![Page 1: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/1.jpg)
Sustainable
Construction -
Oman Botanic
Garden Phase 2
Simon Buttery – RMD
Carillion Alawi LLC
![Page 2: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/2.jpg)
Carillion Alawi LLC• As a business we have been present within the Sultanate of Oman for over 45 years and are a wholly owned subsidiary of our UK parent Carillion PLC a £5BN turnover international construction services business
• Today we specialise in:– Civil Engineering
– Building
– High quality joinery (we have Oman’s 1st FSC accredited joinery workshop)
– MEP
![Page 3: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/3.jpg)
Carillion Alawi Values
![Page 4: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/4.jpg)
Sustainability – Our Approach‘meeting the needs of the present generation without
compromising the ability for future generations to meet
their needs’
![Page 5: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/5.jpg)
Project Details
• Client: Muscat Municipality
• Project Value: circa O.R. 19,500,00
• Start Date: 07/04/09
• Completion Date: 31/12/10
• Project Manager: Bovis Lend Lease
• Main Contractor: Carillion Alawi LLC
• 1st LEED Accredited project within the Sultanate of Oman
![Page 6: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/6.jpg)
Mission
“The Oman Botanic Garden, as a new world class
botanic garden, conserves the unique botanical
and ethnobotanical heritage of Oman and ensures
that the flora, heritage and ecosystems of Oman
are valued by all”
![Page 7: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/7.jpg)
Sustainability: Our Key Themes for the Project
• Collaborative working
• Awareness
• Recycling
• Water usage
• Community engagement
• Monitoring
• Adoption of best practices
![Page 8: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/8.jpg)
Collaborative Working
• Partnership
established with
Project Manager
• Learning from wider
Carillion Businesses
Implemented
• Sustainable
Innovations Group
![Page 9: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/9.jpg)
Awareness
• Regular awareness
training and feedback
sessions
• Environmental “Don’t
Walk By’s”
• LEED Training
![Page 10: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/10.jpg)
Recycling• We currently recycle
– Timber
– Paper
– Cardboard
– Plastic PET
– Aluminium
– Steel
– Concrete
– Glass
– Areca leaf plates
![Page 11: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/11.jpg)
Water Usage
• Use of new curing
membranes to reduce
water
• Flow restrictors to
taps
• None potable water
used for dust control
![Page 12: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/12.jpg)
Community Engagement• Construction of new access stair to local school
• Sponsorship of local football team
• Facilitation of school visits to site
• Provision of furniture to local special needs school
![Page 13: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/13.jpg)
Monitoring
• Background environmental monitoring program to establish ambient values for the following:– Noise
– Dust
– Air Quality
• An ongoing monitoring program has been developed to ensure levels during construction meet prescribed limits and do not impact the environment or local community.
![Page 14: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/14.jpg)
Adoption of Best Practice
• On site crushing of
concrete waste mixed
with soil to use as
backfill behind
retaining walls
• Use of filter fences to
protect wadis from
run off and
sedimentation
![Page 15: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/15.jpg)
Adoption of Best Practice
• Use of Areca plates
for serving operatives
food reduces food,
water consumption
and waste
• Protection and
preservation of
existing trees and
vegetation
![Page 16: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/16.jpg)
Adoption of Best Practice
• Vegetation removed
chipped and turned
into compost
• Coir rope used for
walk ways instead of
nylon rope with plastic
tape
![Page 17: Sustainable Construction - Oman Botanic Garden … Buttery...Sustainable Construction - Oman Botanic Garden Phase 2 Simon Buttery –RMD Carillion Alawi LLC Carillion Alawi LLC •](https://reader030.vdocuments.pub/reader030/viewer/2022021421/5aa0b5177f8b9a89178e70af/html5/thumbnails/17.jpg)
It Does Make A Difference!
• 18mm ply wood usage on target against
tight tender allowance
• Back fill material usage against tender
allowance circa 40% cost saving