PMLC Project Charter eExpense System Implementation Project v1.0 Confidential Not for release outside of The George Washington University without written permission Page 1 PMLC Project Management Life Cycle The George Washington University Electronic Expense (eExpense) System Implementation Project Project Charter Prepared By: J.Seile / A.Donaldson Version: 1.0 Date: 11/16/11 Project Owner: Donna Ginter, Procurement Deb Dickenson, Comptroller’s Office Project Manager: Adam Donaldson PPM: STATUS: Draft Routing for Document Approval Approved Unapproved

Upload: doankien

Post on 23-Mar-2018

252 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 1

 

  

  PMLC Project Management Life Cycle 

The George Washington University Electronic Expense (eExpense) System Implementation Project

Project Charter

  

   

   

   

   

Prepared By:  J.Seile / A.Donaldson 

Version:  1.0 

Date:   11/16/11 

Project Owner:  Donna Ginter, Procurement 

Deb Dickenson, Comptroller’s Office 

Project Manager:  Adam Donaldson 

PPM:   

STATUS:   Draft 

   Routing for Document Approval 

   Approved 

   Unapproved 

Page 2: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 2

 

Table of Contents Revision History ............................................................................................................................................ 2 

1  Project Description................................................................................................................................ 3 

1.1  Business Need ............................................................................................................................... 3 

1.2  Scope & Objectives ....................................................................................................................... 3 

1.2.1  Inclusions & Deliverables ...................................................................................................... 3 

1.2.2  Exclusions .............................................................................................................................. 4 

1.3  Assumptions .................................................................................................................................. 4 

1.4  Constraints .................................................................................................................................... 5 

2  Project Organization ............................................................................................................................. 5 

2.1  Governance ................................................................................................................................... 5 

2.1.1  Project Management Lifecycle (PMLC) Process .................................................................... 5 

2.1.2  Executive Sponsors ............................................................................................................... 5 

2.2  Allocated Project Resources ......................................................................................................... 5 

2.3  High‐Level Project Organization.................................................................................................... 7 

3  Timeline & Milestones .......................................................................................................................... 7 

3.1  Timeline ......................................................................................................................................... 7 

3.2  Project Milestones ........................................................................................................................ 8 

4  Approval ................................................................................................................................................ 9 

 

Revision History 

Version Number 

Date  Author  Notes 

1.0  11/16/11  A.Donaldson Routing for approval

     

     

     

     

        

Page 3: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 3

 

1 Project Description 

1.1 Business Need Current expense reporting and PCard reconciliation processes are manual and labor intensive, with employees required to use two separate processes for justification of expenses.  The eExpense solution will allow for a seamless integration with the proposed Travel Portal solution with data collected at the time of travel booking and through the travel of the user pre‐populating expense reports.  Non‐travelers who are required to submit expense reports are also able to easily navigate the system.  eExpense allows for closer‐to‐paperless end‐to‐end processing, offering a fax‐ or email‐to‐report option for those users without access to electronic versions of receipts.  eExpense will also allow for integration of PCard reconciliation into one process for the end user, and streamline back end auditing functionality. 

1.2 Scope & Objectives The eExpense solution seeks to: 

Achieve paperless expense reimbursements, approvals and journaling. 

Reduce expense processing time and transaction costs. 

Reduce the amount of time and effort required to submit, approve, process and pay expense reports. 

Integrate PCard processing with automated pre‐population of expense reports with PCard transactions to eliminate manual processes and “yellow envelopes” 

Accommodate and automate enforcement of existing and future University‐wide expense policies and rules allowing support staff to focus on value‐added activities including auditing and monitoring of compliance with policies.    

The Travel Portal and eExpense ‐ Project Proposal 1.82.pdf (Proposal) contains specific Business Requirements which are all considered to be included in the scope of this project.  Section 1.2.1 below is a summary of the major deliverables included in the scope of this project.  

1.2.1 Inclusions & Deliverables  eExpense Implementation:  The project will manage the overall implementation and launch of 

the Concur expense management system using GW’s Travel Portal web site as an entrance to the system allowing users to manage expense reimbursement & reconciliation per the approved Business Requirements. 

