Changes in BTS3900 (Ver.D) Installation Guide

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    2

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    12/175

    2OverviewAbout This Chapter

    Familiarize yourself with this information as well as the cabinet interior, application scenarios

    of the cabinets, and relevant clearance requirements before installing the cabinets.

    2.1 Components of BTS3900 Cabinets

    This section describes module and board configurations in BTS3900 cabinets.

    2.2 BTS3900(Ver.D) Configured with RFUs but Without RRUs

    When a BTS3900 is configured with RFUs but without RRUs, the BTS3900 can have different

    scenarios, including a single cabinet, cabinets installed side by side, stacked cabinets, or usingthe IMS06.

    2.3 BTS3900(Ver.D) Configured with RFUs and RRUs

    When a BTS3900 base station is configured with RFUs and RRUs, the BTS3900 can have

    different scenarios, including a single cabinet, cabinets installed side by side, stacked cabinets,

    or using an IMS06.

    2.4 Installation Clearance and Layout Requirements

    During the installation, you need to plan the space for future maintenance and cabling.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    3

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    13/175

    2.1 Components of BTS3900 Cabinets

    This section describes module and board configurations in BTS3900 cabinets.

    Components of a BTS3900 (Ver.B) Cabinet

    The following figure shows the components of a BTS3900 (Ver.B) cabinet.

    Figure 2-1Components of a BTS3900 (Ver.B) cabinet

    The following table lists the components in a BTS3900 (Ver.B) cabinet.

    Table 2-1Components in a BTS3900 (Ver.B) cabinet

    No. Component

    Optional/Mandatory

    MaximumQuantityin a SingleCabinet

    Remarks

    1 RFU

    filler

    panel

    Optional - To ensure proper ventilation of the

    cabinet, install a filler panel in each

    vacant slot in the RFU subrack.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    4

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    14/175

    No. Component

    Optional/Mandatory

    MaximumQuantityin a SingleCabinet

    Remarks

    2 RFU Mandatory 6 A radio frequency unit (RFU) modulates

    and demodulates baseband signals and

    RF signals, processes data, and

    combines and divides signals. For

    details, seeRFU Hardware

    Description.

    The BTS3900 (Ver.B) supports the

    following RFUs: MRFU, DRFU,

    GRFU, WRFU, WRFUa, and LRFU..

    3 FAN Mandatory 1 A FAN dissipates heat from the cabinet.

    The FAN is configured with the fanmonitoring unit type C (FMUC), which

    monitors the fans and reports alarms.

    4 Filler

    panel for

    the air

    intake

    vent

    Mandatory 1 A filler panel is installed in the air intake

    vent.

    5 BBU Mandatory 1 A BBU processes baseband signals and

    enables the base station to interact with

    the base station controller. For details,seeBBU Hardware Description.

    6 DCDU-

    01

    Mandatory 1 The direct current distribution unit-01

    (DCDU-01) distributes DC power to

    components in a cabinet.

    7 Transmi

    ssion

    equipme

    nt

    Optional - 2 U user space is reserved here to house

    the customer's transmission equipment.

    8 EPS24S48100D

    C

    Mandatory 1 The EPS24S48100DC converts +24 VDC power into -48 V DC and supplies

    the power to the DCDU-01.

    9 EPS489

    0

    Mandatory 1 The EPS4890 converts 220 V AC single-

    phase, 220 V AC three-phase, or 110 V

    AC dual-live-wire power into -48 V DC

    power and supplies the power to the

    DCDU-01.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    5

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    15/175

    NOTE

    A BTS3900 -48 V DC cabinet can feed power into the customer's transmission equipment. The customer

    equipment is able to work with an ambient temperature of 55oC or higher.

    Components of a BTS3900 (Ver.C) Cabinet

    The following figure shows the components of a BTS3900 (Ver.C) cabinet.

    Figure 2-2Components of a BTS3900 (Ver.C) cabinet

    The following table lists the components in a BTS3900 (Ver.C) cabinet.

    Table 2-2Components in a BTS3900 (Ver.C) cabinet

    No. Component

    Optional/Mandatory

    MaximumQuantityin a Single

    Cabinet

    Remarks

    1 RFU

    filler

    panel

    Optional - To ensure proper ventilation of the

    cabinet, a filler panel needs to be

    installed in each vacant slot of the RFU

    subrack.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    6

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    16/175

    No. Component

    Optional/Mandatory

    MaximumQuantityin a SingleCabinet

    Remarks

    2 RFU Mandatory 6 An RFU modulates and demodulates

    baseband signals and RF signals,

    processes data, and combines and

    divides signals. For details, seeRFU

    Hardware Description.

    The BTS3900 (Ver.C) supports the

    following RFUs: MRFU, MRFUd,

    MRFUe, DRFU, GRFU, WRFU,

    WRFUa, WRFUd, WRFUe, LRFU,

    LRFUe, CRFUd, and CRFUe..

    3 FAN03B

    Mandatory 1 A FAN 03B dissipates heat from thecabinet. The FAN 03B is configured

    with the fan monitoring unit type E

    (FMUE), which monitors the fans and

    reports alarms.

    4 Filler

    panel for

    the air

    intake

    vent

    Mandatory 1 A filler panel is installed in the air intake

    vent.

    5 BBU Mandatory 1 A BBU processes baseband signals andenables the base station to interact with

    the base station controller. For details,

    seeBBU Hardware Description.

    6 DCDU-

    11A

    Mandatory 1 The DCDU-11A distributes DC power

    to components in a cabinet.

    7 Transmi

    ssion

    equipme

    nt

    Optional - 3 U user space is reserved here to house

    the customer's transmission equipment.

    8 ETP481

    50-A3

    Mandatory 1 The EPS4890 converts 220 V AC single-

    phase, 220 V AC three-phase, or 110 V

    AC dual-live-wire power into -48 V DC

    power and supplies the power to the

    DCDU-11A.

    NOTE

    A BTS3900 -48 V DC cabinet can feed power into the customer's transmission equipment. The customer

    equipment is able to work with an ambient temperature of 55oC or higher.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    7

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    17/175

    Components of a BTS3900 (Ver.D) Cabinet

    The following figure shows the components of a BTS3900 (Ver.D) cabinet.

