facility energy report - s3. · pdf filetown of dover – public library energy audit...
TRANSCRIPT
TOWN OF DOVER
PUBLIC LIBRARY
32 E. CLINTON STREET DOVER, NJ 07801
FACILITY ENERGY REPORT
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32
TABLE OF CONTENTS
I. HISTORIC ENERGY CONSUMPTION/COST ................................................................. 2
II. FACILITY ENERGY USE INDEX (EUI) .......................................................................... 7
III. FACILITY DESCRIPTION ................................................................................................ 9
IV. MAJOR EQUIPMENT LIST ............................................................................................ 11
V. ENERGY CONSERVATION MEASURES ..................................................................... 12
VI. ADDITIONAL RECOMMENDATIONS ......................................................................... 32
Appendix A – ECM Cost & Savings Breakdown
Appendix B – New Jersey Smart Start® Program Incentives
Appendix C – Portfolio Manager “Statement of Energy Performance”
Appendix D – Major Equipment List
Appendix E – Investment Grade Lighting Audit
Appendix F – Renewable / Distributed Energy Measures Calculations
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 2 of 32
I. HISTORIC ENERGY CONSUMPTION/COST The energy usage for the facility has been tabulated and plotted in graph form as depicted within this section. Each energy source has been identified and monthly consumption and cost noted per the information provided by the Owner. Electric Utility Provider: Jersey Central Power & Light Electric Utility Rate Structure: General Service Secondary 3 Phase Third Party Supplier: Hudson Energy Natural Gas Utility Provider: New Jersey Natural Gas Utility Rate Structure: GSL Third Party Supplier: N/A The electric usage profile represents the actual electrical usage for the facility. The electric utility measures consumption in kilowatt-hours (KWH) and maximum demand in kilowatts (KW). One KWH usage is equivalent to 1000 watts running for one hour. One KW of electric demand is equivalent to 1000 watts running at any given time. The basic usage charges are shown as generation service and delivery charges along with several non-utility generation charges. Rates used in this report reflect the historical data received for the facility. The gas usage profile within each facility report shows the actual natural gas energy usage for the facility. The gas utility measures consumption in cubic feet x 100 (CCF), and converts the quantity into Therms of energy. One Therm is equivalent to 100,000 BTUs of energy.
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 3 of 32
Table 1 Electricity Billing Data
Utility Provider: Jersey Central Power & LightRate: General Service Secondary 3 Phase
Meter No: G28658189Account No: 100 001 373 784
Third Party Utility Provider: Hudson EnergyTPS Meter / Acct No:
MONTH OF USE CONSUMPTION KWH TOTAL BILL
Jul-14 9,160 $1,022
Aug-14 4,840 $669
Sep-14 7,160 $919
Oct-14 4,960 $645
Nov-14 4,880 $626
Dec-14 4,720 $614
Jan-15 4,120 $536
Feb-15 4,720 $614
Mar-15 5,240 $681
Apr-15 4,880 $634
May-15 5,360 $697
Jun-15 5,960 $775
Totals 66,000 26.1 Max $8,431
AVERAGE DEMAND 22.2 KW average
AVERAGE RATE $0.128 $/kWh
DEMAND KW
25.2
25.2
25.5
26.1
18.6
18.6
22.0
20.6
19.6
23.6
21.2
19.6
ELECTRIC USAGE SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 4 of 32
Figure 1 Electricity Usage Profile
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 5 of 32
Table 2 Natural Gas Billing Data
Utility Provider: New Jersey Natural GasRate: GSL
Meter No: 00810236Account No: 13-1162-5760-15
Third Party Utility Provider: -TPS Meter No:
MONTH OF USECONSUMPTION
(THERMS)TOTAL BILL
Jun-14 0.00 $104.00
Jul-14 0.00 $104.00
Aug-14 0.00 $104.00
Sep-14 0.00 $109.00
Oct-14 60.00 $136.00
Nov-14 587.00 $356.34
Dec-14 1,012.00 $634.00
Jan-15 1,479.00 $828.00
Feb-15 1,290.00 $722.00
Mar-15 758.00 $682.00
Apr-15 164.00 $498.00
May-15 2.00 $104.00
TOTALS 5,352.00 $4,381.34
AVERAGE RATE: $0.82 $/THERM
-
NATURAL GAS USAGE SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 6 of 32
Figure 2 Natural Gas Usage Profile
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 7 of 32
