  • 7/31/2019 CAPM-StudyNotes

    1/21

    KnowledgeArea

    Processes

    Project Management Process Groups

    InitiatingSelect project manager,consider enterpriseenvironmental factors &organizational process assets,use project selection methods(benefit measurement &

    constrained optimization),consider contracts SOW (ifapplicable), determine lifecycleapproach, identify keystakeholders, determinebusiness needs (strategicobjective/MBO), productdescription, complete high-levelfeasibility studies.

    Planning Executing Monitoring and Controlling

    Monitor, scope/schedule/cost/qualitycontrol, inspect, validate, integratedchange control, risk monitoring andcontrol, recommend correctiveaction/changes, quality control,

    performance reporting, managepro ject team/stakeholder communications, contractadministration

    Closing

    Administrative closure strategy,contract closure/contract file,verify SOWs, productverification/handoff, formalproduct acceptance (point of

    total acceptance), f inalperformance reporting, lessonslearned, formal projectacceptance, archive project-related documents, releaseresources

    4. Project IntegrationManagement

    Develop Project Charter (4.1)

    Project Charter

    Develop Preliminary ScopeStatement (4.2)

    Preliminary ScopeStmt.

    Develop Project Management Plan(4.3)

    Project Mgmt. Plan

    Direct and Manage ProjectExecution (4.4)

    Deliverables

    Req. Changes

    Implemented Change

    Requests Corrective Action

    Preventive Actions

    Defect Repairs

    Work PerformanceInformation

    Monitor and Control Project Work(4.5)

    Recommended correctiveand preventative actions

    Forecasts

    Defect Repair Req. Changes

    Integrated Change Control (4.6)

    Approved & RejectedChange Requests

    Project Mgmt . PlanUpdates

    Project Scope Stmt.Updates

    Approved Corrective &Preventive Actions

    Approve & Validated DefectRepair

    Deliverables

    Close Project (4.7)

    Administrative &Contract ClosureProcedure

    Final Product Service

    or Result Organizational

    Process AssetsUpdates

    5. Project ScopeManagement Scope Planning (5.1)

    Scope Mgmt Plan

    Scope Definition (5.2)

    Scope Statement

    Req. Changes

    Scope Mgmt. PlanUpdates

    Create WBS (5.3)

    Scope Stmt. Updates

    WBS

    WBS Dictionary Scope Baseline

    Scope Verification (5.4)

    Accepted Deliverables

    Requested Changes

    Recommend CorrectiveActions

    Scope Control (5.5)

    Scope Stmt. Updates

    WBS Updates

    WBS Dictionary Updates

    Scope Baseline Updates Req. Changes

    Recommend CorrectiveAction

  • 7/31/2019 CAPM-StudyNotes

    2/21

    Scope Mgmt PlanUpdates

    Req. Changes

    Organizational ProcessAssets Updates

    Project Mgmt . PlanUpdates

    KnowledgeArea

    Processes

    Project Management Process Groups

    Initiating Planning Executing Monitoring and Controlling Closing

    6. Project Time

    Management

    Activity Definition (6.1)

    Activity List & Attributes

    Milestone List

    Req. Changes

    Activity Sequencing (6.2)

    Network Diagram

    Activity List & Attributes Updates

    Req. Changes

    Activity Resource Estimating (6.3)

    Resource Requirements

    Activity Attributes Updates

    RBS

    Resource Calendar Updates

    Req. Changes

    Activity Duration Estimating (6.4)

    Activity Duration Estimates

    Activity Attributes Updates

    Schedule Development (6.5)

    Project Schedule

    Schedule Model Data

    Schedule Baseline

    Resource Requirements Updates

    Activity Attributes Updates

    Project Calendar Updates

    Req. Changes

    Project Mgmt. Plan Updates

    Schedule Mgmt. Plan Updates

    Schedule Control (6.6)

    Schedule Model DataUpdates

    Schedule Baseline Updates Performance Measurement

    Req. Changes

    Recommend CorrectiveAction

    Organizational ProcessAssets Updates

    Activity List & AttributeUpdates

    Project Mgmt . PlanUpdates

    7. Project CostManagement Cost Estimating (7.1)

    Activity Cost Estimates & SupportingDetail

    Req. Changes

    Cost Mgmt. Plan Updates

    Cost Budgeting (7.2)

