NSTX-U Construction
Erik Perry
Princeton Plasma Physics Laboratory
NSTX Upgrade Readiness to Operate Review
LSB B318December 9-11, 2014
NSTX-UNSTX-U Supported by
Culham Sci CtrYork U
Chubu UFukui U
Hiroshima UHyogo UKyoto U
Kyushu UKyushu Tokai U
NIFSNiigata UU Tokyo
JAEAInst for Nucl Res, Kiev
Ioffe InstTRINITI
Chonbuk Natl UNFRI
KAISTPOSTECH
Seoul Natl UASIPP
CIEMATFOM Inst DIFFER
ENEA, FrascatiCEA, Cadarache
IPP, JülichIPP, Garching
ASCR, Czech Rep
Coll of Wm & MaryColumbia UCompXGeneral AtomicsFIUINLJohns Hopkins ULANLLLNLLodestarMITLehigh UNova PhotonicsOld DominionORNLPPPLPrinceton UPurdue USNLThink Tank, Inc.UC DavisUC IrvineUCLAUCSDU ColoradoU IllinoisU MarylandU RochesterU TennesseeU TulsaU WashingtonU WisconsinX Science LLC
Content
• Outage Planning
• Outage Coordination
• Work Control Center
• Outage Adjustments
• Installation Risks and Mitigations
• Work Completed
• Remaining Work
Outage Planning• Outage planning was based on bottoms-up
estimates from Engineering
• Assigned technicians, by name, to critical scope to assure staffing requirements were met
• Adjusted start dates of tasks to assure tasks in the same area were compatible
• Accelerated tasks that made other tasks safer or more efficient
• Worked crews on opposite sides and two shifts
• Daily / hourly coordination was critical
Outage Coordination• Used Work Control Center (like TFTR D&D
Project) to oversee and coordinate all activities in the NSTX Test Cell
• All work in the NSTX Test Cell done with Engineering Work Packages (EWPs)
• EWPs included– Detailed procedure
– Job Hazard Analysis
– Permits required to perform the work
– Drawings required to perform the work
Work Control Center• Work Control Center reviewed all EWPs for the
field– Reviewed removal/installation procedures
– Reviewed Job Hazard Analysis (JHA)
– Attended pre-job and post-job briefs
– Interfaced between Engineering and the field crews
– Assured that the field work was done safely and correctly
– Assured the field crews were used efficiently
EWP Status• 248 Engineering Work Packages (EWPs) since
the start of the NSTX-U Outage
• 167 of these EWPs were for upgrade scope
• Of the upgrade scope EWPs there are 20 that still have work to be done
• There are 28 Operations EWPs that still have work to be done
• All closed-out EWPs are in the Ops Center
Outage Adjustments• Daily Plan-of-the-day meetings coordinated
activities between crews and fine tuned technician assignments– Included field crew leaders, QA, Industrial Hygiene, Health
Physics, DOE
• Twice a week meetings of the Work Control Center reviewed priorities, EWPs and hardware
• Flexibility for adjustments came from– Second shift work
– Multiple crews working on opposite sides
– Having many EWPs ready for field work
Installation Risks and Mitigations• Delays in getting parts delivered to field crews
– Facilitated parts fabrication
– Re-scheduled work sequence
– Scheduled work on two shifts once parts arrived
• Scope creep– Engineering Change Proposal process
– Review of engineering estimates by division heads (WAF review)
Work Completed
October 2011 October 2011
January 2012 April 2012
Work Completed
Work Completed
Work Completed
Work Completed
July 2013
Work Completed
Remaining Work• Install bus inside and outside of umbrellas
• Install gas injection inside umbrella structure
• Install kapton/G10 flash shields on centerstack
• Install TF flex bus and TF lead extensions
Remaining Work cont.
• Field measure space from lead extensions to TF outer leg flags
• Fabricate 72 custom TF flag links
• Install TF flag supports
• Install umbrella lid support rings
• Install new umbrella lids
• All remaining work is understood and is progressing well
Summary• The Upgrade Outage has been planned based
on– Bottoms-up estimates from Engineering
– Scheduling work to maximize safety / efficiency
• The plan is being continually worked– To deal with delays in getting parts
– To accelerate tasks to make full use of resources
• The remaining work is understood and is progressing well
Summary cont.
• Coordination and Control– Provided by the Work Control Center
– At the Plan-of-the-day meeting
– Continuously by the Field Supervisors
• Successfully performing the outage– Will turn over NSTX to Operations at the completion of procedure
OP-NSTX-01: Preparation of Experimental Areas for Operations