doracak japoni

Upload: conya-smathel

Post on 06-Jul-2018

229 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/17/2019 Doracak japoni

    1/268

     

    DEPARTMENT OF ENERGYENERGY UTILIZATION MANAGEMENT BUREAU

    Manuals and Guidelines

    for

    Micro-hydropower Development

    in Rural Electrification

    Volume I

     June 2009

  • 8/17/2019 Doracak japoni

    2/268

     

    Through the Project on “Sustainability Improvement of Renewable EnergyDevelopment for Village Electrification in the Philippines” under technicalassistance of Japan International Cooperation Agency (JICA), this manual wasdeveloped by the Department of Energy (DOE) reviewing the “Manual for Micro-hydropower Development in March 2003.

  • 8/17/2019 Doracak japoni

    3/268

     

    Manuals and Guidelinesfor

    Micro-hydropower Development in Rural Electrification

    Volume I

    MHP-1 Manual for Design, Implementation and Managementfor Micro-hydropower

    Volume II

    MHP-2 Guideline for Selection of Potential Sites and Rehabilitation Sitesof Micro-hydropower

    MHP-3 Project Evaluation Guideline for Micro-hydropower Development

    MHP-4 Micro-hydropower Plant Site Completion Test Manual

    MHP-5 Micro-hydropower Operator Training Manual

    MHP-6 Training Manual for Micro-hydropower Technology

  • 8/17/2019 Doracak japoni

    4/268

    1 

  • 8/17/2019 Doracak japoni

    5/268

     

    DEPARTMENT OF ENERGYENERGY UTILIZATION MANAGEMENT BUREAU

    MANUAL

    for

    Design, Implementation and Management

    For

    Micro-hydropower Development

     June 2009

    MHP – 1

  • 8/17/2019 Doracak japoni

    6/268

     

    Through the Project on “Sustainability Improvement of Renewable Energy

    Development for Village Electrification in the Philippines” under technicalassistance of Japan International Cooperation Agency (JICA), this manual wasdeveloped by the Department of Energy (DOE) reviewing the “Manual for Micro-hydropower Development in March 2003.

  • 8/17/2019 Doracak japoni

    7/268

     Manual for Micro-Hydro Power Development

    Contents

    - c-1 -

     Manual for Micro-Hydro Power Development

    Table of Contents

    EXECUTIVE SUMMARY

    1  Background S-1

    2  User of Manual S-1

    3  Applicable Range of Micro-Hydropower S-1

    4  How to use this Manual S-2

    Chapter 1 INTRODUCTION 1-1

    1.1 Purpose of the Manual for Micro-Hydro Development 1-1

    1.2 Components of Micro-Hydro Power 1-2

    1.3 Concept of Hydropower 1-5

    1.4 The Water Cycle 1-7

    Chapter 2 IDENTIFICATION OF THE POTENTIAL SITES 2-1 

    2.1 Basic Reference Materials 2-1

    2.2 Radius of Site Identification 2-3

    2.3 Calculation of River Flow 2-4

    2.4 Identification of Potential Sites 2-5

    2.4.1 Map Study 2-5

    2.4.2 Identification Based on Local Information 2-6

    2.4.3 Selection of Potential Development Sites 2-7

    [Ref.2-1 Transmission and distribution line distance and voltage drop] 2-10

    [Ref.2-2 Relationship between voltage drop and distribution line distance 2-11[Ref.2-3 Considerations in the indirect estimation of discharge at the project

    site using data from gauging stations in the vicinity. 2-12

    [Ref.2-4 Method of river flow calculation by water balance model of

    drainage area] 2-14

    [Ref.2-5 Example of Micro-hydro Development Scheme Using Natural

    Topography and Various Man-made Structures] 2-21

    Chapter 3 SITE RECONNAISSANCE 3-1

  • 8/17/2019 Doracak japoni

    8/268

     Manual for Micro-Hydro Power Development

    Contents

    - c-2 -

    3.1 Objective of Site Reconnaissance 3-1

    3.2 Preparation for Site Reconnaissance 3-1

    3.2.1 Information gathering and preparation 3-1

    3.2.2 Planning of preliminary site reconnaissance 3-2

    3.2.3 Necessary equipment for preliminary site reconnaissance 3-2

    3.3 Survey for Outline the Project Site 3-3

    3.4 Validation of Geological Conditions Affecting Stability

    of Main Civil Structures 3-5

    3.5 Survey on Locations of Civil Structures 3-6

    3.6 Measurement of River Flow 3-7

    3.7 Measurement of Head 3-9

    3.8 Demand Survey 3-10

    3.8.1 Demand survey 3-10

    3.8.2 Factors to consider in the Demand survey items 3-10

    3.9 Actual Field Survey 3-12

    [Ref.3-1 Method of Stream Flow Measurement] 3-13

    [Ref.3-2 Method of Head Measurement] 3-18

    [Ref.3-3 Sample Form Sheet for Potential Site Survey] 3-22

    [Ref.3-4 Questionnaire for households of non-electrified barangays] 3-26

    Chapter 4 PLANNING 4-1

    4.1 Scheme of Development Layout 4-1

    4.2 Data and Reference to Consider for Planning 4-3

    4.2.1 Hydrograph and Flow Duration Curve 4-3

    4.2.2 Plant Factor and Load Factor 4-4

    4.3 Selection of Locations for Main Civil Structures 4-64.3.1 Location of Intake 4-6

    4.3.2 Headrace Route 4-8

    4.3.3 Location of Head Tank 4-8

    4.3.4 Penstock Route 4-9

    4.3.5 Location of Powerhouse 4-12

    4.3.6 Location of Tailrace 4-13

    4.4 Supply and Demand Plan 4-14

    4.4.1 Selection of Power Demand Facilities 4-14

  • 8/17/2019 Doracak japoni

    9/268

     Manual for Micro-Hydro Power Development

    Contents

    - c-3 -

    4.4.2 Scheme of Development based on Supply and Demand 4-15

    4.4.3 Daily Supply and Demand Plan 4-22

    Chapter 5 DESIGN FOR CIVIL STRUCTURES 5-1

    5.1 Basic Equation for Civil Design 5-1

    5.2 Intake Weir (Dam) 5-1

    5.2.1 Types of Intake Weir 5-1

    5.2.2 Weir Height Calculation 5-5

    5.3 Intake 5-9

    5.3.1 Types of Intake 5-9

    5.3.2 Important Points for Intake Design (for Side-Intake) 5-12

    5.4 Settling basin 5-14

    5.5 Headrace 5-17

    5.5.1 Types and Structures of Headrace 5-17

    5.5.2 Determining the Cross Section and Longitudinal Slope 5-21

    5.6 Headtank 5-24

    5.6.1 Headtank Capacity 5-24

    5.6.2 Important Points for Headtank Design 5-26

    5.7 Penstock 5-30

    5.7.1 Penstock Material 5-30

    5.7.2 Calculation of Steel Pipe Thickness 5-30

    5.7.3 Determining Diameter of Penstock 5-30

    5.8 Foundation of Powerhouse 5-34

    5.8.1 Foundation for Impulse Turbine 5-34

    5.8.2 Foundation for Reaction Turbine 5-35

    [Ref. 5-1 Simple Method for Determining the Cross Section] 5-37[Ref.5-2 Simple Method for Determining the Diameter of Penstock] 5-41