    Figure 2-3Components of a BTS3900 (Ver.D) cabinet

    The following table lists the components in a BTS3900 (Ver.D) cabinet.

    Table 2-3Components in a BTS3900 (Ver.D) cabinet

    No. Component

    Optional/Mandatory

    MaximumQuantityin a Single

    Cabinet

    Remarks

    1 RFU

    filler

    panel

    Optional - To ensure proper ventilation of the

    cabinet, a filler panel needs to be

    installed in each vacant slot of the RFU

    subrack.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    8

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    18/175

    No. Component

    Optional/Mandatory

    MaximumQuantityin a SingleCabinet

    Remarks

    2 RFU Mandatory 6 An RFU modulates and demodulates

    baseband signals and RF signals,

    processes data, and combines and

    divides signals. For details, seeRFU

    Hardware Description.

    The BTS3900 (Ver.D) supports the

    following RFUs: MRFU, MRFUd,

    MRFUe, DRFU, GRFU, WRFU,

    WRFUa, WRFUd, WRFUe, LRFU,

    LRFUe, CRFUd, and CRFUe..

    3 FAN03C

    Mandatory 1 A FAN 03C dissipates heat from thecabinet. The FAN 03C is configured

    with the fan monitoring unit type EA

    (FMUEA), which monitors the fans and

    reports alarms.

    4 Filler

    panel for

    the air

    intake

    vent

    Mandatory 1 A filler panel is installed in the air intake

    vent.

    5 BBU Mandatory 2 A BBU processes baseband signals andenables the base station to interact with

    the base station controller. For details,

    seeBBU Hardware Description.

    If two BBUs are required, the second

    BBU is configured in the 2 U user space

    below the DCDU-12A.

    6 DCDU-

    12A

    Mandatory 1 The DCDU-12A distributes DC power

    to components in a cabinet.

    7 BBU Optional - 2 U user space is reserved for installing

    a BBU.

    8 DCDU-

    12B

    Optional 1 For a BTS3900 configured with RFUs

    and RRUs, a DCDU-12B is installed in

    the 1 U space here to provide DC power

    for RRUs.

    9 Transmi

    ssion

    equipme

    nt

    Optional - 1 U user space is reserved here to house

    the customer's transmission equipment.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    9

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    19/175

    No. Component

    Optional/Mandatory

    MaximumQuantityin a SingleCabinet

    Remarks

    10 Filler

    panel

    Optional - A filler panel is installed in each slot in

    which no PSU(R4850G2) is installed.

    11 PSU

    (R4850

    G2)

    Mandatory 5 A PSU(R4850G2) converts 110 V AC

    or 220 V AC power into -48 V DC

    power.

    12 PMU

    11A

    Mandatory 1 A PMU 11A manages the power system

    and storage batteries, monitors power

    distribution, and reports alarms.

    13 EPU05A

    -02

    Subrack

    Mandatory 1 An EPU05A-02/04 converts 220 V AC

    single- or three-phase power into -48 V

    DC power and feeds the power into the

    DCDU-12A and DCDU-12B.

    NOTE

    A BTS3900 -48 V DC cabinet can feed power into the customer's transmission equipment. The customer

    equipment is able to work with an ambient temperature of 55oC or higher.

    2.2 BTS3900 (Ver.D) Configured with RFUs but WithoutRRUs

    When a BTS3900 is configured with RFUs but without RRUs, the BTS3900 can have different

    scenarios, including a single cabinet, cabinets installed side by side, stacked cabinets, or using

    the IMS06.

    BTS3900 Configured with Only BTS3900 Cabinets

    The following table lists the application scenarios for a BTS3900 that uses various BTS3900

    cabinets and is configured with RFUs but without RRUs.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    10

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    20/175

    Scenario

    Numberof

    BBUs

    ApplicationMode

    MaximumNumber of RF

    Modules

    Illustration Applicable Cabinet

    Sin

    gle

    cabi

    net

    1 Single-, dual-,

    quadruple-, and

    triple-mode

    base stations

    6 RFUs The application

    scenarios are

    shown by

    illustrations 1 and

    2 in Figure 2-4.

    l One BTS3900 DC

    cabinet

    l One BTS3900 AC

    cabinet

    2 Triple- and

    quadruple-

    mode base

    station

    6 RFUs The application

    scenarios are

    shown by

    illustrations 3 and4 in Figure 2-4.

    Cab

    inet

    s

    inst

    alle

    d

    side

    by

    side

    1 Single-, dual-,

    quadruple-, and

    triple-mode

    base stations

    12 RFUs The application

    scenarios are

    shown by

    illustrations 1 and

    2 in Figure 2-5.

    l Two BTS3900 DC

    cabinets

    l 1 BTS3900 AC cabinet

    +1 BTS3900 DC cabinet

    2 Triple- and

    quadruple-

    mode base

    station

    12 RFUs The application

    scenarios are

    shown by

    illustrations 3 and4 in Figure 2-5.

    Stac

    ked

    cabi

    nets

    1 Single-, dual-,

    quadruple-, and

    triple-mode

    base stations

    12 RFUs The application

    scenario is shown

    by illustration 1

    in Figure 2-6.

    Two BTS3900 DC cabinets

    2 Triple- and

    quadruple-

    mode base

    station

    12 RFUs The application

    scenario is shown

    by illustration 2

    in Figure 2-6.

    NOTE

    l A BTS3900 cabinet is configured with one BBU by default and can be configured with a maximum of

    two BBUs whose power consumption cannot exceed 1000 W. This principle applies to new site

    deployment or capacity expansion.

    l When cabinets are installed side by side or stacked, it is recommended that BBU 1 and BBU 0 be

    installed in the same cabinet.

    l One BTS3900 AC cabinet consists of one BTS3900 DC cabinet and one IMS06.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    11

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    21/175

    Figure 2-4Single cabinet

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    12

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    22/175

    Figure 2-5Cabinets installed side by side

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    13

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    23/175

    Figure 2-6Stacked cabinets

    BTS3900 Configured with BTS3900 Cabinets and an IMS06

    The following table lists the application scenarios for a BTS3900 that uses various BTS3900

    cabinets and an IMS06 and is configured with RFUs but without RRUs.