    Allocate & Aggregate

    Cost Baseline (includes contingencyreserves but not Mgmt contingencyreserves)

    Project Funding Requirements Cost Mgmt. Plan Updates

    Req. Changes

    Cost Control (7.3)

    Cost Estimate & BaselineUpdates

    Performance Measurement

    Forecasted Completion

    Req. Changes

    Recommend CorrectiveAction

    Organizational ProcessAssets Updates(Specifically lessonslearned)

    Project Mgmt. PlanUpdates

  • 7/31/2019 CAPM-StudyNotes

    3/21

  • 7/31/2019 CAPM-StudyNotes

    4/21

    KnowledgeArea

    Processes

    Project Management Process Groups

    Initiating Planning Executing Monitoring and Controlling Closing

    8. Project QualityManagement

    Quality Planning (8.1)

    Continuous Improvement

    Quality Policy

    Quality Mgmt. Plan

    Quality Metrics Quality Checklists

    Process Improvement Plan

    Quality Baseline

    Project Mgmt. PlanUpdates

    Perform Quality Assurance (8.2)

    Req. Changes

    Recommend CorrectiveActions

    Organization Process AssetsUpdates

    Project Mgmt. Plan Updates

    Perform Quality Control (8.3)

    Quality Controlmeasurements

    Validated Defect Repair

    Recommended Corrective& Preventive Action

    Req. Changes

    Recommend Defect Repair

    Organizational ProcessAssets Updates

    Validated Deliverables

    Project Mgmt. PlanUpdates

    9. Project HumanResource

    Management

    Human Resources Planning (9.1)

    Roles & Responsibilities

    Project Org. Charts

    Staffing Mgmt. Plan

    Acquire Project team (9.2)

    Project Staff Assignments

    Resource Availability

    Staffing Mgmt. Plan Updates

    Develop Project Team (9.3)

    Team PerformanceAssessment

    Manage Project Team (9.4)

    Req. Changes

    Recommended Corrective& Preventive Actions

    Organizational ProcessAssets Updates

    Project Mgmt. PlanUpdates

    10. ProjectCommunications

    ManagementCommunications Planning (10.1)

    Communications Mgmt.Plan

    Information Distribution (10.2)

    Organizational ProcessAssets Updates

    Req. Changes

    Performance Reporting (10.3)

    Performance Reports

    Forecasts

    Req. Changes

    Recommended CorrectiveActions

    Organization ProcessAssets Updates

    Manage Stakeholders (10.4)

    Resolved Issues

    Approved Change Request

    Approved CorrectiveActions

    Organizational ProcessAssets Updates

    Project Mgmt. PlanUpdates

  • 7/31/2019 CAPM-StudyNotes

    5/21

  • 7/31/2019 CAPM-StudyNotes

    6/21

    KnowledgeArea

    Processes

    Project Management Process Groups

    Initiating Planning Executing Monitoring and Controlling Closing

    11. Project RiskManagement

    Risk Management Planning (11.1)

    Risk Management Plan

    Risk Identification (11.2)

    Risk Register

    Qualitative Risk Analysis (11.3)

    Risk Register Updates

    Quantitative Risk Analysis (11.4)

    Risk Register Updates

    Risk Response Planning (11.5)

    Risk Register Updates

    Project Mgmt. PlanUpdates

    Risk-related ContractualAgreements

    Risk Monitoring and Control (11.6)

    Risk Register Updates Req. Changes

    Recommended Corrective& Preventive Action

    Organizational ProcessAssets Updates

    Project Mgmt. PlanUpdates

    12. ProjectProcurementManagement

    Plan Purchases Acquisitions (12.1)

    Procurement Mgmt. Plan

    SOW

    Make-or-buy decisions

    Req. Changes

    Plan Contracting (12.2)

    Procurement Document

    Evaluation Criteria

    SOW Updates

    Request Seller Responses (12.3)

    Qualified Sellers List

    Procurement DocumentPackage

    Proposals

    Select Sellers (12.4)

    Selected Sellers

    Contract

    Contract Mgmt. Plan

    Resource Availability

    Procurement Mgmt. PlanUpdates

    Req. Changes

    Contract Administration (12.5)

    Contract Documentation

    Req. Changes

    Recommended CorrectiveAction

    Organizational ProcessAssets Updates

    Project Mgmt. PlanUpdates (Procurement &Contract Mgmt. Plan)

