Bensenville School District #2
Addi4ons to Johnson & Tioga
Elementary Schools
Budget Review April 4, 2012
Tioga & Johnson Construc1on Budget Update $ millions Total
Johnson addi1on & renova1on 24.8
Tioga 1st addi1on (Includes Contempla1on Bridge) 21.8
Tioga 2nd addi1on 5.5
Demoli1on Costs 0.6
Total Es1mate 52.7
Less Unallocated Con1ngencies and Possible Allowance Recoveries 0.9
Likely Range $51.8-‐52.7
Allowance & Con1ngency Recap
Allowances Johnson Tioga
(Current Phase) Tioga
(Next Phase) Total
Allowances Awarded 520,000 910,000 1,430,000
Less Authorized to Date 126,225 479,579 605,804
Less Future Spending (est.) 343,775 280,421 624,196
Unspent allowances 50,000 150,000 200,000
Con4ngencies Ini4ally Budgeted 600,000 600,000 200,000 1,400,000
Less Allocated To Date (Wetlands, Asbestos, Bulle4ns)
400,000 300,000 0 700,000
Remaining Con4ngencies 200,000 300,000 200,000 700,000
Bensenville School District #2
Addi4ons to
Johnson & Tioga Elementary Schools
Discussion Overview -‐ Review February progress – WAJ -‐ Review March Major AcCviCes -‐ Review February progress -‐ Tioga -‐ Review March Major AcCviCes
W.A. Johnson Elementary School
March Major Ac4vi4es -‐ Completed masonry interior CMU work – Café, Admin -‐ Completed roofing installaCon at Café & Gym -‐ Started roofing at Learning Center, Admin Area -‐ ConCnued Mech/Elec/Plumb overhead Rough-‐In -‐ ConCnued drywall framing, taping installaCon -‐ ConCnued interior painCng -‐ ConCnued exterior glazing – classroom areas -‐ Complete seWng of mechanical equipment
Exterior Glazing – NE Classrooms April 2, 2012
Exterior Glazing – Art Room April 2, 2012
Exterior Glazing – Innova4on Lab April 2, 2012
Exterior Glazing – Innova4on Lab (Interior) April 2, 2012
Cafeteria April 2, 2012
Courtyard – Music Room Eleva4on April 2, 2012
Roofing – Administra4on Area April 2, 2012
Learning Center -‐ Roofing April 2, 2012
Classroom Area Corridor April 2, 2012
Typical Classroom – Light Fixtures April 2, 2012
Student Commons April 2, 2012
April Major Ac4vi4es -‐ Complete roofing at AdministraCon Area -‐ Complete exterior glazing – classroom areas -‐ ConCnue exterior glazing – café, gym -‐ ConCnue Mech-‐Electrical-‐Plumbing-‐Fire Prot Rough-‐in -‐ ConCnue drywall framing, installaCon, taping, painCng -‐ Start Casework installaCon -‐ Start ceramic Cle work -‐ Start VCT flooring installaCon -‐ Overall CPM schedule currently tracking per plan
Tioga Elementary School
March Major Ac4vi4es -‐ Completed interior masonry CMU work -‐ Completed roofing -‐ gymnasium -‐ ConCnued exterior glazing – classroom wings, Pre-‐K, Admin -‐ ConCnued Mech/Elec/Plumb/Fire Prot overhead Rough-‐In -‐ ConCnued classroom area drywall framing, installaCon, taping -‐ ConCnued classroom area painCng -‐ Poured contemplaCon bridge deck -‐ ConCnued ceiling grid installaCon -‐ Started ceramic Cle work and casework installaCon -‐ Completed seWng of mechanical equipment
Contempla4on Bridge Deck March 16, 2012
Contempla4on Bridge – Mechanical Rough-‐in April 2, 2012
Exterior Glazing – Classroom Areas March 16, 2012
Exterior Glazing – Pre-‐K Classrooms March 22, 2012
Exterior Glazing – Courtyard Stair March 22, 2012
Temporary Walkway April 2, 2012
Temporary Walkway April 2, 2012
Gymnasium – Mechanical Rough-‐in April 2, 2012
Ceramic Tile – Student Bathrooms April 2, 2012
Ceramic Tile – Staff Bathroom April 2, 2012
Classroom Area – Entrance Ves4bule April 2, 2012
Typical Classroom -‐ Interac4on Room April 2, 2012
Innova4on Lab April 2, 2012
Typical Classroom – Radiant Ceiling Panels April 2, 2012
Typical Classrooms April 2, 2012
Typical Classroom – Sliding Markerboard Wall Mock-‐Up April 2, 2012
April Major Ac4vi4es -‐ Complete exterior glazing work – classroom areas -‐ ConCnue exterior glazing – Admin area, Pre-‐K, LRC -‐ ConCnue Mech-‐Electrical-‐Plumbing-‐Fire Prot Rough-‐in -‐ ConCnue drywall framing, installaCon, taping -‐ ConCnue painCng work -‐ ConCnue ceiling grid -‐ ConCnue classroom casework installaCon -‐ Start seWng of light fixtures -‐ Start VCT flooring installaCon -‐ Overall CPM schedule currently tracking ~15 days behind
Bensenville School District #2
Addi4ons to
Johnson & Tioga Elementary Schools