    Scenario Number ofBBUs

    ApplicationMode

    MaximumNumber ofRFModules

    Illustration Description

    1 BTS3900

    AC cabinet+1

    BTS3900 DC

    cabinet+1

    IMS06

    2 Triple-

    mode

    base

    station

    12 RFUs The application

    scenario is

    shown by

    illustration 1 in

    Figure 2-7.

    The IMS06 is used to

    house 100 Ah

    storage batteries,

    which provides low-

    capacity backup

    power.

    1 BTS3900

    AC cabinet+1

    IMS06

    2 Triple-

    mode

    base

    station

    6 RFUs The application

    scenario is

    shown by

    illustration 2 in

    Figure 2-7.

    The IMS06 is used to

    house transmission

    equipment.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    14

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    24/175

    NOTICEThe IMS06 cannot be stacked on the BTS3900 cabinet. Otherwise, the heat dissipation holes on

    the top of the BTS3900 cabinet will be blocked.

    NOTE

    When an IMS06 is configured with storage batteries, the power consumption of a BTS3900 cannot exceed

    10,000 W. If the power consumption exceeds 10,000 W, large-capacity battery packs need to be added.

    Figure 2-7BTS3900 configured with BTS3900 cabinets and an IMS06

    2.3 BTS3900 (Ver.D) Configured with RFUs and RRUs

    When a BTS3900 base station is configured with RFUs and RRUs, the BTS3900 can have

    different scenarios, including a single cabinet, cabinets installed side by side, stacked cabinets,

    or using an IMS06.

    BTS3900 Not Configured with an IMS06

    The following table describes the application scenarios for a BTS3900 base station that uses

    various BTS3900 cabinets and is configured with RFUs and RRUs.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    15

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    25/175

    Scenario

    Numberof

    BBUs

    ApplicationMode

    MaximumNumber ofRF Modules

    Illustration ApplicableCabinet

    Sin

    gle

    cabi

    net

    1 Single-,

    dual-, triple-,

    and

    quadruple-

    mode base

    stations

    6 RFUs+6

    RRUs

    Figure 2-8shows the

    application scenario.

    l One BTS3900

    DC cabinet

    l One BTS3900

    AC cabinet

    2 Triple- and

    quadruple-

    mode basestations

    6 RFUs+9

    RRUs

    The application scenario

    is shown in Figure 2-9

    and Figure 2-10.

    Cab

    inet

    s

    inst

    alle

    d

    side

    by

    side

    1 Single-,

    dual-, triple-,

    and

    quadruple-

    mode base

    stations

    12 RFUs+6

    RRUs

    Figure 2-11shows the

    application scenario.

    Two BTS3900

    DC cabinets

    2 Triple- and

    quadruple-

    mode basestations

    12 RFUs+9

    RRUs

    Figure 2-12shows the

    application scenario.

    Stac

    ked

    cabi

    nets

    1 Single-,

    dual-, triple-,

    and

    quadruple-

    mode base

    stations

    12 RFUs+6

    RRUs

    Figure 2-13shows the

    application scenario.

    2 Triple- and

    quadruple-

    mode basestations

    12 RFUs+9

    RRUs

    Figure 2-14shows the

    application scenario.

    When a BTS3900 (Ver.D) is configured with RFUs and RRUs, a DCDU-12B is installed in the

    BTS3900 cabinet to distribute power to RRUs.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    16

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    26/175

    Figure 2-8One BTS3900 DC cabinet (one BBU)

    Figure 2-9One BTS3900 DC cabinet (two BBUs)

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    17

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    27/175

    Figure 2-10One BTS3900 AC cabinet (two BBUs)

    Figure 2-11Two BTS3900 DC cabinets installed side by side (one BBU)

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    18

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    28/175

    Figure 2-12Two BTS3900 DC cabinets installed side by side (two BBUs)

    Figure 2-13Two BTS3900 DC cabinets stacked together (one BBU)

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    19

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    29/175

    Figure 2-14Two BTS3900 DC cabinets stacked together (two BBUs)

    BTS3900 Configured with an IMS06

    The following table lists the application scenarios where a BTS3900 base station uses an

    BTS3900 cabinet and an IMS06 and is configured with RFUs and RRUs.

    Scenario Number ofBBUs

    ApplicationMode

    MaximumNumber ofRFModules

    Illustration Description

    1 BTS3900

    AC+1 IMS06

    2 Triple-

    andquadrupl

    e-mode

    base

    stations

    6 RFUs+9

    RRUs

    Figure 2-13

    shows theapplication

    scenario.

    An IMS06 houses

    100 Ah storagebatteries, which

    provide low-

    capacity backup

    power.

    NOTICEThe IMS06 cannot be stacked on the BTS3900 cabinet. Otherwise, the heat dissipation holes on

    the top of the BTS3900 cabinet will be blocked.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    20

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    30/175

    NOTE

    When an IMS06 is configured with storage batteries, the power consumption of a BTS3900 cannot exceed

    10,000 W. If the power consumption exceeds 10,000 W, large-capacity battery packs need to be added.

    Figure 2-15BTS3900 configured with an IMS06 (1 BTS3900 AC+1 IMS06)

    2.4 Installation Clearance and Layout Requirements

    During the installation, you need to plan the space for future maintenance and cabling.

    Installation Clearance Requirements

    Clearance requirements of a BTS3900 cabinet are as follows:

    l A BTS3900 DC cabinet can be installed with its rear flush against a wall, whereas a

    minimum of 100 mm (3.94 in.) space must be reserved behind the rear of a BTS3900 AC

    cabinet.

    l The left side of the cabinet can be against a wall. Reserve a minimum of 300 mm (11.81

    in.) clearance on the right side for installing noise reduction modules later.

    l Retain a minimum of 800 mm (31.50 in.) in front of the cabinet for maintenance.

    l Retain a minimum of 200 mm (7.87 in.) between the top of the cabinet and the ceiling for

    cabling.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    21

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    31/175

    The following figure shows the clearance requirements of cabinets in the following installation

    scenarios: a single cabinet is installed alone, two cabinets are installed side by side, or two

    cabinets are stacked.

