PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 1
PMLC Project Management Life Cycle
The George Washington University Electronic Expense (eExpense) System Implementation Project
Project Charter
Prepared By: J.Seile / A.Donaldson
Version: 1.0
Date: 11/16/11
Project Owner: Donna Ginter, Procurement
Deb Dickenson, Comptroller’s Office
Project Manager: Adam Donaldson
PPM:
STATUS: Draft
Routing for Document Approval
Approved
Unapproved
PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 2
Table of Contents Revision History ............................................................................................................................................ 2
1 Project Description................................................................................................................................ 3
1.1 Business Need ............................................................................................................................... 3
1.2 Scope & Objectives ....................................................................................................................... 3
1.2.1 Inclusions & Deliverables ...................................................................................................... 3
1.2.2 Exclusions .............................................................................................................................. 4
1.3 Assumptions .................................................................................................................................. 4
1.4 Constraints .................................................................................................................................... 5
2 Project Organization ............................................................................................................................. 5
2.1 Governance ................................................................................................................................... 5
2.1.1 Project Management Lifecycle (PMLC) Process .................................................................... 5
2.1.2 Executive Sponsors ............................................................................................................... 5
2.2 Allocated Project Resources ......................................................................................................... 5
2.3 High‐Level Project Organization.................................................................................................... 7
3 Timeline & Milestones .......................................................................................................................... 7
3.1 Timeline ......................................................................................................................................... 7
3.2 Project Milestones ........................................................................................................................ 8
4 Approval ................................................................................................................................................ 9
Revision History
Version Number
Date Author Notes
1.0 11/16/11 A.Donaldson Routing for approval
PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 3
1 Project Description
1.1 Business Need Current expense reporting and PCard reconciliation processes are manual and labor intensive, with employees required to use two separate processes for justification of expenses. The eExpense solution will allow for a seamless integration with the proposed Travel Portal solution with data collected at the time of travel booking and through the travel of the user pre‐populating expense reports. Non‐travelers who are required to submit expense reports are also able to easily navigate the system. eExpense allows for closer‐to‐paperless end‐to‐end processing, offering a fax‐ or email‐to‐report option for those users without access to electronic versions of receipts. eExpense will also allow for integration of PCard reconciliation into one process for the end user, and streamline back end auditing functionality.
1.2 Scope & Objectives The eExpense solution seeks to:
Achieve paperless expense reimbursements, approvals and journaling.
Reduce expense processing time and transaction costs.
Reduce the amount of time and effort required to submit, approve, process and pay expense reports.
Integrate PCard processing with automated pre‐population of expense reports with PCard transactions to eliminate manual processes and “yellow envelopes”
Accommodate and automate enforcement of existing and future University‐wide expense policies and rules allowing support staff to focus on value‐added activities including auditing and monitoring of compliance with policies.
The Travel Portal and eExpense ‐ Project Proposal 1.82.pdf (Proposal) contains specific Business Requirements which are all considered to be included in the scope of this project. Section 1.2.1 below is a summary of the major deliverables included in the scope of this project.
1.2.1 Inclusions & Deliverables eExpense Implementation: The project will manage the overall implementation and launch of
the Concur expense management system using GW’s Travel Portal web site as an entrance to the system allowing users to manage expense reimbursement & reconciliation per the approved Business Requirements.
PCard Processing: The solution provides a mechanism for users to access expense data from PCard and travel as well as enter data for other expenses along with the ability to upload supporting documentation. This will require integration of a PCard flat file feed from JP Morgan to capture line‐item expenses charged by PCard users (directly to Concur). The E‐Expense solution will eliminate the need for separate PCard reporting on behalf of users via the yellow envelopes.
Account/Org/Fund Allocation: Users will perform the necessary allocation to the appropriate account/org/fund/award from within the application, before the activity has been interfaced into AP.
Audit Rule Definition & Configuration: The Concur Expense solution allows for significant personalization based on GW’s policy and audit rules and allows for future adjustment of these rules by a GW staff member or members to be trained on administration of the system. The
PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 4
project team will be required to spend significant time prior to implementation determining the manner in which policies and procedures will be applied within the system.
Reporting: Accounts payable personnel will have the ability to select, review or audit any expense submitted and approved without manual intervention or paper, prior to expense report posting to the AP module or GL. Concur Expense includes a robust reporting and auditing capability that meets the stated system requirements and is sufficient to maintain appropriate A/P and PCard controls without the use of a secondary PCMS system.
Interface Development: Recurring interfaces to be developed, implemented and maintained either in flat‐file exchange in the Concur‐defined format or as a web service:
o Approvers list (depth based on workflow implemented).
o List import for cost centers.
o List import for expenditure items.
o Standard Accounting Extract (invoice).
o Payment Confirmation and Funds Checking.
