7/31/2019 CAPM-StudyNotes
1/21
KnowledgeArea
Processes
Project Management Process Groups
InitiatingSelect project manager,consider enterpriseenvironmental factors &organizational process assets,use project selection methods(benefit measurement &
constrained optimization),consider contracts SOW (ifapplicable), determine lifecycleapproach, identify keystakeholders, determinebusiness needs (strategicobjective/MBO), productdescription, complete high-levelfeasibility studies.
Planning Executing Monitoring and Controlling
Monitor, scope/schedule/cost/qualitycontrol, inspect, validate, integratedchange control, risk monitoring andcontrol, recommend correctiveaction/changes, quality control,
performance reporting, managepro ject team/stakeholder communications, contractadministration
Closing
Administrative closure strategy,contract closure/contract file,verify SOWs, productverification/handoff, formalproduct acceptance (point of
total acceptance), f inalperformance reporting, lessonslearned, formal projectacceptance, archive project-related documents, releaseresources
4. Project IntegrationManagement
Develop Project Charter (4.1)
Project Charter
Develop Preliminary ScopeStatement (4.2)
Preliminary ScopeStmt.
Develop Project Management Plan(4.3)
Project Mgmt. Plan
Direct and Manage ProjectExecution (4.4)
Deliverables
Req. Changes
Implemented Change
Requests Corrective Action
Preventive Actions
Defect Repairs
Work PerformanceInformation
Monitor and Control Project Work(4.5)
Recommended correctiveand preventative actions
Forecasts
Defect Repair Req. Changes
Integrated Change Control (4.6)
Approved & RejectedChange Requests
Project Mgmt . PlanUpdates
Project Scope Stmt.Updates
Approved Corrective &Preventive Actions
Approve & Validated DefectRepair
Deliverables
Close Project (4.7)
Administrative &Contract ClosureProcedure
Final Product Service
or Result Organizational
Process AssetsUpdates
5. Project ScopeManagement Scope Planning (5.1)
Scope Mgmt Plan
Scope Definition (5.2)
Scope Statement
Req. Changes
Scope Mgmt. PlanUpdates
Create WBS (5.3)
Scope Stmt. Updates
WBS
WBS Dictionary Scope Baseline
Scope Verification (5.4)
Accepted Deliverables
Requested Changes
Recommend CorrectiveActions
Scope Control (5.5)
Scope Stmt. Updates
WBS Updates
WBS Dictionary Updates
Scope Baseline Updates Req. Changes
Recommend CorrectiveAction
-
7/31/2019 CAPM-StudyNotes
2/21
Scope Mgmt PlanUpdates
Req. Changes
Organizational ProcessAssets Updates
Project Mgmt . PlanUpdates
KnowledgeArea
Processes
Project Management Process Groups
Initiating Planning Executing Monitoring and Controlling Closing
6. Project Time
Management
Activity Definition (6.1)
Activity List & Attributes
Milestone List
Req. Changes
Activity Sequencing (6.2)
Network Diagram
Activity List & Attributes Updates
Req. Changes
Activity Resource Estimating (6.3)
Resource Requirements
Activity Attributes Updates
RBS
Resource Calendar Updates
Req. Changes
Activity Duration Estimating (6.4)
Activity Duration Estimates
Activity Attributes Updates
Schedule Development (6.5)
Project Schedule
Schedule Model Data
Schedule Baseline
Resource Requirements Updates
Activity Attributes Updates
Project Calendar Updates
Req. Changes
Project Mgmt. Plan Updates
Schedule Mgmt. Plan Updates
Schedule Control (6.6)
Schedule Model DataUpdates
Schedule Baseline Updates Performance Measurement
Req. Changes
Recommend CorrectiveAction
Organizational ProcessAssets Updates
Activity List & AttributeUpdates
Project Mgmt . PlanUpdates
7. Project CostManagement Cost Estimating (7.1)
Activity Cost Estimates & SupportingDetail
Req. Changes
Cost Mgmt. Plan Updates
Cost Budgeting (7.2)
Allocate & Aggregate
Cost Baseline (includes contingencyreserves but not Mgmt contingencyreserves)
Project Funding Requirements Cost Mgmt. Plan Updates
Req. Changes
Cost Control (7.3)
Cost Estimate & BaselineUpdates
Performance Measurement
Forecasted Completion
Req. Changes
Recommend CorrectiveAction
Organizational ProcessAssets Updates(Specifically lessonslearned)
Project Mgmt. PlanUpdates
-
7/31/2019 CAPM-StudyNotes
3/21
-
