CAP1400 R&D and Global Application
Dr. Zheng MingguangChief Designer, President of SNERDI
Senior Vice President of SNPTC 2016.5.18
@SNERDI 2016. All Rights Reserved.
知识产权声明
本文件的知识产权上海核工程研究设计院及其相关产权人所有,并含有其保密信息。对本文件的
使用及处置应严格遵循获取本文件的合同及约定的条件和要求。未经上海核工程研究设计院事先
书面同意,不得对外披露、复制。
Intellectual Property Rights Statement
This document is the property of and contains proprietary information owned by SNERDI and/or its
related proprietor. You agree to treat this document in strict accordance with the terms and conditions of
the agreement under which it was provided to you. No disclosure or copy of this document is permitted
without the prior written permission of SNERDI.
@SNERDI 2016. All Rights Reserved.
Contents
1. Overview in China
2. CAP1400 development
3. CAPs - CAP200/50
4. CAP1400 Global Application
5. Summary
@SNERDI 2016. All Rights Reserved.
The installed Capacity by the end of 2015 was 1510GW , increased about
150GW compared to 2014, while the installed capacity of non-fossil energy
raised to 35% from 29% of 2011.
In 2015, 8 units connected to grid, and 6 units received the construction permits.
By 2015, the capacity of nuclear is ~1.6%, but NPPs provided the power ~2%.
1、Overview - Electric Supply in China
@SNERDI 2016. All Rights Reserved.
CNP300/600
Gen-II+ Tech
Self design\manufacture\
construction\operation
AP1000/CAP1000
Gen-III Tech introduction/
absorption/innovation
CAP1400/HPR1000
Gen-II+ Tech
M310/VVER/Candu6
/CPR1000
CPWR1000/CNP1000
1、 Overview - NPP in China
with over 60 years continuous development China has established comprehensive
nuclear power industry system, powerful equipment manufacturing capability, sound
regulation framework, competent human resources and nuclear safety culture system.
@SNERDI 2016. All Rights Reserved.
30 units, 28.38GW in operation
24 units , 26.6GW under construction
30 units under Preliminary Work Permission
Statistics by Feb.2016
HONGYANHE
HAIYANG
SHIDAOWAN(HTR)
TIANWAN
QINSHAN (PHASE –I/II/III)
FANGJIASHAN
SANMEN
NINGDE
FUQING
DAYAWAN
LINGAO
YANGJAING
TAISHANCHANGJAING
FANGCHENGGANGNPPs in OperationNPPs under construction
(PHASE –I/II)
1、 Overview - NPP in China
@SNERDI 2016. All Rights Reserved. Resources Production VS Consumption of Energy
Economic developed zone without primary resource
of energy, ONLY Nuclear power is the feasible
solution.
1、 Overview - NPP in China
@SNERDI 2016. All Rights Reserved.
1、Overview - Gen-III technology import and progress
2007, AP1000 technology was decided to be transferred and imported from WEC by
central government of China, and world’s first four AP1000 units were constructed in
Sanmen and Haiyang for the scale development of nuclear power.
The installation of Unit 1 of Sanmen and Haiyang were completed, and the tests are
undergoing. Now, the absorption and assimilation of the transferred technologies were
basically completed. And based on passive technology and previous experiences, R&D
platform for series passive models was established.
Main pump installation at Haiyang, 2016.3 Sanmen 2016.2 Haiyang 2016.2
@SNERDI 2016. All Rights Reserved.
Chinese Advanced Passive PWR>1400MWe
CAP1400
National key project
Own Intellectual Property
Leaded by Chinese government
(NEA, MOST by State council)
Performed by SNPTC/SNERDI
Supported and involved by
domestic and foreign entity
Based on advanced passive
philosophy and AP1000
Based on experience and
feedbacks from AP1000 projects
2、CAP1400 development – Major part of national
key project
Remarks: Four parts of NKP, which are Enhancement of Industry
Base, AP1000 introduction, Development of CAP1400 and feasibility
study of CAP1700 .
As major part of NKP, CAP1400 development support the nuclear power
sustainable development and the global application strategy.
@SNERDI 2016. All Rights Reserved.
2010.6
Conceptual
Design
finished
2011.12
Basic Design
finished
2014.9
PSAR review
Finished
2016.01
Detailed design
nearly
completed
2007
Proposal
prepared
2014.10
Key tests
before FCD
completed
1 2 3 4 5 6
2、CAP1400 development - Road Map
@SNERDI 2016. All Rights Reserved.
