distribution automation smart feeders in a smart grid ... · pdf file01.09.2011 ·...
TRANSCRIPT
Distribution Automation –Smart Feeders in a Smart Grid World
Automatic Feeder
SwitchingBob Uluski
Switching
© 2010 Quanta Technology LLC
Introduction
• Distribution Feeder Automation is the monitoring and control of devices located out on the feeders themselves– Line reclosers
– Load break switches
– Sectionalizers
– Capacitor banks
– Line regulators
© 2010 Quanta Technology LLC
Main Feeder Automation Applications
• Automated Line Switching (ALS)
• Volt/VAR Control (VVC)• Volt/VAR Control (VVC) (Discussed in next Seminar Module)
© 2010 Quanta Technology LLC
Automatic Line Switching:h lThe Value proposition
• Reduce system SAIDI & SAIFI significantlyReduce system SAIDI & SAIFI significantly
• Accommodate and take advantage of distributed energy resourcesdistributed energy resources
• Optimal network reconfiguration– Reduce peak loading and total technical losses via load balancing
© 2010 Quanta Technology LLC
Primary ALS Application – “FLISR”
• Fault Location, Isolation, and Service Restoration
• Use of automated feeder switching to:– Detect feeder faults
– Determine the fault location (b i h )(between 2 switches)
– Isolate the faulted section of the feeder (between 2 feeder switches)feeder (between 2 feeder switches)
– Restore service to “healthy” portions of the feeder
© 2010 Quanta Technology LLC
Nature of the Problem• When a permanent fault occurs customers on “healthy”• When a permanent fault occurs, customers on healthy
sections of the feeder may experience a lengthy outage
FAULTOCCURS
CustomerReportsOutage
FieldCrews
On-Scene
FaultLocated
POWER RESTOREDTO CUSTOMERS ON HEALTHY SECTIONS
OF FEEDER
FeederBack toNormal
Travel TimeFault Investigation
& Patrol TimeTime to Perform
Manual Switching Repair Time
5 – 10 minutes
15 – 30 minutes
15 – 20 minutes
10- 15 minutes
45 – 75 minutes
• FLISR provides the means to restore service to some customers before field crews arrive on the scene
© 2010 Quanta Technology LLC
Time Line Without and With FLISRF d
FaultOccurs
CustomerReportsOutage
Travel Time
FaultLocated
Fault Investigation& Patrol Time
Time to PerformManual Switching Repair Time
FeederBack toNormal
Without
POWER RESTOREDTO CUSTOMERS ON
5 – 10 minutes
15 – 20 minutes
10 - 15 minutes
45 75
15 – 30 minutes
1 - 4 Hours
FLISR
Field
TO CUSTOMERS ON HEALTHY SECTIONS
OF FEEDER
45 – 75 minutes
Feeder
POWER RESTOREDTO CUSTOMERS ON HEALTHY SECTIONS
OF FEEDERField
CrewsOn-Scene
FAULTOCCURS
FeederBack toNormal
Travel Time Repair TimePatrolTime
CustomerReportsOutage
With FLISR
15 – 30 minutes
1 - 4 Hours
1 to 5
5 - 10 minutes
5 – 10 minutes
FLISR
© 2010 Quanta Technology LLC
1 to 5 minutes
Terminology – Sample Feeder
Substation #2
5
4
Substation #1 Substation #3
1 2
3
6 7 8
© 2010 Quanta Technology LLC
Terminology – Automated Switches
Substation #2Normally
• All switches must be electrically operable
5
yclosed (line)
switch• Can be load break or fault interruptingdevices
4
Normally open (tie)
Substation #1 Substation #3
1 2
3
6 7 8
open (tie) switch
© 2010 Quanta Technology LLC
Terminology – Fault Detector (FD)
Substation #2
5 FD installed on every switchFD indicates whether fault
current has passed through4
current has passed through the switch
No
Substation #1 Substation #3
1 2
3
6 7 8
Fault
Fault Current
NoFaultFaultFault
© 2010 Quanta Technology LLC
Terminology – Feeder Sections
Substation #2Section: a portion of the
5
Section: a portion of the feeder between two automated switches
4
Faulted “Healthy”
Substation #1 Substation #3
1 2
3
6 7 8
FaultFeeder Section
Feeder Section
© 2010 Quanta Technology LLC
Terminology – Sources
Substation #2“Strong” Source
• Alternate sources required f i DA b fit
5
Strong Source – Capable of
carrying a significant part of
for maximum DA benefit
• Strong or Weak Source
4feeder 1 if necessary
“Weak” Source – Capable of
carrying only a small part of
Substation #1 Substation #3
1 2
3
6 7 8
small part of feeder 1
© 2010 Quanta Technology LLC
FLISR Operation – Normal State
Substation #2
5
4
Substation #1 Substation #3
1 2
3
6 7 8
© 2010 Quanta Technology LLC
FLISR Operation – A Fault Occurs
Substation #2 Permanent fault occurs in section surrounded by switches 2, 3 and 6
5
y ,
FDs at switches 1 and 2 detect the fault
FLISR stores value of load through each switch just prior to the fault
4
j p(usually a fifteen minute average).
