CRONOGRAMA VALORIZADO DE OBRA 0102006 Cliente UNIVERSIDAD NACIONAL JOSE FAUSTINO SANCHEZ CARRIÓN 25/07/2013 Lugar LIMA - HUAURA - HUACHO Item Descripción Und. Metrado recio S/ Parcial S/. MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 01 OBRAS PROVISIONALES 01.01 glb 1.00 ### 5,000.00 5,000.00 01.02 CARTEL DE OBRA 3.60x7.20 und 1.00 ### 1,414.07 1,414.07 01.03 ALMACEN DE OBRA Y TALLER glb 1.00 ### 1,100.00 1,100.00 01.04 m 130.14 33.34 4,338.87 4,338.87 02 TRABAJOS PRELIMINARES 02.01 TRAZO, NIVELES Y REPLANTEO m2 870.00 2.30 2,001.00 2,001.00 02.02 m2 934.80 1.19 1,112.41 1,112.41 03 MOVIMIENTO DE TIERRAS 03.01 EXCAVACION A MANO PARA CIMIENTOS m3 374.29 34.57 12,939.21 12,939.21 03.02 m3 46.31 34.57 1,600.94 1,600.94 03.03 m3 169.08 34.15 5,774.08 5,774.08 03.04 m3 246.60 22.84 5,632.34 5,632.34 03.05 m2 810.09 3.29 2,665.20 2,665.20 04 CONCRETO SIMPLE 04.01 SOLADO PARA SUBCIMIENTOS m2 220.00 23.77 5,229.40 1307.35 3922.05 04.02 m2 810.09 24.87 20,146.94 20,146.94 04.03 m3 9.38 168.43 1,579.87 1,579.87 04.04 m2 377.19 42.08 15,872.16 14,284.94 1,587.22 04.05 m2 75.60 38.49 2,909.84 581.97 2327.872 04.06 JUNTA DE DILATACION EN VEREDAS m2 217.00 16.78 3,641.26 728.252 2,913.01 05 SUB ZAPATAS 05.01 m3 35.00 169.59 5,935.65 5,935.65 06 CONCRETO ARMADO Presupues to EXPEDIENTE TECNICO: "CREACION DEL CENTRO DE INVESTIGACION Y DESARROLLO TECNOLÓGICO DE MATERIALES DE LA FACULTAD DE INGENIERÍA QUÍMICA Y METALURGICA -UNJFSC -HUACHO" Cost MOVILIZACION Y DESMOVILIZACION DE CERCO DE OBRA CON POSTES DE MADERA LIMPIEZA Y DESBROCE DEL TERRENO EXCAVACION A MANO PARA ZAPATAS Y RELLENO COMPACTADO CON MATERIAL ELIMINACION MATERIAL EXCEDENTE NIVELACION Y COMPACTACION DE CONCRETO FALSO PISO MEZCLA 1:8 CONCRETO CIMIENTOS CORRIDOS MEZCLA CONCRETO VEREDAS f'c=175 kg/cm2 UN SARDINEL INCORPORADO A=1.00 m. ENCOFRADO Y DESENCOFRADO DE CONCRETO PARA SUB CIMIENTOS 1:12 +

Upload: aaron-zevallos-dominguez

Post on 28-Nov-2015

10 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Cronograma Val

CRONOGRAMA VALORIZADO DE OBRA

Presupuesto 0102006

Cliente UNIVERSIDAD NACIONAL JOSE FAUSTINO SANCHEZ CARRIÓN 25/07/2013

Lugar LIMA - HUAURA - HUACHO

Item Descripción Und. Metrado Precio S/. Parcial S/. MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7