2、CAP1400 development - Requirements of TT
contract meeting for IDP
3730 MWt
First scheme Intermediate
scheme
3820 MWt 4040 MWt 4040 MWt
Concept Design Basic Design
Gross electric
power≥1350MWe
FA from 157193
CV diameter
unchanged
SG improvement
RCP adjusted
Site coverage
Increasing nuclear
power
CV diameter
unchanged
SG improvement
Increasing heat
transfer area
RCP adjusted
Net power ≥
1350MWe
Increasing CV
diameter (project
experience feedback)
Continued
Increasing heat
transfer area of SG
Re-design of RCP
117% Flow rate
121% flow rate
according to the
RCP R&D feedback
Optimization of
general parameters
Increasing average
temperature to 304°
Second side
efficiency
optimization
@SNERDI 2016. All Rights Reserved.
Parameters CAP1400
Core thermal power, MWt 4040
Electric power, MWe ~1500
RCS average temp, ℃ 304
RCS pressure, MPa(a) 15.5
Fuel assemblies 193
Fuel assembly type RFA or Innovated design
Average linear power, W/cm 181
SG type SNP140
SG outlet pressure, MPa (a) 6.0
Steam flow per loop, kg/s 1122
Design flow per pump, m3/h 21642
DNBR margin >15%
2、CAP1400 development - General Parameters
@SNERDI 2016. All Rights Reserved.
SSE 0.3g
HCLPF 0.56-0.96g
Containment design margin 10%
Enhancing capacity to
respond BDBA
• Backup power
• Backup water
• Emergency rescue
• Less waste water
Improve defense in depth
• Non-safety structure
• System and equipment
• Improving seismic capacity and
reliability of power supply
Safety
design
Optimization and balance system
design
• Improved and enhanced safety system
• Capacity allocation of key equipment
• Further enhance the safety design
margin
CDF
LRF
4.02E-7
5.21E-8
CAP1400
Accident response is better, more reliable
in BDBA condition.
GEN2
SSE 0.2g
GEN3
HCLPF
0.5~
0.9g
2、CAP1400 - Safety Performance
@SNERDI 2016. All Rights Reserved.
Economy
~1500MWe(gross)
~Systematic optimization for efficiency
Self reliant development and design1
Key equipment and
material localized
2 Localization
Mature & competitive
equipment supply chain
3 Equipment Supply Chain
Simplified4
2、CAP1400 development - Economy Balance
@SNERDI 2016. All Rights Reserved.
2、CAP1400 development - Other Advancement
besides safety and economy
• LESS philosophy applied: less welding
seam, less spare parts, less waste
generated
• MOX fuel capability (8 control rods
increased)
• RVI redesigned, the neutron shield pad
no longer needed, flow skirt removed
• Enhanced design margin and increased
operation flexibility (CV, squib, base)
• D-RAP implemented
• Utilize the latest safety design standards, As
High As Reasonable Achievable
• Meet the strictest discharge standard, As Low
As Reasonable Achievable
• Integration of human factors balanced PSA
and D-RAP
@SNERDI 2016. All Rights Reserved.
2. CAP1400 development - ALARA in Radiation
Protection & Release
Source control: low cobalt material to minimize the corrosive product,
MSHIM to reduce the boron liquid radwaste, “Zero” crack of fuel cladding.
Process control: advanced process control philosophy like MSHIM
Advanced technology: activated-charcoal treatment technology to reduce
gas waste, Ion exchange and chemical coagulation process for liquid waste,
volume reduction for solid waste.
Reduce the working period of inspection and maintenance
Increase the operating distance
Validate the shielding measure Reduce the radiation source
ALARA
@SNERDI 2016. All Rights Reserved.
2. CAP1400 development - Aircraft Crash Resistance
Steel plate reinforced concrete structure
and high compression strength concrete
to resist large commercial aircraft crash.
@SNERDI 2016. All Rights Reserved.
Scope and depth are Unprecedented
• 5 additional special area review.
• Over 5000 questions replied
• The review requirements reflected in the detailed design.
After the review, NNSA believed the CAP1400 could meet the latest
China and IAEA nuclear safety standards.
Preliminary work
approved
2013.03
Two Evaluation Report
approved
2013.06
Feasibility Study
Report Approved
2014.07
Licensing Review
2013.04~2014.09
Feb. 25th, 2016, CAP1400
PSAR passed the safety review
2、CAP1400 development – To promote National
Safety Review capability
@SNERDI 2016. All Rights Reserved.
All tests before FCD were finished, supporting the design,
safety review, and software development as well as V&V.
Totally 887 cases performed.