II. FACILITY ENERGY USE INDEX (EUI) Energy Use Index (EUI) is a measure of a building’s annual energy utilization per square foot of building. This calculation is completed by converting all utility usage consumed by a building for one year, to British Thermal Units (BTU) and dividing this number by the building square footage. EUI is a good measure of a building’s energy use and is utilized regularly for comparison of energy performance for similar building types. Building Benchmarking data is collected and analyzed within the Commercial Building Energy Consumption Survey (CBECS), performed by the Energy and Information Administration (EIA). Building data is grouped by function types and tabulated, from which a median site and source energy intensity is determined. The national median or PEER Group Comparable in this instance is the middle value of the national population meaning half the buildings use more energy, and half use less. The PEER Group EUI allows us to compare the relative efficiency of the audited building to that of an average building with the same or similar primary function (i.e. group type). Source use differs from site usage when comparing a building’s energy consumption with the national average. Site energy use is the energy consumed by the building at the building site only. Source energy use includes the site energy use as well as all of the losses to create and distribute the energy to the building. Source energy represents the total amount of raw fuel that is required to operate the building. It incorporates all transmission, delivery, and production losses, which allows for a complete assessment of energy efficiency in a building. The type of utility purchased has a substantial impact on the source energy use of a building. The EPA has determined that source energy is the most comparable unit for evaluation purposes and overall global impact. Both the site and source EUI ratings for the building are provided to understand and compare the differences in energy use. The site and source EUI for this facility is calculated as follows:
BuildingSiteEUIElectricUsageinkBtu FuelUsageinkBtu
BuildingSquareFootage
BuildingSourceEUIElectricUsageinkBtu SSRatio FuelUsageinkBtu SSRatio
BuildingSquareFootage
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 8 of 32
Table 3 Energy Use Index Summary
kWh Therms Gallons kBtu kBtu
ELECTRIC 66,000.0 225,324 3.140 707,517
NATURAL GAS 5,352.0 535,200 1.050 561,960
TOTAL 760,524 1,269,477
BUILDING TYPE
BUILDING AREA 10,000 SQUARE FEET
BUILDING SITE EUI 76.05 kBtu/SF/YR 91.6 kBtu/SF/YR
BUILDING SOURCE EUI 126.95 kBtu/SF/YR 235.6 kBtu/SF/YR
46%
*Site - Source Ratio data is provided by the Energy Star Performance Rating Methodology for Incorporating Source Energy Use document.
AUDITED BUILDING PEER COMPARISON
Library Library
More Efficient than PEER Comparison
ENERGY USE INTENSITY CALCULATION
ENERGY TYPEBUILDING USE
SITE ENERGY
SITE-SOURCE RATIO
SOURCE ENERGY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 9 of 32
III. FACILITY DESCRIPTION The Town of Dover Public Library located at 32 East Clinton Street in Dover, NJ was originally constructed in 1964. The facility is made up of a large stack area, reference area, a large basement meeting room, child reading area, staff offices, conference room, study rooms, restrooms, mechanical room and other utility/storage rooms. Occupancy Profile The typical hours of operation for the building are:
Monday through Thursday 8:00 am - 9:00 pm Friday 8:00 am - 5:30 pm Saturday 8:00 am - Noon
The facility is occupied approximately 60 hours per week with a staff of 10 employees. Building Envelope
Exterior walls for the building are masonry brick faced with a concrete block construction. The two-story area of the library has single-pane, 1/8 inch glass thermal windows with aluminum frames that are sliders with a small section being operable. The basement has clearstory windows while the front single-story section has large arch windows. The windows in the remainder of the facility are in average condition. Typical windows are double-pane, 1/8 inch glass thermal windows with aluminum frames.
The front section of the roof is pitched with asphalt shingles over a vapor barrier and insulation. The flat roof section is comprised of a built-up roofing system consisting of a rubber membrane, a cover board and 2-inch rigid roof insulation over metal decking. This portion of the roof is in average condition with areas of the roof showing small signs of ponding. HVAC Systems The building heating is generated by a Burnham Model 5007N gas-fired, flexible water tube steam boiler rated at 468 MBH input, 374 MBH output and with an efficiency of 79% (present age). The boiler is fired by a natural gas 878 CFH (max input) cyclonic burner. The boiler has associated hi/low combustion air dampers that open on a call for heat. Steam is then sent to various steam radiators, steam coils and steam fin-tube radiators throughout the facility. The majority of the library is cooled by two (2) Carrier Model ZS-05C packaged rooftop units that are rated at 5 tons of cooling capacity each and have a cooling efficiency of 10.8 EER. Several smaller offices are cooled by thru-the-wall air conditioning units.