    [Ref.5-3 Calculation of Head Loss] 5-42

    Chapter 6 DESIGN FOR MECHANICAL AND ELECTRICAL STRUCTURES 6-1 

    6.1 Fundamental Equipment Components for Power Plant 6-1

    6.2 Turbine (Water turbine) 6-5

    6.2.1 Types and Output of Water Turbine 6-5

    6.2.2 Specific Speed and Rotation Speed of Turbine 6-8

  • 8/17/2019 Doracak japoni

    10/268

     Manual for Micro-Hydro Power Development

    Contents

    - c-4 -

    6.2.3 Design of Crossflow Turbine 6-12

    6.2.4 Design of Reverse Pump Type Turbine (Pump As Turbine) 6-13

    6.3 Generator 6-14

    6.3.1 Types of Generator 6-14

    6.3.2 Output of Generator 6-16

    6.3.3 Speed and Number of Poles of Generator 6-17

    6.4 Power Transmission Facility (Speed Increaser) 6-19

    6.5 Control Facility of Turbine and Generator 6-20

    6.5.1 Speed Governor 6-20

    6.5.2 Exciter of Generator 6-21

    6.5.3 Single Line Diagram 6-23

    6.6 Control, Instrumentation and Protection of Plant 6-24

    6.6.1 Control Method of Plant 6-24

    6.6.2 Instrumentation of Plant 6-24

    6.6.3 Protection of Plant and 380/220V Distribution Line 6-25

    6.6.4 Protection of 20kV Distribution Line 6-25

    6.7 Inlet Valve 6-26

    Annex 6.1 Brief Design of Cross Flow Turbine (SKAT T-12,13 & 14) 6-28

    Annex 6.2 Brief Design of Reverse Pump Turbine (PAT) 6-33

    Annex 6.3 Technical Application Sheet of Tender for

    for Rural Electrification 6-46

    Annex 6.4 Breif Design for Electro-mechanical Equipment of

    Micro-hydropower Plant 6-49

    Chapter 7 DESIGN OF DISTRIBUTION FACILITIES 7-1

    7.1 Concept of Electricity 7-17.2 Selection for Distribution Route 7-3

    7.3 Distribution Facilities 7-5

    7.4 Pole 7-6

    7.4.1 Span Length of Poles 7-6

    7.4.2 Allowable Minimum Clearance of Conductors and Environment 7-7

    7.4.3 Height of Poles 7-7

    7.4.4 Size of Poles 7-8

    7.5 Guy wire 7-9

  • 8/17/2019 Doracak japoni

    11/268

     Manual for Micro-Hydro Power Development

    Contents

    - c-5 -

    7.6 Conductors and Cables 7-12

    7.6.1 Advantages/Disadvantages of Conductors and Cables 7-12

    7.6.2 Sizes of Conductors 7-12

    7.6.3 Allowable Sag of Conductors 7-12

    7.6.4 Allowable Load per Phase 7-12

    7.6.5 Application of 3-Phase Line 7-12

    7.7 Distribution Transformers 7-13

    7.7.1 Types of Distribution Transformer 7-13

    7.7.2 Necessity of Transformers 7-14

    7.7.3 Application of Distribution Transformers 7-15

    7.7.4 Selection of Unit Capacity 7-15

    7.7.5 Location 7-15

    7.8 House Connection (HC) 7-16

    7.8.1 Application of House Connection 7-16

    7.8.2 In-house Wiring 7-17

    [Ref.7-1 Standard of Steel poles] 7-18

    [Ref.7-2 Construction of house connection crossing village road] 7-19

    Chapter 8 PROJECT COST ESTIMATION 8-1

    8.1 Rough Cost Estimation During Planning Stage 8-1

    8.2 Cost Estimation During Detail Design Stage 8-3

    8.2.1 Items 8-3

    8.2.2 Quantity 8-5

    8.2.3 Unit Cost 8-6

    [ Ref. 8-1 Cross-sectional method to calculate quantity] 8-11

    [Ref.8-2 Example of Bill of Quantities] 8-13

    Chapter 9 CONSTRUCTION MANAGEMENT 9-1

    9.1 Construction Management for Civil Facilities 9-1

    9.1.1 Purpose 9-1

    9.1.2 Progress Control 9-1

    9.1.3 Dimension Control 9-2

    9.1.4 Quality Control 9-3

  • 8/17/2019 Doracak japoni

    12/268

     Manual for Micro-Hydro Power Development

    Contents

    - c-6 -

    9.2 Construction Management for Turbine, Generator and

    their Associated Equipment 9-5

    9.2.1 Installation 9-5

    9.2.2 Adjustment during Test Run Operation 9-6

    Chapter 10 OPERATION AND MAINTENANCE 10-1

    10.1 Introduction 10-1

    10.2 Operation 10-2

    10.2.1 Basic Operation 10-2

    10.2.2 Operation in case of Emergency 10-4

    10.2.3 Others 10-5

    10.3 Maintenance 10-6

    10.3.1 Daily Patrol 10-6

    10.3.2 Periodic Inspection 10-8

    10.3.3 Special Inspection 10-8

    10.4 Recording 10-9

    Chapter 11 MANAGEMENT 11-1

    11.1 Establishment of Organization 11-1

    11.2 Management System 11-1

    11.3 Reporting and Monitoring 11-2

    11.4 Decision-Making System 11-2

    11.5 Accounting System 11-3

    11.6 Roles and Responsibilities of BAPA 11-3

    11.6.1 BAPA Officials 11-3

    11.6.2 Consumers 11-511.6.3 Local Government Unit (LGU) 11-5

    11.6.4 Department of Energy (DOE) 11-5

    11.7 Training 11-5

    11.8 Collection of Electricity Charges and Financial management 11-6

    11.8.1 Tariff Setting 11-6

    11.8.2 Tariff Collection 11-6

    11.8.3 Financial Management 11-7 

  • 8/17/2019 Doracak japoni

    13/268

     Manual for Micro-Hydro Power Development

     Executive Summary 

    - S-1 - 

    EXECUTIVE SUMMARY

    1. Background

    The first micro-hydropower plant was constructed in the 1930’s in San Pablo City,

    Laguna Province. Although the Philippines has more than 60-year history in

    micro-hydro development, most of the micro-hydropower plants, particularly those that

    are recently installed, are not operational or have some problems in their operation.

    Some identified issues or problems are the results of insufficient site assessment, poor

    quality of power plant facilities and electro-mechanical equipment, and inadequate

    operation and maintenance. In order to provide solution to these issues, as well as to

    ensure sustainable development, it is required to use a guide and/or manual for

    micro-hydro development.

    This manual was provided as a technical supplement of the “Guide on Micro-hydro

    Development for Rural Electrification” which was developed under JICA Expert

    Dispatch Program for Rural Electrification utilizing Micro-hydro Technology.

    2. User of Manual

    This manual is intended to assist prospective micro-hydropower developers/proponents

    for rural electrification in the off-grid and/or isolated barangays, such as local

    government units (LGU’s), cooperatives and NGOs. This manual mainly deals with

    technical aspects of micro-hydropower technology to facilitate the community based

    micro-hydro development.

    3. Applicable Range of Micro-Hydropower

    The selection of best turbines depends on the site characteristics, the dominant factor on

    the selection process being the head available and the power required. Selection also

    depends on the speed at which it is desired to run the generator or other device loading

    the turbine. It should be considered that whether or not the turbine will be expected to

     produce power under part-flow conditions, also play an important role in the selection.

    In the micro-hydropower scheme, turbines could be classified and grouped according to

    operating principle as shown in the table below.

  • 8/17/2019 Doracak japoni

    14/268

     Manual for Micro-Hydro Power Development

     Executive Summary 

    - S-2 - 

    Table S.1 Classification and applicability range of turbines

    HEAD (pressure)Turbine Type

    High < 40 m. Medium 20-40 m. Low 5-20 m.

    Impulse Pelton

    Turgo

    Crossflow(Banki)

    TurgoPelton

    Crossflow(Banki)

    Reaction Francis

    Pump-as-turbine (PAT)Kaplan

    Propeller

    Propeller

    Kaplan

    4. How to use this manual

    This manual is composed of eleven (11) chapters in relation with the “Project Cycle of

    Sustainable Rural Electrification by Utilizing Micro-Hydro Technology”.

    The conduct of site assessment and investigation in the study for a proposed

    micro-hydropower development are necessary to upgrade its level of accuracy. However,

    high precision survey or detailed investigation for preliminary design during the

     planning stage is not recommended due to practical and economic reasons. Thedevelopment scale of micro-hydro is small and the cost of survey work is relatively

    high.

    The stages of mini-hydropower development project cycle are as follows.

      Project Planning Stage

      Project Implementation Stage

      Project Operation Stage

    In the first stage of the project cycle, termed as the “Project Planning Stage, the major

    activities are “Selection of Potential Sites”, “Site Reconnaissance”, “Planning of the

    Potential Sites” and “Formulation of the Project Development Plan” in the target area

    utilizing decentralized power generation. Several potential sites will be considered in

    this stage in order to formulate the electrification plan for the whole target area. Chapter

    3 through Chapter 4, Chapter 8-1 and Chapter 11 of this manual will comprise the

     pre-implementation stage.

  • 8/17/2019 Doracak japoni

    15/268

     Manual for Micro-Hydro Power Development

     Executive Summary 

    - S-3 - 

    Figure S.1 Flowchart of Micro-hydropower Development (DOE’s BEP Projects)

    Community

    Dept of Energy

    / Other Donors

    Proponent 

    (LGUs/NGOs)

    List of

    unenergized

    sites identified

    for NRE

    P r  o j   e  c  t  

     O p e r  a t  i   on

     S  t   a g e 

    P r  o j   e  c  t  I  m pl   e m e n t   a t  i   on S  t   a g e 

    P r  o j   e  c  t  

    P l   anni  n g S  t   a g e 

    Site Reconnaissance

    Layout and Design

    Mobilization

    House wiring/Construction/ Installation

      O & M Training

    Monitoring and

    Technical advice

    for the Project

    Management and O & M of the project

    LGU/NGO requestRequest for

    consultant

    Data Analysis

    Commissioning

    Data Collection

    Technical

     Assistance, if

    necessary

    Technical

    BAPA Formulation  Approval

    Proposal preparation

    Periodic

  • 8/17/2019 Doracak japoni

    16/268

     Manual for Micro-Hydro Power Development

     Executive Summary 

    - S-4 - 

    The second stage is the “Project Implementation Stage”. This stage covers the “Detail

    Design” and “Construction” of the particular site. Chapter 5 through Chapter 9 of thismanual will be used in the project implementation stage.

    The final stage is the “Project Operation Stage”. In this stage, “Operation and

    Maintenance” and “Management” will be discussed. These activities are described in

    Chapter 10 through Chapter 11 of this manual.

    The descriptions in each chapter are follows,

     

    Chapter 1 Introduction

      Introduces the concept of the micro-hydropower.

      Chapter 2 Selection of Potential Sites

      Deals with the technical aspects for site selection on the topographical map and

    local information.

      Chapter 3 Site Reconnaissance

      Provides procedural activities on how to conduct the survey on social condition

    as well as technical aspects of the potential site that were revealed in the above

    activities. In site reconnaissance, it is important to consider the possibility and

    capacity of the power generation and the demand in the area concerned.

      Chapter 4 Planning

      Shows the technical aspects for the planning of the project as shown in Figure

    S.2.

     

    Chapter 5 Design of Civil Structures  The main problem for the development of a small-scale hydropower plant is the

    high upfront cost. In this chapter, various techniques were described to possibly

    reduce the construction cost of civil structures.

      Chapter 6 Design of Mechanical and Electrical Structures

      Provides the technical aspects for Mechanical and Electrical Structures such as

    Inlet valve, Turbine and Generator.

  • 8/17/2019 Doracak japoni

    17/268

     Manual for Micro-Hydro Power Development

     Executive Summary 

    - S-5 - 

    Figure S.2 Flowchart for the Planning of the Project

      Chapter 7 Design of Distribution Facilities

      Provides the technical aspects to be considered for Distribution Facilities such as

    a pole, cable, and transformer.

      Chapter 8 Project Cost Estimate

      Shows example and formula of cost estimate per item of work. It also shows

    Identification of System Layout

    (refer to 4.1)

    Confirmation of Design Discharge

    (refer to 4.2)

    Selection of the Civil Structures Location

    (refer to 4.3)

    Confirmation of the Head 

    (refer to Ref.5-3)

    Selection of Power Demand Facilities

    (refer to 4.4.1)

    Selection of the Generating SystemCrossflow Turbine Syst em or Pumps as T urbine Syst em

    Examination of Demand and Supply Balance

    (Refer to 4.4.2)

    Reconnaissance on Potential Site Reconnaissance on Demand Site

    Site Reconnaissance

    (Refer to Chapter 3)

    Unbalanced Unbalanced  

    Rough Estimation of the Project Cost

    (Refer to 8.1)

    Balanced 

    Project Implementation Stage

    :There are the description in Chapter 4

  • 8/17/2019 Doracak japoni

    18/268

     Manual for Micro-Hydro Power Development

     Executive Summary 

    - S-6 - 

    how to calculate quantity per work item.

     Chapter 9 Construction Management  Refers to the purpose of Construction Management. It also includes progress

    control, dimension control and quality control.