7/31/2019 CAPM-StudyNotes
4/21
KnowledgeArea
Processes
Project Management Process Groups
Initiating Planning Executing Monitoring and Controlling Closing
8. Project QualityManagement
Quality Planning (8.1)
Continuous Improvement
Quality Policy
Quality Mgmt. Plan
Quality Metrics Quality Checklists
Process Improvement Plan
Quality Baseline
Project Mgmt. PlanUpdates
Perform Quality Assurance (8.2)
Req. Changes
Recommend CorrectiveActions
Organization Process AssetsUpdates
Project Mgmt. Plan Updates
Perform Quality Control (8.3)
Quality Controlmeasurements
Validated Defect Repair
Recommended Corrective& Preventive Action
Req. Changes
Recommend Defect Repair
Organizational ProcessAssets Updates
Validated Deliverables
Project Mgmt. PlanUpdates
9. Project HumanResource
Management
Human Resources Planning (9.1)
Roles & Responsibilities
Project Org. Charts
Staffing Mgmt. Plan
Acquire Project team (9.2)
Project Staff Assignments
Resource Availability
Staffing Mgmt. Plan Updates
Develop Project Team (9.3)
Team PerformanceAssessment
Manage Project Team (9.4)
Req. Changes
Recommended Corrective& Preventive Actions
Organizational ProcessAssets Updates
Project Mgmt. PlanUpdates
10. ProjectCommunications
ManagementCommunications Planning (10.1)
Communications Mgmt.Plan
Information Distribution (10.2)
Organizational ProcessAssets Updates
Req. Changes
Performance Reporting (10.3)
Performance Reports
Forecasts
Req. Changes
Recommended CorrectiveActions
Organization ProcessAssets Updates
Manage Stakeholders (10.4)
Resolved Issues
Approved Change Request
Approved CorrectiveActions
Organizational ProcessAssets Updates
Project Mgmt. PlanUpdates
-
7/31/2019 CAPM-StudyNotes
5/21
-
7/31/2019 CAPM-StudyNotes
6/21
KnowledgeArea
Processes
Project Management Process Groups
Initiating Planning Executing Monitoring and Controlling Closing
11. Project RiskManagement
Risk Management Planning (11.1)
Risk Management Plan
Risk Identification (11.2)
Risk Register
Qualitative Risk Analysis (11.3)
Risk Register Updates
Quantitative Risk Analysis (11.4)
Risk Register Updates
Risk Response Planning (11.5)
Risk Register Updates
Project Mgmt. PlanUpdates
Risk-related ContractualAgreements
Risk Monitoring and Control (11.6)
Risk Register Updates Req. Changes
Recommended Corrective& Preventive Action
Organizational ProcessAssets Updates
Project Mgmt. PlanUpdates
12. ProjectProcurementManagement
Plan Purchases Acquisitions (12.1)
Procurement Mgmt. Plan
SOW
Make-or-buy decisions
Req. Changes
Plan Contracting (12.2)
Procurement Document
Evaluation Criteria
SOW Updates
Request Seller Responses (12.3)
Qualified Sellers List
Procurement DocumentPackage
Proposals
Select Sellers (12.4)
Selected Sellers
Contract
Contract Mgmt. Plan
Resource Availability
Procurement Mgmt. PlanUpdates
Req. Changes
Contract Administration (12.5)
Contract Documentation
Req. Changes
Recommended CorrectiveAction
Organizational ProcessAssets Updates
Project Mgmt. PlanUpdates (Procurement &Contract Mgmt. Plan)
Contract Closure (12.6)
Closed Contracts
OrganizationalProcess AssetsUpdates
-
7/31/2019 CAPM-StudyNotes
7/21
INTEGRATION
Process Inputs Tools/Techniques Outputs
Initiating
1. Develop Project Charter
Contract (when applicable)
Project SOW
Enterprise environmental factors
Organizational process assets
Project selection methods
Project management methodology
Project management information system
Expert judgment
Project charter
2. Develop Preliminary Project ScopeStatement
Project charter
Project SOW
Enterprise environmental factors
Organizational process assets
Project management methodology
Project management information system
Expert judgment
Preliminary Project Scope statement
Planning
3. Develop Project Management Plan
Preliminary project scope statement
Project management processes
Enterprise environmental factors
Organizational process assets(Which includes historical information and
organizational policies)
Project management methodology
Project management information system
Expert judgment
Project Management Plan
Executing
4. Direct and Manage Project Execution
Project Management Plan
