7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
1/54
Pasangan DPT Sebelum BC 1 Sebelah Kanan
b h
1 A : 0.50 x 3.50 = 1.75
B : 1.75 x 1.25 = 2.19
C : 2.00 x 1.50 = 3.00
: 6.94
V : 6.94 x 9.30 = 64.52
b h
2 A : 0.50 x 4.00 = 2.00
B : 2.00 x 1.50 = 3.00
C : 2.25 1.50 = 3.38
: 8.38
V : 8.38 x 5.00 = 41.88
b h
3 A : 0.50 x 4.50 = 2.25
B : 2.25 x 1.75 = 3.94
C : 2.50 1.50 = 3.75
: 9.94
V : 9.94 x 6.70 = 66.58
b h
4 A : 0.50 x 5.00 = 2.50B : 2.50 x 2.25 = 5.63
C : 3.00 1.50 = 4.50
: 12.63
V : 12.63 x 5.50 = 69.44
b h
5 A : 0.50 x 5.50 = 2.75
B : 2.75 x 2.25 = 6.19
C : 3.00 1.50 = 4.50
: 13.44V : 13.44 x 7.80 = 104.81
b h
6 A : 0.50 x 5.50 = 2.75
B : 2.75 x 2.25 = 6.19
C : 3.00 1.50 = 4.50
: 13.44
V : 13.44 x 8.10 = 108.84
b h
7 A : 0.50 x 5.50 = 2.75
B : 2.75 x 2.75 = 7.56
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
2/54
C : 3.50 1.50 = 5.25
: 15.56
V : 15.56 x 8.10 = 126.06
b h
8 A : 0.50 x 5.50 = 2.75
B : 2.75 x 2.75 = 7.56
C : 3.50 1.50 = 5.25
: 15.56
V : 15.56 x 0.70 = 10.89
Toal Volume Pasangan DPT Sebelum BC 1 Sebelah Kanan 593.02
Pasangan DPT Sebelum BC 1 Sebelah K!"!
b h
1 A : 0.50 x 3.50 = 1.75
B : 1.75 x 1.25 = 2.19
C : 2.00 x 1.50 = 3.00
: 6.94
V : 6.94 x 6.00 = 41.63
b h
2 A : 0.50 x 4.50 = 2.25B : 2.25 x 2.25 = 5.06
C : 3.00 x 1.50 = 4.50
: 11.81
V : 11.81 x 31.40 = 370.91
Toal Volume Pasangan DPT Sebelum BC 1 Sebelah K!"! 412.54
Pasangan DPT Seelah BC 1 Sebelah Kanan
b h
1 A : 0.50 x 3.50 = 1.75
B : 1.75 x 1.25 = 2.19
C : 2.00 x 1.50 = 3.00
: 6.94
V : 6.94 x 14.50 = 100.59
Toal Volume Pasangan DPT Seelah BC 1 Sebelah Kanan 100.59
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
3/54
Pasangan DPT Seelah BC 1 Sebelah K!"!
b h
1 A : 0.50 x 3.50 = 1.75
B : 1.75 x 1.25 = 2.19
C : 2.00 x 1.50 = 3.00
: 6.94
V : 6.94 x 15.00 = 104.06
Toal Volume Pasangan DPT Seelah BC 1 Sebelah K!"! 104.06
Pasangan Sa#a$ BC 1 Sebelah Kanan
b h
1 A : 0.45 x 1.75 = 0.79
B : 0.88 x 0.80 = 0.70
C : 1.25 x 0.75 = 0.94
: 2.43
V : 2.43 x 4.00 = 9.70
b h
2 A : 0.45 x 1.75 = 0.79
B : 0.88 x 0.80 = 0.70
C : 1.25 x 0.75 = 0.94 : 2.43
V : 2.43 x 0.80 = 1.94
b h
3 A : 0.45 x 1.75 = 0.79
B : 0.88 x 0.80 = 0.70
C : 1.25 x 0.75 = 0.94
: 2.43
V : 2.43 x 0.80 = 1.94
b h
1% A : 0.45 x 1.75 = 0.79
B : 0.88 x 0.80 = 0.70
C : 1.25 x 0.75 = 0.94
: 2.43
V : 2.43 x 4.25 = 10.31
b h
2% A : 0.45 x 1.75 = 0.79
B : 0.88 x 0.80 = 0.70
C : 1.25 x 0.75 = 0.94
: 2.43
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
4/54
V : 2.43 x 0.45 = 1.09
Toal Volume Pasangan Sa#a$ BC 1 Sebelah Kanan 24.98
Pasangan Sa#a$ BC 1 Sebelah K!"!