      Chapter 10 Operation and Maintenance

      Shows the necessity of a manual for operation and maintenance and the

    importance of daily and periodic inspection.

      Chapter 11 Management

     

    In this chapter, the importance of establishing an association in the barangay for

    smooth performance in the management of the Micro-hydropower system was

    clarified.

  • 8/17/2019 Doracak japoni

    19/268

     Manual for Micro-Hydro Power Development

    Chapter 1 

    - 1-1 - 

    Chapter 1 INTRODUCTION

    1.1 Purpose of the Manual for Micro-Hydro Development

    Usually, Micro-Hydroelectric Power, or Micro-Hydro, are used in the rural

    electrification and does not necessarily supply electricity to the national grid. They are

    utilized in isolated and off-grid barangays for decentralized electrification.

    There is an increasing need in many developing countries for rural electrification

     purposely to provide illumination at night and to support livelihood projects. Also, the

    government is faced with the high costs of extending electricity grids. Often,

    Micro-Hydro system offers an economical option or alternative to grid extension. The

    high cost of transmission lines and the very low load factor in the rural areas contributes

    to the non-viability of the grid extension scheme. On the contrary, Micro-Hydro

    schemes can be designed and built by the local people and smaller organizations

    following less strict regulations and using local technology like traditional irrigation

    facilities or locally fabricated turbines. This approach is termed as the Localized

    Approach. Fig 1.1.1 illustrates the significance of this approach in lowering the

    development cost of Micro-Hydro systems. It is hoped that this Manual will help to

     promote the Localized Approach.

    Fig 1.1.1 Micro-Hydro’s Economy of Scale ( based on 1985 data)

  • 8/17/2019 Doracak japoni

    20/268

     Manual for Micro-Hydro Power Development

    Chapter 1 

    - 1-2 - 

    1.2 Components of Micro-Hydro Power

    Figure1.2.1 shows the major components of a typical micro-hydro development scheme.

    Fig. 1.2.1 Major components of a micro-hydro scheme

    - Diversion Weir and Intake

    The diversion weir – a barrier built across the river used to divert water through an

    opening in the riverside (the ‘Intake’ opening) into a settling basin.

    - Settling Basin

    The settling basin is used to trap sand or suspended silt from the water before

    entering the penstock. It may be built at the intake or at the forebay.

    eadtank

    eadrace

  • 8/17/2019 Doracak japoni

    21/268

     Manual for Micro-Hydro Power Development

    Chapter 1 

    - 1-3 - 

    - Headrace

    A channel leading water to a forebay or turbine. The headrace follows the contour of

    the hillside so as to preserve the elevation of the diverted water.

    - Headtank

    Pond at the top of a penstock or pipeline; serves as final settling basin, provides

    submergence of penstock inlet and accommodation of trash rack and

    overflow/spillway arrangement.

  • 8/17/2019 Doracak japoni

    22/268

     Manual for Micro-Hydro Power Development

    Chapter 1 

    - 1-4 - 

    - Penstock

    A close conduit or pressure pipe for supplying water under pressure to a turbine.

    - Water Turbine and Generator

    A water turbine is a machine to directly convert the kinetic energy of the flowing

    water into a useful rotational energy while a generator is a device used to convert

    mechanical energy into electrical energy.

    There are of course many variations on the design layout of the system. As an

    example, the water is entered directly to the turbine from a channel without a

     penstock. This type is the simplest method to get the waterpower. Another variation is

    that the channel could be eliminated, and the penstock will run directly to the turbine.

    Variations like this will depend on the characteristics of the particular site and the

    requirements of the user of system.

  • 8/17/2019 Doracak japoni

    23/268

     Manual for Micro-Hydro Power Development

    Chapter 1 

    - 1-5 - 

    1.3 Concept of Hydro Power

    A hydro scheme requires both water flow and a drop in height (referred to as ‘Head’) to produce useful power. The power conversion absorbs power in the form of head and

    flow, and delivering power in the form of electricity or mechanical shaft power. No

     power conversion system can deliver as much useful power as it absorbs –some power

    is lost by the system itself in the form of friction, heating, noise, etc.

    The power conversion equation is :

    Power input = Power output + Loss

    or Power output = Power input ×  Conversion Efficiency

    The power input, or total power absorbed by the hydro scheme, is the gross power,

    (Pgross). The power output is the net power (Pnet). The overall efficiency of the scheme

    (Fig.1.3.2) is termed Eo.

    Pnet = Pgross ×Eo  in kW

    The gross power is the product of the gross head (Hgross), the design flow (Q) and a

    coefficient factor (g = 9.8), so the fundamental hydropower equation is:

    Fig. 1.3.1 Head is the vertical height through which the water drops

  • 8/17/2019 Doracak japoni

    24/268

     Manual for Micro-Hydro Power Development

    Chapter 1 

    - 1-6 - 

    Pnet = g ×Hgross ×  Q ×Eo kW  (g=9.8)

    where the gross head is in meters and the design flow is in cubic meter per second. Eo is

    derived as follows:

    Eo = Ecivil work  ×E penstock  ×  Eturbine ×  Egenerator  ×  Edrive system×  Eline ×  Etransformer

    Usually Ecivil work : 1.0 - (Channel length ×  0.002 ~  0.005)/ Hgross 

    E penstock : 0.90 ~  0.95 (it’s depends on length)

    Eturbine : 0.70 ~  0.85 (it’s depends on the type of turbine)

    Egenerator : 0.80 ~  0.95 (it’s depends on the capacity of generator)

    Edrive system  : 0.97

    Eline : 0.90 ~  0.98 (it’s depends on the transmission length)

    Etransformer : 0.98

    Ecivil  work and E penstock   are usually computed as ‘Head Loss (Hloss)’. In this case, the

    hydropower equation becomes:

    Pnet= g ×(Hgross-Hloss) ×Q ×(Eo - Ecivil work  - E penstock  ) kW

    This simple equation should be memorized: it is the heart and soul of hydro power

    design work.

    Fig 1.3.2 Typical system efficiencies for a scheme running at full design flow.

    Fig 1.3.2 Typical system efficiencies for a scheme running at full design flow.

    Fig 1.3.2 Typical system efficiencies for a scheme running at full design flow.

    Fig 1.3.2 Typical system efficiencies for a scheme running at full design flow.

  • 8/17/2019 Doracak japoni

    25/268

     Manual for Micro-Hydro Power Development

    Chapter 1 

    - 1-7 - 

    1.4 The Water Cycle

    The volume of the river flow or discharge depends on the catchment area and thevolume of rainfall. Figure 1.4.1 shows how the rainfall is divided on both sides (A and

    B) of the watershed. For example, there is an existing Hydropower Plant at A-side, the

    rainfall at B-side cannot be used for power generation at this Hydropower Plant.

    Therefore, the catchment area of a proposed hydropower plant should be known at the

    first step of the study of hydro scheme.

    Fig 1.4.1 The hydrological cycle

    The broken lines in Fig 1.4.2 indicate the watershed of Point-A and Point-B. The

    catchment area is the area enclosed by broken lines.

    Fig 1.4.2 The catchment area and the watershed

  • 8/17/2019 Doracak japoni

    26/268

     Manual for Micro-Hydro Power Development

    Chapter 2

    - 2-1 - 

    Chapter 2 IDENTIFICATION OF POTENTIAL SITES

    It is necessary to roughly examine (i) whether or not the construction of a small-scale

    hydropower plant near the power demand area is feasible and (ii) how much power

    capacity can be generated sufficiently and where, and then (iii) how to select a potential

    site among the candidate sites.

    The initial examination is basically a desk study using available reference materials and

    information and the procedure involved and important issues to be addressed are

    explained below.

    2.1 Basic Reference Materials

    The basic reference materials required are the following:

    1) Topographical map: scale: 1/50,000

    Topographical map provides important information, such as landform, location of

    communities, slope of the river, catchment area of proposed sites, access road, etc.

    In the Philippines, topographical maps of scale 1/50,000 are available at the

     National Mapping & Resources Information Authority (NAMRIA)

    2) Rainfall data: isohyetal map and others (cf. Fig 2.1.1)

    Although it is unnecessary to gather detailed rainfall data at this stage, it is 

    necessary to have a clear understanding of the rainfall characteristics of the project 

    area using an isohyetal map for the region and existing rainfall data for the

    adjacent area. Isohyetal map provides the interpolation and averaging will give an

    approximate indication of rainfall.

  • 8/17/2019 Doracak japoni

    27/268

     Manual for Micro-Hydro Power Development

    Chapter 2

    - 2-2 - 

    Figure 2.1.1 (a)

    Fig 2.1.1(b) An example of isohyetal map for micro-hydro scheme

  • 8/17/2019 Doracak japoni

    28/268

     Manual for Micro-Hydro Power Development

    Chapter 2

    - 2-3 - 

    2.2 Radius of Site Identification

    As most of the electric energy generated by a small-scale hydropower plant is basically

    intended for the consumption of the target area, it is important to consider that the plant

    site should be as nearer as possible to the load center. In the case of highly dispersed

    communities, which are distributed over a relatively large area, it may be more

    advantageous to construct individual micro-hydropower plants, rather than to supply

     power to all groups by a single plant, due to lower transmission cost, easier operation

    and maintenance and fewer impacts due to unexpected plant stoppage, etc. To be more

    efficient in planning individual-type micro-hydropower plants, it is recommended to

    gradually widen the scope of the survey, starting from the geographical area of each

    group.

    The transmission distance from the potential site to the target site should depend on

    various parameters, the power output, demand level, topography, accessibility

    conditions, transmission voltage and cost of transmission lines. In Japan, the

    transmission distance to the demand site is set to ensure a voltage drop rate which does

    not exceed 7%. [Reference 2-1: Transmission and distribution line distance and voltage

    drop]

    In case of Micro-hydro Scheme in the Philippines, the rough estimate for the maximum

    allowable transmission distance is 1.5 kilometers (km) from the load center. This

    distance is based on the premise that the voltage at the end of distribution line should be

    kept at not less than 205 volts (V) or the permissible voltage drop is only 15V on the

    regulated voltage of 220V, without using a transformer. [Reference 2-2 Relationship

     between voltage drop and distribution line distance]

    If a good potential site is not found within the above distance, the radius ofidentification should be expanded over a larger area with the provision that the

    transformer should be installed.