Approved corrective actions
Approved preventive actions
Approved change requests
Approved defect repair
Validated defect repair
Administrative closure procedures
Project management methodology
Project management information system
Deliverables
Requested changes
Implemented change requests
Implemented corrective actions
Implemented preventive actions
Implemented defect repair
Work performance information
Controlling
5. Monitor and Control Project Work
Project Management Plan Work performance information
Rejected change request
Project management methodology Project management information system
Earned value technique
Expert judgment
Recommended corrective actions Recommended preventive actions
Forecasts
Recommended defect repair
Requested changes
6. Integrated Change Control
Project Management Plan
Requested Changes
Work performance information
Recommended corrective actions
Recommended preventive actions
Recommended defect repair
Deliverables
Project management methodology
Project management information system
Expert judgment
Approved change requests
Rejected change requests
Project Management Plan Updates
Project Scope Statement Updates
Approved corrective actions
Approved preventive actions
Approved defect repair
Validated defect repair
Deliverables
-
7/31/2019 CAPM-StudyNotes
8/21
INTEGRATION
Process Inputs Tools/Techniques Outputs
Closing
7. Close Project
Project Management Plan
Contract documentation
Enterprise environmental factors
Organizational process assets
Work performance information
Deliverables
Project management methodology
Project management information system
Expert judgment
Administrative closure procedure
Contract closure procedure
Final product, service, or result
Organizational process assets updates
SCOPE
Process Inputs Tools/Techniques Outputs
Planning
1. Scope Planning
Enterprise environmental factors
Organizational process assets
Project Charter
Preliminary project scope statement Project Management Plan
Expert Judgment
Templates, forms, standards
Project Scope Management Plan
2. Scope Definition
Organizational process assets
Project Charter
Preliminary project scope statement
Project Scope Management Plan
Approved change requests
Product analysis
Alternatives identification
Expert judgment
Stakeholder analysis
Project Scope Statement
Requested changes
Project Scope Management Plan Updates
3. Create WBS
Organizational process assets
Project Scope Statement
Project Scope Management Plan
Approved change requests
WBS templates
Decomposition
Project scope statement updates
WBS
WBS dictionary
Scope baseline
Project Scope Management Plan Updates
Requested changesControlling
4. Scope Verification(Assures ACCEPTANCE)
Project Scope Statement
WBS Dictionary
Project Scope Management Plan
Deliverables
Inspections Accepted deliverables
Requested changes
Recommended corrective actions
5. Scope Control
Project Scope Statement
WBS
WBS dictionary
Project Scope Management Plan
Workaround plans to risk
Performance Reports Approved change requests
Work performance information
Change Control System
Variance analysis
Replanning
Configuration management system
Project scope statement updates
WBS updates
WBS dictionary updates
Scope baseline updates
Requested changes
Recommended corrective action Organizational process assets updates
Project Management Plan Updates
-
7/31/2019 CAPM-StudyNotes
9/21
TIME
Process Inputs Tools/Techniques Outputs
Planning
1. Activity Definition
Enterprise environmental factors
Organizational process assets
Project Scope Statement
WBS
WBS Dictionary
Project Management Plan
Decomposition
Templates
Rolling Wave planning (Progressively)
Expert judgment Planning component
Activity List
Activity attributes
Milestone list
Requested changes
2. Activity Sequencing
Project Scope Statement
Activity List
Activity attributes
Milestone list
Approved change requests
Precedence Diagramming Method (PDM)
Arrow Diagramming Method (ADM)
Schedule network templates
Dependency determination
Applying leads and lags
Project Network Diagrams
Activity List Updates
Activity attributes updates
