case 10-2 treibacher industrie ag v. allegheny technologies inc

17
Case 10-2 Case 10-2 Treibacher Industrie Ag v. Allegheny T Treibacher Industrie Ag v. Allegheny T echnologies Inc echnologies Inc 1024097 1024097 王王王 王王王 1024099 1024099 王王王 王王王 1024104 1024104 王王王 王王王 1024100 1024100 王王 王王

Upload: yanisin-vargas

Post on 03-Jan-2016

97 views

Category:

Documents


1 download

DESCRIPTION

Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc. 1024097 王梦茜 1024099 吴潇婷 1024104 潘春云 1024100 李婕. Content. Background. Issue. Ananlyse. Court Decision. Background. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

Case 10-2Case 10-2Treibacher Industrie Ag v. Allegheny Treibacher Industrie Ag v. Allegheny

Technologies IncTechnologies Inc

1024097 1024097 王梦茜王梦茜1024099 1024099 吴潇婷吴潇婷1024104 1024104 潘春云潘春云1024100 1024100 李婕 李婕

Page 2: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

BackgroundBackground

Issue

AnanlyseAnanlyse

Court DecisionCourt Decision

ContentContent

Page 3: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

This lawsuit arises out of two contracts, This lawsuit arises out of two contracts, executed in November and December of 2000, executed in November and December of 2000, respectively, whereby Treibacher Industrie, AG respectively, whereby Treibacher Industrie, AG ("Treibacher"), an Austrian vendor of hard metal ("Treibacher"), an Austrian vendor of hard metal powders, agreed to sell specified quantities of powders, agreed to sell specified quantities of tantalum carbide ("TaC"), a hard metal powder, to tantalum carbide ("TaC"), a hard metal powder, to TDY Industries, Inc. ("TDY") for delivery to TDY Industries, Inc. ("TDY") for delivery to "consignment." TDY planned to use the TaC in "consignment." TDY planned to use the TaC in manufacturing tungsten-graded carbide powders at manufacturing tungsten-graded carbide powders at its plant in Gurney, Alabama. After it had received its plant in Gurney, Alabama. After it had received some of the amount of TaC specified in the some of the amount of TaC specified in the November 2000 contract, TDY refused to take November 2000 contract, TDY refused to take delivery of the balance of the TaC specified in both delivery of the balance of the TaC specified in both contracts, and, in a letter to Treibacher dated contracts, and, in a letter to Treibacher dated August 23, 2001, denied that it had a binding August 23, 2001, denied that it had a binding obligation to take delivery of or pay for any TaC that obligation to take delivery of or pay for any TaC that it did not wish to use. it did not wish to use.

BackgroundBackground

Page 4: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

BackgroundBackground

• Unbeknownst to Treibacher, TDY had Unbeknownst to Treibacher, TDY had purchased the TaC it needed from another purchased the TaC it needed from another vendor at lower prices than those specified vendor at lower prices than those specified in its contracts with Treibacher. Treibacher in its contracts with Treibacher. Treibacher eventually sold the quantities of TaC of eventually sold the quantities of TaC of which TDY refused to take delivery, but at which TDY refused to take delivery, but at lower prices than those specified in its lower prices than those specified in its contracts with TDY. Treibacher then filed contracts with TDY. Treibacher then filed suit against TDY, seeking to recover the suit against TDY, seeking to recover the balance of the amount Treibacher would balance of the amount Treibacher would have received had TDY paid for all of the have received had TDY paid for all of the TaC specified in the November and TaC specified in the November and December 2000 contracts.December 2000 contracts.

Page 5: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

TreibacherTreibacher

Industrie AgIndustrie Ag

PlaintiffPlaintiff::

Allegheny Allegheny

Technologies IncTechnologies Inc

DefendantDefendant::

TDY, a California corporation, is a subsidiary of TDY, a California corporation, is a subsidiary of Allegheny Technologies, Inc., a Pennsylvania Allegheny Technologies, Inc., a Pennsylvania corporation, which produces various metals and metal-corporation, which produces various metals and metal-based products based products

Treibacher Industrie, AG ("Treibacher"), Treibacher Industrie, AG ("Treibacher"), is is an Austrian an Austrian vendor of hard metal powdersvendor of hard metal powders

Page 6: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

In this case, the court had to decide how to interpret, under the CISG, the word consignment in a contract between two business firms—one in Austria and one in the United States. The result of the case turned on whether that word should be interpreted according to its meaning based on the “course of dealings” between the parties or on its “customary usage in trade.” After reviewing the relevant sections of the CISG, the court found that, in the course of their dealings, TDY and Treibacher had defined the term consignment to require TDY to accept and pay for all of the TaC specified in each contract, and that this is how the term should be interpreted.

CASEPOINT

Page 7: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

ANALYSIS

• We begin our analysis by discussing the CISG, which governs the formation of and rights and obligations under contracts for the international sale of goods. Article 9(1) states that, "parties are bound by any usage to which they have agreed and by any practices which they have established between themselves." Article 9(2) then states that, "parties are considered, unless otherwise agreed, to have impliedly made applicable to their contract . . . a usage of which the parties knew or ought to have known and which in international trade is widely known to . . . parties to contracts of the type involved in the particular trade concerned." Article 8 of the CISG governs the interpretation of the parties' statements and conduct.

Page 8: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

ANALYSIS

• In arguing that a term's customary usage takes precedence over the parties' understanding of that term in their course of dealings, TDY seizes upon the language of article 9(2), which states that, "parties are considered, unless otherwise agreed, to have made applicable to their contract" customary trade usages. TDY contends that article 9(2) should be read to mean that, unless parties to a contract expressly agree to the meaning of a term, the customary trade usage applies. In support of its argument, TDY points to the language of article 9(1), which binds parties to "any usage to which they have agreed and by any practices which they have established between themselves."