  • 8/17/2019 Doracak japoni

    29/268

     Manual for Micro-Hydro Power Development

    Chapter 2

    - 2-4 - 

    2.3 Calculation of River Flow

    Among the river flow data mentioned earlier, historical records of flow data in thearea surrounding the project site should be used to estimate the river flow, taking the

    rainfall distribution characteristics into consideration.

    Qp = Rr ×Qo/Ao

    Where,

    Qp : river flow per unit catchment area in project area (m3/s/km2)

    Rr : rainfall ratio between catchment area of the proposed site for micro-hydro

     project and of existing gauging station

    Qo : observed river flow at existing gauging station or existing hydro-power station

    (m3/s)

    Ao : catchment area of existing gauging station (km2)

    [See Reference 2-3: Considerations when estimating river flow at the project site

    (indirectly from existing data of vicinity gauging stations) for the important points to

    note for river flow based on the existing gauging station nearby.]

    Particularly in the micro-hydro scheme, it is important to note that the firm discharge,

    which is the flow during the driest time of the year, should be estimated accurately.

    If no flow data is available, it is possible to estimate the rough flow duration curve

    referring to “Reference 2-3: Simple calculating method of river flow by the water

     balance model of drainage area”.

  • 8/17/2019 Doracak japoni

    30/268

     Manual for Micro-Hydro Power Development

    Chapter 2

    - 2-5 - 

    2.4 Identification of Potential Sites

    2.4.1 Map Study

    Potential sites are identified on the topographical map with a scale of 1/50,000 by

    interpreting the head.

    The following parameters should be considered in the map study:

    (1) Site identification considering river gradient and catchment area

    Sites with high head, shortest waterway and high discharge level are naturally

    advantageous for hydropower generation.

    The information on the river gradient (elevation difference and river length) and the

    drainage area could be obtained in the map study. While some experience is required to

    identify potential sites from a topographical map, if the diagrams shown Fig 2.4.1 are

     prepared in advance for the subject river, the identification of potential sites is much

    easier.

    (2) Identification based on waterway construction conditions

    As far as the basic layout of a micro-hydro scheme is concerned, most civil structures

    are planned to have an exposed structure. Because of this, the topography at any

     potential site must be able to accommodate such exposed civil structures. (Refer to

    Chapter 4, 4.1 System Layout )

  • 8/17/2019 Doracak japoni

    31/268

     Manual for Micro-Hydro Power Development

    Chapter 2

    - 2-6 - 

    Fig 2.4.1 River Profile and Changes in Drainage Area of River to consider in the

    Identification of Promising Sites for Hydropower Development

    2.4.2 Identification Based on Local Information

    In cases where potential sites cannot be interpreted on the topographical map because of

    the small usable head or the presence of a fall or pool, etc. as well as existing

    infrastructures like intake facilities for irrigation and forest roads, potential sites areidentified on the basis of information provided by a local public body and/or local

    residents’ organization. [Reference 2-5: Example of Natural Topography and Various

    Infrastructures]

    Confluence

    Suitable section for power

       E   l  e  v  a   t   i  o  n

       C  a   t  c   h  m  e  n   t   A  r  e  a

    River

    Change in Catchment Area

    Distance

  • 8/17/2019 Doracak japoni

    32/268

     Manual for Micro-Hydro Power Development

    Chapter 2

    - 2-7 - 

    2.4.3 Selection of Potential Development Sites

    The potential sites identified in the previously described study are then examined fortheir suitability in hydropower development.

    (1) Level of firm discharge

    While it is difficult to judge the suitability for development based on the absolute

    volume of firm discharge, a potential site with a relatively high level of firm discharge

    is more favourable site for a micro-hydro plant designed to supply power throughout the

    year.

    Figure 2.4.2 shows the relation of specific firm discharge and the ratio of firm discharge

    to maximum discharge (Qmax/QF: refer to the figure below) in existing small-scale

    hydropower plants. Generally, the Qmax/QF values of micro hydropower plant for rural

    electrification are shown about 1.0. This is meaning that the maximum discharges of

    micro hydropower plants are the same as the firm discharge. This is because constant

    electric power through a year is required to the micro hydropower plant for the rural

    electrification program. And the specific firm discharge in the Qmax/QF  range are

    0.8~2.0 m3/s/100km2. The difference of vegetation of the catchment area and the

    annual precipitation cause this difference. For the initial identification of potential site,

    the maximum discharge/firm discharge will be set as 1.0 m3/s/100km2  . However,

    the discharge set up in here should be reviewed at the time of site reconnaissance.

    Qmax 

    Duration Curve

    QF    R   i  v  e  r   f   l  o  w

        (  m          3

       /  s

        )

    Days

  • 8/17/2019 Doracak japoni

    33/268

     Manual for Micro-Hydro Power Development

    Chapter 2

    - 2-8 - 

    Fig 2.4.2 Relationship between firm discharge/maximum discharge ratio

    and specific firm discharge

    (2) L/H [ratio between waterway length (L) and total head (H)]

    A site with a smaller L/H value is more advantageous for small-scale hydropower.

    Figure 2.4.3 shows the relation of the ratio between the total head (H) and the waterway

    length (L) (L/H) among existing small-scale hydropower sites where the total head is

    not less than 10 m (the minimum head which can be interpreted on an existingtopographical map). As clearly indicated in the figure, the L/H of existing sites is

    generally not higher than 40 or is an average of 25.

    Figure 2.4.4 shows the relation of firm discharge and L/H, the sites with smaller firm

    discharge has smaller L/H. The L/H of sites with less than 0.2m3/s firm discharge is

    approximately below 15.

    Maximum and Firm Discharge in Hydropower Plant

    0.0

    0.2

    0.4

    0.6

    0.8

    1.0

    1.2

    1.4

    1.6

    1.8

    2.0

    2.2

    0 10 20 30 40 50 60 70 80 90 100 110

    Percentage of Firm/Maximum Discharge (%)

       U  n   i   t   F   i  r  m    D

       i  s  c   h  a  r  g  e

       (  m   3

       /  s   /   1   0   0   k  m

       2   )

    Large

    SmallMini

    Micro

  • 8/17/2019 Doracak japoni

    34/268

     Manual for Micro-Hydro Power Development

    Chapter 2

    - 2-9 - 

    Fig2.4.3 Relation between head and waterway length

    Fig2.4.4 Relation between firm discharge and L/H

    0

    0.1

    0.2

    0.3

    0.4

    0.5

    0 10 20 30 40 50

    Waterway length / Head

       F   i  r  m

       d   i  s  c   h  a

      r  e

        (  m   3   /  s    )

    Head and Waterway Length

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 2 00 4 00 6 00 8 00 1 00 0 12 00 1 40 0 16 00 1 80 0 20 00 2 20 0 24 00 2 60 0 28 00 3 00 0

    Waterway Length (m) L

       H  e  a   d   (  m   )   H

    Micro L/H

  • 8/17/2019 Doracak japoni

    35/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-10 -

    [Ref. 2-1 Relationship between transmission line distance and voltage drop]

       P  e  r  m

       i  s  s   i   b   l  e  v  o   l   t  a  g  e   d  r  o  p

      r  a   t   i  o

    Voltage drop ratio (%)

    Voltage drop ratio (%)

       P  e  r  m   i  s  s   i   b   l  e  v  o   l   t  a  g  e

       d  r  o  p  r  a   t   i  o

       D   i  s   t  a  n  c  e   (   k  m   )

       D   i  s   t  a  n  c  e   (   k  m   )

       R

      e   l  a   t   i  o  n  o   f   t  r  a  n  s  m   i  s  s   i  o  n   l   i  n  e

       d   i  s   t  a  n  c  e  a  n   d  v  o   l   t  a  g  e   d  r  o  p   I

       1

       1   k   V ,

       3   0   0   k   W 

       A   l  u  m   i  n  u  m   C  o  n   d  u  c   t  o  r

       R  e   l  a   t   i  o  n  o   f   t  r  a  n  s  m   i  s  s   i  o  n   l   i  n  e

       d   i  s

       t  a  n  c  e  a  n   d  v  o   l   t  a  g  e   d  r  o  p   I   I

       6 .   6   k

       V ,

       3   0   0   k   W 

       A   l  u  m   i  n  u  m   C  o  n   d  u  c   t  o  r

       D   i  a  m  e   t  e  r  o   f   l   i  n  e

       D   i  a  m  e   t  e  r  o   f   l   i  n  e

  • 8/17/2019 Doracak japoni

    36/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-11 -

    [Ref. 2-2 Relationship between distribution line distance and voltage drop] 

       D   i  s   t  a  n  c  e   (  m   )

    Voltage drop ratio (%)

       P  e  r  m   i  s  s   i   b   l  e  v  o   l   t  a

      g  e

       d  r  o  p  r  a   t   i  o

       R

      e   l  a   t   i  o  n  o   f   t  r  a  n  s  m   i  s  s   i  o  n   l   i  n  e

       d

       i  s   t  a  n  c  e  a  n   d  v  o   l   t  a  g  e   d  r  o  p   I   I   I

       4

       0   0   V ,

       5   0   k   W 

       A   l  u  m   i  n  u  m   C  o  n   d  u  c   t  o  r

       D   i  a  m  e   t  e  r  o   f   l   i  n  e

  • 8/17/2019 Doracak japoni

    37/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-12 -

    Ref. 2-3 Considerations in the estimation of discharge at the project site using data from gauging stations in the

    vicinity.

    If there are multiple gauging stations near the project site, the following parameters should be considered in

    selecting the gauging station to be used.

    1. Drainage Area Ratio

    In estimating the discharge based on data of existing gauging stations, the drainage area should be taken into

    consideration. From the discharge characteristic curve, as shown in the following figure, and drainage area

    ratio between existing gauging station and project site is large, the flow duration curves may be crossing

    each other which will make the discharge computation is unreliable.

    2. Rainfall

    The flow-duration and the rainfall characteristic in the upper portion of the river that has close correlation

    with the long term discharge must be regarded as close correlation between rainfall and discharge. The

    available rainfall data from gauging stations in both small and large drainage areas are useful information to

    evaluate the discharge at the project site.

    The simplest method in estimating the rainfall around the project site is to use the isohyetal maps. This map

    shows contour lines of average rainfall, and can be compared to the amount of rainfall in the project site and

    the gauging station.