FLISR logic does not yet open/close any switches
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault Current Fault
Fault Fault No Fault
© 2010 Quanta Technology LLC
CB Trips – Feeder Deenergized
Substation #2 Circuit breaker trips
5Entire circuit de-energized (dotted line)
FDs at switches 1 and 2 i i k d
4remain picked up
Still no FLISR control actions
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault
Fault Fault No Fault
© 2010 Quanta Technology LLC
CB Recloses – Fault Still There
Substation #2FDs at switches 1 and 2
5
FDs at switches 1 and 2 remain picked up
Still no FLISR control actions
4actions
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault Current Fault
Fault Fault No Fault
© 2010 Quanta Technology LLC
CB Trips Again – Feeder Deenergized
Substation #2
Circuit breaker trips and locks out
Entire circuit de-energized5
Entire circuit de energized (dotted line)
FDs at switches 1 and 2 remain picked up
4
p p
FLISR open/close logic triggered
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault
Fault Fault No Fault
© 2010 Quanta Technology LLC
FLISR Step 1 – Identify Faulted Section
Substation #2 FDs 1 & 2 saw a fault
5FDs 3 and 6 did not see the fault
Fault must be in section b i h 2 3 & 6
4between switches 2,3, & 6
Faulted
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault
Feeder Section
Fault Fault No Fault
© 2010 Quanta Technology LLC
FLISR Step 2 – Isolate Faulted Section
Substation #2 Automatically open switches 2 3 & 6
5
switches 2,3, & 6
4
Faulted
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault
Feeder Section
Fault Fault No Fault
© 2010 Quanta Technology LLC
FLISR Step 3 – Restore “Upstream” Section
Substation #2 FLISR closes CB“Upstream” =
5No need to check load –we know CB can carry the first section
FD i h # 1
between substation and faulted section
4FD at switch # 1 resets
Faulted
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault
Feeder Section
Fault No Fault
© 2010 Quanta Technology LLC
FLISR Step 4 – Restore “Downstream” Load(This is the tricky part)
Substation #2 Substation #2 is a “strong” source – it can carry“Downstream”
(This is the tricky part)
5
source it can carry additional load
Close switch 4 to pick up part of faulted feeder
= between faulted section
and end of feeder
4
part of faulted feederfeeder
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault
Fault No Fault
© 2010 Quanta Technology LLC
FLISR Step 5 – Restore “Downstream” Load (continued)( )
Substation #2 Substation #3 is a “weak” source – can’t carry additional
5
yload at this time
Switch 7 remains open
Feeder section between 4 switches 6 and 7 remain de-
energized
End of FLISR operation
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault
Fault No Fault
© 2010 Quanta Technology LLC
FLISR Benefits
• Reliability Improvement ‐ Significant portion of customers restored quickly (1 minute or less, versus 45 75 minutes without FLISR)versus 45 – 75 minutes without FLISR)
SAIDI Improvement Versus Baseline
52%52%50%60%
SAIFI Improvement Versus Baseline
42%42%40%
50%
33%
0%10%20%30%40%50%
Conventional recloser 1 load break w ith 1 Intellirupter w ith
18%
0%
10%
20%
30%
40%
Conventional recloser 1 load break w ith 1 Intellirupter w ithDA With Load Break
DA With DA With DA With Intelliteam II Intelliteam III Intelliteam II Intelliteam III
SAIFI(MI) Improvement Versus Baseline
21%30%
CAIDI Improvement Versus Baseline
17.9%17.9%18.3%20.0%
Break Switches
Reclosers Load Break Switches
Reclosers
-25%
6%
-30%-20%-10%
0%10%20%
Conventional recloser 1 load break w ith 1 Intellirupter w ith
9%9%
10.0%
12.0%14.0%
16.0%18.0%
Conventional recloser 1 load break w ith 1 Intellirupter w ithDA With DA With DA With DA With
© 2010 Quanta Technology LLC
Conventional recloser 1 load break w ithIntelliteam II
1 Intellirupter w ithIntelliteam III
Conventional recloser 1 load break w ithIntelliteam II
1 Intellirupter w ithIntelliteam IIILoad
Break Switches
DA With Reclosers
DA With Load Break