    Contract Closure (12.6)

    Closed Contracts

    OrganizationalProcess AssetsUpdates

  • 7/31/2019 CAPM-StudyNotes

    7/21

    INTEGRATION

    Process Inputs Tools/Techniques Outputs

    Initiating

    1. Develop Project Charter

    Contract (when applicable)

    Project SOW

    Enterprise environmental factors

    Organizational process assets

    Project selection methods

    Project management methodology

    Project management information system

    Expert judgment

    Project charter

    2. Develop Preliminary Project ScopeStatement

    Project charter

    Project SOW

    Enterprise environmental factors

    Organizational process assets

    Project management methodology

    Project management information system

    Expert judgment

    Preliminary Project Scope statement

    Planning

    3. Develop Project Management Plan

    Preliminary project scope statement

    Project management processes

    Enterprise environmental factors

    Organizational process assets(Which includes historical information and

    organizational policies)

    Project management methodology

    Project management information system

    Expert judgment

    Project Management Plan

    Executing

    4. Direct and Manage Project Execution

    Project Management Plan

    Approved corrective actions

    Approved preventive actions

    Approved change requests

    Approved defect repair

    Validated defect repair

    Administrative closure procedures

    Project management methodology

    Project management information system

    Deliverables

    Requested changes

    Implemented change requests

    Implemented corrective actions

    Implemented preventive actions

    Implemented defect repair

    Work performance information

    Controlling

    5. Monitor and Control Project Work

    Project Management Plan Work performance information

    Rejected change request

    Project management methodology Project management information system

    Earned value technique

    Expert judgment

    Recommended corrective actions Recommended preventive actions

    Forecasts

    Recommended defect repair

    Requested changes

    6. Integrated Change Control

    Project Management Plan

    Requested Changes

    Work performance information

    Recommended corrective actions

    Recommended preventive actions

    Recommended defect repair

    Deliverables

    Project management methodology

    Project management information system

    Expert judgment

    Approved change requests

    Rejected change requests

    Project Management Plan Updates

    Project Scope Statement Updates

    Approved corrective actions

    Approved preventive actions

    Approved defect repair

    Validated defect repair

    Deliverables

  • 7/31/2019 CAPM-StudyNotes

    8/21

    INTEGRATION

    Process Inputs Tools/Techniques Outputs

    Closing

    7. Close Project

    Project Management Plan

    Contract documentation

    Enterprise environmental factors

    Organizational process assets

    Work performance information

    Deliverables

    Project management methodology

    Project management information system

    Expert judgment

    Administrative closure procedure

    Contract closure procedure

    Final product, service, or result

    Organizational process assets updates

    SCOPE

    Process Inputs Tools/Techniques Outputs

    Planning

    1. Scope Planning

    Enterprise environmental factors

    Organizational process assets

    Project Charter

    Preliminary project scope statement Project Management Plan

    Expert Judgment

    Templates, forms, standards

    Project Scope Management Plan

    2. Scope Definition

    Organizational process assets

    Project Charter

    Preliminary project scope statement

    Project Scope Management Plan

    Approved change requests

    Product analysis

    Alternatives identification

    Expert judgment

    Stakeholder analysis

    Project Scope Statement

    Requested changes

    Project Scope Management Plan Updates

    3. Create WBS

    Organizational process assets

    Project Scope Statement

    Project Scope Management Plan

    Approved change requests

    WBS templates

    Decomposition

    Project scope statement updates

    WBS

    WBS dictionary

    Scope baseline

    Project Scope Management Plan Updates

    Requested changesControlling

    4. Scope Verification(Assures ACCEPTANCE)

    Project Scope Statement

    WBS Dictionary

    Project Scope Management Plan

    Deliverables

    Inspections Accepted deliverables

    Requested changes

    Recommended corrective actions

    5. Scope Control

    Project Scope Statement

    WBS

    WBS dictionary

    Project Scope Management Plan

    Workaround plans to risk

    Performance Reports Approved change requests

    Work performance information

    Change Control System

    Variance analysis

    Replanning

    Configuration management system

    Project scope statement updates

    WBS updates

    WBS dictionary updates

    Scope baseline updates

    Requested changes

    Recommended corrective action Organizational process assets updates

    Project Management Plan Updates

  • 7/31/2019 CAPM-StudyNotes

    9/21

    TIME

    Process Inputs Tools/Techniques Outputs

    Planning

    1. Activity Definition

    Enterprise environmental factors

    Organizational process assets

    Project Scope Statement

    WBS

    WBS Dictionary

    Project Management Plan

    Decomposition

    Templates

    Rolling Wave planning (Progressively)