PCard Processing: The solution provides a mechanism for users to access expense data from PCard and travel as well as enter data for other expenses along with the ability to upload supporting documentation.  This will require integration of a PCard flat file feed from JP Morgan to capture line‐item expenses charged by PCard users (directly to Concur).  The E‐Expense solution will eliminate the need for separate PCard reporting on behalf of users via the yellow envelopes. 

Account/Org/Fund Allocation:  Users will perform the necessary allocation to the appropriate account/org/fund/award from within the application, before the activity has been interfaced into AP.   

Audit Rule Definition & Configuration:  The Concur Expense solution allows for significant personalization based on GW’s policy and audit rules and allows for future adjustment of these rules by a GW staff member or members to be trained on administration of the system.  The 

Page 4: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 4

 

project team will be required to spend significant time prior to implementation determining the manner in which policies and procedures will be applied within the system. 

Reporting:  Accounts payable personnel will have the ability to select, review or audit any expense submitted and approved without manual intervention or paper, prior to expense report posting to the AP module or GL.  Concur Expense includes a robust reporting and auditing capability that meets the stated system requirements and is sufficient to maintain appropriate A/P and PCard controls without the use of a secondary PCMS system. 

Interface Development:  Recurring interfaces to be developed, implemented and maintained either in flat‐file exchange in the Concur‐defined format or as a web service: 

o Approvers list (depth based on workflow implemented). 

o List import for cost centers. 

o List import for expenditure items. 

o Standard Accounting Extract (invoice). 

o Payment Confirmation and Funds Checking. 

Single Sign On:  This project will include integration of a single sign on through a GW web portal page along with appropriate feeds to ensure appropriate authentication. 

Vendor Integration:  The project team will coordinate implementation with Concur resources. 

Staffing:  The Project Owner will acquire the additional staff agreed to in the Proposal to manage the eExpense beyond this implementation project. 

Branding:  The eExpense branding will be in line with Travel Portal branding.  This project will manage the initial communications, training and marketing activities through a predefined launch period of 6 weeks from system general availability. 

Travel Portal Integration:  eExpense development should inform and be informed by implementation of Travel Portal so that operation will be seamless to the end user once both systems are functional. 

1.2.2 Exclusions  Travel advances are not being considered as a part of this project 

The Concur Expense module is limited to employee use only for settlement of expenses and PCard reconciliation.  Students, contractors and vendors will not be included in the expense solution or travel portal at this time. 

In‐depth approval workflows are out‐of‐scope for this project, unless, internal audit recommends not implementing workflow “lite” due to controls integrity or other issues. 

Identified as Out‐of‐Scope for this project: 

o Streamlined GW‐wide workflow 

o Consolidation/reduction of number of GL accounts 

o Per Diems 

While PCard reconciliation, reporting and auditing are in‐scope; determination of eligibility, changes to limits and other management of users is not. 

1.3 Assumptions  PCard policies and procedures will be changed based on opportunities of new system. 

A/P policies and procedures will be changed based on opportunities of the new system. 

Page 5: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 5

 

Technical support will be hired and supported by FSS prior to development phase of Concur Expense. 

Technical support will be hired by Division of IT prior to implementation of Concur Expense. 

Workflow lite will be evaluated by internal audit. 

The identification of eligible members into profile groups does not need to be managed by data from GW initial load or recurring interfaces. 

Resources are available to meet the timing requirements of the Division of Finance. 

Types of expenses that are currently submitted on T&Es at GW will be available to submit electronically, including: travel, supplies, meals, and training.  

Paperless (both on user and administrator end) transactions to be included in this project plan: 

o Expense reimbursements. 

o Approval (pre/post expense). 

o Automated processing. 

1.4 Constraints  The GW Travel Portal must be implemented, including single sign on, prior to completion of 

eExpense implementation. 