Requested changes
3. Activity Resource Estimating
Enterprise environmental factors
Organizational process assets
Activity list
Activity attributes
Resource availability
Project Management Plan
Expert judgment
Alternatives analysis
Published estimating data
Project management software
Bottom-up estimating
Activity resource requirements
Activity attributes updates
Resource breakdown structure
Resource calendars updates
Requested changes
4. Activity Duration Estimating
Enterprise environmental factors
Organizational process assets
Project Scope Statement
Activity List
Activity attributes
Activity resource requirements
Resource calendars
Project Management Plan- Risk register- Activity cost estimates
Expert Judgment
Analogous Estimating
Parametric Estimating
Three point estimates
Reserve analysis
Activity duration estimates
Activity attributes updates
5. Schedule Development
Organizational process assets
Project Scope Statement
Activity List Activity attributes
Project schedule network diagrams
Activity resource requirements
Resource calendars
Activity Duration Estimates
Project Management Plan Risk register
Schedule network analysis
Critical path method
Schedule Compression
What if scenario analysis (Monte Carlo) Resource Leveling
Critical chain method
Project management software
Applying calendars
Adjusting leads and lags
Schedule model
Project Schedule
Schedule model data
Schedule baseline Resource Requirement Updates
Activity attributes updates
Project calendar updates
Requested changes
Project Management Plan Updates
Schedule Management Plan Updates
Controlling
6. Schedule Control Schedule Management Plan
Schedule baseline
Performance Reports
Approved change requests
Progress reporting
Schedule Change Control System
Performance Measurement
Project management software
Variance Analysis Schedule comparison bar charts
Schedule model data updates
Schedule baseline updates
Performance measurements
Requested changes
Recommended corrective actions
Organizational process assets updates
Activity list updates
-
7/31/2019 CAPM-StudyNotes
10/21
Activity attributes updates
Project Management Plan Updates
-
7/31/2019 CAPM-StudyNotes
11/21
COST
Process Inputs Tools/Techniques Outputs
Planning
1. Cost Estimating
Enterprise environmental factors
Organizational process assets
Project Scope Statement
Work Breakdown Structure
WBS Dictionary Project Management Plan
- Schedule Management Plan- Staffing Management Plan- Risk register
Analogous Estimating
Determine resource cost rates
Bottom-Up Estimating
Parametric Estimating
Project Management software Vendor bid analysis
Reserve analysis
Cost of quality
Activity Cost Estimates
Activity Cost Estimate Supporting Detail
Requested changes
Cost Management Plan updates
2. Cost Budgeting
Project Scope statement
WBS
WBS dictionary
Activity Cost Estimates
Activity Cost Estimate Supporting Detail
Project Schedule
Resource calendars
Contract
Cost Management Plan
Cost Aggregation
Reserve Analysis
Parametric Estimating
Funding limit reconciliation
Cost Baseline (Same as budget)
Project funding requirements
Cost Management Plan updates
Requested changes
Controlling
3. Cost Control
Cost Baseline
Project funding requirements
Performance Reports
Work performance information
Approved change requests
Project Management Plan
Cost Change Control System
Performance Measurement Analysis(Helps to assess the magnitude of any variation thatoccurs on the project)
Forecasting
Project Performance Reviews
Project Management software
Variance management
Cost Estimate Updates
Cost baseline updates
Performance measurements
Forecasted completion
Requested changes
Recommended corrective actions
Organizational process assets updates
Project Management Plan updates
-
7/31/2019 CAPM-StudyNotes
12/21
QUALITY
Process Inputs Tools/Techniques Outputs
Planning
1. Quality Planning
Enterprise environmental factors
Organizational process assets
Project Scope Statement
Project Management Plan
Cost-Benefit Analysis
Benchmarking
Design Of Experiments
Cost Of Quality
Additional Quality Planning tools
Quality Management Plan
Quality metrics