    Expert judgment Planning component

    Activity List

    Activity attributes

    Milestone list

    Requested changes

    2. Activity Sequencing

    Project Scope Statement

    Activity List

    Activity attributes

    Milestone list

    Approved change requests

    Precedence Diagramming Method (PDM)

    Arrow Diagramming Method (ADM)

    Schedule network templates

    Dependency determination

    Applying leads and lags

    Project Network Diagrams

    Activity List Updates

    Activity attributes updates

    Requested changes

    3. Activity Resource Estimating

    Enterprise environmental factors

    Organizational process assets

    Activity list

    Activity attributes

    Resource availability

    Project Management Plan

    Expert judgment

    Alternatives analysis

    Published estimating data

    Project management software

    Bottom-up estimating

    Activity resource requirements

    Activity attributes updates

    Resource breakdown structure

    Resource calendars updates

    Requested changes

    4. Activity Duration Estimating

    Enterprise environmental factors

    Organizational process assets

    Project Scope Statement

    Activity List

    Activity attributes

    Activity resource requirements

    Resource calendars

    Project Management Plan- Risk register- Activity cost estimates

    Expert Judgment

    Analogous Estimating

    Parametric Estimating

    Three point estimates

    Reserve analysis

    Activity duration estimates

    Activity attributes updates

    5. Schedule Development

    Organizational process assets

    Project Scope Statement

    Activity List Activity attributes

    Project schedule network diagrams

    Activity resource requirements

    Resource calendars

    Activity Duration Estimates

    Project Management Plan Risk register

    Schedule network analysis

    Critical path method

    Schedule Compression

    What if scenario analysis (Monte Carlo) Resource Leveling

    Critical chain method

    Project management software

    Applying calendars

    Adjusting leads and lags

    Schedule model

    Project Schedule

    Schedule model data

    Schedule baseline Resource Requirement Updates

    Activity attributes updates

    Project calendar updates

    Requested changes

    Project Management Plan Updates

    Schedule Management Plan Updates

    Controlling

    6. Schedule Control Schedule Management Plan

    Schedule baseline

    Performance Reports

    Approved change requests

    Progress reporting

    Schedule Change Control System

    Performance Measurement

    Project management software

    Variance Analysis Schedule comparison bar charts

    Schedule model data updates

    Schedule baseline updates

    Performance measurements

    Requested changes

    Recommended corrective actions

    Organizational process assets updates

    Activity list updates

  • 7/31/2019 CAPM-StudyNotes

    10/21

    Activity attributes updates

    Project Management Plan Updates

  • 7/31/2019 CAPM-StudyNotes

    11/21

    COST

    Process Inputs Tools/Techniques Outputs

    Planning

    1. Cost Estimating

    Enterprise environmental factors

    Organizational process assets

    Project Scope Statement

    Work Breakdown Structure

    WBS Dictionary Project Management Plan

    - Schedule Management Plan- Staffing Management Plan- Risk register

    Analogous Estimating

    Determine resource cost rates

    Bottom-Up Estimating

    Parametric Estimating

    Project Management software Vendor bid analysis

    Reserve analysis

    Cost of quality

    Activity Cost Estimates

    Activity Cost Estimate Supporting Detail

    Requested changes

    Cost Management Plan updates

    2. Cost Budgeting

    Project Scope statement

    WBS

    WBS dictionary

    Activity Cost Estimates

    Activity Cost Estimate Supporting Detail

    Project Schedule

    Resource calendars

    Contract

    Cost Management Plan

    Cost Aggregation

    Reserve Analysis

    Parametric Estimating

    Funding limit reconciliation

    Cost Baseline (Same as budget)

    Project funding requirements

    Cost Management Plan updates

    Requested changes

    Controlling

    3. Cost Control

    Cost Baseline

    Project funding requirements

    Performance Reports

    Work performance information

    Approved change requests

    Project Management Plan

    Cost Change Control System

    Performance Measurement Analysis(Helps to assess the magnitude of any variation thatoccurs on the project)