    Large drainage area

    Day

       S  p  e  c   i   f   i  c   d  r  a   i  n  a  g  e  a  r  e  a

    Small drainage area

    Big amount of rainfall

    Small amount of rainfall

    Day

       S  p  e  c   i   f   i  c   d  r  a   i  n  a  g  e  a  r  e  a

  • 8/17/2019 Doracak japoni

    38/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-13 -

    3. Geological conditions

    The evaluation of the discharge in the project site based on the presence of gauging stations in the area is not

    enough to establish the correlation of flow duration curves. Geological condition also influenced the

    similarity of flow duration curves aside from the drainage areas such as the existence of quaternary volcanic

    rock area.

    A quaternary volcanic rock is considered to have high water retention capability. Flow duration curves

    influenced by this type of geology is relatively flat, wherein the discharge in wet season is only slightly

    higher during the dry season, as compared with the flow duration curves of those that are not influenced by

    this type of rocks, as shown in the figure below:

    It is possible to know the distribution of quaternary volcanic rocks from existing geological map, however, it

    is difficult to analyze quantitatively its share in the drainage area and the characteristic or general pattern of

    discharge. Therefore, when quaternary volcanic rocks in the project area exists, it is recommended to select

    gauging stations with equivalent geological characteristic.

    Aside from the quaternary volcanic rock, limestone also affects the runoff and the river discharge. It is also

    very difficult to measure its influence qualitatively and quantitatively. Generally the river with limestone

    shows irregular discharge. Therefore, in case the drainage or catchment area is characterized with limestone

    formation, it is suggested to conduct the stream flow measurement at the intake point of the project site.

    4. Geographical condition 

    Geographical condition is also considered to have a significant influence in the estimation of discharge.

    Generally, it is recognized that the amount of rainfall is larger at higher altitude and steeper mountain. Hence,

    selection of gauging stations with similar geographical conditions, such as altitude, features, and direction of

    drainage area is considered as one of the methods that raise the accuracy of discharge estimation.

    In case no dissecting plain exist in the drainage area of the project site and its outline falls down, the runoff

    may flow out of the drainage area through seepage.

    Existence of Quaternaryvolcanic rock in the

    drainage area 

    Day

       S  p  e  c   i   f   i  c   d  r  a   i  n  a  g  e  a  r  e  a

     Not existence ofQuaternary volcanic rock 

  • 8/17/2019 Doracak japoni

    39/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-14 -

    [Ref. 2-4 Method of river flow by the water balance model of drainage area]

    If there are no discharge observation data and only rainfall data is available, it is possible to estimate river

    discharge from the water balance data of the drainage area.

    1. 

    Calculation method

    (1) Water balance of the drainage area

    The relation of rainfall, runoff (direct runoff, base runoff), and evaporation is indicated by the viewpoint of

    annual water balance as shown in the formula below. In this case, pooling of drainage area and inflow and

    runoff from/to other drainage area are not necessary.

    P = R + Et

    = Rd + Rb + Et

    where,

    P : Annual rainfall (mm)

    R : Annual runoff (mm)

    Rd : Annual direct runoff (mm)

    Rb : Annual base runoff (mm)

    Et : Annual evaporation (mm)

    Runoff (R) is obtained from calculated evaporation (Et) by the presumption formula and observed rainfall

    (P).

    A pattern figure of the relation of rainfall (R), possible evaporation (Etp), and real evaporation (Et) is shown

    Figure 1-1. Indicated as diagonal line is real evaporation, and area above line b-c is river runoff including

    sub-surface water. Possible evaporation (a-b-c-d) is obtained by presumption formula.

    (2) Direct runoff and base runoff

    A pattern of annual runoff is shown Figure 1-2. The runoff is provided from sub-surface water, and it

    contained base runoff with less seasonal fluctuation and direct runoff wherein the rainfall immediately

     becomes the runoff. The ratio of sub-surface water to annual runoff (R) is shown in Table 1-1. Where, Rg = Rb,

    Rb / R = 0.25 constant, and the base runoff is taken as constant.

  • 8/17/2019 Doracak japoni

    40/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-15 -

    Figure 1-1 Pattern figure of amount of rainfall and evaporation

    Figure 1-2 Pattern figure of runoff

    Amount of rainfall

    Amount of realevaporation (Et)

    Possible evaporation(Etp)

    Runoff (R)

       A  m  o  u  n   t  o   f  r  a   i  n   f  a   l   l ,  e  v  a  p  o  r  a   t   i  o  n   (  m  m   ) 

    Month

       A  m  o  u  n

       t  o   f  r  u  n  o   f   f   (  m   3   /  s   ) 

    Month

    Amount of direct runoff

    Amount of base runoff

  • 8/17/2019 Doracak japoni

    41/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-16 -

    Table 1-1 World water balance model

    (Note) Source: Lvovich 1973

    Data of Japan from Ministry of Land, Infrastructure and Transport

    (3) Calculation of possible evaporation

    The calculation formulas are Blaney-Criddle formula, Penman formula, and Thornthwaite formula etc. Herein,

    Blaney-Criddle formula was used which is the simplest method using the longitude and temperature of the

     project site. The observed value of evaporation from free water surface was also considered.

    (a) Calculation method

    ①  Blaney-Criddle formula

    where,

    u : Monthly evaporation (mm)

    K : Monthly coefficient of vegetation

    P : Monthly rate of annual sunshine (%)

    t : Monthly average temperature (℃)

    ②  Monthly average temperature and monthly rate of annual sunshine

    ・Monthly average temperature ; Using temperature at the drainage area of dam site

    ・Monthly rate of annual sunshine ; Obtained by the latitude at the drainage area of dam site

    In the northern hemisphere, use Table 1-2, and in the southern hemisphere, use Table 1-3.

    ③  K value depends on the vegetation condition. Herein, a constant of 0.6 was used.

    (b) Example of calculation

    ① Conditions : Position of drainage area lat. 16  ゚N

    ② Calculation of possible evaporation : Table 1-4

    u = K ・P・ 100

    ( 45.7t + 813 )

    Area Asia Africa   North America South America   Europe Australia JapanRainfall(P) 726 686 670 1648 734 736 1788Runoff 

    (R) 293 139 287 583 319 226 1197 Direct runoff  (Rd) 217 91 203 373 210 172 - Subsoilwater 76 48 84 210 109 54 -Evaporation(Et) 433 547 383 1065 415 510 597

    Rg / R 26 35 32 36 34 24 -

  • 8/17/2019 Doracak japoni

    42/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-17 -

    (4) Calculation of evaporation

    It is shown in Table 1-4, the monthly evaporations are obtained by lower value of rainfall or possible

    evaporation.

    (5) Computation of monthly runoff data

    a)  Computation by the procedure shown in Table 1-5.

     b)  Derivation of the monthly mean discharge data at the dam site by the following formula.

    where,

    Q (i) : Monthly mean discharge at dam site in ‘i (month)’ (m3/s)

    CA : Drainage area (km2)

    n : Number of days in the month

    The discharge for the drainage area of 300 km2 is shown in Table 1-5.

    In addition, the ratio of the base runoff to the total runoff (25%) and the monthly distribution of base

    runoff (constant) can be analyzed with regards to the characteristic of runoff at the area.

    Q (i) = ×CA×106× 

    1000 86,400×n

    Monthly runoff (④of Table 1-5 )  1

  • 8/17/2019 Doracak japoni

    43/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-18 -

    Table 1-2  Monthly rate of annual sunshine (Northern Hemisphere)  (%) 

    North Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec.Latitude

    65 3.52 5.13 7.96 9.97 12.72 14.15 13.59 11.18 8.55 6.53 4.08 2.62

    64 3.81 5.27 8.00 9.92 12.50 13.63 13.26 11.08 8.56 6.63 4.32 3.0263 4.07 5.39 8.04 9.86 12.29 13.24 12.97 10.97 8.56 6.73 4.52 3.3662 4.31 5.49 8.07 9.80 12.11 12.92 12.73 10.87 8.55 6.80 4.70 3.6561 4.51 5.58 8.09 9.74 11.94 12.66 12.51 10.77 8.55 6.88 4.86 3.91

    60 4.70 5.67 8.11 9.69 11.78 12.41 12.31 10.68 8.54 6.95 5.02 4.1459 4.86 5.76 8.13 9.64 11.64 12.19 12.13 10.60 8.53 7.00 5.17 4.3558 5.02 5.84 8.14 9.59 11.50 12.00 11.96 10.52 8.53 7.06 5.30 4.5457 5.17 5.91 8.15 9.53 11.38 11.83 11.81 10.44 8.52 7.13 5.42 4.7156 5.31 5.98 8.17 9.48 11.26 11.68 11.67 10.36 8.52 7.18 5.52 4.87

    55 5.44 6.04 8.18 9.44 11.15 11.53 11.54 10.29 8.51 7.23 5.63 5.0254 5.56 6.10 8.19 9.40 11.04 11.39 11.42 10.22 8.50 7.28 5.74 5.1653 5.68 6.16 8.20 9.36 10.94 11.26 11.30 10.16 8.49 7.32 5.83 5.3052 5.79 6.22 8.21 9.32 10.85 11.14 11.19 10.10 8.48 7.36 5.92 5.4251 5.89 6.27 8.23 9.28 10.76 11.02 11.09 10.05 8.47 7.40 6.00 5.54

    50 5.99 6.32 8.24 9.24 10.68 10.92 10.99 9.99 8.46 7.44 6.08 5.6548 6.17 6.41 8.26 9.17 10.52 10.72 10.81 9.89 8.45 7.51 6.24 5.8546 6.33 6.50 8.28 9.11 10.38 10.53 10.65 9.79 8.43 7.58 6.37 6.0544 6.48 6.57 8.29 9.05 10.25 10.39 10.49 9.71 8.41 7.64 6.50 6.2242 6.61 6.65 8.30 8.99 10.13 10.24 10.35 9.62 8.40 7.70 6.62 6.39

    40 6.75 6.72 8.32 8.93 10.01 10.09 10.22 9.55 8.39 7.75 6.73 6.5438 6.87 6.79 8.33 8.89 9.90 9.96 10.11 9.47 8.37 7.80 6.83 6.6836 6.98 6.85 8.35 8.85 9.80 9.82 9.99 9.41 8.36 7.85 6.93 6.8134 7.10 6.91 8.35 8.80 9.71 9.71 9.88 9.34 8.35 7.90 7.02 6.93