Quality checklists
Process Improvement Plan
Quality baseline Project Management Plan updates
Executing
2. Perform Quality Assurance(Aimed for Processes)
Quality Management Plan
Quality metrics
Process Improvement Plan
Work performance information
Approved change requests
Quality control measurements
Implemented change requests
Implemented corrective actions
Implemented defect repair
Implemented preventive actions
Quality Planning Tools & Techniques
- Cost-benefits analysis- Benchmarking- Design of experiments
Quality Audits(Review of project activities with regard to quality)
Process analysis
Quality control tools and techniques
- Cause and effect diagrams- Control, Pareto and Run charts,- Flowcharting- Histograms
- Scatter diagrams- Statistical sampling- Inspection- Defect repair review
Requested changes
Recommended corrective actions
Organizational process assets updates
Project Management Plan updates
Controlling
3. Perform Quality Control(Aimed for Deliverables.
Assures CORRECTNESS)
Quality Management Plan
Quality metrics
Quality Checklists
Organizational process assets
Work performance information
Approved change requests
Deliverables
Cause and effect diagram
Control Charts
Flowcharting
Histogram
Pareto chart
Run chart
Scatter diagram
Statistical sampling
Inspections
Defect repair review
Quality control measurements
Validated defect repair
Quality baseline updated
Recommended corrective actions
Recommended preventive actions
Requested changes
Recommended defect repair
Organizational process assets updates
Validated deliverables
Project Management Plan updates
-
7/31/2019 CAPM-StudyNotes
13/21
HUMAN RESOURCES
Process Inputs Tools/Techniques Outputs
Planning
1. Human Resource Planning
Enterprise environmental factors
Organizational process assets
Project Management Plan Activityresource requirements
Organization charts and position descriptions
Networking
Organizational Theory
Roles and responsibilities
Project Organization Charts
Staffing Management Plan
Executing
2. Acquire Project Team(Carries out the Staffing Management
Plan)
Enterprise environmental factors
Organizational process assets
Roles and responsibilities
Project Organization Charts
Staffing Management Plan
Pre-assignment
Negotiations
Acquisition
Virtual teams
Project Staff Assignments
Resource availability
Staffing Management Plan updates
3. Develop Project Team
Project Staff Assignments
Staffing Management Plan
Resource availability
General Management Skills
Training
Team-Building Activities
Ground rules
Co-location
Recognition and rewards
Team performance assessment
Controlling
4. Manage Project Team(Checks whether the Staffing
Management Plan is working fine andevaluate team performance problems)
Organizational process assets
Project Staff Assignments
Roles and responsibilities
Project Organization Charts
Staffing Management Plan
Team performance assessment
Work performance information
Performance reports
Observation and conversation
Project performance appraisals
Conflict management
Issues log
Requested changes
Recommended corrective actions
Recommended preventive actions
Organizational process assets updates
Input to organization performance appraisals
Lessons learned documentation
Project Management Plan updates
-
7/31/2019 CAPM-StudyNotes
14/21
COMUNICATIONS
Process Inputs Tools/Techniques Outputs
Planning
1. Communication Planning(Involves determining and documenting
the information and communicationneeds of the stakeholders)
Enterprise environmental factors
Organizational process assets
Project Scope Statement
Project Management Plan -
- Constraints,- Assumptions
Communications requirements analysis
Communication technology
Communications Management Plan
Executing
2 . Information Distribution(Focuses on any kind of information
related to project)
Communications Management Plan Communications Skills
Information Gathering and Retrieval Systems
Information Distribution Methods
Lessons learned process
Organizational process assets updates- Lessons learned documentation- Project Records- Project Reports- Project Presentations- Feedback from stakeholders- Stakeholder notifications
