22 Oktober 2015
KEPERLUAN PERMOHONAN BEKALANELEKTRIK DAN PEMANTAUAN PROJEK TNB
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
2/30
POWERING THE NATION
TNB KUALA LUMPUR TNB PUTRAJAYA
No of Consumer 1,118,483 26,918
Area width (kmsq) 506.801 49
Maximum Demand (MW) 2,679 86
No of Substation PMU : 34PPU : 137
SSU 33kV : 36
PE 11kV : 6911
PMU: 3PPU: 9
SSU 33KV: 2
PE 11KV : 356
SAIDI (min) 28.83 0.27
LATAR BELAKANG TNB KUALA LUMPUR & TNB PUTRAJAYA
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
3/30
POWERING THE NATION
Akta Bekalan Elektrik 1990
Peraturan-Peraturan Bekalan Pemegang
Lesen 1990
Peraturan-Peraturan Elektrik 1994
Piagam Pelanggan TNB
AKTA, PERATURAN & PIAGAM PELANGGAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
4/30
POWERING THE NATION
500kV, 275kV, 132kV
33kV, 22kV and 6.6kV, 11kV, 400/230V
SISTEM BEKALAN ELEKTRIK
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
5/30
POWERING THE NATION
TANGGUNGJAWAB PEMEGANG LESEN & PELANGGAN
Single Tenant -Unit kediaman sesebuah seperti rumah teres atau rumah sebuah
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
6/30
POWERING THE NATION
Shop lot-Unit rumah kedai lebih dari satu tingkat
TANGGUNGJAWAB PEMEGANG LESEN & PELANGGAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
7/30
POWERING THE NATION
Unit kediaman bertingkat dan pusat komersil bertingkat bagi pengguna berkelompok
seperti rumah pangsa (flat), kondominium dan komersil (kompleks beli-belah)
TANGGUNGJAWAB PEMEGANG LESEN & PELANGGAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
8/30
POWERING THE NATION
Unit kediaman bertingkat dan pusat komersil bertingkat bagi pengguna berkelompok
seperti rumah pangsa (flat), kondominium dan komersil (kompleks beli-belah)
ANGGUNGJAWAB PEMEGANG LESEN & PELANGGAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
9/30
POWERING THE NATION
Pilih Commercial & Industrial
1
Pilih Supply Application
2
Pilih READ MORE pada ELECTRICITY
SUPPLY APPLICATION HANDBOOK
(ESAH)
3 4
Muat turun panduan utama berkaitan
CAPAIAN PANDUAN TNB www.tnb.com.my
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
10/30
POWERING THE NATION 10
Dalam seksyen ini, anda boleh membaca tentang caj sambungan ,deposit untuk bayaran , Caj Sambungan Beban ( CLC ), dan Surcaj
Power Factor . Terdapat juga maklumat mengenai peralatan kimpalan
elektrik dan surcaj bagi bekalan elektrik sementara. Maklumat lebih baik
diberi supaya anda dapat mengelakkan kos yang tidak perlu .
CAJ & PENALTI
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
11/30
POWERING THE NATION 11
Pengecualian deposit
Kenalpasti pembayar bil kerana akaun yang dinamakan atas
agensi/badan kerajaan adalah dikecualikan deposit.
Untuk pengecualian deposit, pihak TNB perlu jelas siapakah pihak
yang akan berkontrak dgn TNB. Deposit adalah merujuk kepada
akaun yang bakal didaftarkan.