ACME complex CERT facility Facility for FIV testIVR test facility
Facility for hydro-
simulation
Facility for SG steam-
water separation test
Tests for passive safety systems
• PXS performance test
• PCS performance test
• IVR test
Tests for key equipment
• SG hot-stage
performance test
• Core hydro-simulation
test
• Reactor internal flow-
induced vibration test
2、CAP1400 development – To promote R&D Tests
capability
@SNERDI 2016. All Rights Reserved.
Software system for design and analysis established and moving forward
COre & System INtegrated Engine for design and analysis (COSINE) developed
系统程序
子通道程序
安全壳程序
组件程序
堆芯程序
SA
PSA
Shielding
Reactor M-C
Integrated comprehensive analysis platform
System
Subchannel
Containment
Lattice phy
Reactor core
Neutron kin
Data processingFuel design
2、CAP1400 development – To promote
Software development
@SNERDI 2016. All Rights Reserved.
2、CAP1400 development – To promote Equipment
Manufacturing capability
Over 27 Billion RMB invested, with the manufacturing capability
of ~6 sets per year for Gen-III plants, the localization is >85%
Qualified supply chain established, including 105 domestic , 9
joint venture, and 23 overseas companies. Key equipment is
able to be domestically manufactured.
The manufacturing capability realized from Gen-II to Gen-III
through National Key Project.
@SNERDI 2016. All Rights Reserved.
1# nozzle 1# head
2# nozzle 2# head
CAP1400 RPV
2、CAP1400 development - Equipment Manufacturing (RPV)
@SNERDI 2016. All Rights Reserved.
Drill
2A tube sheet
2A head
2A conical shell
2A shell
STEAM GENERATOR
2、CAP1400 development - Equipment Manufacturing (SG)
@SNERDI 2016. All Rights Reserved. Canned pump material is basically localized
WET
WINDING
PUMP
2、CAP1400 development - Equipment Manufacturing (RCP)
@SNERDI 2016. All Rights Reserved. Spent fuel cooling pump Start-up feedwater pump
Pneumatic two diaphragm
pump
CVS charging pump RNS PUMP
6 category & 8 class
pump prototypes
were developed,
among which 3
finished EQ
2、CAP1400 development - Equipment Manufacturing (Pumps)
Component cooling water pump
@SNERDI 2016. All Rights Reserved.
Main steam isolation valve
ADS valve body
Main steam
safety valve
Electric check valve
Low pressure gap
check valve
Main feedwater
control valvePZR spraying valve
Various types of valve’s
prototypes were developed and
to be EQ qualified
2、CAP1400 development - Equipment Manufacturing (Valves)
Big Din Gate valve
@SNERDI 2016. All Rights Reserved.
• Prototype explosion unit
test finished
• DN450 squib valve
engineering model
explosion test finished
2、CAP1400 development - Equipment Manufacturing (Squib
Valves)
@SNERDI 2016. All Rights Reserved.
SG U-tubes were developed and industrialized
All 21 welding materials were developed and
domestically manufactured.
TIG welding wireStainless steel SAWRPV welding wire and flux SAW equipment
SAW wire and flux
2、CAP1400 development - Equipment Manufacturing (U tube
& welding material)
U- tubes
@SNERDI 2016. All Rights Reserved.
• Reactor protection system (NuPACR) and plant control system (NuCONTM) were self-developed
and tested in 2014. NuCON on-trial started 。
• MCR design fully considerate HFE, to improve the usability, operability, and interface.
• High reliability.
NuPAC standardized engineering model
2、CAP1400 development - Equipment Manufacturing
(Control and Protection System)
@SNERDI 2016. All Rights Reserved.
CAP1400 Zircaloy Alloy
AP1000 Zr production line certificate issued
Self-Developed CAP1400 Fuel Assembly Preliminary Design
Stage Finalization
Critical Material Manufacturing Technology Breakthrough
(Nuclear Grade Zirconium Sponge Melting, Nuclear Grade
Zirconium Alloy Manufacturing, etc)
Critical Fuel Assembly Manufacturing Equipment Localization
(Integral Fuel Burnable Absorber Coating Equipment, Grid Laser
Welding Equipment, etc)
A Full Series of Nuclear Fuel Industrial Chain has been
established which will continuously support AP1000 Fuel
Assembly Localization and CAP1400 Fuel Assembly
Development.
Based on assimilation of AP1000 fuel technology, through
re-test and re-innovation, CAP1400 fuel assembly and
manufacturing system were established.
2、CAP1400 development - Equipment Manufacturing (fuel)
@SNERDI 2016. All Rights Reserved.
Advance Reactors
Small Reactors
Integral
Compact
Gen IV SFR, MSR
3、CAP - S Besides CAP1400 and CAP1700
Multi-purpose and multi-
power grade small
reactor
CAP50
@SNERDI 2016. All Rights Reserved.