    Figure 2-16Clearance requirements for a BTS3900 DC cabinet

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    22

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    32/175

    Figure 2-17Clearance requirements for a BTS3900 AC cabinet

    Layout Requirements

    Layout requirements of BTS3900 cabinets are as follows:

    l Install the cabinets at a position nearest to the feeder window to minimize the feeder length.

    l Install the cabinets in one row in one equipment room to facilitate cabling.

    l No space is required between cabinets and user equipment in the same row.

    The following figure shows the layout requirements of BTS3900 cabinets.

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    23

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    33/175

    Figure 2-18Layout requirements

    BTS3900(Ver.D)

    Installation Guide 2 Overview

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    24

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    34/175

    3Installation PreparationsAbout This Chapter

    This chapter lists the tools and instruments that must be obtained before the installation. It also

    specifies the skills that the onsite personnel must have.

    3.1 Documents

    Before the installation, obtain the following documents:

    3.2 Tools and Instruments

    This section lists the tools and instruments that must be obtained before installation.

    3.3 Requirements for Onsite Personnel

    Onsite personnel must be qualified and trained. Before performing any operation, onsite

    personnel must be familiar with correct operation methods and safety precautions.

    BTS3900(Ver.D)

    Installation Guide 3 Installation Preparations

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    25

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    35/175

    3.1 Documents

    Before the installation, obtain the following documents:

    Before the installation, obtain the following documents:

    l Safety Precautions

    l Installation Reference

    l 3900 Series Base Station Hardware Description

    l 3900 Series Base Station Cables

    l BBU Hardware Description

    l RFU Hardware Description

    A BTS3900 (Ver.D) cabinet can be stacked on an IMS06, thereby meeting power distribution

    and transmission requirements. For details, see the following document:

    l IMS06 Installation Guide

    3.2 Tools and Instruments

    This section lists the tools and instruments that must be obtained before installation.

    Marker Phillips screwdriver (M3 to

    M6)

    Flat-head screwdriver (M3 to

    M6)

    Diagonal pliers

    32 mm (1.26 in.)

    combination wrench

    Socket wrench Torque wrench

    Power cable crimping tool RJ45 crimping tool Cable cutter

    Rubber mallet Soldering iron Wire stripper

    BTS3900(Ver.D)

    Installation Guide 3 Installation Preparations

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    26

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    36/175

    Hammer drill (16) Heat gun Level

    Multimeter Measuring tape Vacuum cleaner

    ESD wrist strap ESD gloves Torque screwdriver

    Gloves Utility knife Hydraulic pliers

    Torx screwdriver - -

    3.3 Requirements for Onsite Personnel

    Onsite personnel must be qualified and trained. Before performing any operation, onsitepersonnel must be familiar with correct operation methods and safety precautions.

    Before the installation, pay attention to the following:

    l The customer's technical engineers must be trained by Huawei and be familiar with the

    proper installation and operation methods.

    l The number of onsite personnel depends on the engineering schedule and installation

    environment. Generally, three to five onsite personnel are necessary.

    BTS3900(Ver.D)

    Installation Guide 3 Installation Preparations

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    27

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    37/175

    4Unpacking CheckUnpack and check the delivered equipment to ensure that all the materials are included and intact.

    Context

    CAUTION

    The gravity center of some cabinets is in the front, for example, the BTS3900AL, IBBS700T

    and IBBS300T . Therefore, avoid toppling of the cabinet when the door of the cabinet is opened,

    especially when you unpack the cabinet or before it has been secured onto a base.

    NOTICE

    l Power on a cabinet or BBU within seven days after unpacking it.

    l Power on an RRU within 24 hours after unpacking it.

    NOTE

    When transporting, moving, or installing the equipment, components, or parts, you must:

    lPrevent them from colliding with doors, walls, shelves, or other objects.

    l Wear clean gloves, and avoid touching the equipment, components, or parts with bare hands, sweat-

    soaked gloves, or dirty gloves.

    Procedure

    Step 1 Check the total number of articles in each case according to the packing list.

    BTS3900(Ver.D)

    Installation Guide 4 Unpacking Check

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    28

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    38/175

    If... Then...

    The total number tallies with the packing

    list

    Go to Step 2.

    The total number does not tally with the

    packing list

    Find out the cause and report any missing

    articles to the local Huawei office.

    Step 2 Check the exterior of the packing case.

    If... Then...

    The outer packing case is intact Go to Step 3.

    The outer packing is severely damaged or

    soaked

    Find out the cause and report the situation to

    the local Huawei office.

    Step 3 Check the type and quantity of the equipment in the cases according to the packing list.

    If... Then...

    Types and quantity of the articles tally with

    those on the packing list

    Sign thePacking Listwith the customer.

    There are any goods missing, incorrectly

    delivered, or damaged

    Report the situation to the local Huawei office.

    CAUTION

    To protect the equipment and prevent damage to the equipment, you are advised to keep the

    unpacked equipment and packing materials indoors, take photos of the stocking environment,

    packing case or carton, packing materials, and any rusted or eroded equipment, and then file the

    photos.

    ----End

    BTS3900(Ver.D)

    Installation Guide 4 Unpacking Check

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    29

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    39/175

    5Obtaining the ESNThe electronic serial number (ESN) is a unique identifier of a NE. Record the ESN of the base

    station before the installation for future commissioning.

    Procedure

    Step 1 Record the ESN on the BBU.

    l If there is no label on the FAN unit of the BBU, the ESN is printed on a mounting ear of the

    BBU, as shown in Figure 5-1. Record the ESN and base station information.

    l If there is a label on the FAN unit of the BBU, the ESN is printed on the label and a mounting

    ear of the BBU, as shown in Figure 5-2. Remove the label and record the base station

    information on the label printed with Site.

    NOTE

    The base station information includes the name, ID, and location of the base station.

    Figure 5-1ESN position (1)

    BTS3900(Ver.D)

    Installation Guide 5 Obtaining the ESN

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    30

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    40/175

    Figure 5-2ESN position (2)

    Step 2 Report the ESN and base station information to the base station commissioning personnel orremove the label and give it to the base station commissioning personnel.

    NOTE

    For base stations configured with multiple BBUs, record the ESNs on all BBUs and submit them to the

    personnel responsible for the base station commissioning.