    Forecasting

    Project Performance Reviews

    Project Management software

    Variance management

    Cost Estimate Updates

    Cost baseline updates

    Performance measurements

    Forecasted completion

    Requested changes

    Recommended corrective actions

    Organizational process assets updates

    Project Management Plan updates

  • 7/31/2019 CAPM-StudyNotes

    12/21

    QUALITY

    Process Inputs Tools/Techniques Outputs

    Planning

    1. Quality Planning

    Enterprise environmental factors

    Organizational process assets

    Project Scope Statement

    Project Management Plan

    Cost-Benefit Analysis

    Benchmarking

    Design Of Experiments

    Cost Of Quality

    Additional Quality Planning tools

    Quality Management Plan

    Quality metrics

    Quality checklists

    Process Improvement Plan

    Quality baseline Project Management Plan updates

    Executing

    2. Perform Quality Assurance(Aimed for Processes)

    Quality Management Plan

    Quality metrics

    Process Improvement Plan

    Work performance information

    Approved change requests

    Quality control measurements

    Implemented change requests

    Implemented corrective actions

    Implemented defect repair

    Implemented preventive actions

    Quality Planning Tools & Techniques

    - Cost-benefits analysis- Benchmarking- Design of experiments

    Quality Audits(Review of project activities with regard to quality)

    Process analysis

    Quality control tools and techniques

    - Cause and effect diagrams- Control, Pareto and Run charts,- Flowcharting- Histograms

    - Scatter diagrams- Statistical sampling- Inspection- Defect repair review

    Requested changes

    Recommended corrective actions

    Organizational process assets updates

    Project Management Plan updates

    Controlling

    3. Perform Quality Control(Aimed for Deliverables.

    Assures CORRECTNESS)

    Quality Management Plan

    Quality metrics

    Quality Checklists

    Organizational process assets

    Work performance information

    Approved change requests

    Deliverables

    Cause and effect diagram

    Control Charts

    Flowcharting

    Histogram

    Pareto chart

    Run chart

    Scatter diagram

    Statistical sampling

    Inspections

    Defect repair review

    Quality control measurements

    Validated defect repair

    Quality baseline updated

    Recommended corrective actions

    Recommended preventive actions

    Requested changes

    Recommended defect repair

    Organizational process assets updates

    Validated deliverables

    Project Management Plan updates

  • 7/31/2019 CAPM-StudyNotes

    13/21

    HUMAN RESOURCES

    Process Inputs Tools/Techniques Outputs

    Planning

    1. Human Resource Planning

    Enterprise environmental factors

    Organizational process assets

    Project Management Plan Activityresource requirements

    Organization charts and position descriptions

    Networking

    Organizational Theory

    Roles and responsibilities

    Project Organization Charts

    Staffing Management Plan

    Executing

    2. Acquire Project Team(Carries out the Staffing Management

    Plan)

    Enterprise environmental factors

    Organizational process assets

    Roles and responsibilities

    Project Organization Charts

    Staffing Management Plan

    Pre-assignment

    Negotiations

    Acquisition

    Virtual teams

    Project Staff Assignments

    Resource availability

    Staffing Management Plan updates

    3. Develop Project Team

    Project Staff Assignments

    Staffing Management Plan

    Resource availability

    General Management Skills

    Training

    Team-Building Activities

    Ground rules

    Co-location

    Recognition and rewards

    Team performance assessment

    Controlling

    4. Manage Project Team(Checks whether the Staffing

    Management Plan is working fine andevaluate team performance problems)

    Organizational process assets

    Project Staff Assignments

    Roles and responsibilities

    Project Organization Charts

    Staffing Management Plan

    Team performance assessment

    Work performance information

    Performance reports

    Observation and conversation

    Project performance appraisals

    Conflict management

    Issues log

    Requested changes

    Recommended corrective actions

    Recommended preventive actions

    Organizational process assets updates

    Input to organization performance appraisals

    Lessons learned documentation

    Project Management Plan updates

  • 7/31/2019 CAPM-StudyNotes

    14/21

    COMUNICATIONS

    Process Inputs Tools/Techniques Outputs

    Planning

    1. Communication Planning(Involves determining and documenting

    the information and communicationneeds of the stakeholders)

