eglinton- mount pleasant construction liaison committee meeting - july 2017
TRANSCRIPT
EGLINTON CROSSTOWNEglinton-Mount Pleasant Construction Liaison CommitteeJuly 11, 2017
2
Agenda
• Eglinton Station Update
• Mount Pleasant Station Update
3
Eglinton Station Updates
Complete
Demolition of the Salvation Army Community Church
Demolition of the abandoned TTC bus depot
Wet utilities stages 1-3 (of 4)
Toronto Hydro stages 1a, 1b
Summer/Fall 2017
• Water main and sanitary sewer relocation works are ongoing at the Yonge-Eglinton intersection
• Toronto Hydro relocation (2b) ongoing on Duplex to Hillsdale to Yonge
• Shoring is underway at the Salvation Army and TTC bus depot sites and along the south side of Eglinton (Three rigs now in operation)
– This is the major activity of 2017; maps attached for each stage
4
Eglinton Station Shoring Stage 1
5
Eglinton Station Shoring Stage 2a
6
Eglinton Station Shoring Stage 2b
7
Eglinton Station Shoring Stage 3
8
Construction Progress Picture
A third rig mobilized at the bus depot site
Crews building a guide wall for shoring
9
Mount Pleasant Station Construction Update
Complete
Demolition at 280 and 280 Eglinton Ave E to make way for the Secondary Entrance
Demolition at 256-58 Eglinton Ave E to make way for the Main Entrance
Installation of geotechnical monitoring equipment
Long-term closure of Rawlinson Ave for site trailers and laydown area
Shoring at the Main Entrance
Installation of temporary traffic signals
Summer 2017
• Continue hydro utilities relocation
• Commence sewer relocation at the Secondary Entrance site
• Piling in the roadway, beginning on the northwest side of Eglinton Avenue East
• Resume piling at the Secondary Entrance
10
Mount Pleasant Station Lookahead
Year Quarter Construction ActivityApprox.
Duration
2017Q2-Q4
(April-December)
• Implement traffic staging on the north side of
Eglinton Ave E, and commence utilities relocation and
piling
• Implement traffic staging on the south side of
Eglinton Ave E, continue utilities relocation and piling
• 2 months
• 4 months
2018
Q1-Q2
(January-June)
• Shallow excavation and roof slab construction on the
south side of Eglinton Ave E
• 6 months
Q3-Q4
(July-December)
• Shallow excavation and roof slab construction on the
north side Eglinton Ave E
• 6 months
11
Current Construction Staging
Began June 2017 for approximately two (2) months
NO TURNS IN ALL DIRECTIONSMT PLEASANT &
EGLINTON
12
Mount Pleasant Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
13
Mount Pleasant Station Main Entrance
*60% rendering
14
Mount Pleasant Station Secondary Entrance
*60% rendering
15
Mount Pleasant Station Construction Progress
15
BACK FILLING TRENCH
EXPOSING UTILITIES
16
Mount Pleasant Station Construction Progress
16
HYDRO TRENCHHYDRO POLE
WORK
17
Mount Pleasant Station Construction Progress
17As of May 2017