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 10 of 32
Exhaust System There is a rooftop exhaust fan that serves the restrooms and an exhaust fan that serves the lobby and large meeting room. A smaller exhaust fan serves the mechanical room. Domestic Hot Water Domestic hot water is generated by a Bradford White Model M240S6DS electric water heater with a 40-gallon capacity. The water heater is rated for 7,000 watts maximum. The domestic hot water is circulated by a 1/25-HP cartridge circulator pump. Plumbing System The sink faucets are rated at 1.0 gallon per minute. The water closets and urinals located in the restroom and locker room areas have a rating of 2.6 and 2.0 gallons per flush, respectively. HVAC System Controls
The boiler operates on an outdoor air lockout/reset through Honeywell control devices. The packaged rooftop units are controlled by stand-alone systems located in the spaces that they serve. There is no front-end BAS computer. The HVAC systems within the building utilize “stand alone” controls. The units are configured to operate in “occupied” mode during the day and “unoccupied” mode at night.
Lighting
Refer to the Investment Grade Lighting Audit Appendix for a detailed list of the lighting throughout the facility and estimated operating hours per space.
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 11 of 32
IV. MAJOR EQUIPMENT LIST
The equipment list contains major energy consuming equipment that through implementation of energy conservation measures could yield substantial energy savings. The list shows the major equipment in the facility and all pertinent information utilized in energy savings calculations. An approximate age was assigned to the equipment in some cases if a manufactures date was not shown on the equipment’s nameplate. The ASHRAE service life for the equipment along with the remaining useful life is also shown in the Appendix.
Refer to the Major Equipment List Appendix for this facility.
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 12 of 32
V. ENERGY CONSERVATION MEASURES Energy Conservation Measures are developed specifically for this facility. The energy savings and calculations are highly dependent on the information received from the site survey and interviews with operations personnel. The assumptions and calculations should be reviewed by the owner to ensure accurate representation of this facility. The following ECMs were analyzed:
Table 1 ECM Financial Summary
ECM #1 Interior Lighting Upgrade $16,757 $2,624 6.4 134.9%
ECM #2 Interior Lighting Controls $1,400 $35 40.0 -62.5%
ECM #3 Exterior Lighting Upgrade $3,444 $766 4.5 233.6%
ECM #4Domestic Water Heater
Upgrade$5,750 $505 11.4 31.7%
ECM #5 Window AC Unit $630 $60 10.5 14.3%
ECM #6 Water Conservation $7,871 $547 14.4 -30.5%
REM #1 4 kW Solar Array $22,000 $1,451 15.2 -1.1%
Notes:
NET INSTALLATION
COSTA
RENEWABLE ENERGY MEASURES (REM's)
ECM NO.
DESCRIPTIONNET
INSTALLATION COST
ANNUAL
SAVINGSB
ANNUAL SAVINGS
SIMPLE PAYBACK
(Yrs)
SIMPLE LIFETIME
ROI
A. Cost takes into consideration applicable NJ Smart StartTM incentives.B. Savings takes into consideration applicable maintenance savings.
ECM NO.
DESCRIPTIONSIMPLE
PAYBACK (Yrs)
SIMPLE LIFETIME
ROI
ENERGY CONSERVATION MEASURES (ECM's)
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 13 of 32
Table 2 ECM Energy Summary
ECM #1 Interior Lighting Upgrade 7.2 20,504 0
ECM #2 Interior Lighting Controls 0.0 277 0
ECM #3 Exterior Lighting Upgrade 2.3 5,983 0
ECM #4Domestic Water Heater
Upgrade0.0 5,083 -177
ECM #5 Window AC Unit 0.6 466 0
ECM #6 Water Conservation 0.0 2,747 0
REM #1 4 kW Solar Array 3.9 5,191 0
ECM NO.
DESCRIPTION
ANNUAL UTILITY REDUCTION
ECM NO.