b h
& A : 0.50 x 1.25 = 0.63
B : 0.63 x 0.75 = 0.47
C : 1.25 x 0.75 = 0.94
: 2.03
V : 2.03 x 5.14 = 10.44
b h
B A : 0.50 x 1.25 = 0.63
B : 0.63 x 0.75 = 0.47
C : 1.25 x 0.75 = 0.94
: 2.03
V : 2.03 x 1.20 = 2.44
b h
&% A : 0.50 x 1.25 = 0.63
B : 0.63 x 0.75 = 0.47
C : 1.25 x 0.75 = 0.94 : 2.03
V : 2.03 x 5.25 = 10.66
b h
B% A : 0.50 x 1.25 = 0.63
B : 0.63 x 0.75 = 0.47
C : 1.25 x 0.75 = 0.94
: 2.03
V : 2.03 x 1.65 = 3.35
Toal Volume Pasangan Sa#a$ BC 1 Sebelah K!"! 26.89
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
5/54
Pasangan &ansam$!ng DPT Sebelum BC 1
b l
1 2.00 x 9.30 =
18.60 x 0.20 =
m2 b l
m3 2 2.25 x 5.00 =
11.25 x 0.20 =
b l
3 2.50 x 6.70 =
16.75 x 0.20 =
m2
m3 b l
4 3.00 x 5.50 =
16.50 x 0.20 =
b l
5 3.00 x 7.80 =
m2 23.40 x 0.20 =
m3
b l
6 3.00 x 8.10 =
24.30 x 0.20 =
b l
m2 7 3.50 x 8.10 =
m3 28.35 x 0.20 =
b l
8 3.50 x 0.70 =
2.45 x 0.20 =
m2m3 Toal Volume Pasangan &ansam$!ng
m2
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
6/54
m2
m3
m2
m3
m3
Pasangan &ansam$!ng DPT Sebelum BC
b l
1 2.00 x 6.00 =
12.00 x 0.20 =
m2 b l
m3 2 3.00 x 31.40 =
94.20 x 0.20 =
Toal Volume Pasangan &ansam$!ng
m2
m3
m2
Pasangan &ansam$!ng DPT Sebelum BC 1
b l
1 2.00 x 14.50 =
29.00 x 0.20 =
m2
m3 Toal Volume Pasangan &ansam$!ng
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
7/54
Pasangan &ansam$!ng DPT Seelah BC 1
b l
1 2.00 x 15.00 =
30.00 x 0.20 =
m2
m3 Toal Volume Pasangan &ansam$!ng
m3
Pasangan &ansam$!ng Pasangan Sa#a$ BC
b l
1 1.25 x 4.00 =
5.00 x 0.20 =
m2 b l
m3 2 1.25 x 0.80 =
1.00 x 0.20 =
b l
3 1.25 x 0.80 =
1.00 x 0.20 =m2
m3 b l
1% 1.25 x 4.25 =
5.31 x 0.20 =
b l
2% 1.25 x 0.45 =
m2 0.56 x 0.20 =
m3
Toal Volume Pasangan &ansam$!ng
m2
m3
m2
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
8/54
m3
m3
Pasangan &ansam$!ng Pasangan Sa#a$ BC
b l
& 1.25 x 5.14 =
6.43 x 0.20 =
m2 b l
m3 B 1.25 x 1.20 =
1.50 x 0.20 =
b l
&% 1.25 x 5.25 =
6.56 x 0.20 =
m2
m3 b l
B% 1.25 x 1.65 =
2.06 x 0.20 =
Toal Volume Pasangan &ansam$!ngm2
m3
m2
m3
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
9/54
ebelah Kanan '"ugan Pas!" DPT Sebelum B
b l
18.60 m2 1 2.00 x 9.30
3.72 m3 18.60 x 0.10
b l
11.25 m2 2 2.25 x 5.00
2.25 m3 11.25 x 0.10
b l
