christian d'hondt, thiess: west to east: continuous improvement from city west to city east...

12
CITY EAST CABLE TUNNEL WEST TO EAST CONTINUOUS IMPROVEMENT FROM CITY WEST TO CITY EAST CABLE TUNNEL The 12th Australian Tunnelling Conference 21st November, 2013 Christian D’Hondt (Thiess) | Tim Burns (Thiess)

Upload: informa-australia

Post on 14-Jun-2015

411 views

Category:

Technology


3 download

DESCRIPTION

Christian D’Hondt, Project Manager, Tunnelling, CECT project, Thiess delivered this presentation at the 2013 Australian Tunnelling conference. The two day conference is supported by the Australasian Tunnelling Society and brings together tunnelling leaders, engineers and industry experts to share best practice in tunnelling design, construction, safety and maintenance. The 2012 program focussed on updates from Australasia’s current and future projects, plus case studies from leading International projects - sharing best practice and lessons learnt from the forefront of the latest tunnelling projects. For more information about the event, please visit the conference website: http://www.informa.com.au/tunnellingconference

TRANSCRIPT

Page 1: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

CITY EAST CABLE TUNNEL

WEST TO EAST CONTINUOUS IMPROVEMENT FROM

CITY WEST TO CITY EAST CABLE TUNNEL

The 12th Australian Tunnelling Conference 21st November, 2013

Christian D’Hondt (Thiess) | Tim Burns (Thiess)

Page 2: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

•  Early contractor involvement (ECI)

•  Flexural strength assessment of SFRC segments

•  Backfill of segment lining annulus

•  Cast in-situ lining

•  Separation of plant and pedestrians

•  TBM specification

CONTINUOUS IMPROVEMENT

Page 3: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

AUSGRID’S SYDNEY CITYGRID PROJECT

CITY WEST CABLE TUNNEL

• 2007 – 2010 Completed & operational

CITY EAST CABLE TUNNEL

• 2011-2015 Under construction

Page 4: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

•  Constructability advice to client and designer

•  Imputing into value engineering workshops

•  Generating construction programs

•  Advice and input into the environmental assessment

•  Providing cost estimates at various stages of the development of the design.

EARLY CONTRACTOR INVOLVEMENT

(ECI)

Page 5: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

•  CWCT project, flexural beams (ASTM C1609)

•  Co-efficient of variation for residual flexural strength 29.4%.

•  CECT project, supersized round panels (ASTM c1550)

•  Co-efficient of variation of super-size round panel residual flexural strength 10.9%

CONTINUOUS IMPROVEMENT

FLEXURAL STRENGTH ASSESSMENT OF SFRC

SEGMENTS

Residual Flexural Strength Spread at CWCT

Residual Flexural Strength Spread at CECT

Page 6: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

•  Open mode hard rock TBM

•  A two component A / B annulus grout

•  Injected through tail-shield grouting ports directly into the annulus.

•  Inject the B component into the a component stream inside the tail-shield as opposed to in the annulus

CONTINUOUS IMPROVEMENT

BACKFILLING OF SEGMENT LINING

ANNULUS

Page 7: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

•  Horizontal crown with curved chamfers

•  Bespoke steel shutter was made to form the curved obvert

•  Wall pours separate to crown pours

•  Heavy steel shutter in tight workspace

•  Average productivity of 0.55m/day

CONTINUOUS IMPROVEMENT

CAST IN-SITU LINING

Page 8: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

•  Horizontal crown with two 45 degree chamfers

•  Standard formwork components

•  Allowed integrated wall and crown pour

•  Lighter more manageable components

•  Average productivity of 1.47m/day (167% IMPROVEMENT)

CONTINUOUS IMPROVEMENT

CAST IN-SITU LINING

Page 9: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

Key control - physically separate plant movement from pedestrian movements

• 1000 semi trailers

• 5000 truck & dogs

Constrained CBD site

Pedestrian bridge and elevated walkway

Spoil loading inside acoustic shed to separate from public

CONTINUOUS IMPROVEMENT

SEPARATION OF PLANT AND PEDESTRIANS

Page 10: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

•  Offset TBM backup

•  Reduced need for persons to enter the rail envelope

•  Access, control and maintenance of all devices from walkway

•  Beneficial for shaft launch

•  Integral with TBM design

CONTINUOUS IMPROVEMENT

SEPARATION OF PLANT AND PEDESTRIANS

Page 11: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

Cutter head

•  Mono directional

•  Openings 15%

•  17” cutters

•  Inclined loading plates

Erector

•  6 degrees of functionality

•  Vacuum erector

Dewater

•  Hydraulically removable dewater tank

CONTINUOUS IMPROVEMENT

TBM SPECIFICATION

Page 12: Christian D'Hondt, Thiess: West to East: Continuous Improvement from City West to City East Cable Tunnel

WEST TO EAST

Continuous improvement from city west to city east cable tunnel

Acknowledgements:

• Ausgrid

• Structural concrete industries (SCI)

• SMEC

• Caterpillar tunnelling Canada

• Tachibana material co.

CONTINUOUS IMPROVEMENT