Switches
DA With Reclosers
Estimating Reliability Improvement Benefits From FLISRSome Useful Formulas
Note: These formulas assume that customers are evenly distributed over the length of the feeder, faults are equally likely to occur anywhere AND there is a suitable alternative source that is located downstream of the switch
• % customer minute (CM) & customers interrupted (CI) savings with DA– Assumes all DA switches have a suitable “downstream” source
– No reclosers initially:• % Improvement = (NSW) / (NSW + 1) * 100
– Where NSW = # of normally closed DA switches– Example: if NSW = 3, % improvement = 3/(3+1)*100 = 75%
Have reclosers to start with:– Have reclosers to start with:• % Improvement = 0.5 * (NSW) / (NSW + 1) * 100
– Example: If NSW = 3, % improvement = 0.5*3/(3+1)*100 = 37.5%
© 2010 Quanta Technology LLC
Other FLISR Benefits
• Labor Savings Less fault investigation and patrol• Labor Savings – Less fault investigation and patrol time because fault location is narrowed down considerablyconsiderably
• Reduction in Unserved Energy – Get some metersReduction in Unserved Energy Get some meters turning sooner
© 2010 Quanta Technology LLC
Feeder Load Balancingb d k d d• Objective: Reduce peak demand on
feeders/substations by periodically shifting load between connected feeders to achieve better balancebetween connected feeders to achieve better balance
• Must have significant diversity between feeders
5
6
7
0
1
2
3
4
01 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27
© 2010 Quanta Technology LLC
• “Make before break” to avoid momentary outages
Load Balancing – Normal Configuration
Substation #2
Sub #1 at Peak Load
Substation #1 Substation #3
© 2010 Quanta Technology LLC
Load Balancing – Sub#1 At Peak Load
Substation #2
Sub #1 at Peak Load
Substation #1 Substation #3
Load TransferredTo Sub #3
© 2010 Quanta Technology LLC
Load Balancing – Sub#3 At Peak Load
Substation #2
L d
Sub #3 at Peak Load
Substation #1 Substation #3
Load TransferredTo Sub #1
© 2010 Quanta Technology LLC
Load Balancing ‐ Benefits
• Reduction of Peak Demand on individual substation– Defer capacity addition
– Reduce individual substation demand chargesReduce individual substation demand charges
• Reduction of Electrical Losses• Reduction of Electrical Losses– Total losses with balanced load < Total losses with one heavily loaded feeder and one lightlywith one heavily loaded feeder and one lightly loaded feeder
© 2010 Quanta Technology LLC
Beyond Load Balancing –l k fOptimal Network Reconfiguration
• Objectives :l f d l ( f f l l h d )– Minimize energy losses on feeder lines (time frame of multiple hours or days)
– Balance loads among phases, feeders, substations, transformers– Plan outages for equipment or feeder section maintenance
• Seasonal OptimizationSeasonal Optimization– Goal => optimize topology for steady state operations
• Minimal power and energy losses• Maximum reliability• Best load balance• Best load balance• Best voltage profiles
• Near Real‐Time Optimization– Normal operations => Loss Optimization Mode– Emergency operations => Voltage Reduction Mode– Peak load shaving => MW Reduction Mode
© 2010 Quanta Technology LLC
Cold Load Pickup
• Objective: Reduce the time to restore loadObjective: Reduce the time to restore load following extended outage for which cold load conditions applyconditions apply
R i i i i• Restore service a section at a time via remote control
© 2010 Quanta Technology LLC
Cold Load Pickup Example
Substation #2
Substation #1 Substation #3
Open all switches via
remote control
© 2010 Quanta Technology LLC
Cold Load Pickup Example
Substation #2
Restore one section
t ti
Substation #1 Substation #3
at a time
© 2010 Quanta Technology LLC
Cold Load Pickup Example
Substation #2
Restore one section
t ti
Substation #1 Substation #3
at a time
© 2010 Quanta Technology LLC
Cold Load Pickup Benefits
• Reliability Improvement Benefit: Faster overallReliability Improvement Benefit: Faster overall service restoration
