Development of port terminal infrastructure in Leningrad region, Russia
ООО «Морское строительство и технологии»
Gzhatskaya street, 21, Saint-Petersburg, RussiaPhone: (812) 333-13-10, Fax: (812) 333-13-11
e-mail: [email protected] www.morproekt.ru
МОРСТРОЙТЕХНОЛОГИЯ
http://www.morproekt.ru/ 226.06.2015
Ports and terminals, industrial design, engineering
Logistic centers’ master-plans, business-plans, design
Transport market research (shipping, ports, rail)
Cargo flows analysis and outlook,
Logistic optimization for industries and export.
Morstroytechnology, LLC (MCT)
Morstroytechnology is design, engineering and consulting company providing full range of services including:
Turn-key port engineering: from idea to efficient operation
Detailed engineeringDetailed engineeringBasic designBasic designConceptual designConceptual design
МОРСТРОЙТЕХНОЛОГИЯ
Для продуктов нефтепереработкииспользуется транспорт: Трубопроводный Железнодорожный Речной
Sea ports of Leningrad region and their competitors in Baltic sea
http://www.morproekt.ru/ 326.06.2015
Riga
Ventspils
Klaipeda
Kaliningrad
Tallinn
HelsinkiHamina-Kotka
Vysotsk Vyborg
Primorsk
Saint-Petersburg
Ust-Luga
Moscow
МОРСТРОЙТЕХНОЛОГИЯ Dynamics and cargo throughput structure of the Russian ports in Baltic sea
http://www.morproekt.ru/26.06.2015 4
Mln. tons
Other cargo
Liquid cargo
Ro-Ro cargo
Ferry cargo
Containers
General cargo
Timber
Dry Bulk cargo
Total
МОРСТРОЙТЕХНОЛОГИЯ
Для продуктов нефтепереработкииспользуется транспорт: Трубопроводный Железнодорожный Речной
Transit of the Russian export and import cargo in non-Russian Baltic ports in 2014
http://www.morproekt.ru/ 526.06.2015
Total cargo flow – 67,2 mln. tons
Scrap metals
Containers
Ore
Coal
Grain
Fertilizers
Other cargo
Liquid cargo
МОРСТРОЙТЕХНОЛОГИЯ Cargo throughput of the Russian Baltic sea ports in 2014
http://www.morproekt.ru/ 626.06.2015
Liquid cargo
Ro-Ro cargo
Ferry cargo
Containers
General cargo
Timber
Dry Bulk cargo
Total
Total
Mln. tons
МОРСТРОЙТЕХНОЛОГИЯ
Для продуктов нефтепереработкииспользуется транспорт: Трубопроводный Железнодорожный Речной
Big Port Saint-Petersburg – leader of the Russian container terminals
http://www.morproekt.ru/ 726.06.2015
Container throughput of the main Russian ports in 2014, thou. TEU
МОРСТРОЙТЕХНОЛОГИЯ
Who is the biggest in the Big Port Saint-Petersburg?
http://www.morproekt.ru/ 826.06.2015
Structure of container throughput by terminals of the Big port Saint-Petersburg, 2014, in thou. TEU
387,6 thou. TEU
227,5 thou. TEU
940,8 thou. TEU
657,8 thou. TEU
Total: 2375,4 thou. TEU
= + + = 77%
МОРСТРОЙТЕХНОЛОГИЯ Main Development Projects in the Inner Harbors of St. Petersburg
http://www.morproekt.ru/ 926.06.2015
Petrolesport, Public JSC
1000 => 1400 thou. TEU by 2015
First Container Terminal, Private JSC
1400 => 1600 thou. TEU by 2015
CT St. Petersburg, Private JSCContainer terminal500 => 1500 thou. TEU by 2016
МОРСТРОЙТЕХНОЛОГИЯ
St. Petersburg Outer Ports Development Projects
http://www.morproekt.ru/ 1026.06.2015
Moby Dick, LLC:Expansion to ~600 th. TEU
Construction of Port Bronka~1400 th. TEU containers+2400 th. tons Ro-Ro cargo
МОРСТРОЙТЕХНОЛОГИЯ Multifunctional Sea Cargo Complex “Bronka” –the deep-water port of Saint-Petersburg
http://www.morproekt.ru/ 1126.06.2015
Designed capacity 1 900 thou. TEU, 260 thou. units of Ro-Ro cargoArea 164 haWater area depth 14,4 mQuai length 1930 mBerth number 5 for containerships, 3 for Ro-Ro vessels
Crane equipmentSTS Post-Panamax PlusUniversal mobile crane of load capacity 302 tons
Containership capacity 6500 TEU Ro-Ro vessel capacity 4200 lane meters, 500 passengers
МОРСТРОЙТЕХНОЛОГИЯ
LNG projects
http://www.morproekt.ru/ 1226.06.2015
LNG-Gorskaya, LLC• Floating LNG plant with 1,26 mln. Tons per
annum capacity by 2016• Building of 9 LNG-bunkering barges (3 of them
ordered from United Shipbuilding Company)• Several LNG bunkering terminals abroad
CryoGAS, JSC(100% belongs to Gazprombank)• LNG plant and terminal capacity – 660 thou.