Single Sign On: This project will include integration of a single sign on through a GW web portal page along with appropriate feeds to ensure appropriate authentication.
Vendor Integration: The project team will coordinate implementation with Concur resources.
Staffing: The Project Owner will acquire the additional staff agreed to in the Proposal to manage the eExpense beyond this implementation project.
Branding: The eExpense branding will be in line with Travel Portal branding. This project will manage the initial communications, training and marketing activities through a predefined launch period of 6 weeks from system general availability.
Travel Portal Integration: eExpense development should inform and be informed by implementation of Travel Portal so that operation will be seamless to the end user once both systems are functional.
1.2.2 Exclusions Travel advances are not being considered as a part of this project
The Concur Expense module is limited to employee use only for settlement of expenses and PCard reconciliation. Students, contractors and vendors will not be included in the expense solution or travel portal at this time.
In‐depth approval workflows are out‐of‐scope for this project, unless, internal audit recommends not implementing workflow “lite” due to controls integrity or other issues.
Identified as Out‐of‐Scope for this project:
o Streamlined GW‐wide workflow
o Consolidation/reduction of number of GL accounts
o Per Diems
While PCard reconciliation, reporting and auditing are in‐scope; determination of eligibility, changes to limits and other management of users is not.
1.3 Assumptions PCard policies and procedures will be changed based on opportunities of new system.
A/P policies and procedures will be changed based on opportunities of the new system.
PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 5
Technical support will be hired and supported by FSS prior to development phase of Concur Expense.
Technical support will be hired by Division of IT prior to implementation of Concur Expense.
Workflow lite will be evaluated by internal audit.
The identification of eligible members into profile groups does not need to be managed by data from GW initial load or recurring interfaces.
Resources are available to meet the timing requirements of the Division of Finance.
Types of expenses that are currently submitted on T&Es at GW will be available to submit electronically, including: travel, supplies, meals, and training.
Paperless (both on user and administrator end) transactions to be included in this project plan:
o Expense reimbursements.
o Approval (pre/post expense).
o Automated processing.
1.4 Constraints The GW Travel Portal must be implemented, including single sign on, prior to completion of
eExpense implementation.
2 Project Organization
2.1 Governance
2.1.1 Project Management Lifecycle (PMLC) Process This project will follow the Project Management Lifecycle (PMLC) process. The project will consist of gate reviews with the Executive Sponsors after the Planning, Analysis/Design/Development, Testing/Readiness, Cutover and Closing Phases. For details on the PMLC, please visit the PMLC Toolkit eRoom at https://eroom.gwu.edu/eRoom/EVPT/PMToolkit (contact Adam Donaldson at
for access to that eRoom).
2.1.2 Executive Sponsors The Executive Sponsors of the project are:
Dave Lawlor, Senior Associate Vice President of Finance
Dave Steinour, CIO or Ed Martin, Deputy CIO Division of Information Technology
2.2 Allocated Project Resources
Resource Group Role / Activity
Project Leaders Deb Dickenson Finance – Comptroller’s Office
Project Co‐Owner – Responsible for overall implementation
Donna Ginter Finance ‐ Procurement Project Co‐Owner – Responsible for overall implementation
Adam Donaldson Finance ‐ Business Mgt & Analysis Group
Project Manager / Communications Lead – Responsible for managing overall implementation and communications planning
PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 6
Resource Group Role / Activity Division of IT
Tom Breslin Enterprise Information Services
Sr. Mgt. Technical SME – Coordinate IT resources for the project and serve as IT escalation point
Kishan Devineni Enterprise Information Services
Technical Lead – IT development of solution
Anna de Lapparent
Enterprise Information Services
Technical Lead – IT analysis, IT design and IT testing of solution
To‐Be‐Hired IT Technical SME – IT development, implementation & administrative support
Office of Finance
Dan MacGregor Financial & Accounting Operations
Sr. Mgt. Functional SME –Coordinate and lead A/P resources
Lennox Jones Financial & Accounting Operations – A/P & Travel
Functional Lead – A/P and Travel
George Bedford Procurement Functional Lead – PCard Integration
Josh Rubin Procurement Technical Lead – Procurement Technology Inputs
Jeff Pearson Financial Systems Support
Sr. Mgt. Technical SME – Configuration and Testing Support
Kevin Perry Financial Systems Support
Functional Lead – Configuration and Testing Support
To‐Be‐Hired Financial Systems Support
Functional SME – Configuration, Testing and ongoing administrative Support
Others
Steven Van Der Werf
Concur Vendor Implementation Lead
Mike Cullen Baker Tilly – Internal Audit
Verification of Financial and Data Controls Integrity
TBD Finance Director(s) Stakeholder Input
Table 1 – Allocated Project Resources
PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 7
2.3 HighLevel Project Organization
Figure 1 – Project Organization Chart
3 Timeline & Milestones 3.1 Timeline The following timeline is based on the activities and milestones listed in the approved Travel & Expense Proposal. Additionally, this timeline accounts for GW holidays and adds deployment activities not listed in the proposal.