01 OBRAS PROVISIONALES

01.01 glb 1.00 5,000.00 5,000.00 5,000.00

01.02 CARTEL DE OBRA 3.60x7.20 und 1.00 1,414.07 1,414.07 1,414.07

01.03 ALMACEN DE OBRA Y TALLER glb 1.00 1,100.00 1,100.00 1,100.00

01.04 m 130.14 33.34 4,338.87 4,338.87

02 TRABAJOS PRELIMINARES

02.01 TRAZO, NIVELES Y REPLANTEO m2 870.00 2.30 2,001.00 2,001.00

02.02 LIMPIEZA Y DESBROCE DEL TERRENO h=0.30 m m2 934.80 1.19 1,112.41 1,112.41

03 MOVIMIENTO DE TIERRAS

03.01 EXCAVACION A MANO PARA CIMIENTOS m3 374.29 34.57 12,939.21 12,939.21

03.02 m3 46.31 34.57 1,600.94 1,600.94

03.03 m3 169.08 34.15 5,774.08 5,774.08

03.04 m3 246.60 22.84 5,632.34 5,632.34

03.05 m2 810.09 3.29 2,665.20 2,665.20

04 CONCRETO SIMPLE

04.01 SOLADO PARA SUBCIMIENTOS m2 220.00 23.77 5,229.40 1307.35 3922.05

04.02 m2 810.09 24.87 20,146.94 20,146.94

04.03 m3 9.38 168.43 1,579.87 1,579.87

04.04 m2 377.19 42.08 15,872.16 14,284.94 1,587.22

04.05 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 75.60 38.49 2,909.84 581.97 2327.872

04.06 JUNTA DE DILATACION EN VEREDAS m2 217.00 16.78 3,641.26 728.252 2,913.01

05 SUB ZAPATAS

05.01 m3 35.00 169.59 5,935.65 5,935.65

06 CONCRETO ARMADO

EXPEDIENTE TECNICO: "CREACION DEL CENTRO DE INVESTIGACION Y DESARROLLO TECNOLÓGICO DE MATERIALES DE LA FACULTAD DE INGENIERÍA QUÍMICA Y METALURGICA -UNJFSC -HUACHO"

Costo al

MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS

CERCO DE OBRA CON POSTES DE MADERA Y TRIPLAY

EXCAVACION A MANO PARA ZAPATAS Y ESTRUCTURASRELLENO COMPACTADO CON MATERIAL PROPIOELIMINACION MATERIAL EXCEDENTE ACARREADONIVELACION Y COMPACTACION DE TERRENO NATURAL P/FALSO PISO

CONCRETO FALSO PISO MEZCLA 1:8 CEMENTO-HORMIGON e=4"CONCRETO CIMIENTOS CORRIDOS MEZCLA 1:10 + 30% P.G. (CEM. TIPO V)CONCRETO VEREDAS f'c=175 kg/cm2 UN SARDINEL INCORPORADO A=1.00 m. INCLUYE BASE DE AFIRMADO E=0.10 m.

CONCRETO PARA SUB CIMIENTOS 1:12 + 30% P.G.