    32 7.20 6.97 8.36 8.75 9.62 9.60 9.77 9.28 8.34 7.95 7.11 7.05

    30 7.31 7.02 8.37 8.71 9.54 9.49 9.67 9.21 8.33 7.99 7.20 7.1628 7.40 7.07 8.37 8.67 9.46 9.39 9.58 9.17 8.32 8.02 7.28 7.2726 7.49 7.12 8.38 8.64 9.37 9.29 9.49 9.11 8.32 8.06 7.36 7.3724 7.58 7.16 8.39 8.60 9.30 9.19 9.40 9.06 8.31 8.10 7.44 7.4722 7.67 7.21 8.40 8.56 9.22 9.11 9.32 9.01 8.30 8.13 7.51 7.56

    20 7.75 7.26 8.41 8.53 9.15 9.02 9.24 8.95 8.29 8.17 7.58 7.6518 7.83 7.31 8.41 8.50 9.08 8.93 9.16 8.90 8.29 8.20 7.65 7.7416 7.91 7.35 8.42 8.47 9.01 8.85 9.08 8.85 8.28 8.23 7.72 7.8314 7.98 7.39 8.43 8.43 8.94 8.77 9.00 8.80 8.27 8.27 7.79 7.9312 8.06 7.43 8.44 8.40 8.87 8.69 8.92 8.76 8.26 8.31 7.85 8.01

    10 8.14 7.47 8.45 8.37 8.81 8.61 8.85 8.71 8.25 8.34 7.91 8.098 8.21 7.51 8.45 8.34 8.74 8.53 8.78 8.66 8.25 8.37 7.98 8.186 8.28 7.55 8.46 8.31 8.68 8.45 8.71 8.62 8.24 8.40 8.04 8.264 8.36 7.59 8.47 8.28 8.62 8.37 8.64 8.58 8.23 8.43 8.10 8.342 8.43 7.63 8.49 8.25 8.55 8.29 8.57 8.53 8.22 8.46 8.16 8.42

    0 8.50 7.67 8.49 8.22 8.49 8.22 8.50 8.49 8.21 8.49 8.22 8.50

  • 8/17/2019 Doracak japoni

    44/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-19 -

    Table 1-3  Monthly rate of annual sunshine (Southern Hemisphere)  (%) 

    (Note) Southern part more than lat. 50°S will be calculated using example from Table 1-2. Concretely,

    the monthly rate of southern latitude is corresponding to below showing months of northern

    latitude.

    Southern lat. - Northern lat. Southern lat. - Northern lat.

    January - July July - January

    February - August August - February

    March - September September - March

    April - October October - April

    May - November November - May

    June - December December - June 

    South Jan. Feb. Mar. Apr. May Jun. Jul. Aug. Sep. Oct. Nov. Dec.Latitude

    0 8.50 7.67 8.49 8.22 8.49 8.22 8.50 8.49 8.21 8.49 8.22 8.50

    2 8.55 7.71 8.49 8.19 8.44 8.17 8.43 8.44 8.20 8.52 8.27 8.554 8.64 7.76 8.50 8.17 8.39 8.08 8.20 8.41 8.19 8.56 8.33 8.656 8.71 7.81 8.50 8.12 8.30 8.00 8.19 8.37 8.18 8.59 8.38 8.748 8.79 7.84 8.51 8.11 8.24 7.91 8.13 8.12 8.18 8.62 8.47 8.84

    10 8.85 7.86 8.52 8.09 8.18 7.84 8.11 8.28 8.18 8.65 8.52 8.9012 8.91 7.91 8.53 8.06 8.15 7.79 8.08 8.23 8.17 8.67 8.58 8.9514 8.97 7.97 8.54 8.03 8.07 7.70 7.08 8.19 8.16 8.69 8.65 9.0116 9.09 8.02 8.56 7.98 7.96 7.57 7.94 8.14 8.14 8.78 8.72 9.1718 9.18 8.06 8.57 7.93 7.89 7.50 7.88 8.10 8.14 8.80 8.80 9.24

    20 9.25 8.09 8.58 7.92 7.83 7.41 7.73 8.05 8.13 8.83 8.85 9.3222 9.36 8.12 8.58 7.89 7.74 7.30 7.76 8.00 8.13 8.86 8.90 9.3824 9.44 8.17 8.59 7.87 7.65 7.24 7.68 7.95 8.12 8.89 8.96 9.4726 9.52 8.28 8.60 7.81 7.56 7.07 7.49 7.90 8.11 8.94 9.10 9.6128 9.61 8.31 8.61 7.79 7.49 6.99 7.40 7.85 8.10 8.97 9.19 9.74

    30 9.69 8.33 8.63 7.75 7.43 6.94 7.30 7.80 8.09 9.00 9.24 9.8032 9.76 8.36 8.64 7.70 7.34 6.85 7.20 7.73 8.08 9.04 9.31 9.8734 9.88 8.41 8.65 7.68 7.25 6.73 7.10 7.69 8.06 9.07 9.38 9.9936 10.06 8.53 8.67 7.61 7.16 6.59 6.99 7.59 8.06 9.15 9.51 10.2138 10.14 8.61 8.68 7.59 7.07 6.46 6.87 7.51 8.05 9.19 9.60 10.34

    40 10.24 8.65 8.70 7.54 6.96 6.33 6.73 7.46 8.04 9.23 9.69 10.4242 10.39 8.72 8.71 7.49 6.85 6.20 6.60 7.39 8.01 9.27 9.79 10.5744 10.52 8.81 8.72 7.44 6.73 6.04 6.45 7.30 8.00 9.34 9.91 10.7246 10.68 8.88 8.73 7.39 6.61 5.87 6.30 7.21 7.98 9.41 10.03 10.90

    48 10.85 8.98 8.76 7.32 6.45 5.69 6.13 7.12 7.96 9.47 10.17 11.09

    50 11.03 9.06 8.77 7.25 6.31 5.48 5.98 7.03 7.95 9.53 10.32 11.30

  • 8/17/2019 Doracak japoni

    45/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-20 -

    Table 1-4 Calculation example of possible evaporation and real evaporation

    (Note) ①: obtained data ②: from Table 1-2 ③: parenthetic numbers are observed evaporation value

    from water surface

    Table 1-5 Calculation example of river flow

    (Note) ③Base runoff: distribute uniformity 434.3×0.25 = 108.6 mm to each month 

    ①Temperature ②Monthly rate of annual sunshine

    ④Rainfall ⑤Realevaporation

    Month t psmaller valueof ③ and ④

    (℃) (%) (mm) (mm)

    Jan. 22.1 7.91 86.4 ( 91.0 ) 8.5 8.5Feb. 24.7 7.35 85.6 ( 106.4 ) 16.8 16.8Mar. 27.2 8.42 103.8 ( 129.7 ) 38.3 38.3Apr. 28.9 8.47 108.4 ( 138.2 ) 62.3 62.3May 28.4 9.01 114.2 ( 116.3 ) 170.0 114.2Jun. 27.7 8.85 110.4 ( 91.1 ) 180.3 110.4Jul. 27.1 9.08 111.8 ( 81.2 ) 202.9 111.8Aug. 27.0 8.85 108.7 ( 72.7 ) 197.7 108.7Sep. 27.1 8.28 101.9 ( 74.6 ) 207.7 101.9Oct. 26.5 8.23 100.0 ( 79.7 ) 123.0 100.0Nov. 24.1 7.72 88.6 ( 73.4 ) 30.2 30.2Dec. 22.0 7.83 85.4 ( 80.2 ) 17.9 17.9

    Total 1,205.2 ( 1,134.5 ) 1,255.6 821.0

    ③Possible evaporation

    from Blaney-Criddleformula

    (mm)

    ①Runoff ②Direct runoff ③Base runoff ④Monthly runoff 

    Month④-⑤of Chart 1-4 ①×0.75 (Note) ②+③

    (mm) (mm) (mm) (mm) (m3/s)

    Jan. 0 0 9.2 9.2 1.03Feb. 0 0 8.3 8.3 1.03Mar. 0 0 9.2 9.2 1.03Apr. 0 0 8.9 8.9 1.03May 55.8 41.9 9.2 51.1 5.72Jun. 69.6 52.2 8.9 61.1 7.07Jul. 91.1 68.3 9.2 77.5 8.69Aug. 89.0 66.8 9.2 76.0 8.51Sep. 105.8 79.4 8.9 88.3 10.22Oct. 23.0 17.3 9.2 26.5 2.96

    Nov. 0 0 8.9 8.9 1.03Dec. 0 0 9.2 9.2 1.03

    Total 434.3 325.7 108.6 434.3

    Monthlymean

    discharge

  • 8/17/2019 Doracak japoni

    46/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-21 -

    [Ref. 2-5 Example of Micro-hydro Development Scheme Using Natural Topography and Various Man-Made

    Structures]

    1. Using existing irrigation channel and naturally formed pool downstream of fall

    River

    Headrace

    River

    Power house

    PenstockSpillway

    Irrigation channelHeadtank 

    Screen

    Intake weir 

    Water fall

  • 8/17/2019 Doracak japoni

    47/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-22 -

    2. Intake water from two rivers

    Ⅱ-2-5入る

    Headrace

    Intake weir

    River

    Intake weir

    Headtank 

    Screen

    Penstock 

    Power house

    Tailrace

    River 

  • 8/17/2019 Doracak japoni

    48/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-23 -

    3. Using a head drop structure of existing irrigation channel

    Ⅱ-2-6入るIntake

    Headtank 

    Irrigationchannel

    Head dropstructure

    Penstock 

    Power house

  • 8/17/2019 Doracak japoni

    49/268

     Manual for Micro-Hydro Power Development

    Chapter 2 (Reference) 

    - 2-24 -

    4. Using a head drop structure of existing irrigation channel

    Ⅱ-2-7入る 

    River

    Intake

    Headrace

    RoadIrrigation

    channel

    Headtank 

    Penstock 

    Power house

    Tailrace

  • 8/17/2019 Doracak japoni

    50/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-1 - 

    CHAPTER 3 SITE RECONNAISSANCE

    3.1 Objective of Site Reconnaissance

    The objective of site reconnaissance for micro-hydro is to investigate potential sites and

    supply area in order to evaluate the feasibility of projects and get information for

    electrification planning. One of the most important activities in site reconnaissance is to

    measure water discharge and head that could be utilized for micro-hydropower

    generation. Investigations of intake site, waterway route, powerhouse site and

    transmission route etc. are also conducted to assess the feasibility of project sites.