• Labor Savings: Fewer manual switching i i i l l iactivities, less travel time
© 2010 Quanta Technology LLC
Emergency Load Shedding
• Some utilities are limited in amount of load shedding that is possible due to presenceshedding that is possible due to presence of critical (non‐interruptible) loads
• Automated switches can be used to shed l d h f d ith t i tiload on such feeders without impacting non‐interruptibles
© 2010 Quanta Technology LLC
Load Shedding Using Line SwitchesSubstation #2
Non-Interruptible
Substation #1 Substation #3
Interruptible Customer in this section
Substation #3
Open This Switch
© 2010 Quanta Technology LLC
Use of Faulted Circuit Indicators
Remotely monitored faulted i it i di t i t i
4
circuit indicator can assist in pinpointing fault location
Substation #1
1 2
3
6 7
© 2010 Quanta Technology LLC
Benefits of FCI MonitoringBenefits of FCI MonitoringFault Prediction by OMS/AMI
© 2010 Quanta Technology LLC
Benefits of FCI MonitoringBenefits of FCI MonitoringFault Prediction by OMS/AMI & FCI
© 2010 Quanta Technology LLC
Risk – Section “Net Load” Problem
Substation #2
With DG running, pre-fault load through switch 6 is 1 MW
However, total load in this section is 3 MW (DG supplying
5
section is 3 MW (DG supplying 2MW)
FLISR may use prefault load thru switch 6 to make
d i hi d i i4
2MW
downstream switching decision
This could overload Substation 3
Substation #1 Substation #3
1 2
3
6 7 8
Prefault Load
1MW
© 2010 Quanta Technology LLC
FLISR with Large DG or Distribution NetworksDistribution Networks
Substation #2 FLISR fault detectors
5might predict fault
beyond switch number 6, and….
4
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault Current Fault Fault
Current
Fault Fault Fault
© 2010 Quanta Technology LLC
FLISR with Large DG or Distribution NetworksDistribution Networks
Substation #2 Trip switch 6, ultimately
5resulting in…
4
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault Current Fault
Fault Fault Fault
© 2010 Quanta Technology LLC
FLISR with Large DG or Distribution NetworksDistribution Networks
Substation #2 Entire feeder outage
5
4
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault
Fault Fault Fault
© 2010 Quanta Technology LLC
FLISR with Large DG or Distribution NetworksDistribution Networks
Substation #2 With directional fault
5indicators, FLISR would locate the fault properly,
resulting in
4
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault Current Fault Fault
Current
Fault Fault Fault
© 2010 Quanta Technology LLC
FLISR with Large DG or Distribution NetworksDistribution Networks
Substation #2 Power restored to as
5many customers as
possible!
4
Substation #1 Substation #3
1 2
3
6 7 8
No Fault
Fault
Fault Fault Fault
© 2010 Quanta Technology LLC
Use of Line Reclosers for FLISR
Substation #2
5
4
Line Recloser
Substation #1 Substation #3
1 2
3
6 7 8
No Fault Fault
Fault Fault Fault
© 2010 Quanta Technology LLC
Line Recloser Trips –Portion of Feeder DeenergizedPortion of Feeder Deenergized
Substation #2 If line reclosers are used instead of load break
5
instead of load break switches, only a portion of the feeder is interrupted, but….
4
Line Recloser
Substation #1 Substation #3
1 2
3
6 7 8
No Fault Fault
Fault Fault Fault
© 2010 Quanta Technology LLC
FLISR With Line ReclosersFLISR With Line Reclosers
• May have difficulty10
Current in Amperes: x 100 at 12.47 kV.
A1A1May have difficulty coordinating several reclosers in series
1
A2A2
A3A3A3A3reclosers in series– Trip faster than upstream switches 0.1
Tim
e in
Sec
onds
A4A4
upstream switches
– Trip slower than downstream switches 0 01do s ea s c es
– Trip slower than downstream fuses
PLOTTING VOLTAGE:
BY:
DATE:
NO:
12.47 kV
8-9-2005
10
0.015 10 100
© 2010 Quanta Technology LLC
Line Recloser Trips –Portion of Feeder DeenergizedPortion of Feeder Deenergized
Substation #2 May have difficulty coordinating a series of line
5
coordinating a series of line reclosers, resulting in….
