customer acceptance sign off sheet(t umts61 ipclk v1.0 20071023)

5
Customer Acceptance Sign-off Sheet UMTS6.1 IP CLOCK Internal use Customer Acceptance Sign-off Sheet Test category Test item Test sub-item Test result IPCLK01 Basic function IPCLK01-01 Basic function test IPCLK01-0101 IP clock function test when server in lock and NODEB as a client □Pass □Fail □NA Remarks: * NA: Not applicable. Huawei Representative Customer Representative Signature:__________________ Signature:__________________ Date:______________________ Date:______________________ T-umts61-ipclk-v1.0- 20071023 HUAWEI Proprietary and Confidential Page 1 of 5

Upload: 4shared4

Post on 22-Nov-2015

1 views

Category:

Documents


0 download

TRANSCRIPT

Customer Acceptance Sign-off Sheet

UMTS6.1 IP CLOCKInternal use

Customer Acceptance Sign-off Sheet

Test categoryTest itemTest sub-itemTest result

IPCLK01 Basic functionIPCLK01-01 Basic function testIPCLK01-0101 IP clock function test when server in lock and NODEB as a clientPass Fail NA

Remarks:

* NA: Not applicable.

Huawei Representative Customer Representative

Signature:__________________ Signature:__________________

Date:______________________ Date:______________________

Test categoryTest itemTest sub-itemTest result

IPCLK02 Stability TestIPCLK02-01 Long-time stability testIPCLK02-0101 IP clock long-time stability test when server in locked state and NODEB as a clientPass Fail NA

Remarks:

* NA: Not applicable.

Huawei Representative Customer Representative

Signature:__________________ Signature:__________________

Date:______________________ Date:______________________

Test categoryTest itemTest sub-itemTest result

IPCLK03 Reliability TestIPCLK03-01 Test of Server in abnormalIPCLK03-0101 Test of Server 's clock source lostPass Fail NA

IPCLK03-0102 Test of Server's power turn off -standby server existPass Fail NA

IPCLK03-0103 Test of Server's power turn off -standby server not existPass Fail NA

IPCLK03-0104 Test of Server's reset - standby server existPass Fail NA

IPCLK03-0105 Test of Server's reset -standby server not existPass Fail NA

IPCLK03-02 Test of transmission in abnormalIPCLK03-0201 Test of transmission broken off -- standby server existPass Fail NA

IPCLK03-0202 Test of transmission broken off -- standby server not existPass Fail NA

IPCLK03-0203 Test of transmission QOS abnormal--Clock over ip to restore itPass Fail NA

IPCLK03-0204 Test of transmission QOS abnormal-- clock stability dependance on delayPass Fail NA

IPCLK03-0205 Test of transmission QOS abnormal-- clock stability dependance on jitterPass Fail NA

IPCLK03-0206 Test of transmission QOS abnormal-- clock stability dependance on packet lossPass Fail NA

IPCLK03-03 Test of NODEB in abnormalIPCLK03-0301 Test of NODEB power offPass Fail NA

IPCLK03-0302 Test of NODEB resetPass Fail NA

IPCLK03-04 Test of transmission congestionIPCLK03-0401 Test of transmission congestionPass Fail NA

Remarks:

* NA: Not applicable.

Huawei Representative Customer Representative

Signature:__________________ Signature:__________________

Date:______________________ Date:______________________

Final Sign-off

Conclusion: Totally 16 items are covered in this acceptance test, in which ______ passed, ____ failed, and ____ were not applicable.

Huawei Representative Customer Representative

Signature:__________________ Signature:__________________

Date:______________________ Date:______________________

T-umts61-ipclk-v1.0-20071023HUAWEI Proprietary and ConfidentialPage 1 of 5