    Power demand survey is also important in the planning of the electrification system.

    Socio-economic data such as number of households and public facilities in supply area,

    availability of local industries which will use electricity, solvency of local people for

    electricity and the acceptability of local people to the electrification scheme are

    gathered during the reconnaissance survey.

    3.2 Preparation for Site Reconnaissance

    To achieve effective and fruitful site reconnaissance, it is important to prepare for site

    reconnaissance such as gathering of available information, devise sufficient plan and

    schedule of survey activities in advance.

    3.2.1 Information gathering and preparation

    As advance information, 1/50,000 topographic maps are prepared to check thetopography of the target site and villages, the catchment area, village’s distribution and

    access road. More accurate information on site accessibility could be collected by

    contacting local people concerned.

    Copies of 1/50,000 topographic maps and route maps enlarged by 200 to 400% are

     prepared for the fieldwork.

    Check list and interview sheet are also prepared for each site reconnaissance.

  • 8/17/2019 Doracak japoni

    51/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-2 - 

    3.2.2 Planning of preliminary site reconnaissance

    Although it may be required to deviate from original plan and schedule in accordancewith site condition, it is important to make sufficient plan and schedule for site

    reconnaissance activities in advance. It is also necessary to coordinate with local

    officials concerned to insure safety and successful conduct of the reconnaissance

    activities. Since most of micro-hydro sites are located in mountainous and isolated areas,

    it requires longer time to conduct site reconnaissance activities. Therefore, sufficient

    schedule should be considered to have enough time for the fieldwork. Also,

    measurement and other activities for site reconnaissance should be taken into account. A

    check list or interview sheet should be prepared beforehand to efficiently perform

    necessary activities of site reconnaissance.

    3.2.3  Necessary equipment for preliminary site reconnaissance

     Necessary equipment for preliminary site reconnaissance depends on purpose and

    accuracy and site condition. Basic equipment is as follows:

    Table 3.2.1 Check sheet of basic equipment for site reconnaissance as an example

    Equipment Equipment

    ○  Route map ○ Altimeter

    ○  Topographic map ○ GPS (portable type)

    ○  Reconnaissance schedule ○ Camera, Film

    ○  Check list ○ Current meter

    ○  Interview sheet ○ Distance meter, measuring tape

    Geological map ○ Hand level

    Aerial photograph ○ Convex scale (2-3m)

    Related reports Hammer

       M  a  p ,

       S   h  e  e   t

      Clinometer

    ○  Field notebook Knife○  Scale Scoop

    ○  Pencil ○ Torch, Flashlight

    ○  Eraser Sampling baggage

    ○  Color pencil Label

    Section paper ○ Compass

    Stop watch

       S   t  a   t   i  o  n  a  r  y

     

       E  q  u   i  p  m  e  n   t

      Battery

     Notes: ○: necessary equipment for preliminary site reconnaissance

  • 8/17/2019 Doracak japoni

    52/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-3 - 

    3.3 Survey to Outline the Project Site

    During the reconnaissance at the proposed site of power generating facilities and aroundthe power demand area, a survey is conducted on the following items:

    (1) Access conditions

    The equipment and machinery used for the construction and operation of a micro-

    hydropower plant are smaller and lighter than those used for an ordinary hydropower

     plant and it may be possible in some cases that such equipment and machinery can be

     brought to the site either manually or using simple vehicles.

    Given the smaller capacity of the power generated by a micro-hydropower plant, careful

    consideration is required in the use of transportation method and access other than the

    use of an existing road or vehicle since the construction of a new access road could be a

    factor that would considerably reduces the economy of a project. In the case of a

    mountainous area, there may be an abandoned road (previously used for the hauling of

    cut trees, etc.) which is difficult to find because it has been covered by vegetation and it

    is important to interview local residents on the existence of such a road.

    (2) Situation of existing system and future plan

    Even for a project site in which the development of an individual system is assumed, a

    survey should be conducted on the tail end location, route and voltage, etc. of the

    existing system and also on the availability of extension and rehabilitation plans for the

    said system.

    (3) Situation of river water utilization

    The existence of facilities utilizing the river flow, the flow volume and any relevant

    future plans regarding the river from which a planned micro-hydropower plant will

    draw water should also be surveyed. At the project formulation stage, the situation of

    the portion or section of the river for water utilization should be surveyed taking into

    consideration the assumed recession section and the possibility of changes in the

     position of the intake and the waterway route.

    When a fall or steep valley is to be used for power generation, local information on the

    use of such a fall or valley should be obtained together with a survey on the relevant

    legal regulations.

  • 8/17/2019 Doracak japoni

    53/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-4 - 

    (4) Existence of other development plans/projects

    A survey should be conducted on the existence of other development plans/projects in

    terms of roads, farmland, housing and tourism, etc. which may affect the planned

     project site and/or its surrounding area.

    (5) Civil structures in adjacent area and materials used

    Most civil structures of a small-scale hydropower plant are similar to those of irrigation

    facilities and road drainage facilities. The materials used for these structurers are often

    available or can be obtained near the planned project site.

    The use of constructors, human resources and local materials involved in these civil

    structures is important from the viewpoint of reducing the construction cost,

    contribution to the local economy and ensuring easy maintenance and repair. Hence, a

    survey should be conducted on similar civil structures in the adjacent area of a project

    site to obtain useful reference materials for project planning and design.

    (6) Presence of natural topographical features and existing structures usable for power

    generation

    When an existing irrigation channel or similar is used (including widening and/or

    reinforcement) as a waterway for power station, it is necessary to check the

    cross-section, gradient and current water conveyance volume, etc. of such a channel.

    (7) Existence of important ground features and vegetation

    Even a small-scale hydropower plant necessitates some alteration of the localtopography. When important ground features and/or vegetation exist along the planned

    route of the waterway, they must be carefully dealt with. For this purpose, their

    locations and conditions, etc. should be duly noted for discussions with concerned

     parties such as the landowner(s) and representatives of the local government.

  • 8/17/2019 Doracak japoni

    54/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-5 - 

    3.4 Validation of Geological Conditions Affecting Stability for Main Civil

    Structures

    The survey on the ground stability, especially that of the surface layer, is required for

    the construction of a small-scale hydropower plant due to (i) the exposed structure of

    most of the main civil structures and (ii) the rooting of the waterway on a sloping

    hillside. The results of investigation should be presented in the form of sketch drawings

    (refer to Fig 3.4.1) for reference purposes when determining the basic structures for

    civil works.

    Fig.3.4.1 A geological sketch based on site observations

  • 8/17/2019 Doracak japoni

    55/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-6 - 

    3.5 Survey on Locations of Civil Structures

    Field reconnaissance by the hydropower specialist is important to establish a waterwayroute based on an existing topographical map and other relevant information for the

     planning of a micro-hydropower plant. The results of the reconnaissance survey will

    determine if the project will proceed or not.

    The items to be checked during this survey are listed below. It is necessary to repeat the

    field reconnaissance in line with the progress of the planning and design. When

    uncertainties emerge, particularly at the design stage, field verification is necessary.

    Moreover, there is a need to keep the expected demand in mind. Therefore, this survey

    should be conducted in parallel with the demand survey.

    It is important not only to select suitable locations for such individual facilities as the

    intake weir and waterway, etc. but also to carefully examine the locations of their tie-in

    sites.

    For the development of micro-hydro, the maximum use of natural topographical

    features is important from the viewpoint of cost reduction. It is, therefore, necessary to

    conduct the survey based on a full understanding of the items discussed in “Chapter

    4,4.3 Selection of Location for Main Civil Structures”.

  • 8/17/2019 Doracak japoni

    56/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-7 - 

    3.6 Measurement of River Flow

    (1) 

     Necessity of Measurement of River Flow(2) 

    The estimated river flow at a project site is considered reasonably reliable if it is based

    on data from a nearby gauging station. As such, it may not be necessary to conduct

    actual discharge measurement at the project site.

    However, when river flow data is difficult to obtain, it is preferable to measure the river

    discharge in the dry season, by means of simple method, to confirm the appropriateness

    of the estimated flow duration. Any stoppage of power generation due to a reduced

    water flow volume significantly affects the generation of a micro-hydropower plant,

    thus it is essential to check the discharge at dry season. Although it is necessary to

    record the river flow for at least one year in mini hydropower development, the river

    flow during the dry season should be checked even for micro hydropower development.

    Fig.3.4.2 shows the Flowchart to check Minimum Flow/ Duration Curve.

    Should there be a need to measure the discharge, the observation period must be

    carefully determined based on past rainfall records and information relative to the

    climate.

    It is also necessary to check and evaluate the observation results in connection with the

    characteristics (for example, drought year or wet year) of the year of observation based

    on past rainfall records, etc.

    The stream flow measuring method, frequency and water level observation unit can be

    simplified in the following manner to reduce the survey cost.

  • 8/17/2019 Doracak japoni

    57/268

     Manual

    - 3-8 - 

    Water Level Discharg

    H Q

    (m) (m3/s)

    XXX   0.230 0.1

    YYY   0.550 1.7

    ZZZ   0.300 0.2

    WWW   0.380 0.6

    Date

    Installation of Staff Gauge

    (Base Point)

    Selection of Measurement

    Point

    Measuring of Cross Section

    Measuring of Cross Sectional

     Area

    (A)

    Measuring of Velocity /Speed

    (V)

    Calculation of Discharge

    (Q=A x V)

    Record the water level

    on Staff gauge (H)

       A  n  o   t   h  e  r   d  a  y

      a   t   l  e  a  s   t   3   t   i  m  e  s

      r  e  p  e  a   t

     Daily

    Record

    (Hd)

    Calculation o f Rating Curve

    Calculation of Daily

    Discharge

    Calculation of Duration

    Curve

    1

    2

    3

    4

    5

    Staff Gauge

    Fig.3.4.2 Flowchart to check Minimum Flow/ Duration Curve 

  • 8/17/2019 Doracak japoni

    58/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-9 - 

    (2) Flow measuring method

    A stream flow measuring method which is appropriate for the river conditions can be

    adopted. [Reference 3-1: Simple method of stream flow measuring]

    (3) Frequency of stream flow measuring

    In principle, stream flow measuring should be conducted at least three times a year to

    analyze the relation between the water level and the discharge in the range below the

    assumed maximum discharge.

