dr. jingran wang jibei electric power dispatch and control ... large scale_wang.pdf · senior...
TRANSCRIPT
Dr. Jingran Wang
Jibei Electric Power Dispatch and Control Centre
State Grid Corporation of China
2018.10
新能源并网技术要求 2
新能源消纳全过程评估 3
国家电网公司概况
Overview of SGCC
RE integration technical requirements
Whole-process assessment on RE accommodation
1
1. Overview of SGCC
SGCC’s core business is to build and operate power grids in China
The service area covers 26 of 32 provinces, taking 88% of China’s
territory. SGCC is the biggest utility company worldwide
The total installed capacity had reached 1,379GW by the end of 2017
Wind: 129GW (9.3%); Solar: 115GW (8.3%)
火电, 88887,
64.5%
水电, 22414,
16.3%
风电, 12890,
9.3%
太阳能, 11506,
8.3%
核电, 2176,
1.6%
2. Integration technical requirements
In 2011 and 2012, 10 times of power grid faults occurred in some
provinces, which results in 5,087 wind turbines tripping due to lack of
LVRT capability
Revised two national standards: Technical rule for connecting wind
farm and photovoltaic power station to power system
By the end of 2015, completed a total of 200 types of wind turbine
testing of LVRT capability
246
598
400
677 644
1278
790 814
660 584
103
837
568
976
854
1535
1016 1055
876
737
0
200
400
600
800
1000
1200
1400
1600
1800
2011.1.30 2011.2.24 2011.4.3 2011.4.17 2011.4.17 2011.4.25 2011.11.16 2011.12.21 2012.3.30 2012.5.14
脱网风机台数
损失出力MW
Jilin
Gansu
2012 脱网1244台次 损失1613MW
Gansu
Gansu
Gansu
Jibei
Jibei Jibei
Jibei
Jibei
2011 脱网3843台次 损失4873MW
Number of wind turbine tripping
Loss of power (MW)
The transient overvoltage of power
grid reached 1.2 or 1.3 times of the
rated voltage
Large number of wind turbines tripped
at the sending region of UHV DC lines
when phase changing failure
In 2016, choose some wind farms in
Mengdong area as pilots to carry out
the capability improvement of high
voltage ride through (HVRT)
Simulation results of Hami-Zhengzhou UHV line
phase changing failure Simulation results of Zhalute-Qingzhou UHV line
phase changing failure
LVRT Improvement Cost
(thousand yuan) HVRT Improvement
Cost (thousand yuan)
UPS 5, (3.8%) UPS —
Control system logic 10, (7.7%) Control system logic —
Converter testing and control
50, (38.5%) Converter testing and
control —
Converter protection circuit
45, (34.6%) Converter protection
circuit —
Converter LVRT control strategy
20, (15.4%) Converter HVRT control
strategy 20,(100%)
Total 130 Total 20
Cost of LVRT and HVRT Improvement of wind turbine
测试点电压
(p
u)
时间(s)
0 1 2 3 9
1.00
1.10
1.20
1.30
0.2
电压水平
要求风电机组
不脱网连续运行
风电机组
可以切出
10…… 11
High voltage ride through curve of
wind turbine HVRT requirements
Wind turbine: 1.3Un, 200ms
PV inverter: 1.3Un, 500ms
Frequency tolerance requirements
51.5Hz
Revising the standards for HVRT
?% ?%
outage
maintenance
passive
maintenance interface
peak-valley
theoretical generation real generation Inner-plant curtailment Outer-plant curtailment
outage
RE Utilization Level
100% 82% 8% 10%
3. Whole-process Assessment on RE accommodation
Many factors influence renewable generation utilization level: wind and
solar resources, equipment reliability, grid operation constraints, and
priority dispatching
The purpose of whole-process assessment is to analyze the influence
of each factor quantitatively
Basic Principle
Establish the mapping relationship between active
power and nacelle wind speed for each turbine
Calculate the theoretical power when curtailment
occurs
Integrate the theoretical power to get the theoretic
generation during one period
Calculate components of inner-plant and outer-plant
curtailment
Calculation of theoretical generation
0
5
10
15
20
25
30
Jan. Feb. Mar. Apr. May. Jun. Jul. Aug. Sep. Oct. Nov. Dec.
Ene
rgy
curt
ailm
en
t (G
Wh
)
inner-plant outer-plant
Components of iner-plant and
outer-plant curtaiment Calculation of curtailment energy
for one wind farm
Dr. Jingran Wang
Senior supervisor of Jibei Electric Power Dispatch and Control
Centre, State Grid Corporation of China. Main research field
includes power system planning and renewable energy
dispatching.
TEL: +86-13810751782,
EMAIL: [email protected]
More than 80% of the power demand is distributed in astern and southern
areas in China. By contrast, renewable energy is mainly in the ‘3-North’
area.
欧美陆上风电 市场需求导向 靠近负荷中心 小规模 多业主 高度分散
中国陆上风电 资源导向 远离负荷中心 大规模 少业主 高度集中
Comparison of renewable energy development between China and Europe
Europe and US
Market demand oriented
Near the load
Small-scale
Many owners
Highly dispersive
China Resource oriented Far from the
load
Large-Scale
A few owners
Highly centralized
中外新能源发展特点对比 The development characteristic comparison
The average capacity of wind farm in China is 88MW(3 times of
Spain),and the largest one exceeds 400MW. Many wind farms in the
region with good wind resources are integrated into the same substation,
thus forming wind farm cluster (2-3GW). And then many wind farm
clusters are integrated into higher-voltage level substation, forming a wind
power base (10GW).
Testing Contents Testing Requirements
Mandatory
Wind farm active/reactive
power control capability
Whether AGC/AVC substation meets the
operating conditions accessing to the main
station
Wind farm Power quality Whether wind power quality meets the
standard requirements
Wind farm low voltage
ride through capacity and
grid adaptive capacity
verification
To ensure that the wind turbines are consistent
with the testing unit parameters and
configuration, and wind farms low voltage ride
through capacity and grid adaptive capacity
Dynamic reactive power
compensation device
performance test
The reactive power compensation device
should have reactive power regulation and
voltage control capability
Detection of reactive power compensation
device performance whether meet the standard
requirements, for dynamic control performance
optimization of reactive power compensation
device to provide test data.
Optional Wind turbines power
characteristics test
Consistency of Wind turbines actual power
curve inspection and theory power curve
Integration testing requirements
Signal data Telemetry
data
wind turbine
Operatin
g
Generation
real power,
reactive power,
nacelle wind
speed
Idle with low wind velocity
Deregulated generation of dispatch
Shutdow
n
Shutdown reserve from AGC
Schedule maintenance
Non-planed outage (inside)
Non-planed outage (outside)
PV inverter
Operatin
g
Generation
real power,
reactive
power
Deregulated generation of
dispatch
Shutdow
n similar with wind turbine
anemometer
tower wind speed (10m, 30m,50m,70m) 12
Remote telemetry and signal data
The component analysis of energy curtailment is based on high-quality operation information of each wind turbine and PV inverter
2018/10/22
The impact of wind turbine component outage
on wind curtailment
Wind farms in different
geographical locations
Power generation companies
Equipment manufacturers
Assessment of wind power utilization