Page 2: Cronograma Val

06.01 ZAPATAS

06.01.01 CONCRETO ZAPATAS f'c=210 kg/cm2 m3 14.50 331.75 4,810.38 4,810.38

06.01.02 kg 655.20 4.96 3,249.79 3,249.79

06.02 CIMIENTO ARMADO

06.02.01 CONCRETO EN CIMIENTO f´c = 210 kg/cm2 m3 255.36 308.43 78,760.68 78,760.68

06.02.02 m2 952.60 52.91 50,402.07 50,402.07

06.02.03 kg 25,611.00 4.96 127,030.56 127,030.56

06.03 SOBRECIMIENTO ARMADO

06.03.01 CONCRETO EN SOBRECIMIENTO f'c=210 kg/cm2 m3 75.80 340.71 25,825.82 25,825.82

06.03.02 m2 2,250.50 36.62 82,413.31 82,413.31

06.03.03 kg 4,010.30 4.96 19,891.09 19,891.09

06.04 COLUMNAS

06.04.01 CONCRETO COLUMNAS f'c=210 kg/cm2 m3 102.63 371.95 38,173.23 38,173.23

06.04.02 m2 1,406.20 56.05 78,817.51 78,817.51

06.04.03 kg 12,562.30 4.96 62,309.01 62,309.01

06.05 VIGAS

06.05.01 CONCRETO VIGAS f'c=210 kg/cm2 m3 60.50 346.62 20,970.51 20,970.51

06.05.02 ENCOFRADO Y DESENCOFRADO DE VIGAS m2 110.24 70.07 7,724.52 7,724.52

06.05.03 kg 3,542.65 4.96 17,571.54 7028.616 10542.924

06.06 LOSAS ALIGERADAS

06.06.01 CONCRETO LOSAS f'c= 210 kg/cm2 m3 85.60 437.21 37,425.18 37,425.18

06.06.02 m2 954.25 45.92 43,819.16 43,819.16

06.06.03 kg 11,365.20 4.96 56,371.39 56,371.39

06.06.04 und 6,521.30 3.29 21,455.08 21,455.08

06.07 LOSAS MACIZA H=0.15m.

06.07.01 CONCRETO LOSAS f'c= 210 kg/cm2 m3 12.60 437.21 5,508.85 5,508.85

06.07.02 ENCOFRADO Y DESENCOFRADO LOSA MACIZA m2 86.95 50.98 4,432.71 4,432.71

06.07.03 kg 796.35 4.96 3,949.90 3,949.90

06.08 JUNTA DE DILATACION

06.08.01 JUNTA DE DILATACION e=1" m 220.30 20.83 4,588.85 4,588.85

06.09 ESTRUCTURA METALICA

06.09.01 ESTRUCTURA METALICA m2 313.14 550.50 172,383.57 172,383.57

01 MUROS Y TABIQUES DE ALBAÑILERÍA

01.01 m2 1,586.20 69.00 109,447.80 98503.02 10944.78

01.02 m2 56.80 108.59 6,167.91 6,167.91

02 REVOQUES Y REVESTIMIENTOS

02.01 TARRAJEOS

02.01.01 TARRAJEO RAYADO PRIMARIO m2 150.20 24.33 3,654.37 3,654.37

ACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 ZAPATAS

ENCOFRADO Y DESENCOFRADO DE CIMIENTOS ARMADOSACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 EN CIMIENTO

ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO h=0.30 mACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 SOBRECIMIENTO

ENCOFRADO Y DESENCOFRADO DE COLUMNASACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 COLUMNAS

ACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 VIGAS

ENCOFRADO Y DESENCOFRADO LOSA ALIGERADAACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 LOSA ALIGERADALADRILLO DE TECHO DE ARCILLA DE 30 x 30 x 15 cm

ACERO DE REFUERZO fy=4,200 kg/cm2 GRADO 60 LOSA MACIZA

MURO LADRILLO K.K.DE ARCILLA 18 H ( 0.09x0.13x0.24) AMARRE DE SOGA JUNTA 1.5 cm. MORTERO 1:1:5MURO LADRILLO K.K DE ARCILLA 18H ( 09x013x0.24) AMARRE DE CABEZA, JUNTA 1.5 cm. MORTERO 1:1:5