    ----End

    BTS3900(Ver.D)

    Installation Guide 5 Obtaining the ESN

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    31

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    41/175

    6Installation ProcessBefore the BTS3900 cabinets are delivered, boards inside the cabinets have been installed. You

    only need to install the cabinet and cables onsite. Some optional components may also need to

    be installed based on onsite requirements.

    The following figure shows the installation process.

    BTS3900(Ver.D)

    Installation Guide 6 Installation Process

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    32

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    42/175

    Figure 6-1Installation process

    BTS3900(Ver.D)

    Installation Guide 6 Installation Process

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    33

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    43/175

    7Checking Installed Modules and CablesAbout This Chapter

    Modules and cables in the cabinet have been installed before delivery. You need to check whether

    the modules and cables are installed securely.

    7.1 Checking a BTS3900 DC Cabinet

    Modules and cables have been installed in a BTS3900 DC cabinet before delivery. You need to

    check whether the modules and cables are installed securely.

    7.2 Checking a BTS3900 AC Cabinet

    Modules and cables in the BTS3900 AC cabinet have been installed. You need to check whetherthe modules and cables are installed securely.

    BTS3900(Ver.D)

    Installation Guide 7 Checking Installed Modules and Cables

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    34

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    44/175

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    45/175

    No. Cable One End The Other End

    Connector InstallationPosition

    Connector InstallationPosition

    P6 FAN 03C

    power cable

    3V3 connector -48V port on

    the FAN 03C

    EPC4

    connector

    LOAD6 port

    on the

    DCDU-12A

    P7 and

    P8

    BBU power

    cables

    3V3 connector -48V port on

    the UPEU

    EPC4

    connector

    LOAD7 and

    LOAD8 ports

    on the

    DCDU-12A

    Step 3 Check whether the signal cables in the cabinet are routed correctly and connected securely

    according to the following figure and table.

    Figure 7-2Signal cables installed in the cabinet

    BTS3900(Ver.D)

    Installation Guide 7 Checking Installed Modules and Cables

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    36

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    46/175

    Table 7-2List of the signal cables installed in the cabinet

    No. Cable One End The Other End

    Connector Installation

    Position

    Connector Installation

    Position

    S1 ELU signal

    cable

    RJ45

    connector

    SENSOR port

    on the FAN

    03C

    RJ45

    connector

    ELU

    S2 FMUEA-

    BBU

    monitoring

    signal cable

    RJ45

    connector

    COM_IN port

    on the FAN

    03C

    RJ45

    connector

    MON0 port on

    the UPEU

    NOTE

    If no BBU is

    installed in the

    cabinet, this

    cable should

    be bound to

    the right side

    of the cabinet.

    Step 4 Check that the CPRI cables in the cabinet are routed correctly and connected securely. For detailsabout how to connect and disconnect CPRI cables, see Inserting and Removing CPRI Cables.

    ----End

    7.2 Checking a BTS3900 AC CabinetModules and cables in the BTS3900 AC cabinet have been installed. You need to check whether

    the modules and cables are installed securely.

    Procedure

    Step 1 Check whether the modules are installed securely in the cabinet, and tighten any loose screw.

    Step 2 Check that the equipotential cables are installed securely, the power cables are correctlyconnected, and the screws are tightened according to the following table and figure.

    BTS3900(Ver.D)

    Installation Guide 7 Checking Installed Modules and Cables

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    37

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    47/175

    Figure 7-3Equipotential cables and power cables installed inside the cabinet

    Table 7-3Equipotential cables and power cables installed inside the cabinet

    No. Cable One End The Other End

    Connector InstallationPosition

    Connector InstallationPosition

    P0 to

    P5

    RFU power

    cable

    3V3 connector PWR port on

    an RFU

    EPC4

    connector

    One of the

    LOAD0 to

    LOAD5 ports

    on the

    DCDU-12A

    P6 FAN 03C

    power cable

    3V3 connector -48V port on

    the FAN 03C

    EPC4

    connector

    LOAD6 port

    on the

    DCDU-12A

    BTS3900(Ver.D)

    Installation Guide 7 Checking Installed Modules and Cables

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    38

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    48/175

    No. Cable One End The Other End

    Connector InstallationPosition

    Connector InstallationPosition

    P7 and

    P8

    BBU power

    cable

    3V3 connector -48V port on

    the UPEU

    EPC4

    connector

    LOAD7 and

    LOAD8 ports

    on the

    DCDU-12A

    P9 and

    P10

    DCDU-12A

    power cable

    OT terminal

    (M6)

    RTN(+) and

    NEG(-)

    terminals on

    the

    DCDU-12A

    OT terminal

    (M6)

    RTN(+) and

    NEG(-)

    terminals near

    RFC_1 and

    RFC_2 on the

    EPU05A-02

    G0 Equipotentia

    l cable

    between the

    BTS3900

    and IMS06

    OT terminal

    (M6)

    Ground bar in

    the BTS3900

    cabinet

    OT terminal

    (M6)

    Ground bar in

    the IMS06

    G1 Equipotentia

    l cable

    between the

    EPU and

    IMS06

    OT terminal

    (M6)

    Ground bar in

    the EPU

    OT terminal

    (M6)

    Ground bar in

    the IMS06

    Step 3 Check that the signal cables are installed securely and the screws are tightened according to thefollowing table and figure.

    BTS3900(Ver.D)

    Installation Guide 7 Checking Installed Modules and Cables

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    39

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    49/175

    Figure 7-4Signal cables installed in the cabinet

    Table 7-4Signal cables installed in the cabinet

    No. Cable One End The Other End

    Connector InstallationPosition

    Connector InstallationPosition

    S1 ELU signal

    cable

    RJ45

    connector

    SENSOR port

    on the FAN

    03C

    RJ45

    connector

    ELU

    BTS3900(Ver.D)

    Installation Guide 7 Checking Installed Modules and Cables

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    40

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    50/175

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    51/175

    8Installing a BaseAbout This Chapter

    A BTS3900 cabinet can be installed on a base. The base can be installed either on a concrete

    floor or ESD floor according to the equipment room conditions and customer's requirements.

    8.1 Installing a Base on the Concrete Floor

    This section describes the procedure and precautions for installing a base on the concrete floor.

    8.2 Installing the Base on the ESD Floor

    This section describes the procedure and precautions for installing a base on the ESD floor.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    42

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    52/175

    8.1 Installing a Base on the Concrete Floor

    This section describes the procedure and precautions for installing a base on the concrete floor.