Requested changes
Controlling
3. Performance Reporting(Focuses solely on project performance)
Work performance information
Performance measurements
Forecasted completion
Quality control measurements
Project Management Plan Performancemeasurement baseline
Approved change requests
Deliverables
Information presentation tools
Performance information gathering and compilation
Status review meetings
Time reporting systems
Cost reporting systems
Performance Reports
Forecasts
Requested changes
Recommended corrective actions
Organizational process assets updates
4. Manage Stakeholders
(Ensures that stakeholders needs areaddressed)
Communications Management Plan
Organizational process assets
Communications methods
Issue logs
Resolved issues
Approved change requests
Approved corrective actions
Organizational process assets updates
Project Management Plan updates
-
7/31/2019 CAPM-StudyNotes
15/21
RISK
Process Inputs Tools/Techniques Outputs
Planning
1. Risk Management Planning
Enterprise environmental factors
Organizational process assets
Project Scope Statement
Project Management Plan
Planning Meetings and analysis Risk Management Plan
2. Risk Identification
Enterprise environmental factors
Organizational process assets
Project Scope Statement
Risk Management Plan
Project Management Plan
Documentation Reviews
Information-Gathering Techniques(Interviewing, Delphi Technique and Brainstorming)
Checklist analysis
Assumptions Analysis
Diagramming Techniques
Risk register
3. Qualitative Risk Analysis
Organizational process assets
Project Scope Statement
Risk Management Plan
Risk register
Risk Probability & Impact Assessment
Probability and Impact Matrix
Risk Data Quality Assessment
Risk categorization
Risk urgency assessment
Risk Register updates
4. Quantitative Risk Analysis
Organizational process assets
Project Scope Statement
Risk Management Plan
Risk register
Project Management Plan- Project Schedule Management Plan- Project Cost Management Plan
Data gathering and representation techniques
Qualitative risk analysis and modeling techniques
Decision tree analysis
Risk Register updates
5. Risk Response Planning(Plans how each risk will be handled)
Risk Management Plan
Risk register
Strategies for negative risk or threats
Strategies for positive risks or opportunities
Strategy for both threats and opportunities
Contingent response strategy
Risk Register updates
Project Management Plan updates
Risk-related contractual agreements
Controlling
6. Risk Monitoring & Control(Carries out the Risk Response Plan)
Risk Management Plan
Risk Register
Approved change requests
Work performance information
Performance reports
Risk reassessment
Risk audits
(Concerned with overall risk management insteadof individual risks)
Variance and trend analysis
Technical performance measurement
Reserve analysis
Status meetings
Risk register updates
Requested changes
Recommended corrective actions- May include workaround plans which may arisescope changes
Recommended preventive actions
Organizational process assets updates
Project Management Plan updates
-
7/31/2019 CAPM-StudyNotes
16/21
PROCUREMENT
Process Inputs Tools/Techniques Outputs
Planning
1. Plan Purchases and Acquisitions
Enterprise environmental factors
Organizational process assets
Project Scope Statement
WBS
WBS dictionary Project Management Plan
- Risk register- Risk-related contractual agreements- Resource requirements- Project Schedule- Activity cost estimates- Cost baseline
Make-Or-Buy Analysis
Expert Judgment
Contract Types
Procurement Management Plan
Contract Statement of Work
Make-or-buy decisions
Requested changes
2. Plan Contracting(Prepares documents for solicitation)
Procurement Management Plan
Contract Statement Of Work
Make-or-buy decisions
Project Management Plan
- Risk register
- Risk-related contractual agreements- Resource requirements- Project Schedule- Activity cost estimates- Cost baseline
Standard Forms
Expert Judgment
Procurement Documents
Evaluation Criteria
Contract Statement of Work Updates
Executing