16.75 m2 3 2.50 x 6.70
3.35 m3 16.75 x 0.10
b l
16.50 m2 4 3.00 x 5.50
3.30 m3 16.50 x 0.10
b l
23.40 m2 5 3.00 x 7.80
4.68 m3 23.40 x 0.10
b l
24.30 m2 6 3.00 x 8.10
4.86 m3 24.30 x 0.10
b l
28.35 m2 7 3.50 x 8.10
5.67 m3 28.35 x 0.10
b l
2.45 m2 8 3.50 x 0.70
0.49 m3 2.45 x 0.10
28.32 m3 Toal Volume '"u
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
10/54
Sebelah K!"! '"ugan Pas!" DPT Sebelum
b l
12.00 m2 1 2.00 x 6.00
2.40 m3 12.00 x 0.10
b l
94.20 m2 2 3.00 x 31.40
18.84 m3 94.20 x 0.10
21.24 m3 Toal Volume '"u
ebelah Kanan '"ugan Pas!" DPT Sebelum B
b l
29.00 m2 1 2.00 x 14.50
5.80 m3 29.00 x 0.10
5.80 m3 Toal Volume '"u
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
11/54
Sebelah K!"! '"ugan Pas!" DPT Seelah
b l
30.00 m2 1 2.00 x 15.00
6.00 m3 30.00 x 0.10
6.00 m3 Toal Volume '"u
Sebelah Kanan '"ugan Pas!" Pasangan Sa#a$
b l
5.00 m2 1 1.25 x 4.00
1.00 m3 5.00 x 0.10
b l
1.00 m2 2 1.25 x 0.80
0.20 m3 1.00 x 0.10
b l
1.00 m2 3 1.25 x 0.80
0.20 m3 1.00 x 0.10
b l
5.31 m2 1% 1.25 x 4.25
1.06 m3 5.31 x 0.10
b l
0.56 m2 2% 1.25 x 0.45
0.11 m3 0.56 x 0.10
2.58 m3 Toal Volume '"u
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
12/54
1 Sebelah K!"! '"ugan Pas!" Pasangan Sa#a
b l
6.43 m2 & 1.25 x 5.14
1.29 m3 6.43 x 0.10
b l
1.50 m2 B 1.25 x 1.20
0.30 m3 1.50 x 0.10
b l
6.56 m2 &% 1.25 x 5.25
1.31 m3 6.56 x 0.10
b l
2.06 m2 B% 1.25 x 1.65
0.41 m3 2.06 x 0.10
3.31 m3 Toal Volume '"u
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
13/54
C 1 Sebelah Kanan
= 18.60 m2
= 1.86 m3
= 11.25 m2
= 1.13 m3
= 16.75 m2
= 1.68 m3
= 16.50 m2
= 1.65 m3
= 23.40 m2
= 2.34 m3
= 24.30 m2
= 2.43 m3
= 28.35 m2
= 2.84 m3
= 2.45 m2
= 0.25 m3
gan Pas!" 14.16 m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
14/54
BC 1 Sebelah K!"!
= 12.00 m2
= 1.20 m3
= 94.20 m2
= 9.42 m3
gan Pas!" 10.62 m3
C 1 Sebelah Kanan
= 29.00 m2
= 2.90 m3
gan Pas!" 2.90 m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
15/54
C 1 Sebelah K!"!
= 30.00 m2
= 3.00 m3
gan Pas!" 3.00 m3
BC 1 Sebelah Kanan
= 5.00 m2
= 0.50 m3
= 1.00 m2
= 0.10 m3
= 1.00 m2
= 0.10 m3
= 5.31 m2
= 0.53 m3
= 0.56 m2
= 0.06 m3
gan Pas!" 1.29 m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
16/54
$ BC 1 Sebelah K!"!