    Procedure

    Step 1 Determine the holes for installing the cabinet according to the positioning holes on the marking-off template, as shown in the following figure.

    Figure 8-1Positioning the base

    (1) Anchor point (2) Marking-off template (3) Concrete floor

    Step 2 Drill holes at the anchor points and insert expansion bolt assemblies in the holes, as shown inthe following figure.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    43

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    53/175

    Figure 8-2Drilling a hole and inserting an expansion bolt assembly

    (1) M12x60 bolt (2) Spring washer (3) Flat washer (4) Expansion tube

    1. Use a hammer drill with a 16 drill bit to drill holes with a depth ranging from 55 mm

    (2.17 in.) to 60 mm (2.36 in.).

    CAUTION

    Take proper safety measures to protect your eyes and respiratory tract against the dust

    before drilling holes.

    NOTE

    Generally, the concrete floor is solid and smooth. Therefore, you can use the center punch to help

    locate the drill bit. If the conditions of the floor allow direct drilling, skip this step.

    2. Use a vacuum cleaner to clear the dust out from inside and around the holes, and measure

    the distances between holes. If any of the hole is beyond the acceptable range, mark a new

    anchor point and drill a new hole.

    3. Tighten an expansion bolt slightly and place it vertically into each hole.

    4. Hit the expansion bolt with a rubber mallet until the expansion tube completely enters the

    hole.

    5. Remove the M12x60 bolt, spring washer, and flat washer in sequence.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    44

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    54/175

    CAUTION

    After dismantling the expansion bolt assembly, ensure that the top of the expansion tube

    is level with the concrete floor. Otherwise, the cabinet cannot be installed on the concretefloor evenly and securely.

    Step 3 Install the base and level it.

    1. Place the insulation plate and the base on the floor in sequence. Align holes on the base

    with those on the insulation plate and those for inserting expansion bolt assemblies on the

    floor. Insert four M12x60 expansion bolts into the holes, and partially tighten them, as

    shown in the following figure.

    Figure 8-3Preinstalling the base on the floor

    (1) M12x60 bolt (2) Spring washer (3) Flat washer

    (4) Insulation washer (5) Insulation plate -

    2. Measure and level the base.

    Place a level on the base and observe the position of the mercury, as shown in the following

    figure. If the base is not level, use leveling bolts to level it.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    45

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    55/175

    Figure 8-4Checking the base levelness

    (1) Leveling bolts (2) Level

    3. Use a socket wrench to fasten the M12x60 bolts in a diagonal sequence to secure the base

    on the floor, and tighten the bolts to 45 Nm (398.25 lbfin.), as shown in the following

    figure.

    Figure 8-5Securing the base on the floor

    Step 4 Measure the insulation between the base and expansion bolts.1. Set the multimeter to the megohm scale (M).

    2. Measure the resistance between the leveling bolt and the expansion bolt, as shown in the

    following figure.

    Figure 8-6Measuring the resistance between the leveling bolt and the expansion bolt

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    46

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    56/175

    l If the resistance is lower than 5 megohms, the base is not insulated from the ground.

    Go to Step 4.3.

    l If the resistance is higher than 5 megohms, the base is insulated from the ground.

    3. Remove the expansion bolt assemblies and check whether the insulation washers are

    missing or damaged.

    l If yes, reinstall the expansion bolt assemblies and re-level the base.

    l If no, check whether the multimeter works properly and whether the setting is correct.

    ----End

    8.2 Installing the Base on the ESD Floor

    This section describes the procedure and precautions for installing a base on the ESD floor.

    Context

    The following figure shows the support for installing the ESD floor.

    Figure 8-7Support for installing the ESD floor

    (1) Mounting holes for the ESD floor (2) Support (3) Mounting holes for the concretefloor

    There are three models of ESD floor supports, all of which are adjustable. The heights of ESD

    floors supported by the three models are listed in the following table.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    47

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    57/175

    Table 8-1Heights of the two types of supports

    Component Applicable Height Remark

    Model I 200 (7.87 in.)H270 (10.63 in.) l The height can be adjusted

    within the adjustable range.l When the height of the ESD floor

    is the same as the maximum or

    minimum value of the adjustable

    ranges, the model with a smaller

    adjustable range is preferred. For

    example, when the height of the

    ESD floor is 410 mm (16.14 in.),

    model II is preferentially

    selected.

    Model II 270 (10.63 in.)H410 (16.14

    in.)

    Model III 410 (16.14 in.)H700 (27.56

    in.)

    NOTE

    The height of an ESD floor is the spacing between the concrete floor and the upper surface of the ESD

    floor.

    Procedure

    Step 1 Determine the installation position for the base on the ESD floor. For details, seeInstalling aBase on the Concrete FloorstepStep 1.

    Step 2 Drill holes on the ESD floor.

    1. Use a hammer drill with bit 16 to drill holes at the anchor points. The holes should penetrate

    the ESD floor, as shown in the following figure.

    Figure 8-8Drilling a hole on the ESD floor

    (1) ESD floor

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    48

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    58/175

    CAUTION

    Take proper safety measures to protect your eyes and respiratory tract against the dust

    before drilling holes.

    2. Use a vacuum cleaner to clear the dust inside and around the holes. If the inter-hole spacing

    is too wide or too narrow, locate and drill holes again.

    Step 3 Position the support.

    1. Place the support under the ESD floor. Use bolts to fix the support to the ESD floor

    temporarily, as shown in the following figure.

    Figure 8-9Fixing the support to the ESD floor

    (1) Mounting holes on the ESD floor (2) ESD floor (3) Mounting holes for the concrete floor

    2. Use a ruler to measure the distance between the concrete floor and the lower surface of the

    ESD floor. Adjust the support to a specified height based on the measurement result, ensure

    that the top of the support is leveled with the lower surface of the ESD floor, and use a

    socket wrench to tighten the nuts on the support to 45 Nm (33.19 lbfft), as shown in the

    following figure.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    49

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    59/175

    Figure 8-10Adjust the support's height

    3. According to the mounting holes in the concrete floor, mark the positions for installing

    expansion bolt assemblies, as shown in the following figure.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    50

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    60/175

    Figure 8-11Marking the positions for installing expansion bolt assemblies

    (1) Mounting hole in the

    concrete floor

    (2) Concrete floor

    4. Use a measuring tape to measure the inter-hole spacing, and ensure that the center-to-center

    distances between the holes are consistent.