4
Line Recloser
Substation #1 Substation #3
1 2
3
6 7 8
No Fault Fault
Fault Fault Fault
© 2010 Quanta Technology LLC
Line Recloser Trips –Coordination of Reclosers in SeriesCoordination of Reclosers in Series
Substation #2 Overtripping!
5
4
Line Recloser
Substation #1 Substation #3
1 2
3
6 7 8
No Fault Fault
Fault Fault Fault
© 2010 Quanta Technology LLC
This switch must operate slower than downstream fuse, but faster than upstream recloser
Using Directional Blocking Scheme
Substation #2 Controller at “6” detects fault and fault direction
5
fault and fault direction
4
Line Recloser
Substation #1 Substation #3
1 2
3
6 7 8
No Fault Fault
Fault Fault Fault
© 2010 Quanta Technology LLCRadio Radio
Using Directional Blocking SchemeUsing Directional Blocking Scheme
Substation #2 Controller at “6” detects sends blocking signal to “2”
5
sends blocking signal to 2
4
Line Recloser
Substation #1 Substation #3
1 2
3
6 7 8
No Fault Fault
Fault Fault Fault
© 2010 Quanta Technology LLCRadio Radio
Please don’t trip!
Using Directional Blocking SchemeUsing Directional Blocking Scheme
Substation #2 Only the recloser at switch 6 trips
5
6 trips
4
Line Recloser
Substation #1 Substation #3
1 2
3
6 7 8
No Fault Fault
Fault Fault Fault
© 2010 Quanta Technology LLCRadio Radio
Please don’t trip!
System Components
Distribution SCADA system
Remote controlled feeder switches– Remote controlled feeder switches
– Feeder RTU or Controller
– Fault detectorsFault detectors
– Two‐way communication facilities
( Sp.SpectrumMAS
© 2010 Quanta Technology LLC
Distribution SCADA System
• Supervisory Control and Data Acquisition (SCADA)• Supervisory Control and Data Acquisition (SCADA) system:
– Minimum requirement: Allow distribution system operator to monitor and oversee operation of the feeder automation facilitiesfeeder automation facilities
– May also perform the bulk of the feeder automation ( l d h l hprocessing (centralized scheme only – more on this in
Module 5)
© 2010 Quanta Technology LLC
Feeder Automation SwitchesAll i h b l i ll• All switches must be electrically operable
• Can be load break or faultCan be load break or fault interrupting devices
• Can be overhead or underground( )Load Break Switch (padmount) switchesLoad Break Switch.
Photo courtesy of Bridges Electric
Kyle® Type NOVA™ RecloserPad Mounted Switch
© 2010 Quanta Technology LLC
(Fault Interrupting Device).Photo courtesy of Cooper Power Systems
ABB OVR Recloser
Retrofit Motor Operators
may be able to save money by retrofitting a motor operator
Retrofit PadmountRetrofit Pole Mounted Switch
g pon an existing manual switch
Retrofit Motor-Operator
Retrofit Padmount. Photo Courtesy of S&C Electric
Co
Retrofit Pole Mounted SwitchPhoto Courtesy of Cleaveland Price, Inc
© 2010 Quanta Technology LLC
DA Switch Vendors
Vendor Name W ebsite RecloserLoad Break
bb / d t/ /9AAC
Current InterruptingPole
Mount PadmountRe trofit
KitFault
Interrupting
ABBwww.abb.com/produc t/us /9AAC720078.aspx X X
Cooper Power Systems www.cooperpower.com X X X XS&C Electric Company www.sandc .com X X X XJoslyn Hi Voltage www.joslynhivoltage.com X X X
X
G&W www.gwelec .com X X X XBridges Electric www.bridgeselec tric.com XCleaveland Price www.cleavelandprice.com X
Turner Electric Co. LLChttp://www.turnerswitch.com/installation/operators .html X
Siemens
pFederal Pac ific http://www.federalpac ific .com/ X X
NOJA Power (Australia) www.nojapower.com.au X
© 2010 Quanta Technology LLC
Feeder RTU or Local Controller
• Acquires data from FD or local sensors (or can serve as FD!)
