Page 1: Ernst Bolt, Rijkswaterstaat

15 February 2012

Offshore Windfarm Planning Learning by doing in the Netherlands… Ernst Bolt Ministry of Infrastucture and Environment Rijkswaterstaat Centre for Shipping andTransport

Page 2: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 2 15 February 2012

Contents

•  Spatial plans •  First offshore windfarms •  Second round applications •  Preparing the third round

Page 3: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 3 15 February 2012

Spatial plans

•  National Spatial Strategy (Nota Ruimte) •  Structure plan of Military Areas (Structuurschema Militaire Terreinen) •  Policy statement Water Management (Nationaal Waterplan)

–  water quality management, fresh water –  safety against flooding –  anticipating climate changes –  recreation –  inland water transport

•  Integral Management Policy North Sea (IBN)

Page 4: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 4 15 February 2012

National Spatial Strategy

Spatial planning policy •  Vision statement for spatial development into

2020/2030. •  North Sea: key area of the National Ecological

Network. –  strengthening the economic significance,

linked to –  preservation and development of nature

and landscape values

Page 5: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 5 15 February 2012

National Spatial Strategy Principal spatial structure: Water, Nature and Landscapes

Page 6: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 6 15 February 2012

National Water Plan

National Spatial Strategy

Structure scheme Military Areas

Spatial planning policy

Spatial policy for water areas

EU guidelines à National legislation

Functions of National Waters Integrated Management

Plan North Sea

(elaboration of the North Sea paragraph)

Page 7: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 7 15 February 2012

Integrated Management Plan North Sea (IBN) •  Elaboration of North Sea paragraph of the Water Plan •  Coproduction of Ministries of

–  Transport, Public Works and Water Management 1

–  Agriculture, Nature and Food Quality 2

–  Housing, Spatial planning and Environment3

–  Economic Affairs4

–  Defense 2,4):Ministry of Economic Affairs, Agriculture and Innovation

1,3):Ministry of Infrastructure and the Environment •  Functions:

–  shipping –  oil and gas –  sand –  fishing –  nature –  renewable energy

Page 8: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 8 15 February 2012

Water quality

Page 9: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 9 15 February 2012

Shipping

Clearways •  corridors free of obstacles

for the passage of ship traffic.

•  Logical routes, connecting the existing TSSs.

•  All oil&gas rigs have to stay out of these areas.

Page 10: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 10 15 February 2012

Wind energy areas

•  Existing •  Permits •  Prospect areas

Page 11: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 11 15 February 2012

Clearways and traffic density

Page 12: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 12 15 February 2012

Egmond aan Zee / NoordzeewindQ7 / Amalia

Egmond aan Zee / NoordzeewindFirst offshore windfarms

•  Egmond aan Zee (2006) 36 x 3 MW = 108 MW

•  Q7 Amalia (2008) 60 x 2 MW = 120 MW

Page 13: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 13 15 February 2012

Second Round Wind farms

•  Boundary condition: no constructions in the clearways •  No turbines within 12 nm from coastline •  Financial support for maximum 1000 MW •  Invititation to apply for financial support:

–  Apply for permit –  Environmental impact study

- including shipping safety effects - SAMSON model had to be used

•  Ministry of Economic Affairs would choose the most cost-effective initiatives that received a permit

•  Result: 80 applications!

Page 14: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 14 15 February 2012

2nd round applications

Page 15: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 15 15 February 2012

Finally, 12 permits

Key issues: •  Ecological impact •  Safe helicopter flight paths •  Shipping safety

Page 16: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 16 15 February 2012 16

Permits round 2

Page 17: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 17 15 February 2012

Ecological impact Natura 2000

•  Distance to lesser seagull colony •  Underwater noise

–  Disturbance of seals and fish larvae –  No pile driving January - July

Page 18: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 18 15 February 2012 Wind op Zee 18 13-09-2011

Helicopter-approach availability of the platform

Page 19: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 19 15 February 2012 Wind op Zee 19 13-09-2011

Shipping safety / efficiency

Page 20: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 20 15 February 2012

Shipping safety – points of discussion

•  Does SAMSON produce representative figures? –  Influence on radar image –  Influence of ‘complex traffic situations’ –  Visual disorientation in combination with anchorage area and on-

shore lights •  Minimum safe distance between shipping route and wind farm? •  Which accident probability can be accepted

–  Political damage –  Economical consequences –  Casualties

•  Legal procedures

Page 21: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 21 15 February 2012 21

BARD/TYPHOON BUITENGAATS 300 MW

BARD/TYPHOON ZEE-ENERGIE 300 MW

ENECO Q10 120 MW

AND THE € WINNERS ARE…

Page 22: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 22 15 February 2012

3rd Round

•  Political goal: 6000 MW to be created by 2020 •  Indicate possible areas in Integral Management Plan North Sea

•  Coastal area determined by clearways •  Modification of shipping routes affects granted permits of 2nd round

Page 23: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 23 15 February 2012

Variant 2a

Page 24: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 24 15 February 2012

Variant 4a

Page 25: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 25 15 February 2012

Variant 5a

Page 26: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 26 15 February 2012

Variant 6a

Page 27: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 27 15 February 2012

Routes variant 2a

Page 28: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 28 15 February 2012

Routes variant 5a

Page 29: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 29 15 February 2012

Routes variant 6a

Page 30: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 30 15 February 2012

Current routes Maas

Page 31: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 31 15 February 2012

Routes Maas variant 5a

Page 32: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 32 15 February 2012

Cost – effectiveness (subsidies for production)

Page 33: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 33 15 February 2012

Formal Safety Assessment

•  Navigational Risk Review –  Hazard workshop –  SAMSON

•  Variant 5 favourable –  Less complex traffic pattern in Maas Junction –  Accident frequency (SAMSON) no significant change –  Combined with new TSS IJmuiden

Page 34: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 34 15 February 2012

Cost – effectiveness (shipping)

Page 35: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 35 15 February 2012

Total costs

Page 36: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 36 15 February 2012

Current proposal for IMO approval

Page 37: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 37 15 February 2012

Current state

•  Modification of shipping routes – proposal to IMO •  Modification of granted round 2 plan •  New government since 2010 •  No funds/subsidy for round 3 •  New energy policy expected 2014/15

Page 38: Ernst Bolt, Rijkswaterstaat

Rijkswaterstaat Offshore wind farm planning 38 15 February 2012

To be continued…