Page 3: Cronograma Val

02.01.02 TARRAJEO MUROS INTERIORES m2 1,596.50 27.37 43,696.21 8,739.24 34,956.97

02.01.03 TARRAJEO MUROS EXTERIORES m2 450.60 33.52 15,104.11 15,104.11

02.01.04 TARRAJEO COLUMNAS m2 156.24 32.57 5,088.74 5,088.74

02.01.05 TARRAJEO DE VIGAS m2 455.36 32.57 14,831.08 14,831.08

02.02 VESTIDURAS, UNIONES Y BRUÑAS

02.02.01 VESTIDURAS DE DERRAMES m 452.30 13.54 6,124.14 6,124.14

02.02.02 BRUÑAS DE 1 X 1 cm m 83.20 6.80 565.76 565.76

03 CIELO RASOS

03.01 CIELORASO CON MEZCLA C:A m2 752.40 28.39 21,360.64 21,360.64

03.02 CIELO RASO DE FIBRA MINERAL DE 0.60X1.20m m2 225.36 53.12 11,971.12 9,576.90 2394.224

04 PISOS Y PAVIMENTOS

04.01 CONTRAPISOS

04.01.01 CONTRAPISO DE 30mm m2 650.60 31.92 20,767.15 20,767.15

04.02 PISOS

04.02.01 PISO CERAMICO VERANO MARFIL 45X45cm. m2 56.38 93.31 5,260.82 1315.205 3945.615

04.02.02 PISO PORCELANATO NANOMETRICO 55X55 cm m2 224.60 127.60 28,658.96 28,658.96

04.02.03 m2 965.30 37.68 36,372.50 36,372.50

04.03 VEREDAS

04.03.01 m2 265.20 74.85 19,850.22 19,850.22

04.04 SARDINELES

04.04.01 SARDINEL DE BORDE EN VEREDA m 325.00 6.59 2,141.75 2,141.75

05 ZOCALOS Y CONTRAZOCALOS

05.01 ZOCALOS

05.01.01 ZOCALO DE CERAMICA 45 X 45 m2 165.20 79.87 13,194.52 13,194.52

05.02 CONTRAZOCALOS

05.02.01 CONTRAZOCALO DE PORCELANATO0 H=0.10 m. m 1,065.40 26.97 28,733.84 28,733.84

06 COBERTURAS Y CERRAMIENTOS

06.01 COBERTURA CON PLANCHA TRASLÚCIDA m2 56.80 55.60 3,158.08 3,158.08

06.02 m2 460.50 176.46 81,259.83 81,259.83

06.03 m2 450.20 177.90 80,090.58 80,090.58

07 CARPINTERIA DE MADERA

07.01 PUERTAS DE MADERA CONTRAPLACADA m2 120.60 361.30 43,572.78 8,714.56 34,858.22

07.02 m2 25.60 136.01 3,481.86 3,481.86

08 CARPINTERIA METALICA

08.01 PUERTA METALICA C/Fe LISO 1/2" m2 16.20 1,550.00 25,110.00 25,110.00

08.02 PUERTA METALICA C/PLATINA DE 2"X 3/16" m2 14.30 2,500.00 35,750.00 35,750.00

08.03 m2 35.80 210.58 7,538.76 7,538.76

09 CERRAJERIA

PISO DE CEMENTO SEMIFROTACHADO Y BRUÑADO e=0.10m.

VEREDA EXTERIOR INCLUYE BASE DE AFIRMADO, SEMIPULIDO Y BRUÑADO.E=0.10m

COBERTURA CON PLANCHA TERMOTECHO TCA-PUR PRECOR O CALAMINON 950x90x0.50mm. AZUL NÁUTICOCERRAMIENTO CON TERMOTECHO TERMOACÚSTICO ONDULADO

TABIQUE DE MADERA MELAMINE 6mm C/marco Aluminio 1 1/2"x 1 1/2"

CELOSÍA CON TUBO DE ALUMIINIO CUADRADO DE 1 1/2"x 1 1/2" (INC. ACCESORIOS)