tons per annum in port Vysotsk• Construction start - 2016,• Commissioning - 2018
Baltic LNG project by Gazprom• LNG plant in Ust-Luga port – 2 trains of 5 mln. tons and
possible extension up to 15 mln. tons.• Commissioning of 1st and 2nd trains - by 2020-2022
1. Cargo terminal2. Crew building;3. Outlet, trading mall; 4. Passenger terminal; 5. Apartments;6. Exhibition hall; 7. Technical service for boats; 8. Marina; 9. Floating LNG storage; 10. LNG liquefaction plant
МОРСТРОЙТЕХНОЛОГИЯ
Port of Ust-Luga
http://www.morproekt.ru/ 1326.06.2015
Throughput of Ust-Luga port in 2005-2014, mln. tons
1 LPG complex
2 Logistic center
3 Container terminal
4 Motor-Railway Ferry Complex
5 Multipurpose transloading complex «Yug-2»
6 Coal terminal
7 Oil depot “Ust-Luga”
8 Universal transloading complex
9 Sulphur complex
10 Liquid cargo complex
11 Oil transfer terminal
12 Bunkering terminal
13 Fractional stable gas condensate transloading complex
14 Metallurgical terminal
15 Mineral fertilizer terminal
16 “New Haven” terminal
17 Timber terminal
МОРСТРОЙТЕХНОЛОГИЯ Development of gas chemical complex in Ust-Luga port
http://www.morproekt.ru/26.06.2015
Baltic Fertilizer Terminal, LLC (ICT Group)
Smart Bulk Terminal, LLC
Fertilizer and general cargo terminal – 4 mln. tons by 2018.Baltic Urea Plant, LLC• ammonia – 350 thou. tons• urea – 1200 thou. tons
Fertilizer terminal – 1,0-1,5,0 mln. tons by 2015
Eurochem Terminal Ust-Luga, LLCFinal capacity – up to 7 mln. tons:• area – 21 ha, including 17 ha of reclaimed area• 3 berths - 773,2 m in total, depths - 16,0 m• 2 warehouses * 100 thou m3
European Sulphur Terminal, JSCWarehouse for 100 thou tons of fertilizers for Phosagro, handling of 1 mln tons per year
Baltic Gas Chemical Company, LLC
NGSK, LLC – project “Northern Methanol”Production of 1,65 mln. tons per year, 80% - for export.Engineering design - 2015, Construction - 2016,Start of production - 2018.
Production of 1,7 mln. tons of methanol per annum and shipments by sea, by 2018
МОРСТРОЙТЕХНОЛОГИЯ
Для продуктов нефтепереработкииспользуется транспорт: Трубопроводный Железнодорожный Речной
Port of Vysotsk
http://www.morproekt.ru/ 1526.06.2015
VysotskPort Vysotsk, LLC Coal terminal5,0 => 7,0 mil tons by ~2016
Port development depends on construction of Losevo-Kamennogorsk railway line (due to be completed in 2015)
Throughput of Vysotsk port in 2005-2014, mln. tons
Mln. tons
Oil products Total Oil Coal
МОРСТРОЙТЕХНОЛОГИЯ
Для продуктов нефтепереработкииспользуется транспорт: Трубопроводный Железнодорожный Речной
Port of Primorsk
http://www.morproekt.ru/ 1626.06.2015
Primorsk
Oil terminal – 75 mln. tons capacityOil products terminal – connected to “North” oil product pipeline project – implies growth of diesel oil handling capacity in Primorsk from 14,5 to 25,0 mln. tons by 2016
Throughput of Primorsk port in 2005-2014, mln. tons
Mln. tons
Oil products Total Oil
МОРСТРОЙТЕХНОЛОГИЯ
Для продуктов нефтепереработкииспользуется транспорт: Трубопроводный Железнодорожный Речной
Automotive logistics – port terminals in Russia - Baltic Sea
http://www.morproekt.ru/ 1726.06.2015
St. Petersburg
Ust-Luga
Terminal “Novaya Gavan”1st stage – 250 th. CEUTo be extended
Terminal “Yug-2”Capacity – 500 th. CEUPCC & PCTC
Terminal “Petrolesport”Capacity – 190 th. CEU
Sea Port of SPb, JSC, former “Perstiko”Capacity – 700 th. CEU (estimation)Ro-Ro – 0,8 mln. Tons (estimation)
Terminal “3rd Stevedoring Company”Capacity – 80 th. CEU
Terminal “Sea Fishery Port”Capacity – 160 th. CEU (estimation)
Total St. Petersburg ~ 430 thou. CEU +0,8 mln. tons
Total Ust-Luga ~ 0,75 mil CEU
+ Terminal in BronkaCapacity – 260 th. unitsUnder construction