engineers ireland permitting of energy projects shannon lng · engineers ireland permitting of...
TRANSCRIPT
Production Liquefaction Shipping Regasification Marketing
What is LNG
• LNG is natural gas that has been cooled to -160 oC at which point it condenses to a liquid
• LNG’s volume is 1/600th of the volume of gas, for the
equivalent amount of energy • transported worldwide using ships
4
0
20000
40000
60000
80000
100000
120000
140000
1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
mil
lio
n c
ub
ic m
etr
es
Declining UK Gas Production
* Source: UK Department of Energy and Climate Change (Oct 2014)
5
Kinsale
* Source: Gaslink Draft 2014 Network Development Plan and Shannon LNG
Shannon LNG was Established to Address Security of Supply
0
100
200
300
400
500
600
700
800
900
1000 1978
1980
1982
1984
1986
1988
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
2034
2036
2038
2040
MM
scf/
day
Indigenous production UK Imports
UK Imports
Kinsale Corrib
6
0
100
200
300
400
500
600
700
800
900
1000
MM
sc
f/d
ay
Indigenous (Kinsale and Corrib) Shannon LNG UK Imports
Corrib
Shannon LNG
UK Imports
Kinsale
* Source: Gaslink 2014 Network Development Plan and Shannon LNG
Shannon LNG Creates Diversity and Provides
Access to World Markets
Site is also close to the electrical transmission system
Red lines = 400 kV
Green lines = 220 KV
Black lines = 110 kV
Shannon LNG
Project Organisation
16
• Shannon LNG - Client
• Arup - Planning consultants, EIS, pipeline
and civil design
• CB&I - LNG Terminal design
• Poten & Partners - LNG and marine consultants
• Mott MacDonald - CHP Plant design
• Halcrow - Marine facilities design
• Mouchel - AGI design
• ERM - Safety and risk consultants
Shannon LNG Terminal
• Strategic Infrastructure
Development
• Upper Tier Seveso site -
HSA was consulted
• Approval received from
ABP six months after
the application was
submitted
• A subsequent alteration
application was
approved by ABP
18
Shannon Pipeline
• 26 km 30” gas
transmission pipeline
• Strategic Infrastructure
Development
• Approval was received
from ABP six months after
application submitted
Combined Heat and Power plant
19
• Combined Heat and Power
plant
• Strategic Infrastructure
Development
• Upper Tier Seveso site -
HSA was consulted
• Approval was received
from ABP six months after
the application was
submitted.
Regulatory Approvals
Terminal planning permission – ABP (Strategic
Infrastructure Development)
Pipeline planning permission – ABP
(Strategic Infrastructure Development)
Foreshore lease / licences – DoE / CSSO
Regulated third party access exemption - CER
LNG Terminal planning alteration - ABP
CHP planning permission – ABP (Strategic
Infrastructure Development)
Feb 2009
Mar 2008
Dec 2010
Nov 2010
Mar 2013
Granted
July 2013
Shannon LNG’s Planning Process
21
Demonstrated project need and benefits (national and local)
• Basic fundamentals of the proposal were clearly demonstrated - Irish
offshore gas production unlikely to deliver security of supply - Kinsale
depleted, Corrib relatively short life, UK North Sea declining
• Complied with national and local policies (Energy White Paper, SIFP* etc.)
Alternatives' Examined
• Ideal site and best technologies selected from a critical assessment of
alternatives
Local communication
• Consulted with Tarbert, Kilcolgan and Ballylongford development
associations.
• Direct Shannon LNG participation
• Open and frank dialogue on safety and environmental issues. Confronted
difficult issues
• Listened to concerns
• As a result of local input, implemented appropriate changes to the design
before planning submission
*Strategic Integrated Framework Plan for the Shannon Estuary (SIFP)
Shannon LNG’s Planning Process
22
Best Practice Design • Designed to key safety, environmental and industry best practices and
standards, e.g. BAT (Best Available Techniques)
• Extensive safety and environmental studies completed such as engineering
designs, environmental impact statements, Quantitative Risk Assessments
(QRA), site investigation works, environmental baseline studies, marine
simulations, archaeological site investigations, economic analysis, etc.
Pre application consultations • Pre application dialogue and consultation with Local Authorities (KCC & LCC),
SFPC, An Bord Pleanála and other key regulators
Shannon LNG (client) involvement • Shannon LNG, as client, reviewed and approved all designs, communications
and submissions
• Direct relationship with the local community
• Awareness of the need for honest and direct communication
Lesson Learned / Observations
• Good local relationships essential
• Superb advice and interest from key authorities: ABP, Kerry County
Council, Limerick County Council, Shannon Foynes Port Company
and the Health and Safety Authority
• The advice and guidance received within the pre application
consultation phase is vitally important and critical to the success of
the final planning application
• Other key success factors:
• Ideal site
• Demonstration of need and examination of alternatives
• Alignment with Government policy
• Ensure design complies with best practice e.g. Best Available
Techniques (BAT)
• Statements backed by data and capable of withstanding
challenge
• Experienced and knowledgeable consultants
23
Shannon LNG’s view of the SID planning process
• Effective - Highly effective and transparent planning
process
• Timely - Approval was received within 6 months of
application for all 3 projects
• Efficient - One overall approval which incorporates the
input of various statutory consultees
• Helpful - Route mapped at pre-application consultation
stage
24
Summary of Shannon LNG’s experience of the
SID Process
• A world class, fair and transparent process
• Decisions based upon critical analysis of submissions
• Professional, prompt and through consultations and
analysis by An Bord Pleanála
• A similar approach taken from other key regulators such
as Kerry County Council, Limerick County Council,
Shannon Foynes Port Company and the Health and
Safety Authority.
25