Page 4: Cronograma Val

09.01 und 63.00 16.20 1,020.60 1,020.60

09.02 und 21.00 73.54 1,544.34 1,544.34

09.03 CERRADURA PARA EXTERIOR de 3 golpes und 2.00 86.48 172.96 172.96

09.04 CERRADURA PARA EXTERIOR de 2 golpes und 1.00 75.30 75.30 75.30

09.05 TIRADOR DE ACERO PARA PUERTAS DE VIDRIO und 4.00 191.08 764.32 764.32

10 VIDRIOS, CRISTALES Y SIMILARES

10.01 ESPEJO BISELADO E=6mm (2.40x0.90m) und 2.00 784.08 1,568.16 1,568.16

10.02 m2 10.60 489.86 5,192.52 5,192.52

10.03 m2 195.40 494.06 96,539.32 96,539.32

10.04 BLOCK DE VIDRIO DE 30 X 30 cm und 24.50 54.81 1,342.85 1,342.85

10.05 CERRAMIENTO DE VIDRIOS EN TEATINAS m2 42.36 504.84 21,385.02 21,385.02

11 PINTURAS

11.01 PINTURA LATEX 2 MANOS EN MURO INTERIOR m2 1,013.50 14.10 14,290.35 14,290.35

11.02 PINTURA LATEX 2 MANOS EN MURO EXTERIOR m2 298.20 12.66 3,775.21 3,775.21

11.03 PINTURA LATEX 2 MANOS EN COLUMNAS m2 76.70 8.07 618.97 618.97

11.04 PINTURA LATEX 2 MANOS EN VIGAS m2 308.90 9.63 2,974.71 2,974.71

11.05 PINTURA LATEX 2 MANOS EN DERRAMES m2 34.60 7.83 270.92 270.92

11.06 PINTURA LATEX 2 MANOS EN CIELO RASOS m2 549.70 11.54 6,343.54 6,343.54

11.07 PINTURA AL DUCO EN PUERTAS DE MADERA m2 40.80 16.05 654.84 654.84

11.08 PINTURA ESMALTE EN CARPINTERIA METALICA m2 15.60 15.28 238.37 238.37

12 VARIOS

12.01 APARATOS SANITARIOS Y ACCESORIOS

12.01.01 INODORO COLOR BLANCO SEGÚN MODELO und 4.00 359.76 1,439.04 1,439.04

12.01.02 LAVATORIO OVALIN C/GRIFERÍA TIPO SENSOR und 4.00 184.61 738.44 738.44

12.01.03 und 2.00 546.70 1,093.40 1,093.40

12.01.04 SECAMANOSAUTOMÁTICO DE MANO und 2.00 610.00 1,220.00 1,220.00

12.01.05 und 4.00 13.50 54.00 54.00

12.01.06 DISPENSADOR DE JABON CROMADO und 2.00 35.00 70.00 70.00

12.01.07 und 2.00 280.00 560.00 560.00

12.01.08 und 6.00 280.00 1,680.00 1,680.00

13 MITIGACION DE IMPACTO AMBIENTAL

13.01 MITIGACION DEL IMPACTO AMBIENTAL glb 1.00 120,000.00 120,000.00 48000 72000

14 DESARROLLO Y CAPACITACIÓN

14.01 DESARROLLO Y CAPACITACIÓN glb 1.00 75,000.00 75,000.00 7500 7500 7500 7500 15000 15,000.00 15000

01 SISTEMA DE AGUA FRÍA

01.01 SALIDA DE AGUA FRIA TUBERIA PVC SAP 1/2" und 22.00 217.26 4,779.72 1433.916 3345.804

01.02 VALVULA COMPUERTA DE 3/4" und 4.00 145.55 582.20 582.20

01.03 VALVULA COMPUERTA DE 1" und 1.00 153.69 153.69 153.69

BISAGRA CAPUCHINAS ALUMINIZADA DE 3½" X 3½"CERRADURA CILINDRICA PARA PUERTA INTERIORES

PUERTA DE VIDRIO TEMPLADO E=10mm (INC. ACCESORIOS)VENTANA DE ALUMINIO CON VIDRIO TRANSPARENTE 6mm

URINARIO MINGITORIO SECO C/DISPOSITIVO ESFERA

DISPENSADOR DE PAPEL HIGUIENICO CROMADO

MESA DE CONCRETO C/REVESTIMIENTO DE MICROCEMENTO (0.80x0.60m.)MESA DE CONCRETO C/REVESTIMIENTO DE GRANITO (2.35x0.60m.) EN SSHH