= 6.43 m2
= 0.64 m3
= 1.50 m2
= 0.15 m3
= 6.56 m2
= 0.66 m3
= 2.06 m2
= 0.21 m3
gan Pas!" 1.66 m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
17/54
Pasangan DPT Sebelum BC 2
b h
1 A : 0.90 x 4.45 = 4.01
B : 2.23 x 1.35 = 3.00
C : 2.50 x 1.25 = 3.13
: 10.13
V : 10.13 x 22.35 = 226.49
b h
2 A : 0.90 x 4.45 = 4.01
B : 2.23 x 1.35 = 3.00
C : 2.50 1.25 = 3.13
: 10.13
V : 10.13 x 20.00 = 202.68
Toal Volume Pasangan DPT Sebelum BC 2 429.16
Pasangan DPT Sesu(ah BC 2
b h
1% A : 0.60 x 4.75 = 2.85
B : 2.38 x 1.65 = 3.92C : 2.50 x 1.25 = 3.13
: 9.89
V : 9.89 x 16.85 = 166.71
b h
2% A : 0.60 x 4.75 = 2.85
B : 2.38 x 1.65 = 3.92
C : 2.50 1.25 = 3.13
: 9.89
V : 9.89 x 16.25 = 160.77
Toal Volume Pasangan DPT Sesu(ah BC 2 327.48
Pasangan DPT Sa#a$ Kanan BC 2
b h
& A : 0.55 x 2.25 = 1.24
B : 1.13 x 0.70 = 0.79
C : 1.50 x 1.00 = 1.50
: 3.53
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
18/54
V : 3.53 x 5.90 = 20.80
b h
B A : 0.55 x 2.25 = 1.24
B : 1.13 x 0.70 = 0.79
C : 1.50 x 1.00 = 1.50
: 3.53
V : 3.53 x 1.55 = 5.46
b h
&% A : 0.55 x 2.25 = 1.24
B : 1.13 x 0.70 = 0.79
C : 1.50 x 1.00 = 1.50
: 3.53
V : 3.53 x 5.00 = 17.63
b h
B% A : 0.55 x 2.25 = 1.24
B : 1.13 x 0.70 = 0.79
C : 1.50 x 1.00 = 1.50
: 3.53
V : 3.53 x 3.00 = 10.58
Toal Volume Pasangan DPT Sa#a$ Kanan BC 2 54.46
Pasangan DPT Sa#a$ K!"! BC 2
b h
& A : 0.55 x 2.25 = 1.24
B : 1.13 x 0.70 = 0.79
C : 1.50 x 1.00 = 1.50
: 3.53
V : 3.53 x 4.90 = 17.27
b h
B A : 0.55 x 2.25 = 1.24
B : 1.13 x 0.70 = 0.79
C : 1.50 x 1.00 = 1.50
: 3.53
V : 3.53 x 2.25 = 7.93
b h
&% A : 0.55 x 2.25 = 1.24
B : 1.13 x 0.70 = 0.79
C : 1.50 x 1.00 = 1.50
: 3.53
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
19/54
V : 3.53 x 2.65 = 9.34
b h
B% A : 0.55 x 2.25 = 1.24
B : 1.13 x 0.70 = 0.79
C : 1.50 x 1.00 = 1.50
: 3.53
V : 3.53 x 4.55 = 16.04
b h
C% A : 0.55 x 2.25 = 1.24
B : 1.13 x 0.70 = 0.79
C : 1.50 x 1.00 = 1.50
: 3.53
V : 3.53 x 0.95 = 3.35
Toal Volume Pasangan DPT Sa#a$ K!"! BC 2 53.93
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
20/54
Pasangan &ansam$!ng Pasangan DPT S
b l
1 2.50 x 22.35 =
55.88 x 0.20 =
m2 b l
m3 2 2.50 x 20.00 =
50.00 x 0.20 =
Toal Volume Pasangan &ansam$!ng
m2
m3
m3
Pasangan &ansam$!ng Pasangan DPT S
b l
1% 2.50 x 16.85 =
42.13 x 0.20 =
m2 b l
m3 2% 2.50 x 16.25 =
40.63 x 0.20 =
Toal Volume Pasangan &ansam$!ng
m2
m3
m3
Pasangan &ansam$!ng Pasangan DPT Sa#
b l
& 1.50 x 5.90 =8.85 x 0.20 =
m2
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
21/54
m3 b l
B 1.50 x 1.55 =
2.33 x 0.20 =
b l
&% 1.50 x 5.00 =
m2 7.50 x 0.20 =
m3
b l
B% 1.50 x 3.00 =
4.50 x 0.20 =
m2 Toal Volume Pasangan &ansam$!ng
m3
m2
m3
m3
Pasangan &ansam$!ng Pasangan DPT Sa
b l
& 1.50 x 4.90 =
7.35 x 0.20 =
m2 b l
m3 B 1.50 x 2.25 =
3.38 x 0.20 =
