construction claims management & eot delays analysis · lesson 7 time impact window delay...
TRANSCRIPT
Presented by :
Hany Ismail, MSc, PMP
CONSTRUCTION CLAIMS MANAGEMENT
&
EOT DELAYS ANALYSIS
LESSON 7
TIME IMPACT WINDOW DELAY ANALYSIS
TECHNIQUE
TIME IMPACT – WINDOW ANALYSIS
CONSTRUCTION CLAIMS MANAGEMENT
EOT DELAYS ANALYSIS
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Agenda • Introduction.
• Why is TIA preferred technique ?
• Window Analysis Technique
• Window Analysis Technique Steps
• Smart Windows Time Periods
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Introduction
Time Impact Analysis Technique is Actual Based Approach
Which depends on the actual consequence and dates
happened in the site during the execution not only the
planning schedule.
TIA is widely recognized by the construction industry as
the most accepted method to quantify schedule delay.
In this method the analyst develops and adds a model of
the change to an approved schedule to quantify the delay
to project completion WWW.PLANNINGENGINEER.NET
TIA is preferred delay analysis technique
TIA is preferred delay analysis technique for the following reasons
it allows assessment of the actual state of progress at the time the
delay event occurred.
the responsibility for delay prior to the impact of the delaying event
is not material to the calculation of the effect of the delaying event
itself.
It determines whether the delay event impacted the critical path.
The exact impact of the delay event can be calculated.
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Analysis Technique
Window analysis is a time impact technique which focus on the
impact of delays in specific periods of time , identifying gains or
losses ( delays and recovery ) to the actual critical and sub-critical
paths as they occur with each period of time.
The project life cycle is divided into a series of consecutive time
“Windows”.
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Analysis Technique – Cont’
For Each window
- Each window is analyzed to identify the activities that were
impacted , delay or recovery and the results are investigated to
identify the events that caused the deviation in progress.
- Analysis steps
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Analysis Steps
Step 1 : Incorporate delay events that have been occurred in the period
Step 2 : Establish the impact on time for Completion.
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Analysis Steps
Step 3 : Update the impacted programme with progress with in the
window period.
Step 4 : Establish the impact on the Time for Completion.
D1 : Impact delay period due to “Employer Delay Events”
D2 : Impact delay period due to “Contactor Delays ” from the
update.WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
CASE STUDY
BANK XYZ PROJECT
CONSTRUCTION CLAIMS MANAGEMENT
EOT DELAYS ANALYSIS
WWW.PLANNINGENGINEER.NET
Window Technique – Case study General Information
Project Planned Start Date : 12,March,2012.
Project Planned Finish Date : 22,April,2013.
Available Updates Programme : 4 Programme
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Technique – Case study- Window 0
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window
Window
Start
(1)
Window
Finish
(2)
Window
Duration
(3) = 2-1
Prog.Source
Programme
Project
Finish
date
Delay Total
Entitlemen
tContractor Employer
W0 31
P0Appr.
Baseline
A.01
P1P0+Delay
Events
P2P1+Progress
update on
DD
Total Window Entitlement
22,April,
2013
13,May,
2013
14,May,
2013
Window Technique – Case study- Window 1
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window
Window
Start
(1)
Window
Finish
(2)
Window
Duration
(3) = 2-1
Prog.Source
Programme
Project
Finish
date
Delay Total
Entitlemen
tContractor Employer
W1 264
P3 Approved
P2
P4P3+Delay
Events
P5P4+Progress
update on
DD
Total Window Entitlement
14,May,
2013
25,May,
2013
3,Jun
, 2013
Window Technique – Case study- Window 2
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window
Window
Start
(1)
Window
Finish
(2)
Window
Duration
(3) = 2-1
Prog.Source
Programme
Project
Finish
date
Delay Total
Entitlemen
tContractor Employer
W2 264
P6 Approved
P5
P7P6+Delay
Events
P8P7+Progress
update on
DD
Total Window Entitlement
3,Jun
, 2013
9,July,
2013
21,July,
2013
Window Technique – Case study- Window 3
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window
Window
Start
(1)
Window
Finish
(2)
Window
Duration
(3) = 2-1
Prog.Source
Programme
Project
Finish
date
Delay Total
Entitlemen
tContractor Employer
W3 79
P9 Approved
P8
P10P9+Delay
Events
P11P10+Progres
s update on
DD
Total Window Entitlement
21,July,
2013
15,Aug,
2013
15,Sep.,
2013
Window Technique – Case study- Summary
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
Window Window Start Window Finish window
Duration Programme Programme
Project Finish
Date
DelayTotal
EntitlementContractor
Delay
Employer
Delay
Window 0 10-Mar-12 10-Apr-12 31
P0Approved
BaseLine22-Apr-13 0 0
P1P0+Delay
Events 13-May-13 21
P2P1+Progress
update on DD14-May-13 1 22
window 1 11-Apr-12 31-Dec-12 264
P3 Approved P2 14-May-13
P4P3+Delay
Events 25-May-13 11
P5P4+Progress
update on DD3-Jun-13 9 20
Window 2 1-Jan-13 1-Feb-13 31
P6 Approved P5 3-Jun-13
P7P6+Delay
Events 9-Jul-13 36
P8P7+Progress
update on DD21-Jul-13 12 48
Window 3 2-Feb-13 22-Apr-13 79
P9 Approved P8 21-Jul-13
P10P9+Delay
Events 15-Aug-13 25
P11 P10+Progress
update on DD15-Sep-13 31 56
Total Entitlement
Window Technique – Case study- Conclusion
WWW.PLANNINGENGINEER.NET
Construction Claims Management & EOT Delay Analysis
According to the previous analysis the contractor entitled
for (93) Calendar day as Excusable Delays
Total Entitlement
146 Calendar Day
Excusable
93 Day
CompensableNon-
Compensable
Non-Excusable
53 Day
Thank You …
Contact InfoWWW.PLANNINGENGINEER.NET
Mobile : +20 1277767728 /PlanningEngineerDotNet
We hope you enjoy our lecture today
Hope to receive your feedback and recommendations
/groups/4809645