Page 5: Cronograma Val

01.04 m 51.17 30.00 1,535.10 460.53 1074.57

01.05 m 68.07 27.66 1,882.82 1,882.82

01.06 m 18.25 30.57 557.90 557.90

01.07 CAJAS Y/O NICHOS PARA TUBERÍA DE 3/4" und 4.00 272.10 1,088.40 1,088.40

01.08 CAJAS Y/O NICHOS PARA TUBERÍA DE 1" und 1.00 272.10 272.10 272.10

02 SISTEMA DE LA RED DE DESAGUE

02.01 SALIDA DESAGUE DE PVC-SAL 4" pto 9.00 75.65 680.85 680.85

02.02 SALIDA DESAGUE DE PVC SAL 2" pto 13.00 55.11 716.43 716.43

02.03 SALIDA VENTILACION DE PVC-SAL 2" pto 10.00 64.08 640.80 640.80

02.04 TUBERIA PVC SAL 2" m 55.71 26.83 1,494.70 597.88 896.82

02.05 TUBERIA PVC SAL 3" m 5.21 28.81 150.10 60.04 90.06

02.06 TUBERIA PVC SAL 4" m 28.74 42.22 1,213.40 485.36 728.04

02.07 SUMIDERO DE 3" und 3.00 75.16 225.48 90.19 135.288

02.08 REGISTRO DE BRONCE 2" und 4.00 50.01 200.04 200.04

02.09 REGISTRO DE BRONCE 4" und 6.00 49.51 297.06 297.06

02.10 CAJAS DE REGISTRO DE DESAGUE 12" x 24" und 7.00 164.73 1,153.11 1,153.11

02.11 CODO PVC SAL 2"X90º und 37.00 30.67 1,134.79 567.395 567.395

02.12 CODO PVC SAL 2"X45ª und 16.00 30.38 486.08 243.04 243.04

02.13 CODO PVC SAL 4"X90º und 1.00 44.43 44.43 22.215 22.215

02.14 YEE PVC SAL 4" und 8.00 45.10 360.80 180.4 180.4

02.15 YEE PVC SAL 2" und 3.00 41.13 123.39 61.695 61.695

02.16 YEE C/REDUCCION PVC SAL 4"-2" und 6.00 45.81 274.86 137.43 137.43

02.17 YEE C/REDUCCION PVC SAL 4"-3" und 3.00 47.65 142.95 71.475 71.475

02.18 YEE C/REDUCCION PVC SAL 3"-2" und 4.00 43.13 172.52 86.26 86.26

02.19 CODO PVC 4"-2" und 9.00 81.17 730.53 365.265 365.265

02.20 SOMBRERO DE VENTILACION 2" und 10.00 22.11 221.10 221.10

03 VARIOS

03.01 PRUEBA HIDRAULICA PARA AGUA FRIA glb 1.00 2,200.09 2,200.09 2,200.09

03.02 PRUEBA HIDRAULICA DE DESAGUE glb 1.00 2,250.09 2,250.09 2,250.09

03.03 ACOMETIDA A RED PÚBLICA -AGUA glb 1.00 3,648.53 3,648.53 3,648.53

03.04 ACOMETIDA A RED PÚBLICA -DESAGUE glb 1.00 3,648.53 3,648.53 3,648.53

0101.01 SALIDA PARA ALUMBRADO

01.01.01 und 90.00 416.30 37,467.00 29,973.60 7493.4

01.01.02 SALIDA PARA SPOT LIGHT pto 38.00 200.22 7,608.36 6,086.69 1521.672

01.01.03 SALIDA PARA INTERRUPTOR SIMPLE H=1.20m und 16.00 203.59 3,257.44 2,605.95 651.488

01.01.04 SALIDA PARA INTERRUPTOR DOBLE H=1.20m und 11.00 203.24 2,235.64 1,788.51 447.128

01.01.05 und 17.00 389.77 6,626.09 5,300.87 1325.218

RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 1/2"RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 DE 3/4"RED DE DISTRIBUCION INTERNA CON TUBERIA DE PVC C-10 O 1"

SALIDA PARA ALUMBRADO, TOMACORRIENTES, FUERZA Y SEÑALES DEBILESSALIDA PARA CENTRO DE LUZ ADOSADO A TECHO

SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE ESTABILIZADO CON TOMA A TIERRA H=0.40m.