b l
&% 1.50 x 2.65 =
3.98 x 0.20 =
m2
m3 b l
B% 1.50 x 4.55 =
6.83 x 0.20 =
b l
C% 1.50 x 0.95 =
m2 1.43 x 0.20 =
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
22/54
m3
Toal Volume Pasangan &ansam$!ng
m2
m3
m2
m3
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
23/54
belum BC 2 '"ugan Pas!" Pasangan D
b l
55.88 m2 1 2.50 x 22.35
11.18 m3 55.88 x 0.10
b l
50.00 m2 2 2.50 x 20.00
10.00 m3 50.00 x 0.10
21.18 m3 Toal Volume '"u
su(ah BC 2 '"ugan Pas!" Pasangan D
b l
42.13 m2 1% 2.50 x 16.85
8.43 m3 42.13 x 0.10
b l
40.63 m2 2% 2.50 x 16.25
8.13 m3 40.63 x 0.10
16.55 m3 Toal Volume '"u
$ Kanan BC 2 '"ugan Pas!" Pasangan DPT
b l
8.85 m2 & 1.50 x 5.901.77 m3 8.85 x 0.10
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
24/54
b l
2.33 m2 B 1.50 x 1.55
0.47 m3 2.33 x 0.10
b l
7.50 m2 &% 1.50 x 5.00
1.50 m3 7.50 x 0.10
b l
4.50 m2 B% 1.50 x 3.00
0.90 m3 4.50 x 0.10
4.64 m3 Toal Volume '"u
a$ K!"! BC 2 '"ugan Pas!" Pasangan DP
b l
7.35 m2 & 1.50 x 4.90
1.47 m3 7.35 x 0.10
b l
3.38 m2 B 1.50 x 2.25
0.68 m3 3.38 x 0.10
b l
3.98 m2 &% 1.50 x 2.65
0.80 m3 3.98 x 0.10
b l
6.83 m2 B% 1.50 x 4.55
1.37 m3 6.83 x 0.10
b l
1.43 m2 C% 1.50 x 0.95
0.29 m3 1.43 x 0.10
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
25/54
4.59 m3 Toal Volume '"u
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
26/54
T Sebelum BC 2
= 55.88 m2
= 5.59 m3
= 50.00 m2
= 5.00 m3
gan Pas!" 10.59 m3
T Sesu(ah BC 2
= 42.13 m2
= 4.21 m3
= 40.63 m2
= 4.06 m3
gan Pas!" 8.28 m3
Sa#a$ Kanan BC 2
= 8.85 m2= 0.89 m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
27/54
= 2.33 m2
= 0.23 m3
= 7.50 m2
= 0.75 m3
= 4.50 m2
= 0.45 m3
gan Pas!" 2.32 m3
Sa#a$ K!"! BC 2
= 7.35 m2
= 0.74 m3
= 3.38 m2
= 0.34 m3
= 3.98 m2
= 0.40 m3
= 6.83 m2
= 0.68 m3
= 1.43 m2
= 0.14 m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
28/54
gan Pas!" 2.30 m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
29/54
Pasangan Salu"an D"a!nase Ke Bo) Cul*e" 2
b h
1 A : 0.30 x 1.25 = 0.38
B : 0.30 x 1.25 = 0.38
C : 0.63 x 0.10 = 0.06
D : 0.63 x 0.10 = 0.06
E : 0.40 x 0.20 = 0.08
: 0.96
V : 0.96 x 48.30 = 46.13
Toal Volume Pasangan Salu"an D"a!nase Ke Bo) Cul*e" 2 46.13
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
30/54
asangan &ansam$!ng Pasangan Salu"an D"a!n
b l
1 1.50 x 48.30 =
72.45 x 0.20 =
Toal Volume Pasangan &ansam$!ng
m2
m3
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
31/54
se Ke Bo) Cul*e" '"ugan Pas!" Pasangan Salu"an D
b l
72.45 m2 1 1.50 x 48.30
14.49 m3 72.45 x 0.10
14.49 m3 Toal Volume '"u
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
32/54
a!nase Ke Bo) Cul*e" 2
= 72.45 m2
= 7.25 m3
gan Pas!" 7.25 m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
33/54
Pasangan Sa#a$ Bo) Cul*e" 3 Sebelah K!"!