    (4) Water level observation unit

    A staff gauge should be set up at a point near the flow observation point where visual

    water level observation can be easily carried out.

    3.7 Measurement of Head

    The head between the intake point and the headtank and the head between the headtank

    and the outlet point should be measured. At the initial planning stage, however, it may

     be sufficient to measure the head between the planned headtank location and the outlet

    level.

    While a surveying level can be used for the purpose of measuring, a more simple head

    measuring method may be sufficient. [Reference 3-2: Simple methods of head

    measuring]

  • 8/17/2019 Doracak japoni

    59/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-10 - 

    3.8 Demand Survey

    3.8.1 Demand survey method

    There can be many types of power demand facilities for small-scale hydropower

    generation to respond to the conditions of the subject area for development. In the

     preparation of development plan, accurate understanding of the power demand facilities

    in the subject area for development is essential.

    What is important is to ensure the efficiency and practicality of a demand survey. It is

    necessary to estimate a slightly higher demand level than the assumed scale of power

    generation so that it would adequately respond to the scale of development as well as to

    the seasonal fluctuations of the power demand.

    3.8.2 Factors to consider in demand survey

    The demand survey items are described below. When there is more than one power

    demand facility, each facility should be survey.

    (1) Location

    The suitable route and distance, etc. to each power demand facility should be surveyed

    to examine the optimal transmission and distribution lines.

    (2) Owners

    The opinions and intentions of the owners of power demand facilities regarding the

    introduction of a new power supply source should be clarified.

    (3) Types and required quality of equipment

    The situation of power use by equipment (for power, heating, lighting and electrical

    control, etc.) and the required level of accuracy (in terms of the allowable voltage

    fluctuation and frequency fluctuation) should be surveyed.

    (4) Equipment capacity, etc.

    The equipment capacity, power consumption level and electricity tariff (or estimated

    electricity tariff in the case of planning) should be surveyed.

  • 8/17/2019 Doracak japoni

    60/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-11 - 

    (5) Period of use

    Any seasonal or daily fluctuation of power use and the range of fluctuation should be

    surveyed.

    (6) Year of installation and service life

    The year (date) of installation of each power demand equipment and its service life or

     planned period of use should be surveyed.

    (7) Likely problems associated with power cut

    The likely problems and financial losses associated with a power cut to power demand

    facilities should be surveyed.

  • 8/17/2019 Doracak japoni

    61/268

     Manual for Micro-Hydro Power Development

    Chapter 3

    - 3-12 - 

    3.9 Actual Field Survey

    Actual field survey for the design of structures for micro-hydropower system should be

    conducted after the identification of their location and route. The following should be

    done if necessary:

    (1) A proper understanding of the local topography is important for the planning of a

    small-scale hydropower plant like the main exposed structure civil structures.

    Topographical surveying is particularly required for such structures as the intake

    facility, headtank and generating station, etc., each of which covers a wide area, to

    improve their design accuracy. In general, the accuracy of the topographical

    surveying around civil structures tends to be in the range of 1/100 – 1/200 for small

    to medium-scale hydropower plants. However, topographical surveying accuracy in

    the region of 1/500 should be sufficient for independent micro-hydro scheme

     because an error in topographical surveying hardly affects the work volume for

    small structures.

    (2) During the implementation stage: For the waterway and access road, etc., route

    surveying (center line and cross-section surveying) may be sufficient for planning

    and design purposes and should be effective from the viewpoint of cost reduction,

     particularly when the required surveying length is long. These routes must, however,

     be carefully determined based on the results of the field reconnaissance conducted

     by the planner(s).

  • 8/17/2019 Doracak japoni

    62/268

     Manual for Micro-Hydro Power Development

    Chapter 3 (Reference) 

    - 3-13 -

    [Ref. 3-1  Method of stream flow measurement]

    1. Using electromagnetic current meter

    Generally, the current meter used for the measurement of river flow is screw type. But nowadays, an

    electromagnetic current meter that doesn’t have rotating parts is available in the market. This is suitable for

    measurement of river flow in a small-scale hydro site. It is lightweight, and can be measured even in shallow

    river.

    In case of survey for small-scale hydropower development, a simple method like the following are sufficient

    for discharge measurement using electromagnetic current meter.

    (1)  Three-points measuring method ・・・・Vm = 0.25×( V0.2 + 2V0.6 + V0.8 )

    (2)  Two-points measuring method ・・・・Vm = 0.50×( V0.2 + V0.8 )

    (3)  One-point measuring method ・・・・・Vm = V0.6

    (4)  Surface measuring method ・・・・・・Vm = 0.8×Vs

    where, Vm: Mean velocity  Vs: Surface velocity

    V0.2: Velocity at the depth of 20% below the water surface

    V0.6: Velocity at the depth of 60% below the water surface

    V0.8: Velocity at the depth of 80% below the water surface

    Following should be considered when selecting the point of measurement in the stream .

    (1)   No irregular wave and whirlpools at the surface.

    (2)   No subsurface flow, back-flow, and stagnation.

    (3)   No irregular change of water level.

    (4) No crossing-over of stream line.

    During measurement, the riverbed should be cleaned, if necessary.

  • 8/17/2019 Doracak japoni

    63/268

     Manual for Micro-Hydro Power Development

    Chapter 3 (Reference) 

    - 3-14 -

    2. Float measuring method 

    Basically, float measuring method is applied during floods when measurement with current meter is not

     possible. But, it is applicable during the stage where development sites are not decided yet or the current meter

    is not available.

    (1) Measuring method

    1) Measurement should be made at the place where the axis of streambed is straight and the cross section

    of the river is almost uniform.

    2) Flowing distance of floats should be more than the width of river.

    3)Setting transverse lines at the upstream and downstream perpendicular to the axis of streambed.

    Flow-down distance (upstream and downstream lines) = L

    4) Measuring the cross sectional areas at the upper and lower transverse lines to get the average value of

    the cross sectional areas of flow (Amean).

    Additional measurement should be made at the middle section of two lines if the cross

    section of river is not uniform.

    5) Floats are dropped at upstream of the upper transverse line, the time required from upper to lower

    transverse line is measured.

    6) Measurement should be done several times at different divisions of the river cross-section in the

    transverse direction. (more than three divisions)

    (2) Stream flow calculation formula

    Vm = C×Vmean 

    C: (1) Concrete channel which cross section is uniform = 0.85

    (2) Small stream where a riverbed is smooth = 0.65

    (3) Shallow flow (about 0.5m) = 0.45

    (4) Shallow and riverbed is not flat = 0.25

    (1) (2)

    Vm = 0.85×Vmean  Vm = 0.65×Vmean 

    (3) (4)

    0.5 m

    Vmean

    Vmean  Vmean

    Vm = 0.45×Vmean  Vm = 0.25×Vmean 

    Vmean 

  • 8/17/2019 Doracak japoni

    64/268

     Manual for Micro-Hydro Power Development

    Chapter 3 (Reference) 

    - 3-15 -

    3. Weir measuring method

    The discharge is small and the use of current meter or float measuring method is impossible, the weir as shown

     below is built and discharge is measured by measuring the overflow depth at the river.

    Upstream line

    Downstream line

       F

       l  o  w   i  n  g   d   i  s   t  a  n  c  e  o   f   f   l  o  a   t  s   (   L   )

    Drop line of floats

    A – A’ Cross section

    B – B’ Cross section

    C – C’ Cross section

    A – A’

    C – C’ Mean Cross section

  • 8/17/2019 Doracak japoni

    65/268

     Manual for Micro-Hydro Power Development

    Chapter 3 (Reference) 

    - 3-16 -

    In this method, the stream flow can be obtained by following formula.

    Q = C・L・h1.5

     

    Q:Discharge (m3/s) C:Discharge coefficient L:Opening width of weir (m)

    h:Overflow depth (m)

    4. Others 

    It is applicable to use the following method to measure smaller stream flow.

    C = 1.838 ( 1 + ) ( 1 - )h 10

    0.0012 ( h/L )1/2 

  • 8/17/2019 Doracak japoni

    66/268

     Manual for Micro-Hydro Power Development

    Chapter 3 (Reference) 

    - 3-17 -

    Place of survey date time : water level

    No. Remarks

    Distance from left bankDepth of riverArea of flow section

    Waterdepth Discharge

    Waterdepth Discharge

    Waterdepth Discharge

    Waterdepth Discharge

    Waterdepth Discharge

     Average of Veloc ity (cm/s )

    dischage(l/s)

    Survey sheet of discharge

    1 2 3 4 5 6 7 8 9 10 11

    50.0

    40.0

    30.0

    20.0

    10.0

    Depth at point and velocity(cm, cm/s)

    60.0

    Cross Section of river

    0.0

  • 8/17/2019 Doracak japoni

    67/268

     Manual for Micro-Hydro Power Development

    Chapter 3 (Reference) 

    - 3-18 -

    [Ref. 3-2  Method of head measurement] 

    1. Using clear hose method 

    The figure below shows this method. The method is useful for low head sites, since it is cheap and reasonably

    accurate. To get the head of two points, measuring the difference of water level of the water-filled clear hose at

    two points. Even a man who does not have a skill of survey work can apply this method.

    H1

    H3

    H4

    H5

    H6

    H2

    Head

    H1

    H3

    H4

    H5

    H6

    H2

    Head

    Head = H1+H2+H3+H4+H5+H6

    H1 = B1-A1

    B1

    H1

     A1

    Date :

    No.   Hi=Bi-Ai(meters)

    1 0.85

    2 0.86

    3 0.86

    4 0.91

    5 0.99

    6 0.75

    7 0.30

    8 0.90

    9 0.7010 0.74

    11 2.30

    12 0.66

    10.82

    Location :

    0.70 1.36

    Total Height (meters)=

    1.00 1.74

    0.20 2.50

    1.00 1.90

    1.00 1.70

    1.00 1.75

    1.00 1.30

    1.00 1.91

    1.00 1.99

    1.00 1.86

    1.00 1.86

     Ai(meters)

    Bi(meters)

    1.00 1.85