2 Project Organization 

2.1 Governance 

2.1.1 Project Management Lifecycle (PMLC) Process This project will follow the Project Management Lifecycle (PMLC) process.   The project will consist of gate  reviews  with  the  Executive  Sponsors  after  the  Planning,  Analysis/Design/Development, Testing/Readiness, Cutover and Closing Phases.  For details on the PMLC, please visit the PMLC Toolkit eRoom  at  https://eroom.gwu.edu/eRoom/EVPT/PMToolkit  (contact  Adam  Donaldson  at 

 for access to that eRoom). 

2.1.2 Executive Sponsors The Executive Sponsors of the project are: 

Dave Lawlor, Senior Associate Vice President of Finance 

Dave Steinour, CIO or Ed Martin, Deputy CIO Division of Information Technology 

2.2 Allocated Project Resources 

  Resource  Group Role / Activity 

Project Leaders  Deb Dickenson Finance – Comptroller’s Office 

Project Co‐Owner – Responsible for overall implementation

Donna Ginter  Finance ‐ Procurement Project Co‐Owner – Responsible for overall implementation

Adam Donaldson Finance ‐ Business Mgt & Analysis Group 

Project Manager / Communications Lead – Responsible for managing overall implementation and communications planning

Page 6: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 6

 

  Resource  Group Role / Activity Division of IT 

Tom Breslin Enterprise Information Services 

Sr. Mgt. Technical SME – Coordinate IT resources for the project and serve as IT escalation point 

Kishan Devineni Enterprise Information Services 

Technical Lead – IT development of solution 

Anna de Lapparent 

Enterprise Information Services 

Technical Lead – IT analysis, IT design and IT testing of solution

To‐Be‐Hired  IT  Technical SME – IT development, implementation & administrative support

Office of Finance 

Dan MacGregor  Financial & Accounting Operations 

Sr. Mgt. Functional SME –Coordinate and lead A/P resources

Lennox Jones Financial & Accounting Operations – A/P & Travel 

Functional Lead – A/P and Travel 

George Bedford  Procurement  Functional Lead – PCard Integration 

Josh Rubin  Procurement  Technical Lead – Procurement Technology Inputs

Jeff Pearson Financial Systems Support 

Sr. Mgt. Technical SME – Configuration and Testing Support

Kevin Perry Financial Systems Support 

Functional Lead – Configuration and Testing Support 

To‐Be‐Hired Financial Systems Support 

Functional SME – Configuration, Testing and ongoing administrative Support

Others 

Steven Van Der Werf 

Concur  Vendor Implementation Lead 

Mike Cullen  Baker Tilly – Internal Audit 

Verification of Financial and Data Controls Integrity 

TBD  Finance Director(s) Stakeholder Input

Table 1 – Allocated Project Resources 

Page 7: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 7

 

2.3 High­Level Project Organization 

 

Figure 1 – Project Organization Chart 

3 Timeline & Milestones 3.1 Timeline The following timeline is based on the activities and milestones listed in the approved Travel & Expense Proposal.  Additionally, this timeline accounts for GW holidays and adds deployment activities not listed in the proposal. 

 

Figure 2 – Project Timeline 

 

Page 8: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 8

 

3.2 Project Milestones 

  Milestone & Major Activities   E*Expense critical path tasks

  Engage team and stakeholder participants 10/19/11

Approval to make A/P, PCard, Travel process changes Project start + 4 weeks 

Identify policy changes necessary  Project start + 4 weeks 

Stakeholder meetings/buy‐in  Project start + 8 weeks 

E*Coordinate implementation schedules with vendors Project start + 4 weeks 

E*Finalize IT Requirements & Functional Design includingrequirements for integrations and validate security requirements 

Project start + 4 weeks 

Hire new staff (FSS/IT)  Project start + 8 weeks 

Planning Gate Review Board  Project Start + 8 weeks 

Analysis, Design & Development 

Engage vendors  Plan Approval 

Establish configuration  Plan Approval + 4 weeks 

Knowledge transfer on system configuration and maintenance tools 

Initial configuration + 2 weeks

Develop test plan  Plan Approval + 8 weeks 

Develop communication & training plans Plan Approval + 8 weeks 

Develop Expense Interfaces  Plan Approval + 18 weeks E*IT Analyst Testing Completed  Plan Approval + 31 weeks E*Initial FSS Testing Completed  IT Analyst testing complete + 2 weeks