• Executes control commands
S&C 5800
• May perform bulk of feeder automation processing (distributed architecture) SEL 451
S&C( )
• Provides interface to communication facilities
S&C UIM
DAQ Polaris Pole Top
Cooper Form 6 Pole-Top
RTU Controller
© 2010 Quanta Technology LLC
Fault Detector (FD)
• Determines that a fault has occurred “downstream” (further from the substation)
• Basic Requirementsq– Must be able to identify and “capture” the fault information before fault is cleared (in a few
l )cycles)
– Must be able to detect all kinds of faults
• Phase faults• Phase faults
• Ground faults – current may be less than normal load – must use “residual” current
© 2010 Quanta Technology LLC
Two Ways to Accomplish FD
• Faulted Circuit• Faulted Circuit Indicator (FCI)
• Current/Voltage Sensor
© 2010 Quanta Technology LLC
Faulted Circuit IndicatorsF lt d Ci it I di t (FCI)
Photo Courtesy of Horstmann/Power Delivery Products
Faulted Circuit Indicator (FCI)Close a contact when pre-established ampere threshold is exceeded
– Clamp on style
– Current inrush restraint
exceeded
– Must work in either direction
– Reset conditions
• Time
• Restoration of voltage or current
– Local indicator visible from ground level
– Output signal to feeder RTUEdison Controls FD
p g
• Radio signal
• Fiber optic/metallic cable
© 2010 Quanta Technology LLC
Current & Voltage Sensors
– Perform basic current & voltage measurementProvide measurement to a separate device– Provide measurement to a separate device for analysis (“does measurement exceed threshold?”)
– Doubles as data acquisition unit for feeder ( )monitoring (SCADA) system
– Voltage sensor may also serve as a power source for DA feeder equipment
– Basic requirementsFisher Pierce Line P t SBasic requirements
• Accuracy at least + or ‐ 3%• Suitable for measuring fault current (should not saturate)C b t d l it( ) i t l t f
Post Sensor
• Can be standalone unit(s) or integral part of switch itself
Lindsey CurrentSensor
© 2010 Quanta Technology LLC
Current & Voltage Sensors
Can be an integral part of the DA switch
Current-Voltage Sensor
“S d M t ” b S&C El t i“ScadaMate” by S&C Electric
© 2010 Quanta Technology LLC
Bidirectional Fault Indicatorsid f l d i d• Provide fault detection and
direction of fault• Useful Required for
– Systems with DGSystems with DG– closed loop, paralleled or
networked distribution systems
Power Delivery Productshttp://www.powerdeliveryproducts.com/directionalfaultindicator.htmQuanta Technology has seen a
growing number of utilities using
© 2010 Quanta Technology LLC
growing number of utilities using directional overcurrent relays
for this purpose
Communication Facilities
• System requires reliable 2‐way communication facilities to feeder locations
• Common approaches:– Licensed UHF MAS radio
– Unlicensed Spread spectrum radio
– Cellular telephone & other commercial services
– Power line carrier
– WiMAXMore details on DA Communications laterMore details on DA Communications later
© 2010 Quanta Technology LLC
Control Panels
• Open/Close Pushbuttons
h ( / l d) d• Switch status (open/closed) indicators
• Alarm indicators
• Local/remote switch
• Operations counterOperations counter– Electrical operations
Mechanical operations?– Mechanical operations?
© 2010 Quanta Technology LLC
Switch Power Supply (SPS)
• Key Point:Most switch operations run off the SPS with the line dead!– Should specify a required number ofShould specify a required number of
operations with the power off (biggest power drain is radio transmitter)
– As an absolute minimum must be able toAs an absolute minimum, must be able to open switch and close switch once without recharging (with the line dead)
• Power SourcePower Source– Voltage sensor may provide all the power
needed by the switch, controller, and radio
If not use dedicated voltage transformer or– If not use dedicated voltage transformer or connect to local secondary circuit
© 2010 Quanta Technology LLC
Categories for Automated Line Switching
• Approaches categorized on how control isApproaches categorized on how control is performed:– SupervisedSupervised
– Semi‐Automatic
– Fully Automatic
© 2010 Quanta Technology LLC
Feeder Automation CategoriesS i d• Supervised
• No automatic control – “person in the loop”• System delivers information (recommendations) to Dispatcher• Dispatcher initiates remote control actions
– Pro’s• Simpler than fully automaticSimpler than fully automatic• Good “starter” approach until confidence is built up
– Con’s• Takes longer to restore service (3 5 minutes)• Takes longer to restore service (3 – 5 minutes)
– Communication time (both ways)– Dispatcher decision time