    Step 4 Drill holes at the anchor points on the concrete floor. Then install the expansion bolt assembly.as shown in the following figure.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    51

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    61/175

    Figure 8-12Drilling a hole and inserting an expansion bolt assembly

    (1) M12x60 bolt (2) Spring washer (3) Flat washer (4) Expansion tube

    Step 5 Secure the support for installing the ESD floor.

    Use M12x60 bolts, spring washers, and flat washers to secure the support for installing the ESD

    floor on the concrete floor, and tighten the bolts to 45 Nm (398.25 lbfin.), as shown in the

    following figure.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    52

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    62/175

    Figure 8-13Securing the ESD floor

    (1) M12x60 bolts (2) Spring washer (3) Flat washer

    Step 6 Remove the bolts that are used to temporarily fix the support instep 3.a.

    Step 7 Install the base and level it.

    1. Place the insulation plate and the base on the ESD floor in sequence. Align holes on the

    base with those on the insulation plate and those for inserting expansion bolt assemblies

    on the ESD floor. Use a socket wrench to fasten the M12x80 bolts in a diagonal sequence

    to secure the base on the ESD floor, and tighten the bolts to 45 Nm (398.25 lbfin.), as

    shown in the following figure.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    53

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    63/175

    Figure 8-14Securing the base on the ESD floor

    (1) M12x80 bolt (2) Spring washer (3) Flat washer

    (4) Insulation washer (5) Insulation plate -

    2. Place a level on the base and observe the position of the mercury, as shown in the following

    figure. If the base is not level, use the leveling bolts to level it.

    NOTE

    Screwing the bolts clockwise will raise the base, and screwing the bolts counterclockwise will lower

    the base.

    Figure 8-15Checking the base levelness

    (1) Leveling bolts (2) Level

    Step 8 Measure the insulation between the base and expansion bolts.

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    54

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    64/175

    1. Set the multimeter to the megohm scale (M).

    2. Measure the resistance between the leveling bolt and the expansion bolt, as shown in the

    following figure.

    Figure 8-16Measuring the resistance between the leveling bolt and the expansion bolt

    l If the resistance is lower than 5 megohms, the base is not insulated from the ground.

    Go to Step 8.3.l If the resistance is higher than 5 megohms, the base is insulated from the ground.

    3. Remove the expansion bolt assemblies and check whether the insulation washers are

    missing or damaged.

    l If yes, reinstall the expansion bolt assemblies and re-level the base.

    l If no, check whether the multimeter works properly and whether the setting is correct.

    ----End

    BTS3900(Ver.D)

    Installation Guide 8 Installing a Base

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    55

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    65/175

    9Installing the CabinetAbout This Chapter

    A BTS3900 cabinet can be installed alone, side by side with another BTS3900 cabinet, or stacked

    on another BTS3900 cabinet. This section describes the procedure for installing the BTS3900

    (Ver.D) cabinets in the preceding modes. The procedures for installing the BTS3900(Ver.B),

    BTS3900(Ver.C), and BTS3900(Ver.D) cabinets are the same.

    9.1 Installinga Cabinet Without a Base

    This section describes the procedure and precautions for installing a BTS3900 DC cabinet

    without a base on the concrete floor. BTS3900 AC cabinet should not be installed without a base

    on the concrete floor.

    9.2 Installing a Cabinet on a Base

    This section describes the procedure and precautions for installing a BTS3900 AC or DC cabinet

    on a base.

    9.3 InstallingCabinets Side by Side

    This section describes the procedure and precautions for installing two BTS3900 cabinets side

    by side. The combination of One BTS3900 (Ver.D) AC cabinet and one BTS3900 (Ver.D) DC

    cabinet doesn't support this installation.

    9.4 Stacking Two Cabinets

    This section describes the procedure and precautions for stacking two BTS3900 cabinets.

    BTS3900 (Ver.D) AC cabinet should not be stacked.

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    56

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    66/175

    9.1 Installing a Cabinet Without a Base

    This section describes the procedure and precautions for installing a BTS3900 DC cabinetwithout a base on the concrete floor. BTS3900 AC cabinet should not be installed without a base

    on the concrete floor.

    Context

    To facilitate operations, you can remove the cabinet door and then install the cabinet.

    Procedure

    Step 1 Take the marking-off template out from the position 3 U above the bottom of the cabinet, and

    determine the holes for installing the cabinet according to the anchor points on the marking-offtemplate, as shown in the following figure.

    Figure 9-1Positioning the cabinet

    (1) Anchor point (2) Marking-off template (3) Concrete floor

    Step 2 Drill holes at the anchor points and insert expansion bolt assemblies in the holes, as shown in

    the following figure.

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    57

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    67/175

    Figure 9-2Drilling a hole and inserting an expansion bolt assembly

    (1) M12x80 bolt (2) Spring washer (3) Flat washer (4) Cushion collar (5) Expansion tube

    1. Use a hammer drill with a 16 drill bit to drill holes with a depth ranging from 55 mm

    (2.17 in.) to 60 mm (2.36 in.).

    CAUTION

    Take proper safety measures to protect your eyes and respiratory tract against the dust

    before drilling holes.

    NOTE

    Generally, the concrete floor is solid and smooth. Therefore, you can use the center punch to help

    locate the drill bit. If the conditions of the floor allow direct drilling, skip this step.

    2. Use a vacuum cleaner to clear the dust out from inside and around the holes, and measure

    the distances between holes. If any of the hole is beyond the acceptable range, mark a new

    anchor point and drill a new hole.

    3. Tighten an expansion bolt slightly and place it vertically into each hole.

    4. Hit the expansion bolt with a rubber mallet until the expansion tube completely enters the

    hole.

    5. Remove the M12x80 bolt, spring washer and flat washer in sequence.

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    58

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    68/175

    CAUTION

    After dismantling the expansion bolt assembly, ensure that the top of the expansion tube

    is level with the concrete floor. Otherwise, the cabinet cannot be installed on the concretefloor evenly and securely.