    Enterprise environmental factors

    Organizational process assets

    Project Scope Statement

    Project Management Plan -

    - Constraints,- Assumptions

    Communications requirements analysis

    Communication technology

    Communications Management Plan

    Executing

    2 . Information Distribution(Focuses on any kind of information

    related to project)

    Communications Management Plan Communications Skills

    Information Gathering and Retrieval Systems

    Information Distribution Methods

    Lessons learned process

    Organizational process assets updates- Lessons learned documentation- Project Records- Project Reports- Project Presentations- Feedback from stakeholders- Stakeholder notifications

    Requested changes

    Controlling

    3. Performance Reporting(Focuses solely on project performance)

    Work performance information

    Performance measurements

    Forecasted completion

    Quality control measurements

    Project Management Plan Performancemeasurement baseline

    Approved change requests

    Deliverables

    Information presentation tools

    Performance information gathering and compilation

    Status review meetings

    Time reporting systems

    Cost reporting systems

    Performance Reports

    Forecasts

    Requested changes

    Recommended corrective actions

    Organizational process assets updates

    4. Manage Stakeholders

    (Ensures that stakeholders needs areaddressed)

    Communications Management Plan

    Organizational process assets

    Communications methods

    Issue logs

    Resolved issues

    Approved change requests

    Approved corrective actions

    Organizational process assets updates

    Project Management Plan updates

  • 7/31/2019 CAPM-StudyNotes

    15/21

    RISK

    Process Inputs Tools/Techniques Outputs

    Planning

    1. Risk Management Planning

    Enterprise environmental factors

    Organizational process assets

    Project Scope Statement

    Project Management Plan

    Planning Meetings and analysis Risk Management Plan

    2. Risk Identification

    Enterprise environmental factors

    Organizational process assets

    Project Scope Statement

    Risk Management Plan

    Project Management Plan

    Documentation Reviews

    Information-Gathering Techniques(Interviewing, Delphi Technique and Brainstorming)

    Checklist analysis

    Assumptions Analysis

    Diagramming Techniques

    Risk register

    3. Qualitative Risk Analysis

    Organizational process assets

    Project Scope Statement

    Risk Management Plan

    Risk register

    Risk Probability & Impact Assessment

    Probability and Impact Matrix

    Risk Data Quality Assessment

    Risk categorization

    Risk urgency assessment

    Risk Register updates

    4. Quantitative Risk Analysis

    Organizational process assets

    Project Scope Statement

    Risk Management Plan

    Risk register

    Project Management Plan- Project Schedule Management Plan- Project Cost Management Plan

    Data gathering and representation techniques

    Qualitative risk analysis and modeling techniques

    Decision tree analysis

    Risk Register updates

    5. Risk Response Planning(Plans how each risk will be handled)

    Risk Management Plan

    Risk register

    Strategies for negative risk or threats

    Strategies for positive risks or opportunities

    Strategy for both threats and opportunities

    Contingent response strategy

    Risk Register updates

    Project Management Plan updates

    Risk-related contractual agreements

    Controlling

    6. Risk Monitoring & Control(Carries out the Risk Response Plan)

    Risk Management Plan

    Risk Register

    Approved change requests

    Work performance information

    Performance reports

    Risk reassessment

    Risk audits

    (Concerned with overall risk management insteadof individual risks)

    Variance and trend analysis

    Technical performance measurement

    Reserve analysis

    Status meetings

    Risk register updates

    Requested changes

    Recommended corrective actions- May include workaround plans which may arisescope changes

    Recommended preventive actions

    Organizational process assets updates

    Project Management Plan updates

  • 7/31/2019 CAPM-StudyNotes

    16/21

    PROCUREMENT

    Process Inputs Tools/Techniques Outputs

    Planning

    1. Plan Purchases and Acquisitions

    Enterprise environmental factors

    Organizational process assets

    Project Scope Statement

    WBS

    WBS dictionary Project Management Plan

    - Risk register- Risk-related contractual agreements- Resource requirements- Project Schedule- Activity cost estimates- Cost baseline

    Make-Or-Buy Analysis

    Expert Judgment

    Contract Types

    Procurement Management Plan

    Contract Statement of Work

    Make-or-buy decisions

    Requested changes

    2. Plan Contracting(Prepares documents for solicitation)

    Procurement Management Plan

    Contract Statement Of Work

    Make-or-buy decisions

    Project Management Plan

    - Risk register

    - Risk-related contractual agreements- Resource requirements- Project Schedule- Activity cost estimates- Cost baseline