Page 9: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

The judgment of the court

The first court decision

TDY appealed

The final court decision

COURT DECISION

Page 10: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

The first court decision

The district court ruled that, under the United Nations Convention on Contracts for the International Sale of Goods (“CISG” 国际货物销售公约 ), evidence of the parties' interpretation of the term in their course of dealings trumped evidence of the term's customary usage in the industry, and found that Treibacher and TDY, in their course of dealings, understood the term to mean "that a sale had occurred, but that invoices would be delayed until the materials were withdrawn.“ The court therefore entered judgment against TDY, awarding Treibacher $5,327,042.85 in compensatory damages (including interest).

The district court ruled that, under the United Nations Convention on Contracts for the International Sale of Goods (“CISG” 国际货物销售公约 ), evidence of the parties' interpretation of the term in their course of dealings trumped evidence of the term's customary usage in the industry, and found that Treibacher and TDY, in their course of dealings, understood the term to mean "that a sale had occurred, but that invoices would be delayed until the materials were withdrawn.“ The court therefore entered judgment against TDY, awarding Treibacher $5,327,042.85 in compensatory damages (including interest).

COURT DECISION

Page 11: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

TDY appealed

TDY contends that, under the CISG, a contract term should be construed according to its customary usage in the industry unless the parties have expressly agreed to another usage. TDY argues, in the alternative, that the district court erred in finding that, in their course of dealings, Treibacher and TDY understood the term "consignment" to require TDY to use and pay for all of the TaC specified in each contract. Finally, TDY contends that, if we uphold the district court's ruling that TDY breached its contracts with Treibacher, we should remand the case for a new trial on damages on the ground that the district court erroneously found that Treibacher reasonably mitigated its damages.

TDY contends that, under the CISG, a contract term should be construed according to its customary usage in the industry unless the parties have expressly agreed to another usage. TDY argues, in the alternative, that the district court erred in finding that, in their course of dealings, Treibacher and TDY understood the term "consignment" to require TDY to use and pay for all of the TaC specified in each contract. Finally, TDY contends that, if we uphold the district court's ruling that TDY breached its contracts with Treibacher, we should remand the case for a new trial on damages on the ground that the district court erroneously found that Treibacher reasonably mitigated its damages.

COURT DECISION

Page 12: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

The final court decision

Reviewing the district court's legal conclusions de novo and factual findings for clear error, we hold that the district court properly construed the contract under the CISG — according to the parties' course of dealings — and did not commit clear error in finding that the parties understood the contracts to require TDY to use all of the TaC specified in the contracts. As to the mitigation of damages issue, which we review for clear error, we find that the evidence before the district court supported its finding that Treibacher's mitigation efforts were reasonable under the circumstances. We therefore affirm the judgment of the district court.

Reviewing the district court's legal conclusions de novo and factual findings for clear error, we hold that the district court properly construed the contract under the CISG — according to the parties' course of dealings — and did not commit clear error in finding that the parties understood the contracts to require TDY to use all of the TaC specified in the contracts. As to the mitigation of damages issue, which we review for clear error, we find that the evidence before the district court supported its finding that Treibacher's mitigation efforts were reasonable under the circumstances. We therefore affirm the judgment of the district court.

COURT DECISION

Page 13: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

Treibacher's complaint contains six counts. Count I is a claim for "Breach of Contract under the United Nations Convention on Contracts for the International Sale of Goods." Count II is a claim for “Anticipatory Breach of Contract” under the same United Nations convention. Count III is a claim for “Breach of Contract” under Alabama( 阿拉巴马州 ) law. Count IV is a claim for "Moneys Owed and Unjust Enrichment" under Alabama law. Count V is a claim for "Conversion" under Alabama law. Count VI is a claim for "Misrepresentation," alleging that TDY misrepresented that it would accept and pay for the goods Treibacher shipped to it.

Analysis

Page 14: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

Analysis

• Counts II through VI incorporate by reference the allegations of all previous counts On TDY's motion for summary judgment, the district court isolated Treibacher's claims from the complaint and granted the motion on all counts but Counts I and VI.

• The court, following a bench trial, gave Treibacher judgment on Counts I and VI, awarding Treibacher $5,327,042.85. Since we affirm the court's judgment on Count I, we need not review the court's disposition of Count VI.

Page 15: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

Analysis

• The parties do not dispute that the CISG governs their dispute.

• Article 1 of the CISG provides, in relevant part, that it "applies to contracts of sale of goods between parties whose places of business are in different States . . . when the States are Contracting States." The United States and Austria are contracting states.

• Article 4 of the CISG provides, in relevant part, that it "governs . . . the formation of the contract and the rights and obligations of the seller and buyer arising from such a contract." The parties dispute their respective "rights and obligations" under the contracts at issue in this case.

Page 16: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

In sum, under the CISG, the meaning the parties ascribe to a contractual term in their course of dealings establishes the meaning of that term in the face of a conflicting customary usage of the term. The district court was not clearly erroneous in finding that Treibacher and TDY understood their contracts to require TDY to purchase all of the TaC specified in each contract and that Treibacher took reasonable measures to mitigate its losses after TDY breached. Accordingly, the judgment of the district court is AFFIRMED

点击添加标题

Page 17: Case 10-2 Treibacher Industrie Ag v. Allegheny Technologies Inc

谢谢观赏