3. Request Seller Responses Organizational process assets
Procurement Management Plan
Procurement documents
Bidder/Vendor/Contractor Conferences
Advertising
Develop qualified sellers list
Qualified sellers list
Procurement document package
Proposals
4. Select Sellers(Involves negotiation and selection)
Organizational process assets
Procurement Management Plan
Evaluation Criteria Procurement document package
Proposals
Qualified Sellers list
Project Management Plan- Risk register- Risk-related contractual agreements
Weighting System
Independent Estimates
Screening system Contract negotiation
Seller rating systems
Expert judgment
Proposal evaluation techniques
Selected sellers
Contract
Contract Management Plan Resource availability
Procurement Management Plan updates
Requested changes
-
7/31/2019 CAPM-StudyNotes
17/21
PROCUREMENT
Process Inputs Tools/Techniques Outputs
Controlling
5. Contract Administration
Contract
Contract Management Plan
Selected sellers
Performance reports Approved change requests
Work performance information
Contract Change Control System
Buyer-conducted performance review
Inspections and audits
Performance Reporting Payment System
Claims administration
Records management system
Information technology
Contract documentation
(Contains requested, but unapproved contract changes)
Requested changes
Recommended corrective actions Organizational process assets updates
Correspondence
Contract Changes
Payment Requests
Project Management Plan Updates
- Procurement Management Plan- Contract Management Plan
Closing
6. Contract Closure
Procurement Management Plan
Contract Management Plan
Contract documentation
Contract closure procedure
Procurement audits(Capture lessons learned from a contractperspective)
Records management system
Closed contracts
Organization process assets updates
Components of the Project Management Plan:
Project Scope Management Plan
Schedule Management Plan
Cost Management Plan
Quality Management Plan
Process Improvement Plan
Staffing Management Plan
Communication Management Plan
Risk Management Plan
Procurement Management Plan
Milestone List Resource Calendar
Schedule Baseline
Cost Baseline (Same as budget)
Quality Baseline
Risk Register (which includes risk owners, risk thresholds and common risk causes)
Constraints and Planning Assumptions
For the exam the bottom line is : All management plans become part of the Project Management Plan
-
7/31/2019 CAPM-StudyNotes
18/21
Components of the Enterprise Environmental Factors:
Culture and Structure of the organization
Governmental and Industry standards
Infrastructure
Human Resources
Personnel Administration and Documentation
Marketplace conditions
Risk Tolerance
Commercial Databases
Academic Studies
Project Management Information Systems (Which is composed by Configuration Management System including Change Management System)
Project Quality Management DOES emphasize:
Customers Specifications (That also implies in Customers Satisfaction because if customers specifications are met, the customer should be satisfied with the product)
Quality Standards
Team Responsibility (The entire team has a responsibility towards quality)
Prevention over inspection (It costs less to fix a problem than it does to fix one)
Types of diagrams/charts:
Project Network diagrams (Show activities sequences and dependences)
Precedence Diagramming Method (PDM) => Activities on nodes (Also known as AON Activity On Node)
Arrow Diagramming Method (ADM) => Activities on arrows (Also known as AOA Activity On Arrow)
Graphical Evaluate Review Technique (GERT) => Can show conditional branches and loops whereas other representations cannot.
Bar Charts (a.k.a. Gantt Charts) (Show activities represented as horizontal bars and typically have calendar and percentage complete associated with them)
Milestone Chart (Only represent key events for the project)
Cause and Effect Diagrams (a.k.a. Fishbone Diagram or Ishikawa Diagram) (Are used in Quality Control process to show how different factors can lead to problems)
Control Charts
Show whether or not a process is in control. Containing.