Figure 2 – Project Timeline
PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 8
3.2 Project Milestones
Milestone & Major Activities E*Expense critical path tasks
Engage team and stakeholder participants 10/19/11
Approval to make A/P, PCard, Travel process changes Project start + 4 weeks
Identify policy changes necessary Project start + 4 weeks
Stakeholder meetings/buy‐in Project start + 8 weeks
E*Coordinate implementation schedules with vendors Project start + 4 weeks
E*Finalize IT Requirements & Functional Design includingrequirements for integrations and validate security requirements
Project start + 4 weeks
Hire new staff (FSS/IT) Project start + 8 weeks
Planning Gate Review Board Project Start + 8 weeks
Analysis, Design & Development
Engage vendors Plan Approval
Establish configuration Plan Approval + 4 weeks
Knowledge transfer on system configuration and maintenance tools
Initial configuration + 2 weeks
Develop test plan Plan Approval + 8 weeks
Develop communication & training plans Plan Approval + 8 weeks
Develop Expense Interfaces Plan Approval + 18 weeks E*IT Analyst Testing Completed Plan Approval + 31 weeks E*Initial FSS Testing Completed IT Analyst testing complete + 2 weeks
Code Freeze IT Analyst testing complete + 2 weeksE*EndtoEnd FSS Analyst Testing Completed IT & FSS Initial testing complete + 4
weeks
AD&D Gate Review Board Plan Approval + 39 weeks
Testing and
Rdi
E*UAT AD&D+4 weeks
Rework UAT +2 weeks
E*Regression Testing UAT + 4 weeks
T&R Gate Review Board AD&D+8 weeks
Deploy t/ Implementation Testing & readiness + 1 week
Production Validation Implementation +1 week
Post GoLive Gate Review Board T&R + 2 weeks
Total Duration 57 weeks**
** The total duration gets the project through implementation of for system availability for users. Shortly before, during and after
implementation, an initial communications / adoption campaign will occur. This time is accounted for in Figure 2 above.
Table 2 ‐ Proposed Milestones & Major Activities
PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 9
4 Approval By signing, the individuals listed below have approved this project charter and have committed to the project scope, organization and timeline detailed within.
Name: Dave Lawlor Name: David P. Steinour Title: SAVP Finance Title: CIORole: Project Executive Sponsor Role: Project Executive Sponsor Date: Date: Name: Deb Dickenson Name: Donna Ginter Title: Comptroller Title: Director of Procurement Role: Project Owner Role: Project OwnerDate: Date:
<For an approval received via electronic means, such as email, please indicate by placing “Electronic Approval” on the approval line. Please then place a copy of the electronic approval in the same project file folder where the approved version of this document is stored.>
Electronic Approval Received (see attached)
Electronic Approval Received (see attached)
Electronic Approval Received (see attached)
Electronic Approval Received (see attached)
PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 10
Appendix A – Related Documents
File Name Document Owner
Document Location or Link
GW Concur Agreement ‐ 25 Sep 11.pdf D.Ginter https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e969
Travel and Expense ‐ Project Proposal 1,82 APPROVED.pdf
A.Donaldson https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e963
Travel Portal Concur Expense Management Proposal ‐ APPROVED BY
KATZ.pdf D.Lawlor https://eroom.gwu.edu/eRoom/EVPT/eExpense/0_1e963
PMLC Project Charter eExpense System Implementation Project v1.0
Confidential Not for release outside of The George Washington University without written permission
Page 11
Appendix B – Glossary Term / Acronym Definition
AD&D Analysis Design & Development
AEBTS American Express Business Travel Services
AP or A/P Accounts Payable
AR Accounts Receivable
BMAG Office of Finance ‐ Business Management & Analysis Group
CIO Chief Information Officer
CO Office of Finance ‐ Comptroller's Office
CSV Comma Separated Values
EAS Enterprise Accounting System
EIS Division of IT – Enterprise Information Services group
ETS Endowment Tracking System
FSS Office of Finance ‐ Financial Systems Support
GL or G/L General Ledger
GM Grants Module
GW The George Washington University
GWU The George Washington University
HR Human Resources
DivIT or IT Division of Information Technology
PCard Procurement Card
PCMS Payment Confirmation Management System
PMLC Project Management Lifecycle
SAML Security Assertion Markup Language
SAVP Senior Associate Vice President
SME Subject Matter Expert
T&E Travel and Expense
T&R Testing & Readiness
UAT User Acceptance Testing
XML Extensible Markup Language