3、 CAP200 General Design Parameters
Core thermal power 660 MWt
Electric power output >200MWe
Design plant lifetime 60 years
Operating pressure 15.5 MPa
Fuel Assembly89 shorten CAP1400 Fuel assemblies
2.4 m active length
Control Rod Assemblies 37
Average Linear Power
Density114 W/cm
Operation cycle length 24 -33 Months
Plant layout Single Arrangement
Reactor type 2-loop PWR
Safety system Passive system, None operator
intervention required for 7 days
Containment Underground
RCS Flow Rate 12000 m3/RCP
@SNERDI 2016. All Rights Reserved.
3、CAP50 - Nuclear Floating Platform
50MWe/200MWt with desalination over 3000 tons/day
Proven semi-submerged Platform design
Proven fuel and core design
Proven key equipments
Proven passive safety systems using ocean as ultimate heat sink
@SNERDI 2016. All Rights Reserved.
Global application of CAP1400 is a complicated systematic project. Besides
the advanced technology, it shall meet the new market needs by establishing
“government-industry-education-research-banking” collaboration mode.
UK
BRASIL
ARGENTINASOUTH
AFRICA
VIETNAM
PAKISTAN
TURKEY
BULGARIA
4、NPP Global Application such as CAP1400 and
CAPs
Indian
@SNERDI 2016. All Rights Reserved.
4、NPP Global Application for Chashma projects
Pakistan
Chashma NPPs in Pakistan, C1-C4, designed by SNERDI
• C1 COD 2000.6
• C2 COD 2011.3
• C3~C4 COD to be 2016~2017•Design Phase, partly participation
•Improve the technical ability of Owner
Design Participation
•Related to 115 items, including tools, storage racks, tanks, heat exchanger, cooler, separator, filter etc
Localizationsupport
•Cooperate with Pakistan, complete the technology transfer
•More than 200 technicians participated
TechnologyTransfer
•Using of training resources, provide the training to Pakistan technicians
•Develop the training plan
Talents training
•Ensure Safety
•Create ValueTechnicalSupport
How the export goes?
@SNERDI 2016. All Rights Reserved.
4、NPP Global Application Preconditions both for
import and export
Fundamental industrial infrastructure
Stable political environment
Continuous policies and efforts to push forward
Public acceptance to nuclear power
Nuclear safety culture and related agencies
For importing country For exporting country
Support from home government
competitiveness of NPP both technology and economy
comprehensive equipment supply industry chain
sound regulation system
Sustainable research and technology service capability
Investment and financing ability
@SNERDI 2016. All Rights Reserved.
RSA government is about to commence RFP(request for proposal)
ESKOM is the utility and operator of new built NPPs
2014-04, SNPTC, ICBC, and South Africa Standard Bank singed “Financing Frame Agreement for South
Africa Nuclear Power Plant”.
2014-04, SNPTC and NECSA signed “Nuclear Power Training and Cooperation Agreement in Beijing.
Up to now, 2 rounds of training program have carried out.
On 29th, September, 2015, National Assembly Chairperson of South African, Cedric Thomas Frolick
visited SNERDI.
2015-12, President Xi Jinping and South African President Jacob Zuma Witness the Signing of “CAP1400
Project Management Cooperation Agreement” between SNPTC and NECSA.
4、NPP Global Application - RSA
@SNERDI 2016. All Rights Reserved.
• Turkey Government has made plan that the nuclear power capacity increases from 0% present to 5% in 2023, and has proposed 3 sites.
• SNPTC,WEC and EUAS signed MOU for 2 AP1000 and 2 CAP1400 in Nov/24/2014.
• DR submitted to Turkey DOE in 2015.
• 2016.3.24 energy and natural resource Minister visited SNERDI
4、NPP Global Application - Turkey
@SNERDI 2016. All Rights Reserved.
• SAGNE committee
• CAP1400 got through GSR
• Academic exchange and host international conference
With IAEA
• ANS、WNA、ASME、GRS、
EPRI、IEEE、Tecnatom、
OECD….
With other
international
organization
• Michigan、OSU、Purdue、
TAMU…With
universities
4、NPP Global Application - Cooperation with
international organizations
@SNERDI 2016. All Rights Reserved.
5、 Summary
Presently, China government efforts to promote Belt And
Road strategy, which aims to achieve common development with
all countries.
The CAP1400 development would promote China’s nuclear
power industry, including equipment manufacturing, test and
research, regulation review, etc., from Gen-II to Gen-III.
Therefore it can encourage the nuclear power export.
SNERDI has successful experiences for both import and
export.
CAP1400, CAP-S and the serial passive models are able to
support the world application of NPP.