    Standard Forms

    Expert Judgment

    Procurement Documents

    Evaluation Criteria

    Contract Statement of Work Updates

    Executing

    3. Request Seller Responses Organizational process assets

    Procurement Management Plan

    Procurement documents

    Bidder/Vendor/Contractor Conferences

    Advertising

    Develop qualified sellers list

    Qualified sellers list

    Procurement document package

    Proposals

    4. Select Sellers(Involves negotiation and selection)

    Organizational process assets

    Procurement Management Plan

    Evaluation Criteria Procurement document package

    Proposals

    Qualified Sellers list

    Project Management Plan- Risk register- Risk-related contractual agreements

    Weighting System

    Independent Estimates

    Screening system Contract negotiation

    Seller rating systems

    Expert judgment

    Proposal evaluation techniques

    Selected sellers

    Contract

    Contract Management Plan Resource availability

    Procurement Management Plan updates

    Requested changes

  • 7/31/2019 CAPM-StudyNotes

    17/21

    PROCUREMENT

    Process Inputs Tools/Techniques Outputs

    Controlling

    5. Contract Administration

    Contract

    Contract Management Plan

    Selected sellers

    Performance reports Approved change requests

    Work performance information

    Contract Change Control System

    Buyer-conducted performance review

    Inspections and audits

    Performance Reporting Payment System

    Claims administration

    Records management system

    Information technology

    Contract documentation

    (Contains requested, but unapproved contract changes)

    Requested changes

    Recommended corrective actions Organizational process assets updates

    Correspondence

    Contract Changes

    Payment Requests

    Project Management Plan Updates

    - Procurement Management Plan- Contract Management Plan

    Closing

    6. Contract Closure

    Procurement Management Plan

    Contract Management Plan

    Contract documentation

    Contract closure procedure

    Procurement audits(Capture lessons learned from a contractperspective)

    Records management system

    Closed contracts

    Organization process assets updates

    Components of the Project Management Plan:

    Project Scope Management Plan

    Schedule Management Plan

    Cost Management Plan

    Quality Management Plan

    Process Improvement Plan

    Staffing Management Plan

    Communication Management Plan

    Risk Management Plan

    Procurement Management Plan

    Milestone List Resource Calendar

    Schedule Baseline

    Cost Baseline (Same as budget)

    Quality Baseline

    Risk Register (which includes risk owners, risk thresholds and common risk causes)

    Constraints and Planning Assumptions

    For the exam the bottom line is : All management plans become part of the Project Management Plan

  • 7/31/2019 CAPM-StudyNotes

    18/21

    Components of the Enterprise Environmental Factors:

    Culture and Structure of the organization

    Governmental and Industry standards

    Infrastructure

    Human Resources

    Personnel Administration and Documentation

    Marketplace conditions

    Risk Tolerance

    Commercial Databases

    Academic Studies

    Project Management Information Systems (Which is composed by Configuration Management System including Change Management System)

    Project Quality Management DOES emphasize:

    Customers Specifications (That also implies in Customers Satisfaction because if customers specifications are met, the customer should be satisfied with the product)

    Quality Standards

    Team Responsibility (The entire team has a responsibility towards quality)

    Prevention over inspection (It costs less to fix a problem than it does to fix one)

    Types of diagrams/charts:

    Project Network diagrams (Show activities sequences and dependences)

    Precedence Diagramming Method (PDM) => Activities on nodes (Also known as AON Activity On Node)

    Arrow Diagramming Method (ADM) => Activities on arrows (Also known as AOA Activity On Arrow)

    Graphical Evaluate Review Technique (GERT) => Can show conditional branches and loops whereas other representations cannot.

    Bar Charts (a.k.a. Gantt Charts) (Show activities represented as horizontal bars and typically have calendar and percentage complete associated with them)

    Milestone Chart (Only represent key events for the project)

    Cause and Effect Diagrams (a.k.a. Fishbone Diagram or Ishikawa Diagram) (Are used in Quality Control process to show how different factors can lead to problems)

    Control Charts

    Show whether or not a process is in control. Containing.