Definisi Agensi Kerajaan
Pihak Berkuasa Tempatan, Institusi Pengajian Awam, Lembaga &
Perbadanan
Kedutaan dan Suruhanjaya Tinggi
Jabatan-Jabatan Kerajaan dan Badan-Badan Berkanun
PENGECUALIAN DEPOSIT
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
12/30
POWERING THE NATION
< 100kVA
Dipohon oleh
kontraktor elektrikberdaftar dengan
Suruhanjaya
Tenaga(ST)
> 100kVA
Dipohon oleh
Jurutera Perundingyang berdaftar
dengan BEM
Jenis
Permohonan
Bekalan
Elektrik
JENIS PERMOHONAN BEKALAN ELEKTRIK
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
13/30
POWERING THE NATION
Voltan
Rendah
VoltanTinggi
Bekalan Tahap Voltan (V) Beban Maksima (kVA)
1 fasa 230 < 12
3 fasa400 < 45
400 < 1,000
Bekalan Tahap Voltan (kV) Beban Maksima (kVA)
3 fasa
11 > 1,000
33 > 5,000
132 & 275 > 25,000
TAHAP VOLTAN BEKALAN ELEKTRIK
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
14/30
POWERING THE NATION
Beban Maksima Tahap Voltan
Keperluan Pencawang
Elektrik
350kVA
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
15/30
POWERING THE NATION
P2 P3
Pemberitahuan
Mula Kerja
Pertimbangan
kepada Pelan-
pelanCadangan
Pemajuan
Proses 2
Proses 3
Pengumpulan
Maklumat
Teknikal
P5
Pemeriksaan
Akhir
Peringkat I &Peringkat II
Akhir
P1
Proses
Mula
Pendepositan
CCC
danBorang-
Borang G
P4
Pemeriksaan
Interim
Proses 4 Proses 5 Proses 6
P6
Merangkumi dari peringkat Mula hingga Akhir pembinaan
PROSES ONE STOP CENTER (OSC 3.0)YANG MELIBATKAN
TNB
HUBUNGKAIT PROSES
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
16/30
POWERING THE NATION
Proses OSC3.0 oleh PBT
Proses TNB
[Proses 1]
Pengumpulan
Maklumat
Teknikal
Pra-rundingan Kebenaran Merancang (KM)
Pihak TNB akan mengulas keperluan pencawang elektrik dari segi
bilangan, lokasi dan jenis. Keperluan pembekal (PPU & PMU) turut
dinyatakan. Ulasan rezab talian penghataran (jika terlibat)
[Proses 2]
Pertimbangan
Pelan-pelan
Cadangan
Perakuan Kebenaran Merancang kepada PBT & Permohonan
Bekalan Elektrik kepada TNB
Pihak TNB akan meluluskan pelan-pelan cadangan serta menetapkan
Tapping Point of Supplyuntuk permohonan ini untuk proses
berikutnya
[Proses 3]
Pemberitahua
n Mula Kerja
Penyediaan dan kelulusan Cadangan Perancangan Projek (CPP) bagipermohonan yang diterima.
Pihak TNB akan mengeluarkan Caj Sambungan Pengguna (CSP)
selepas kelulusan diperolehi untuk dibayar oleh pemaju/pemilik
Jurutera Perunding perlu menguruskan permohonan izinlalu pada
peringkat ini
HUBUNGKAIT PROSES ONE STOP CENTER (OSC 3.0)
DENGAN PERMOHONAN BEKALAN ELEKTRIK
HUBUNGKAIT PROSES
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
17/30
POWERING THE NATION
Proses OSC3.0 oleh PBT
Proses TNB
[Proses 4]
Pemeriksaan
Interim
Penerimaan Bangunan Pencawang Elektrik/Tapak Pembangunan
Pihak TNB akan membuat semakan tapak dan pencawang-
pencawang elektrik yang dibina sebelum diterima
Kerja-kerja rentangan dan pemasangan aset TNB dimulakan
[Proses 5]
Pemeriksaan
Akhir
Pengeluaran Surat Sokongan CCC
Pihak TNB akan membuat semakan kerja-kerja pemasangan aset
TNB di tapak dan semua syarat-syarat TNB dipatuhi sepenuhnya
Surat sokongan akan dikeluarkan selepas semua keperluan TNB
dipatuhi dan aset TNB telah dimulatugas sehingga ke kabel servis
TNB
[Proses 6]
Pendepositan
CCC &
Borang-
Borang G
Tidak berkaitan dengan TNB
Pihak TNB akan memasang meter elektrik setelah deposit selesai
dibayar untuk akaun-akaun elektrik yang terlibat
HUBUNGKAIT PROSES ONE STOP CENTER (OSC 3.0)
DENGAN PERMOHONAN BEKALAN ELEKTRIK
PROSES PERMOHONAN BEKALAN ELEKTRIK TNB 100kVA
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
18/30
POWERING THE NATION
Nos. of process
/procedures
Nos. of customer
Interaction required
Stage 1: OSC
infrastructure
needsStage 2: Detail
Supply
Requirement
data (Checklist)
Process 1
Pre-
Consultation
process
Process 2
OSC
submission
& PlanApproval
(Inclusive of
Wayleave &
Permit
approval)
Process 3
Tech.
