Role of Services Coordination
Integration of MEP systems into the architectural andstructural envelope.
Coordinate with the client and consultant for various details.
Selection of suppliers
Installation and procurement scheduling for MEP systems
Tracking and formalizing procedures for submittals
-
8/9/2019 Aes Delhi Services 2009
2/21
TAXE S & DU TIE S
Service tax, Labor cess or any other statutory cess and ESI was paid by AES.The Services contractor bore all other taxes, levies, duties andassessments .
P AYMENT S TE R M S & CO N D ITI O N S
10% Mobilization advance against B.G. in favour of AES .70% Against Material Supply.15% Against mechanical completion on pro-rata basis.5% Against complete commissioning of the system.5% Performance bank guarantee valid till DLP Should be
submitted at the time of start of work to AES.
-
8/9/2019 Aes Delhi Services 2009
3/21
G reen Building
Green Building involves design and construction practices thatsignificantly reduce or eliminate the negative impact of
buildings on the environment and occupants in five broadareas:
1 Sustainable site planning2 Safeguarding water and water efficiency3 Energy efficiency and renewable energy4 Conservation of materials and resources5 Improving Indoor environmental quality
-
8/9/2019 Aes Delhi Services 2009
4/21
-
8/9/2019 Aes Delhi Services 2009
5/21
Rs. 0.00
Rs. 2,000,000.00
Rs. 4,000,000.00
Rs. 6,000,000.00
Rs. 8,000,000.00
Rs. 10,000,000.00
Rs. 12,000,000.00
Rs. 14,000,000.00
Rs. 16,000,000.00
Rs. 18,000,000.00
Rs. 20,000,000.00
Electrical Fire fighting Plumbing HVAC BMS Lift R.O. SystemInsulationGas generator
Rs. 12,311,700.00
Rs. 2,424,708.00
Rs. 6,640,535.00
Rs. 18,961,344.00
Rs. 1,967,900.00
Rs. 2,453,074.00
Rs. 3,000,000.00
Rs. 3,597,846.00
Rs. 14,283,000.00
Rs. 16,177,804.00
Rs. 2,381,290.00
Rs. 9,096,454.00
Rs. 19,513,647.00
Rs. 2,020,431.00
Rs. 2,453,074.00
Rs. 2,566,630.00
Rs. 3,395,807.00
Rs. 14,149,126.00
Contract Amount original
Contract Amount revised
Scope of Work
-
8/9/2019 Aes Delhi Services 2009
6/21
Ty pes of Services
-
8/9/2019 Aes Delhi Services 2009
7/21
HV A C ( H eating V entilating and A ir Conditioning)
HVAC is an initialism or acronym that standsfor "heating, ventilating, and air conditioning".
-
8/9/2019 Aes Delhi Services 2009
8/21
HV A C ( H eating V entilating and A ir Conditioning)
Schematic Diagram of HV A C S y stem
-
8/9/2019 Aes Delhi Services 2009
9/21
-
8/9/2019 Aes Delhi Services 2009
10/21
Cooling Tower
Capacity: Suitable for 310 TRWater Flow Rate: 1408 USGPMCondenser Water In 100 oFCondenser Water Out 90 oF
Water Pumps
Primary CHW Pump 15 HPSecondary CHW Pump 20 HPCondenser Water Pump 20 HP
-
8/9/2019 Aes Delhi Services 2009
11/21
Complete Room Conditioning S y stem
-
8/9/2019 Aes Delhi Services 2009
12/21
Sequence of HV A C Work Equipment Installation
VAMInstallation
TFAinstallation
Pr ima ry, seconda ry and condense r pump installation
Cooling Towe r Installation
Air Washe r
-
8/9/2019 Aes Delhi Services 2009
13/21
Sequence of HV A C Work FCU installation Chilled wate r pipe line installation Hydr o p r essu r e testing of chilled wate r pipe line Duct installation and silicon filling Smoke testing of duct
Insulation of Duct and chilled wate r pipe lines
Aluminium Cladding of Chilled wate r pipe lines( Inside the Building) Cement Cladding of chilled wate r pipe lines (at te rr ace) Valves fitting fo r: CHW pumps Condense r wate r pump Cooling towe r
FCU Coppe r fitting FCU Canvass connection FCU P lenum fixing Dr ain installation and insulation
-
8/9/2019 Aes Delhi Services 2009
14/21
Observations made at the time of installation
W ooden Support should not be above FCU.
Supports should be at proper distance.
Strainer Valve should be properly aligned otherwise itwould not filter the CH W pipe line water which mightcause blockage in FCU.
Valve should be fitted inside the tray.
Tapping from main header line should have proper spaceto carry out the insulation work.
-
8/9/2019 Aes Delhi Services 2009
15/21
B M S (Building M anagement S y stem)
Building management system is a tool that isused to monitor and control variousmechanical systems and/or electrical systemsin a building .
-
8/9/2019 Aes Delhi Services 2009
16/21
Field Devices (Sensors) For BMS:
Temperature Sensors
Air Differential Pressure Switch for Filter status (TFA)
Tank Level Sensor (Plantroom)
Cooling Tower Tank Level Sensor (Terrace)
Oil Tank Level Sensor (Plantroom)
Occupancy Sensor
Chilled Water Flow Meter Sensor (Plantroom)
Components in B M S s y stem
Duct Temperature Sensor (All Rooms)
Valve actuators
Immersion Temperature Sensor (CHW& CDSW Temp.)
Damper actuators
Duct Temperature & RH Sensor (TFA)
Outside Air Temperature & RH Sensor
Air Differential Pressure Switch for Run status (TFA)
-
8/9/2019 Aes Delhi Services 2009
17/21
Supervisory Level:
NAE SupervisoryController ADS Software (UI)
Components in B M S s y stem F ield Level Controllers:
RCU (Room control Unit) DDC Controllers
MIG Controller(Plantroom)
-
8/9/2019 Aes Delhi Services 2009
18/21
Components in B M S s y stem
Fire Alarm SystemFire Alarm Panel (BMS Room)
Fire Detector Multicriteria (Rooms)
Fire Detector Photo electric (Rooms)
Control Module (Lobby area)
Monitor Module (Flow switch)
Hooter with Horn/Strobe (Lobby area)
Manual Call Point Lobb area
Public Address SystemSpeakers (All Rooms)
DVC Digital Voice Command(Fire Panel, BMS Room)
DAA Digital Audio Amplifier (Fire Panel, BMS Room)
-
8/9/2019 Aes Delhi Services 2009
19/21
B M S (Building M anagement S y stem)
-
8/9/2019 Aes Delhi Services 2009
20/21
B M S S y stem A rchitecture
DDCController - 1
DDCController - 2
DDCController - x
NAEControllerBMS PC with
ADS Software
Legend:
N 2 communication Bus(3core X 1.5 sq.mm. Cable)
Controller to PC connectivityThro TCP/IP protocolDDCController - 3
DDCController - 4
F ield sensors F ield sensorsF ield sensors F ield sensors
F ield sensors
M IG - 1
T hird PartyEquipments
-