Page 6: Cronograma Val

01.01.06 und 53.00 338.97 17,965.41 14,372.33 3593.082

01.02 SALIDA PARA TOMACORRIENTES

01.02.01 und 3.00 914.37 2,743.11 2,194.49 548.622

01.02.02 und 3.00 923.42 2,770.26 2,216.21 554.052

01.03 SALIDA PARA INTERRUPTORES

01.03.01 SALIDA PARA INTERRUPTOR TRIPLE H=1.20m und 2.00 243.36 486.72 389.38 97.344

01.03.02 und 2.00 174.49 348.98 279.18 69.796

01.03.03 und 2.00 197.99 395.98 316.78 79.196

01.03.04 und 2.00 76.21 152.42 121.94 30.484

01.03.05 und 2.00 85.81 171.62 137.30 34.324

01.0401.04.01 SALIDA PARA DATA H=0.40m und 2.00 1,986.02 3,972.04 3,177.63 794.408

01.04.02 SALIDA PARA TELEFONO H=0.40m und 2.00 182.40 364.80 291.84 72.96

01.05 SALIDA PARA SEGURIDAD Y PROTECCIÓN

01.05.01 und 2.00 306.26 612.52 490.02 122.504

01.05.02 und 2.00 91.21 182.42 145.94 36.484

01.05.03 SALIDA PARA SIRENA (INC EQUIPO) und 2.00 321.45 642.90 514.32 128.58

01.05.04 und 2.00 824.01 1,648.02 1,318.42 329.604

01.05.05 und 1.00 246.24 246.24 196.99 49.248

01.06 SALIDA ESPECIAL

01.06.01 und 2.00 169.91 339.82 271.86 67.964

02 CAJAS DE PASE

02.01 und 4.00 91.42 365.68 292.54 73.136

02.02 und 4.00 91.42 365.68 292.54 73.136

03 CANALIZACIONES, CONDUCTOS O TUBERÍAS

03.01 m 1.00 38.47 38.47 30.78 7.694

0404.01 m 1.00 371.00 371.00 296.80 74.2

04.02 m 1.00 275.35 275.35 220.28 55.07

05 TABLEROS DE DISTRIBUCIÓN

05.01 pza 1.00 1,030.84 1,030.84 1,030.84

05.02 pza 1.00 731.04 731.04 731.04

05.03 pza 1.00 773.87 773.87 773.87

05.04 pza 1.00 773.87 773.87 773.87

06 DISPOSITIVOS DE MANIOBRA Y PROTECCIÓN

06.01 INSTALACION DEL SISTEMA PUESTA A TIERRA

06.01.01 und 1.00 845.74 845.74 845.74

07 ARTEFACTOS DE ILUMINACION

SALIDA PARA TOMACORRIENTE BIPOLAR CON TOMA A TIERRA H=0.40m.

SALIDA PARA TOMACORRIENTE BIPOLAR CON TOMA A TIERRA H=1.50m.SALIDA PARA TOMACORRIENTE BIPOLAR CON TOMA A TIERRA H=2.50m.

SALIDA PARA INTERRUPTOR SIMPLE DE CONMUTACION H=1.20mSALIDA PARA INTERRUPTOR DOBLE DE CONMUTACION H=1.20mSALIDA PARA INTERRUPTOR TERMOMAGNÉTICO BIPOLAR C/FUSILE PROTEC.SALIDA PARA INTERRUPTOR TERMOMAGNÉTICO TRIPOLAR C/FUSILE PROTEC.SALIDA DE SEÑALES DÉBILES (DATA Y COMUNICACIONES)

SALIDA PARA PULSADOR Y CAMPANA TIPO CONG (INC. EQUIPO)SALIDA PARA SENSOR DE ALARMA CONTRA HUMO O GAS (INC EQUIPO)

SALIDA CENTRAL DE ALARMA CONTRA INCENDIOSALIDA PARA PANEL DE CONTROL (INC. EQUIPO)

SALIDA ESPECIAL PARA ARTEFACTOS ELECTRICOS

SUM E INST. CAJA DE PASE OCTOGONAL C/TAPA 100x100x40mm. FºGº.SUM E INST. CAJA DE PASE CUADRADA C/TAPA 150x150x100mm. FºGº.

SUMINISTRO E INSTALACION DE TUBERIA PVC SAP, NTP 399.006 D=50mm.CONDUCTOS Y CABLES DE ENERGÍA EN TUBERÍASSUMINISTRO E INSTALACION DE CONDUCTOR N2XH (3-1X50MM2+1X50MM2(N)+1X16MM2(T))SUMINISTRO E INSTALACION DE CONDUCTOR N2XH (3-1X25MM2+1X25MM2(N)+1X10MM2(T))

SUM E INST. TABLEROS DISTRIBUCION TDG SEGÚN E.T.SUM E INST. TABLEROS DISTRIBUCION ST1 SEGÚN E.T.SUM E INST. TABLEROS DISTRIBUCION ST2 SEGÚN E.T.SUM E INST. TABLEROS DISTRIBUCION ST3 SEGÚN E.T.