evaluation
(ProjectPlanning &
issue Conn.
Charge)
Process 4
1. Pay Conn.
Charge
2. HandoverSubstation
3. Handover
site
4. Obtained
excavation
permit
Process 5
Prepare &
install
supplysystem/
service
Process 6
Pay
deposit
Process 7
Install
meter &
connectsupply
7
3
14 days 14 days 5 days
Installation ConnectionPlanningOSC (One
Stop Center)Pre-Consultation
30 days 60 days
PROSES PERMOHONAN BEKALAN ELEKTRIK TNB > 100kVA
PURATA JANGKA MASA PROSES PERMOHONAN BEKALAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
19/30
POWERING THE NATION
TAHAP VOLTAN
132kV ke atas
33 kV
11 kV
400 V ke bawah
(dengan pencawang)
400 V ke bawah
(tanpa pencawang)
JANGKA MASA
3 - 5 tahun
18 - 24 bulan
6 - 12 bulan
3 - 12 bulan
< 3 bulan
PURATA JANGKA MASA PROSES PERMOHONAN BEKALAN
ELEKTRIK > 100kVA
PROSES PERMOHONAN BEKALAN ELEKTRIK TNB < 100kVA
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
20/30
POWERING THE NATION
Step number#
Submit andpay at TNB
Installation
and meterinstall
Issue 1stbill
Conduct
self
estimation
Submit & pay
at Kedai
Tenaga
Meter Only /
Overhead
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
21/30
POWERING THE NATION
Terms & Conditions:
The completion of application forms submitted by contractors/customers
The electricity connection fee and deposit have been paid by contractors/customers
Service cable and premise meter board are presented and in good condition
Permit has been approved by Local Authority
New Supply Connection Application
Estimation Duration (days)
1 - 3 Days Meter Only
Overhead(Talian Atas)
10 - 14 days
(non protocol area by PBT)
Underground cable
(Kabel Bawah Tanah)
30 - 50 days
(protocol area by PBT)
Underground Cable
(Kabel Bawah Tanah)
3
5 Days
With/Without Permit
With Permit
Customer charter for New Individual Supply Application up to 140kVA
Customer Charter
published in TNB Kepong
PURATA JANGKA MASA PROSES PERMOHONAN BEKALAN
ELEKTRIK < 100kVA
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
22/30
22
POWERING THE NATION
PERMOHONAN BEKALAN SECARA ONLINE
Layari di sesawang TNB
www.tnb.com.my
Fungsi Permohonan bekalan elektrik
dapat dilaksankan secara on-line
Faedah Mudah, senang hanya di
hujung jari anda!