    6. Remove and dispose of the cushion collar. Then take out the insulation washer from the

    accessory bag and put it on the expansion bolt with the flat side upwards, as shown in the

    following figure.

    Figure 9-3Putting the insulation washer on the expansion bolt

    Step 3 Move the cabinet onto the installation holes, place the expansion bolt assemblies into the holes,and partially tighten them, as shown in the following figure.

    CAUTION

    The cabinet is heavy so that two persons are required to move it.

    Figure 9-4Installing the cabinet

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    59

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    69/175

    Step 4 Use a level to check the levelness of the cabinet, as shown in the following figure. If the cabinetis not level, adjust the leveling bolts.

    NOTE

    Screwing the bolts clockwise will raise the cabinet, and screwing the bolts counterclockwise will lower the

    cabinet.

    Figure 9-5Checking the levelness of the cabinet

    Step 5 Use a socket wrench to fasten the cabinet in a diagonal sequence onto the concrete floor with atorque of 45 Nm (398.28 lbfin.), as shown in the following figure.

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    60

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    70/175

    Figure 9-6Securing the cabinet

    Step 6 Check the insulation between the cabinet and expansion bolt assemblies.

    1. Set the multimeter to the megohm scale (M).

    2. Measure the resistance between the cabinet and the expansion bolt assemblies, as shown

    in the following figure.

    Figure 9-7Measuring the resistance

    (1) Expansion bolt assembly (2) Ground bar on the cabinet

    NOTE

    Measure the resistance between the ground bar on the cabinet and the expansion bolt assemblies.

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    61

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    71/175

    l If the resistance is lower than 5 M, the cabinet is not insulated from the ground. Go

    to 7.c.

    l If the resistance is higher than 5 M, the cabinet is insulated from the ground.

    3. Remove the expansion bolt assemblies and check whether the insulation washers are

    missing or damaged.

    l If yes, reinstall the expansion bolt assemblies and re-level the cabinet.

    l If no, check whether the multimeter works properly and whether the setting is correct.

    ----End

    9.2 Installing a Cabinet on a Base

    This section describes the procedure and precautions for installing a BTS3900 AC or DC cabinet

    on a base.

    Context

    To facilitate operations, you can remove the cabinet door and then install the cabinet.

    Procedure

    l Install a BTS3900 DC cabinet on a base.

    1. Stand the cabinet, place the cabinet on the base, and push the cabinet until its rear

    aligns with the rear of the base.

    CAUTION

    The cabinet is heavy so that two persons are required to move it.

    2. Use a torque wrench to secure the two M12x50 bolts in the front of the cabinet to 45

    Nm (398.28 lbfin.), as shown in the following figure.

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    62

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    72/175

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    73/175

    CAUTION

    The cabinet is heavy so that two persons are required to move it.

    3. Install the fixture block with the M12x60 expansion bolt onto the front of the cabinet,

    and use a socket wrench to tighten the bolt to 45 Nm (398.2 lbfin), as shown in the

    following figure.

    Figure 9-10Installing a BTS3900 AC cabinet

    ----End

    9.3 Installing Cabinets Side by Side

    This section describes the procedure and precautions for installing two BTS3900 cabinets side

    by side. The combination of One BTS3900 (Ver.D) AC cabinet and one BTS3900 (Ver.D) DC

    cabinet doesn't support this installation.

    Procedure

    Step 1 Remove the connection plates on the top of the cabinets, as shown in the following figure.

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    64

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    74/175

    Figure 9-11Removing the connection plates

    Step 2 Install the connection plates in the way shown in the following figure, and then use a torquescrewdriver to tighten the M5 screw to 2 Nm (17.7 lbfin.), as shown in the following figure.

    Figure 9-12Installing the connection plates

    ----End

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    65

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    75/175

    9.4 Stacking Two Cabinets

    This section describes the procedure and precautions for stacking two BTS3900 cabinets.

    BTS3900 (Ver.D) AC cabinet should not be stacked.

    Procedure

    Step 1 Remove the screws and connection plates from the top of the lower cabinet, and install themounting blocks on the top rear of the cabinet. Then use a socket wrench to secure the bolts to

    45 Nm (398.28 lbfin.). as shown in the following figure. The mounting block is delivered with

    the cabinet.

    Figure 9-13Removing the screws and connection plates

    (1) M12 screw (2) Connection plate (3) Mounting block

    Step 2 Remove the cover plate from the top of the upper cabinet, as shown in the following figure.

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    66

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    76/175

    Figure 9-14Removing the cover plate

    Step 3 Place one cabinet on the top of the other cabinet, and push the upper cabinet until the two cabinetsare aligned in the rear. Use a socket wrench to secure the front two M12x55 bolts to 45 Nm

    (398.28 lbfin.). The following figure shows the BTS3900 cabinets installed in stacking mode.

    Figure 9-15Securing the cabinet

    ----End

    BTS3900(Ver.D)

    Installation Guide 9 Installing the Cabinet

    Issue 03 (2014-08-30) Huawei Proprietary and Confidential

    Copyright Huawei Technologies Co., Ltd.

    67

  • 8/9/2019 BTS3900 (Ver.D) Installation Guide(V100R009C00_03)(PDF)-En

    77/175

    10Installing a PGND Cable and anEquipotential Cable

    A PGND cable connects a PGND screw in a cabinet and a PGND bar to ensure proper grounding

    of the cabinet. An equipotential cable connects PGND screws on different cabinets to ensure the

    equipotential bonding between the cabinets.

    Context

    The following table lists the specifications of a PGND cable and an equipotential cable.

    Table 10-1Specifications of a PGND cable and an equipotential cable

    Cable One End The Other End Remarks

    PGND cable OT terminal (M8) OT terminal (M8) Green and yellow

    cable

    l 1x160 A: 25

    mm2(0.039 in.2)

    l 2x80 A: 16 mm2

    (0.025 in.2)

    Equipotential cable OT terminal (M6) OT terminal (M6) Green and yellow

    cable with a cross-

    sectional area of 16mm2(0.025 in.2)

    Procedure

    l Install a PGND cable.

    1. Cut the cable to a length suitable for the actual cable route.

    2. Add OT terminals at each end of the cable according to the instructions in Assembling

    the OT Terminal and the Power Cabl