b h
1 A : 0.40 x 0.80 = 0.32
B : 0.40 x 0.80 = 0.32
C : 2.00 x 0.50 = 1.00
: 1.64
V : 1.64 x 3.20 = 5.25
b h
2 A : 0.45 x 1.20 = 0.54
B : 0.60 x 0.60 = 0.36
C : 1.05 x 0.60 = 0.63
: 1.53
V : 1.53 x 6.00 = 9.18
b h
3 A : 0.60 x 0.90 = 0.54
: 0.54
V : 0.54 x 3.40 = 1.84
b h
4 A : 0.45 x 1.20 = 0.54
B : 0.60 x 0.60 = 0.36
C : 1.05 x 0.60 = 0.63
: 1.53V : 1.53 x 9.60 = 14.69
Toal Volume Pasangan Sa#a$ Bo) Cul*e" 3 Sebelah K!"! 30.95
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
34/54
Pasangan &ansam$!ng Pasangan DPT Sa#
b l
1 2.00 x 3.20 =
6.40 x 0.20 =
m2 b l
m3 2 0.60 x 6.00 =
3.60 x 0.20 =
b l
3 0.60 x 3.40 =
2.04 x 0.20 =
m2
m3 b l
4 1.05 x 9.60 =
10.08 x 0.20 =
m2
m3 Toal Volume Pasangan &ansam$!ng
m2m3
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
35/54
$ Kanan BC 2 '"ugan Pas!" Pasangan DPT
b l
6.40 m2 1 2.00 x 3.20
1.28 m3 6.40 x 0.10
b l
3.60 m2 2 0.60 x 6.00
0.72 m3 3.60 x 0.10
b l
2.04 m2 3 0.60 x 3.40
0.41 m3 2.04 x 0.10
b l
10.08 m2 4 1.05 x 9.60
2.02 m3 10.08 x 0.10
4.42 m3 Toal Volume '"u
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
36/54
Sa#a$ Kanan BC 2
= 6.40 m2
= 0.64 m3
= 3.60 m2
= 0.36 m3
= 2.04 m2
= 0.20 m3
= 10.08 m2
= 1.01 m3
gan Pas!" 2.21 m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
37/54
Salu"an D"a!nase Ke Bo) Cul*e" 3
b h
1 A : 0.30 x 0.60 = 0.18
B : 0.20 x 0.60 = 0.12
C : 1.10 x 0.20 = 0.22
: 0.52
V : 0.52 x 84.90 = 44.15
b h
2 A : 0.30 x 0.60 = 0.18
B : 0.90 x 0.20 = 0.18
: 0.36
V : 0.36 x 13.50 = 4.86
Toal Volume Salu"an D"a!nase Ke Bo) Cul*e" 3 49.01
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
38/54
m2
m3
m2
m3
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
39/54
Pasangan DPT Sa. 4+212
b h
1 A : 0.30 x 1.40 = 0.42
B : 0.70 x 0.40 = 0.28
: 0.70
V : 0.70 x 53.16 = 37.21
Toal Volume Pasangan DPT Sa. 4+212 37.21
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
40/54
Pasangan &ansam$!ng Pasangan DPT
b l
1 0.70 x 53.16 =
37.21 x 0.20 =
m2
m3
Toal Volume Pasangan &ansam$!ng
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
41/54
a. 4+212 '"ugan Pas!" Pasangan
b l
37.21 m2 1 0.70 x 53.16
7.44 m3 37.21 x 0.10
7.44 m3 Toal Volume '"u
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
42/54
PT Sa. 4+212
= 37.21 m2
= 3.72 m3
gan Pas!" 3.72 m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
43/54
Pasangan DPT Pe"em$aan ,an-asengang
b h
1 A : 0.30 x 0.80 = 0.24
: 0.24
V : 0.24 x 13.00 = 3.12
b h
2 A : 0.30 x 0.65 = 0.20
: 0.20
V : 0.20 x 8.00 = 1.56
Toal Volume Pasangan DPT Pe"em$aan ,an-asengang 4.68
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
44/54
m2
m3
m2
m3
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
45/54
Salu"an D"a!nase Ke Pla Du!-e" Sa. 4+400
b h
1 A : 0.30 x 0.60 = 0.18
B : 0.30 x 0.60 = 0.18
C : 1.15 x 0.20 = 0.23
: 0.59
V : 0.59 x 34.00 = 20.06
Toal Volume Salu"an D"a!nase Ke Pla Du!-e" Sa. 4+400 20.06
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
46/54
m2
m3
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
47/54
Pasangan Salu"an D"a!nase /aa &!" 'ung om!)
