eglinton- mount pleasant construction liaison committee meeting - july 2017

17
EGLINTON CROSSTOWN Eglinton-Mount Pleasant Construction Liaison Committee July 11, 2017

Upload: crosstown-to

Post on 22-Jan-2018

1.976 views

Category:

Government & Nonprofit


0 download

TRANSCRIPT

Page 1: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

EGLINTON CROSSTOWNEglinton-Mount Pleasant Construction Liaison CommitteeJuly 11, 2017

Page 2: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

2

Agenda

• Eglinton Station Update

• Mount Pleasant Station Update

Page 3: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

3

Eglinton Station Updates

Complete

Demolition of the Salvation Army Community Church

Demolition of the abandoned TTC bus depot

Wet utilities stages 1-3 (of 4)

Toronto Hydro stages 1a, 1b

Summer/Fall 2017

• Water main and sanitary sewer relocation works are ongoing at the Yonge-Eglinton intersection

• Toronto Hydro relocation (2b) ongoing on Duplex to Hillsdale to Yonge

• Shoring is underway at the Salvation Army and TTC bus depot sites and along the south side of Eglinton (Three rigs now in operation)

– This is the major activity of 2017; maps attached for each stage

Page 4: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

4

Eglinton Station Shoring Stage 1

Page 5: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

5

Eglinton Station Shoring Stage 2a

Page 6: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

6

Eglinton Station Shoring Stage 2b

Page 7: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

7

Eglinton Station Shoring Stage 3

Page 8: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

8

Construction Progress Picture

A third rig mobilized at the bus depot site

Crews building a guide wall for shoring

Page 9: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

9

Mount Pleasant Station Construction Update

Complete

Demolition at 280 and 280 Eglinton Ave E to make way for the Secondary Entrance

Demolition at 256-58 Eglinton Ave E to make way for the Main Entrance

Installation of geotechnical monitoring equipment

Long-term closure of Rawlinson Ave for site trailers and laydown area

Shoring at the Main Entrance

Installation of temporary traffic signals

Summer 2017

• Continue hydro utilities relocation

• Commence sewer relocation at the Secondary Entrance site

• Piling in the roadway, beginning on the northwest side of Eglinton Avenue East

• Resume piling at the Secondary Entrance

Page 10: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

10

Mount Pleasant Station Lookahead

Year Quarter Construction ActivityApprox.

Duration

2017Q2-Q4

(April-December)

• Implement traffic staging on the north side of

Eglinton Ave E, and commence utilities relocation and

piling

• Implement traffic staging on the south side of

Eglinton Ave E, continue utilities relocation and piling

• 2 months

• 4 months

2018

Q1-Q2

(January-June)

• Shallow excavation and roof slab construction on the

south side of Eglinton Ave E

• 6 months

Q3-Q4

(July-December)

• Shallow excavation and roof slab construction on the

north side Eglinton Ave E

• 6 months

Page 11: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

11

Current Construction Staging

Began June 2017 for approximately two (2) months

NO TURNS IN ALL DIRECTIONSMT PLEASANT &

EGLINTON

Page 12: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

12

Mount Pleasant Station Concept Aerial View

Main Entrance

Secondary Entrance

*60% rendering

Page 13: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

13

Mount Pleasant Station Main Entrance

*60% rendering

Page 14: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

14

Mount Pleasant Station Secondary Entrance

*60% rendering

Page 15: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

15

Mount Pleasant Station Construction Progress

15

BACK FILLING TRENCH

EXPOSING UTILITIES

Page 16: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

16

Mount Pleasant Station Construction Progress

16

HYDRO TRENCHHYDRO POLE

WORK

Page 17: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017

17

Mount Pleasant Station Construction Progress

17As of May 2017