Customer Specification Limits,
Control Limits Defined as three standard deviations above or below the mean
Mean of all data points
Rule of Seven where if seven or more consecutive points are on the same side of the mean, they should be investigated
-
7/31/2019 CAPM-StudyNotes
19/21
Pareto Chart (A kind of a histogram that shows on columns defects ranked from greatest to least. Paretos law states that 80% of problems come from 20% of the causes 80/20)
Run Chart (Quality measure snapshots compiled over time showing trends )
Scatter Diagram (Best for spotting trends in data. May be No Relation, Negative Linear Correlation, and Positive Linear Correlation)
Project Organizational Charts (Show project roles hierarchy or package associations)
Hierarchical Charts (Shows project roles hierarchically)
RACI Charts (R Responsible, A Accountable, C Consultant, I Input => Show project roles associated with work packages)
Text (States the position description and responsibilities)
-
7/31/2019 CAPM-StudyNotes
20/21
Resource Histogram (Its part of the Staffing Management Plan and shows the resource usage for a given period of time)
Tornado Diagrams (Evaluates projects sensitivity to cost or other factors)
Decision Tree Diagrams (Used to quantify which risks have the most impact on the project)
Key Formulas:
Term Abbreviation Description Formula
Three Point Estimate PERTUsed to estimate activity duration based on knownPessimistic, Realistic and Optimistic estimates.Its also used to predict the most likely, best-caseand worst-case scenarios for a given costestimate.
(Pessimist + 4xRealistic + Optimistic) / 6
Standard DeviationShows how diverse our estimates are. (Pessimistic Optimistic) / 6
Communication ChannelsShows how different communication channels existfor a given project
N * (N 1) / 2Where N is the number of people in your team.
Budgeted at Completion BAC How much was originally planned for this project tocost.
No one formula exists. BAC is derived by looking atthe total budgeted cost for the project.
Planned Value(a.k.a. Budgeted Cost of Work Scheduled)
PV (or BCWS)
How much work should have been completed ata point in time based on the plan. (Derived by
measuring where you had planned to be in
terms of work completed at a point in the
schedule).
PN = Planned % Complete X BAC
Earned Value(a.k.a. Budgeted Cost of Work Performed)
EV (or BCWP)
How much work was actually completed during a
given period of time. Derived by measuring where
you actually are in terms of work completed during
a given period of time in the schedule.
EV = Actual % Complete X BAC
Actual Cost(a.k.a. Actual Cost of Work Performed)
AC (orACWP)The money spent during a given period of time.
Sum of the costs for the given period of time.
Cost Variance CV The difference between what we expected to
spend and what was actually spent.
CV = EV-AC
Schedule Variance SVThe difference between where we planned to
be in the schedule and where we are in the
schedule.
SV=EV-PV
Cost Performance Index CPIThe rate at which the project performance is
meeting cost expectations during a given
period of time.
CPI = EV / AC
-
7/31/2019 CAPM-StudyNotes
21/21
Term Abbreviation Description Formula
Schedule Performance Index SPIThe rate at which the project performance is
meeting schedule expectations up to a point in
time.
SPI = EV / PV
Cumulative CPI CPICThe rate at which the project performance is
meeting cost expectations from the beginning up
to a point in time. CPIC
is also used to forecastproject costs at completion.
CPIC = EVC / ACC
Estimate at Completion EAC Projecting the total cost at completion based on
project performance up to a point in time.
EAC = BAC / CPIC
Estimate to Completion ETC Projecting how much will be spent on the
project, based on past performance.
ETC = EAC - AC
Variance at Completion VAC The difference between what was budgeted
and what will actually be spent.
VAC = BAC - EAC
Tips for calculating EAC on different scenarios
When current variances are viewed as typical of future variances :
EAC is calculated by adding the remaining budget (BAC EV) modified by a performance factor (CPI), to the actuals date.
When current variances are viewed as typical :
EAC is calculated by adding the remaining budget to the actuals to date (BAC EV).In this case, the project management team expects that similar variances will no occur in the future.
When original estimating assumptions are considered to be fundamentally flawed:
EAC is calculated by adding an all-together new estimate (ETC) to the actuals to date.
When original estimating assumptions are no longer reliable because conditions have changed:
EAC is calculated by adding an all-together new estimate (ETC) to the actuals to date.