• Difficult for dispatcher to manage many switches duringDifficult for dispatcher to manage many switches during emergencies involving multiple disturbances
© 2010 Quanta Technology LLC
Feeder Automation Categories• SEMI‐AUTOMATIC
– Mix of automatic and supervised control– ExampleExample
– DA system automatically isolates fault and performs “upstream” restoration (the “easy” part)
– Dispatcher supervises “downstream” restoration activities based on DA system recommendations (the “hard” part)on DA system recommendations (the hard part)
– Pro’s• Simpler than fully automatic• Natural progression from supervised approach• Where many utilities end up• “Upstream” customers restored in less than 1 minute
– Con’sCon s• Takes longer to restore “downstream” service (3 – 5 minutes)• Difficult for dispatcher to manage many switches during emergencies involving multiple disturbances
• Not supported by some DA vendors
© 2010 Quanta Technology LLC
• Not supported by some DA vendors
Feeder Automation Categories– FULLY AUTOMATIC
– All fault isolation and restoration activities performed automatically
Current state of the art– Current state of the art
– No dispatcher intervention
• Pro’s
– Possible to restore all service in less than one minute
– Less burden on Dispatcher to manage the switching activities
• Con’s
– Most complex approach
– Acceptance difficultiesAcceptance difficulties
» Ranges from “Why not?” to “Over my dead body”
© 2010 Quanta Technology LLC
• Tradeoff: “Permanent” vs. “Momentary” Outages
• Definitions:
Permanent: Duration > threshold– Permanent: Duration > threshold
– Momentary: Duration < threshold
• Use of FLISR will:
Improve permanent outage statistics– Improve permanent outage statistics
• SAIDI, SAIFI, CAIDI
– Make momentary outage statistics worse
• MAIFI• MAIFI
• Most utilities are willing to accept this tradeoff!
© 2010 Quanta Technology LLC
• Limitations on Transferring Load to Adjacent Feedersj– It is often difficult to transfer all the “healthy” load
to adjacent feeders without causing overloads and/or voltage problems/ g p
– Especially true during peak load period
– May need to split load being transferred to alternative sources
– May require additional automated switches and addition tie points to accomplish FLISR objectives p p jat certain times of the day
– Key Point: Must have backup source to get incremental reliability improvement beyondincremental reliability improvement beyond simple recloser!
– Can use DG, Energy Storage, and other Distributed f d
© 2010 Quanta Technology LLC
Energy resources for downstream restoration (More later in DG Section – Farid)……
Estimating Reliability Improvement BenefitsA h U f l F l (C i d)Another Useful Formula (Continued)
• reduction in reliability improvement if some switches do not have a suitable downstream source
% reduction in reliability Improvement = 100 *– % reduction in reliability Improvement = 100
• Where: NDSS = # of DA switches that do not have a suitable downstream source
• Example: with total of 4 normally closed DA switches (NSW = 4), what is the reduction in benefits if 2 of these switches does not have a suitable downstream source?
100 * (1 + 2) / (4+1)2 = 300 / 25 = 12% reduction in savings
© 2010 Quanta Technology LLC
Reliability Improvement versus Number of Switches ‐Diminishing Returns
Additional reliability improvement benefit declines dramatically as more switches are added
Reliability Improvement
90100
a e added
5060708090
ovem
ent
No reclosers
1020304050
% Im
pro
Reclosers
00 1 2 3 4 5 6 7
Number of DA Switches
© 2010 Quanta Technology LLC
Reliability Improvement versus Number of SwitchesUsually 2 ½ switches is best for reliability improvement BFTB – more
switches added due to load transfer constraints, critical customers, and unusual feeder configuration
Reliability Improvement
90100
5060708090
ovem
ent
No reclosers
1020304050
% Im
pro
Reclosers
00 1 2 3 4 5 6 7
Number of DA Switches
© 2010 Quanta Technology LLC
Importance of Switch Placement• Predicted reliability improvement varies widely withPredicted reliability improvement varies widely with
switch placement strategy
• KEY POINT!: Splitting customer count into equal physicalKEY POINT!: Splitting customer count into equal physical parts is only best when customers and fault exposure are evenly distributed across the feeder (rarely the case!)
• Hypothetical Case – all customers concentrated in one spot
• If Length “A” is really small, and
Backup source
N/OPrimary source
• the backup sources is strong (able to carry the entire sample feeder)
• SAIDI and SAIFI for concentrated load could be nearly reduced to
All Load Concentrated
here
load could be nearly reduced to zero!.....