SUMINISTRO E INSTALACION DE POZO DE PUESTA A TIERRA

Page 7: Cronograma Val

07.01 LÁMPARAS

07.01.01 und 90.00 350.60 31,554.00 31,554.00

07.01.02 und 50.00 225.65 11,282.50 11,282.50

07.01.03 SUM E INST. LAMPARA DE EMERGENCIA und 10.00 215.30 2,153.00 2,153.00

08 SISTEMA DE TELEFONÍA

08.01 und 1.00 3,500.00 3,500.00 3,500.00

09 SISTEMA DE DATA CENTER 11,000.00 11,000.00

09.01 und 1.00 5,500.00 5,500.00 5,500.00

09.02 SUMINISTRO E INSTALACION DE UPS und 1.00 5,500.00 5,500.00 5,500.00

10 VARIOS

10.01 und 1.00 6,535.15 6,535.15 6,535.15

11 PRUEBAS ELECTRICAS

11.01 PRUEBAS ELECTRICAS glb 8.00 1,375.42 11,003.36 11,003.36

01 AREA FUNDICION, MOLDEO Y SOLDADURA

01.01 HORNO ROTATIVO und 1.00 36,112.30 36,112.30 36,112.30

01.02 HORNO CRISOL VASCULABLE und 1.00 35,211.23 35,211.23 35,211.23

01.03 HORNO ELECTRICO DE INDUCCIÓN und 1.00 45,211.23 45,211.23 45,211.23

01.04 GRÚA PUENTE und 1.00 85,522.18 85,522.18 85,522.18

02 AREA DE METALURGICA EXTRACTIVA

02.01 JEFATURA DE METALURGICA EXTRACTIVA und 1.00 8,011.23 8,011.23 8,011.23

02.02 AREA DE RECEPCION DE MUESTRAS und 1.00 20,261.23 20,261.23 20,261.23

02.03 AREA DE ALMACEN und 1.00 656.23 656.23 656.23

02.04 AREA DE FUNDICIÓN MINERAL und 1.00 28,154.98 28,154.98 28,154.98

02.05 AREA DE PESADO ANALÍTICA und 1.00 22,261.23 22,261.23 22,261.23

03 AREA DE METALURGICA FISICA

03.01 JEFATURA DE METALURGICA FÍSICA und 1.00 7,511.23 7,511.23 7,511.23

03.02 AREA DE RECEPCION DE MUESTRAS und 1.00 20,261.23 20,261.23 20,261.23

03.03 AREA DE ALMACEN 2 und 1.00 656.23 656.23 656.23

0404.01 und 1.00 7,511.23 7,511.23 7,511.23

04.02 AREA DE RECEPCION DE MUESTRAS und 1.00 20,261.23 20,261.23 20,261.23

04.03 AREA DE ALMACEN 3 und 1.00 656.23 656.23 656.23

01 OPERACIONES

01.01 HORNOS DE CUBILOTE -INSUMOS und 1.00 21,670.80 21,670.80 21,670.80

01 MOBILIARIO

01.01 ESTANTES PARA OFICNA und 5.00 380.00 1,900.00 1,900.00

01.02 PROYECTOR MULTIMEDIA und 1.00 7,300.00 7,300.00 7,300.00

01.03 SILLA DE MADERA und 20.00 180.00 3,600.00 3,600.00

SUMINISTRO E INSTALACION DE ARTEFACTO FLUORESCENTE PARA ADOSAR TIPO HERMÉTICO 18WSUMINISTRO E INSTALACION DE ARTEFACTO FLUORESCENTE PARA ADOSAR TIPO HERMÉTICO 2X36W

SUMINISTRO E INSTALACION DE CENTRAL TELEFÓNICA

SUMINISTRO E INSTALACION DE CENTRAL DE DATA

SUMINSTRO E INSTALACION DE MURETE DE LADRILLO P/TABLERO ELECTRICO

AREA DE METALURGICA DE PROCESAMIENTO DE METALESJEFATURA DE METALURGICA DE PROCESAMIENTO DE METALES

Page 8: Cronograma Val

01.04 ESTANTES DE ALMACEN und 12.00 380.00 4,560.00 4,560.00

01.05 SILLA PARA OFICINA und 8.00 145.00 1,160.00 1,160.00

01.06 MESA DE MADERA und 8.00 420.00 3,360.00 3,360.00

Page 9: Cronograma Val

COSTO DIRECTO

GASTOS GENERALES 10% 268,806.86

UTILIDAD 8% 215,045.49

-------------------

SUBTOTAL 3,171,920.96

IMPUESTO (18%) 570,945.77

=============

TOTAL PRESUPUESTO 3,742,866.73