DESCRIPTION
ANNUAL UTILITY REDUCTION
RENEWABLE ENERGY MEASURES (REM's)
NATURAL GAS (THERMS)
ELECTRIC DEMAND
(KW)
NATURAL GAS (THERMS)
ELECTRIC CONSUMPTION
(KWH)
ENERGY CONSERVATION MEASURES (ECM's)
ELECTRIC DEMAND
(KW)
ELECTRIC CONSUMPTION
(KWH)
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 14 of 32
Table 3 ECM Emissions Summary
ECM #1 Interior Lighting Upgrade 31,166 57 133
ECM #2 Interior Lighting Controls 421 1 2
ECM #3 Exterior Lighting Upgrade 9,094 17 39
ECM #4Domestic Water Heater
Upgrade5,655 13 33
ECM #5 Window AC Unit 708 1 3
ECM #6 Water Conservation 4,175 8 18
Total Emissions Savings 51,220 97 228
ENERGY CONSERVATION MEASURES (ECM's)
ECM NO.
DESCRIPTION
GREENHOUSE GAS EMISSIONS REDUCTION
CO2
EMISSIONS (LBS)
NOX
EMISSIONS (LBS)
SO2
EMISSIONS (LBS)
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 15 of 32
Table 4 Facility Project Summary
Note that the measure totals in this table do not take into account interactive effects of measures; see Method of Analysis Section III in Executive Report for further explanation. This project does not qualify for additional incentives through the Pay for Performance Program; please see the Installation Funding Options section for additional program options.
Interior Lighting Upgrade $2,624 $18,622 $1,865 $16,757 6.4
Interior Lighting Controls $35 $1,600 $200 $1,400 40.0
Exterior Lighting Upgrade $766 $4,869 $1,425 $3,444 4.5
Domestic Water Heater Upgrade
$505 $5,800 $50 $5,750 11.4
Window AC Unit $60 $630 $0 $630 10.5
Water Conservation $547 $7,871 $0 $7,871 14.4
Total Project $4,537 $39,392 $3,540 $35,852 7.9
FACILITY PROJECT SUMMARY TABLE
ENERGY CONSERVATION
MEASURES
ANNUAL ENERGY
SAVINGS ($)
PROJECT COST ($)
CUSTOMER COST
SIMPLE PAYBACK
SMART START
INCENTIVES
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 16 of 32
ECM #1: Interior Lighting Upgrade Description: Approximately half of the interior lighting in the Library is provided with fluorescent fixtures with T12 lamps and magnetic ballasts. The other half of the lighting is provided by older generation, 700 series and 741/ECO 32W T8 lamps and electronic ballasts. Considerable energy savings can be achieved by replacing the existing T12 lighting fixtures with equivalent LED lighting fixtures with the appropriate wattage. The fixtures with T8 lamps can be retro-fitted with Light Emitting Diode (LED) direct replacement T8 ballast compatible lamps without compromising light output. Any older T12 fixtures with magnetic ballasts (reading area, restrooms, basement workroom, basement storage, etc.) would be replaced with the appropriate new LED lighting fixtures. This ECM also includes replacement of any incandescent lamps with Phillips Endura LED lamps which can be retrofit into existing incandescent A-lamp fixtures. All exit signs throughout the building are currently high efficiency LED exit signs. Energy Savings Calculations:
The Investment Grade Lighting Audit Appendix outlines the hours of operation, proposed retrofits, costs, savings, and payback periods for each set of fixtures in the each building.
DESCRIPTION SAVINGSElectric Demand Savings (kW) 7.2Electric Usage Savings (kWh) 20,504
Electric Cost Savings ($) $2,624
LIGHTING UPGRADE SAVINGS SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 17 of 32
Energy Savings Summary:
Installation Cost ($): $18,622
NJ Smart Start Equipment Incentive ($): $1,865
Net Installation Cost ($): $16,757
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $2,624
Total Yearly Savings ($/Yr): $2,624
Estimated ECM Lifetime (Yr): 15
Simple Payback 6.4
Simple Lifetime ROI 134.9%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $39,360
Internal Rate of Return (IRR) 13%
Net Present Value (NPV) $14,568.14
ECM #1 - ENERGY SAVINGS SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 18 of 32
ECM #2: Interior Lighting Controls Upgrade – Occupancy Sensors Description: Some of the lights in the Library are left on unnecessarily. In many cases the lights are left on because of the inconvenience to manually switch lights off when a room is left or on when a room is first occupied. This is common in rooms that are occupied for only short periods and only a few times per day. In some instances lights are left on due to the misconception that it is better to keep the lights on rather than to continuously switch lights on and off. Although increased switching reduces lamp life, the energy savings outweigh the lamp replacement costs. The payback timeframe for when to turn the lights off is approximately two minutes. If the lights are expected to be off for at least a two minute interval, then it pays to shut them off.