© 2010 Quanta Technology LLC
Importance of Switch Placement• Predicted reliability improvement varies widely withPredicted reliability improvement varies widely with
switch placement strategy
• KEY POINT!: Splitting customer count into equal physicalKEY POINT!: Splitting customer count into equal physical parts is only best when customers and fault exposure are evenly distributed across the feeder (rarely the case!)
• Hypothetical Case – all customers concentrated in one spot
If L th “A” i ll ll d
Backup source
N/OPrimary source
• If Length “A” is really small, and • the backup sources is strong
(able to carry the entire sample feeder)
• SAIDI and SAIFI for concentratedAll Load
Concentrated here
SAIDI and SAIFI for concentrated load could be nearly reduced to zero!.......
Hypothetical case is not realistic, but
© 2010 Quanta Technology LLC
yp ,shows that its beneficial to surround concentrated load with DA switches
Importance of Switch Placement• Switch placement analysis is not trivial – should use
engineering analysis tool!
• Sample variation between equal physical division and optimal placement :– SAIDI ‐ 22%– SAIDI ‐ 22%– SAIFI ‐ 31%– MAIFI ‐ 23%
• Small change in placement (a few hundred feet) produced a 5% change in SAIDI!
© 2010 Quanta Technology LLC
Single Phase Trippingg pp g• Some newer line reclosers support single phase tripping
• Can perform FLISR operation on only the faulted phase – avoid service interruption on unfaulted phases (SAIDI, SAIFI benefit)p ( , )
• Issues:– Adverse impact on 3 phase loadsR i i t h t i d l l d– Remaining two phases may trip ground relay on load imbalance
• Typical solution:– Trip and reclose single faulted phase for temporary fault– Trip and lockout all three phases for permanent fault
© 2010 Quanta Technology LLC
Faults on Fused Laterals
• No incremental benefit for permanentfaults on fused lateralsfaults on fused laterals– Must take this into account when computing potential benefitspotential benefits
• For temporary faults:– Can apply fuse saving
– New S&C “TripSaver” Dropout Recloser
© 2010 Quanta Technology LLC
First Segment Fault Detection• Always an issue!Always an issue!
• System requires a “lockout for fault”• System requires a “lockout for fault” signal from the substation to trigger feeder switching activitiesfeeder switching activities– Fault has occurred– Feeder protection has completed itsFeeder protection has completed its automatic reclosing cycle
• Works best if a protective relay IED is available in the substation and can be
© 2010 Quanta Technology LLC
interfaced to the FLISR system
Non‐Fault vs Fault TrippingS b bl di i i h b “• System must be able to distinguish between “non fault” and “fault” tripping of the substation circuit breaker/recloser
• “Fault” Tripping– A feeder fault has occurred or supply has been lost due to a
t i i b t ti f lttransmission substation fault
– FLISR should attempt to restore service
• “Non‐Fault” Trippingpp g– Substation CB tripped for reasons other than a feeder fault
• Manual operation by switching personnel or supervisory
control from the control center
• Underfrequency/undervoltage load shedding
– FLISR should not attempt to restore service
© 2010 Quanta Technology LLC
FLISR should not attempt to restore service
Impact on Feeder Protection
Substation #2 Entire feeder must
5remain protected following FLISR operation!.....
4
Substation #1 Substation #3
1 2
3
6 7 8
© 2010 Quanta Technology LLC
Impact on Feeder Protection
Substation #2 So if source at
5substation 1 is lost.....
4
Substation #1 Substation #3
1 2
3
6 7 8
© 2010 Quanta Technology LLC
Impact on Feeder Protection
Substation #2 FLISR May
5reconfigure feeders as shown…..
4
Substation #1 Substation #3
1 2
3
6 7 8
© 2010 Quanta Technology LLC
Impact on Feeder Protection
Substation #2
Feeder relays at “5” must be able to reach all the way to switch 1
5
y
Note: relay IEDs can switch between setting groups but most DA/DMS
4groups but most DA/DMS systems don’t auto switch the settings
Substation #1 Substation #3
1 2
3
6 7 8
© 2010 Quanta Technology LLC
Safety Issues
• Safety for workers and general public must not be compromised!!!
• Operating practices and procedures must be reviewed and modified if necessary to address presence of automatic switchgearaddress presence of automatic switchgear
• Safety related recommendations:Requirement for “visible gap”– Requirement for “visible gap”
– No automatic closures after two minutes have elapsed following the initial faultp g
– System disabled during maintenance (“live line”) work
© 2010 Quanta Technology LLC