Code Freeze IT Analyst testing complete + 2 weeksE*End­to­End FSS Analyst Testing Completed IT & FSS Initial testing complete + 4 

weeks

AD&D Gate Review Board  Plan Approval + 39 weeks 

Testing and 

Rdi

 E*UAT  AD&D+4 weeks 

Rework   UAT +2 weeks 

E*Regression Testing  UAT + 4 weeks 

T&R Gate Review Board  AD&D+8 weeks 

Deploy t/ Implementation  Testing & readiness + 1 week

Production Validation  Implementation +1 week 

Post Go­Live Gate Review Board  T&R + 2 weeks 

Total Duration  57 weeks** 

** The total duration gets the project through implementation of for system availability for users.  Shortly before, during and after 

implementation, an initial communications / adoption campaign will occur.  This time is accounted for in Figure 2 above. 

 Table 2 ‐ Proposed Milestones & Major Activities 

Page 9: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 9

 

4 Approval By signing, the individuals listed below have approved this project charter and have committed to the project scope, organization and timeline detailed within.  

                   

Name:  Dave Lawlor  Name: David P. Steinour Title:  SAVP Finance  Title:  CIORole: Project Executive Sponsor  Role: Project Executive Sponsor Date:    Date:        Name:  Deb Dickenson Name: Donna Ginter Title: Comptroller  Title: Director of Procurement Role: Project Owner  Role: Project OwnerDate:    Date:      

<For  an  approval  received  via  electronic means,  such  as  email,  please  indicate  by  placing  “Electronic Approval” on the approval line.  Please then place a copy of the electronic approval in the same project file folder where the approved version of this document is stored.> 

   

Electronic Approval Received (see attached) 

Electronic Approval Received (see attached)

Electronic Approval Received (see attached) 

Electronic Approval Received (see attached)

Page 10: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 10

 

Appendix A – Related Documents 

File Name Document Owner

Document Location or Link 

GW Concur Agreement ‐ 25 Sep 11.pdf  D.Ginter https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e969

Travel and Expense ‐ Project Proposal 1,82 APPROVED.pdf 

A.Donaldson  https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e963 

Travel Portal Concur Expense Management Proposal ‐ APPROVED BY 

KATZ.pdf D.Lawlor  https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e963 

 

 

 

   

Page 11: eExpense - Project Charter v1 - Business Management and ... · PDF fileImplementation Project Project Charter ... the Concur expense management system using GW’s Travel Portal web

PMLC Project Charter  eExpense System Implementation Project v1.0 

Confidential Not for release outside of The George Washington University without written permission

Page 11

 

Appendix B – Glossary Term / Acronym  Definition

AD&D  Analysis Design & Development

AEBTS  American Express Business Travel Services

AP or A/P  Accounts Payable 

AR  Accounts Receivable 

BMAG  Office of Finance ‐ Business Management & Analysis Group

CIO  Chief Information Officer 

CO  Office of Finance ‐ Comptroller's Office

CSV  Comma Separated Values 

EAS  Enterprise Accounting System

EIS  Division of IT – Enterprise Information Services group

ETS  Endowment Tracking System

FSS  Office of Finance ‐ Financial Systems Support

GL or G/L  General Ledger 

GM  Grants Module 

GW  The George Washington University

GWU  The George Washington University

HR  Human Resources 

DivIT or IT  Division of Information Technology

PCard  Procurement Card 

PCMS  Payment Confirmation Management System

PMLC  Project Management Lifecycle

SAML  Security Assertion Markup Language

SAVP  Senior Associate Vice President

SME  Subject Matter Expert 

T&E  Travel and Expense 

T&R  Testing & Readiness 

UAT  User Acceptance Testing 

XML  Extensible Markup Language