b h
1 A : 0.40 x 0.80 = 0.32
B : 0.40 x 0.15 = 0.06
C : 0.40 x 0.80 = 0.32
D : 0.40 x 0.80 = 0.32
E : 1.50 x 0.20 = 0.30
: 1.32
V : 1.32 x 59.50 = 78.54
Toal Volume Pasangan Salu"an D"a!nase /aa &!" 78.54
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
48/54
m2
m3
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
49/54
Pasangan DPT Sebelum ,eloas! Sunga!
b h
1 A : x = -
B : x = -
C : x = -
:
V : - x 11.50 =
b h
2 A : x = -
B : x = -
C : x = -
:
V : - x 12.50 =
Toal Volume Pasangan DPT Sebelum ,eloas! Sunga!
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
50/54
m2
m3
m2
m3
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
51/54
Pasangan DPT C!unen
b h
1 A : 0.60 x 3.50 = 2.10
B : 1.75 x 0.90 = 1.58
C : 1.75 x 1.00 = 1.75
: 5.43
V : 5.43 x 45.00 = 244.13
b h
2 A : 0.60 x 3.50 = 2.10
B : 1.75 x 0.65 = 1.14
C : 1.50 x 1.00 = 1.50
: 4.74
V : 4.74 x 21.00 = 99.49
b h
3 A : 0.60 x 2.50 = 1.50
B : 1.25 x 0.40 = 0.50
C : 1.25 x 1.00 = 1.25
: 3.25
V : 3.25 x 24.00 = 78.00
b h
4 A : 0.60 x 2.00 = 1.20B : 1.00 x 0.15 = 0.15
C : 1.00 x 0.75 = 0.75
: 2.10
V : 2.10 x 21.00 = 44.10
Toal Volume Pasangan DPT C!unen 465.71
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
52/54
Pasangan &ansam$!ng Pasangan DPT
b l
& 1.75 x 45.00 =
78.75 x 0.20 =
m2 b l
m3 B 1.50 x 21.00 =
31.50 x 0.20 =
b l
&% 1.25 x 24.00 =
30.00 x 0.20 =
m2
m3 b l
B% 1.00 x 21.00 =
21.00 x 0.20 =
Toal Volume Pasangan &ansam$!ng
m2
m3
m2
m3
m3
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
53/54
C!unen '"ugan Pas!" Pasangan
b l
78.75 m2 & 1.75 x 45.00
15.75 m3 78.75 x 0.10
b l
31.50 m2 B 1.50 x 21.00
6.30 m3 31.50 x 0.10
b l
30.00 m2 &% 1.25 x 24.00
6.00 m3 30.00 x 0.10
b l
21.00 m2 B% 1.00 x 21.00
4.20 m3 21.00 x 0.10
32.25 m3 Toal Volume '"u
-
7/25/2019 Volume Pasangan Batu, Aanstamping, Urugan Pasir
54/54
DPT C!unen
= 78.75 m2
= 7.88 m3
= 31.50 m2
= 3.15 m3
= 30.00 m2
= 3.00 m3
= 21.00 m2
= 2.10 m3
gan Pas!" 16.13 m3