https://eapplication.tnb.com.my/
http://www.tnb.com.my/http://www.tnb.com.my/http://www.tnb.com.my/ -
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
23/30
23
POWERING THE NATION
Layari di sesawang TNB
www.tnb.com.my
FUNGSI Ketelusan perkhidmatandalam pemantauan statusprojek secara on-line
FAEDAH Pengguna dapat membuat
semakan status bekalansecara on-line
SEMAK BEKALAN SECARA ONLINE
O C G
http://www.tnb.com.my/http://www.tnb.com.my/http://www.tnb.com.my/ -
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
24/30
POWERING THE NATION 24
Keperluan Pra-Rundingan
Setiap perancangan projek amat digalakkan membuat pra-
rundingan sebelum dokumen tender dibuat
Memastikan keperluan pencawang dan tahap voltan bekalan yang
akan diberi adalah mengikut panduan TNB yang terkini
Pematuhan senarai semak permohonan bekalan
Permohonan yang lengkap adalah diperlukan sebelum
permohonan bekalan elektrik diproses mengikut jangka masa
lazim. Pihak TNB akan memastikan pelan-pelan yang dimajukan
diperakukan mengikut panduan TNB yang terkini
WAY FORWARDPERANCANGAN
PROJEK
WAY FORWARD PERANCANGAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
25/30
POWERING THE NATION 25
Izinlalu dalam kawasan persendirian
Pepasangan yang dipasang dalam kawasan/jalan persendirian
perlu bersetuju dengan perjanjian izinlalu bagi memastikan akses
untuk operasi TNB apabila diperlukan
Dokumen Tapak Pencawang
Perlu dimajukan sebelum Caj Sambungan Pengguna dikeluarkan
Jaminan RM 20,000 setiap pencawang dikecualikan
Borang Pindahmilik/Pajakan Tapak Pencawang
Warta Tanah Kerajaan pada lot asal pembangunan
Pelan Pra-hitungan bagi setiap tapak pencawang elektrik
WAY FORWARDPERANCANGAN
PROJEK
WAY FORWARD PERANCANGAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
26/30
POWERING THE NATION 26
Pembayaran Caj Sambungan Pengguna (CSP)
CSP perlu dibayar segera supaya unit Pembinaan TNB boleh
memulakan proses kertas kerja pembinaan dan kerja-kerja tapak
Mempunyai tempoh sah laku 6 bulan dan sekiranya lewat, CSP
dibatalkan.
Pemantauan status
Ada pegawai pemantau tetap bagi setiap kementerian/agensi
kerajaan supaya pihak TNB boleh memantau secara terus projek-
projek secara bulanan supaya sebarang kemajuan/halangan dapat
dikemaskini dan diambil tindakan segera oleh kedua pihak
WAY FORWARDPERANCANGAN
PROJEK
WAY FORWARD PEMANTAUAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
27/30
POWERING THE NATION 27
Permohonan Permit
Jurutera Perunding Elektrik perlulah menguruskan permohonan
kebenaran izinlalu laluan kabel (pemotongan terbuka, HDD,
korekan atas jalan, korekan atas tanah) daripada Pihak Berkuasa
Tempatan (PBT) termasuk JKR (Jabatan Kerja Raya), KTM (Keretapi
Tanah Melayu), LLM (Lembaga Lebuhraya Malaysia) dan PGN
(Perbadanan Gas Negara) dan lain-lain serta menguruskan
pembayaran kos-kos yang dikenakan oleh pihak PBT bagi
membolehkan pihak TNB memulakan kerja rentangan kabel.
WAY FORWARDPEMANTAUAN
PEMBINAAN
WAY FORWARD PEMANTAUAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
28/30
POWERING THE NATION 28
Pemantauan status Kemaskini status kemajuan/halangan projek berkala dengan
tindakan seterusnya
Pematuhan bangunan pencawang dan penyediaanpepasangan
Kontraktor perlu memastikan bangunan dan infrastruktur
pepasangan TNB adalah mengikut pelan-pelan yang telah
diluluskan kepada perunding elektrikal (susunatur perparitan
kabel, penyediaan paip, jenis MSB / panel meter)
Isu kerap berbangkit apabila kontraktor membina mengikut
dokumen tender dan bukannya mengikut pelan-pelan diluluskan
TNB
WAY FORWARDPEMANTAUAN
PEMBINAAN
WAY FORWARD PEMANTAUAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
29/30
POWERING THE NATION 29
Pembayaran Deposit
Kenalpasti pembayar bil kerana akaun yang dinamakan atas
agensi/badan kerajaan adalah dikecualikan deposit.
Kelewatan pembayaran bagi akaun-akaun terlibat akan
melewatkan pemasangan meter
WAY FORWARDPEMANTAUAN
PEMBINAAN
-
7/26/2019 KWP - Keperluan Permohonan Bekalan Elekrik Dan Pemantauan Projek TNB
30/30