    Customer Specification Limits,

    Control Limits Defined as three standard deviations above or below the mean

    Mean of all data points

    Rule of Seven where if seven or more consecutive points are on the same side of the mean, they should be investigated

  • 7/31/2019 CAPM-StudyNotes

    19/21

    Pareto Chart (A kind of a histogram that shows on columns defects ranked from greatest to least. Paretos law states that 80% of problems come from 20% of the causes 80/20)

    Run Chart (Quality measure snapshots compiled over time showing trends )

    Scatter Diagram (Best for spotting trends in data. May be No Relation, Negative Linear Correlation, and Positive Linear Correlation)

    Project Organizational Charts (Show project roles hierarchy or package associations)

    Hierarchical Charts (Shows project roles hierarchically)

    RACI Charts (R Responsible, A Accountable, C Consultant, I Input => Show project roles associated with work packages)

    Text (States the position description and responsibilities)

  • 7/31/2019 CAPM-StudyNotes

    20/21

    Resource Histogram (Its part of the Staffing Management Plan and shows the resource usage for a given period of time)

    Tornado Diagrams (Evaluates projects sensitivity to cost or other factors)

    Decision Tree Diagrams (Used to quantify which risks have the most impact on the project)

    Key Formulas:

    Term Abbreviation Description Formula

    Three Point Estimate PERTUsed to estimate activity duration based on knownPessimistic, Realistic and Optimistic estimates.Its also used to predict the most likely, best-caseand worst-case scenarios for a given costestimate.

    (Pessimist + 4xRealistic + Optimistic) / 6

    Standard DeviationShows how diverse our estimates are. (Pessimistic Optimistic) / 6

    Communication ChannelsShows how different communication channels existfor a given project

    N * (N 1) / 2Where N is the number of people in your team.

    Budgeted at Completion BAC How much was originally planned for this project tocost.

    No one formula exists. BAC is derived by looking atthe total budgeted cost for the project.

    Planned Value(a.k.a. Budgeted Cost of Work Scheduled)

    PV (or BCWS)

    How much work should have been completed ata point in time based on the plan. (Derived by

    measuring where you had planned to be in

    terms of work completed at a point in the

    schedule).

    PN = Planned % Complete X BAC

    Earned Value(a.k.a. Budgeted Cost of Work Performed)

    EV (or BCWP)

    How much work was actually completed during a

    given period of time. Derived by measuring where

    you actually are in terms of work completed during

    a given period of time in the schedule.

    EV = Actual % Complete X BAC

    Actual Cost(a.k.a. Actual Cost of Work Performed)

    AC (orACWP)The money spent during a given period of time.

    Sum of the costs for the given period of time.

    Cost Variance CV The difference between what we expected to

    spend and what was actually spent.

    CV = EV-AC

    Schedule Variance SVThe difference between where we planned to

    be in the schedule and where we are in the

    schedule.

    SV=EV-PV

    Cost Performance Index CPIThe rate at which the project performance is

    meeting cost expectations during a given

    period of time.

    CPI = EV / AC

  • 7/31/2019 CAPM-StudyNotes

    21/21

    Term Abbreviation Description Formula

    Schedule Performance Index SPIThe rate at which the project performance is

    meeting schedule expectations up to a point in

    time.

    SPI = EV / PV

    Cumulative CPI CPICThe rate at which the project performance is

    meeting cost expectations from the beginning up

    to a point in time. CPIC

    is also used to forecastproject costs at completion.

    CPIC = EVC / ACC

    Estimate at Completion EAC Projecting the total cost at completion based on

    project performance up to a point in time.

    EAC = BAC / CPIC

    Estimate to Completion ETC Projecting how much will be spent on the

    project, based on past performance.

    ETC = EAC - AC

    Variance at Completion VAC The difference between what was budgeted

    and what will actually be spent.

    VAC = BAC - EAC

    Tips for calculating EAC on different scenarios

    When current variances are viewed as typical of future variances :

    EAC is calculated by adding the remaining budget (BAC EV) modified by a performance factor (CPI), to the actuals date.

    When current variances are viewed as typical :

    EAC is calculated by adding the remaining budget to the actuals to date (BAC EV).In this case, the project management team expects that similar variances will no occur in the future.

    When original estimating assumptions are considered to be fundamentally flawed:

    EAC is calculated by adding an all-together new estimate (ETC) to the actuals to date.

    When original estimating assumptions are no longer reliable because conditions have changed:

    EAC is calculated by adding an all-together new estimate (ETC) to the actuals to date.