Lighting controls come in many forms. Sometimes an additional switch is adequate to provide reduced lighting levels when full light output is not needed. Occupancy sensors detect motion and will switch the lights on when the room is occupied. Occupancy sensors can either be mounted in place of a current wall switch, or on the ceiling to cover large areas. The U.S. Department of Energy sponsored a study to analyze energy savings achieved through various types of building system controls. The referenced savings is based on the “Advanced Sensors and Controls for Building Applications: Market Assessment and Potential R&D Pathways,” document posted for public use April 2005. The study has found that commercial buildings have the potential to achieve significant energy savings through the use of building controls. The average energy savings are as follows based on the report:
Occupancy Sensors for Lighting Control 20% - 28% energy savings.
Savings resulting from the implementation of this ECM for energy management controls are estimated to be 20% of the total light energy controlled by occupancy sensors (The majority of the savings is expected to be after hours when rooms are left with lights on) This ECM includes installation of ceiling or switch mount sensors for offices, large storage rooms, and restrooms. The larger rooms/spaces will have multiple sensors that will automatically turn off lights when the spaces are unoccupied. These new sensors will contain the latest dual-sensor technology (passive infrared and ultrasonic activated). The Investment Grade Lighting Audit Appendix of this report includes the summary of lighting controls implemented in this ECM and outlines the proposed controls, costs, savings, and payback periods. The calculations adjust the lighting power usage by the applicable percent savings for each area that includes lighting controls. Energy Savings Calculations:
kWh/YrEnergyLightControlledSavings%SavingsEnergy
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 19 of 32
kWh
$CostElecAvekWhSavingsEnergySavings.
Rebates and Incentives:
From the NJ Smart Start® Program Incentives Appendix, the installation of a lighting control device warrants the following incentive: SmartStartIncentive
#Wallmountsensors $20persensor#Ceilingmountsensors $35persensor
Energy Savings Summary:
DESCRIPTION SAVINGSElectric Demand Savings (kW) 0.0Electric Usage Savings (kWh) 277
Electric Cost Savings ($) $35
LIGHTING CONTROLS SAVINGS SUMMARY
Installation Cost ($): $1,600
NJ Smart Start Equipment Incentive ($): $200
Net Installation Cost ($): $1,400
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $35
Total Yearly Savings ($/Yr): $35
Estimated ECM Lifetime (Yr): 15
Simple Payback 40.0
Simple Lifetime ROI -62.5%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $525
Internal Rate of Return (IRR) -10%
Net Present Value (NPV) ($982.17)
ECM #2 - ENERGY SAVINGS SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 20 of 32
ECM #3: Exterior Lighting Upgrade Description: Exterior lighting throughout the Library is provided by various types, sizes and wattages of metal halide wall-mounted fixtures and canopy 60-watt incandescent lamp fixtures. This ECM includes the replacement of existing fixtures with new high-efficiency LED lighting fixtures that require a lower energy use for the same light output. LED bulbs and diodes have an outstanding operational life time expectancy of 100,000 hours which equates to 22 years at 50% operation. This results in substantial savings in bulb replacement. Exterior lighting is controlled via time clock and typically operates from dusk to dawn or less. Energy Savings Calculations:
The Investment Grade Lighting Audit Appendix outlines the hours of operation, proposed retrofits, costs, savings, and payback periods for each set of exterior fixtures on the building. Maintenance Savings and Project Costs: Maintenance savings have not been included in the energy savings summary. Project Costs were obtained from lighting vendor quotes and a local lighting contractor.
DESCRIPTION SAVINGSElectric Demand Savings (kW) 2.3Electric Usage Savings (kWh) 5,983
Electric Cost Savings ($) $766
LIGHTING UPGRADE SAVINGS SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 21 of 32
Energy Savings Summary:
Installation Cost ($): $4,869
NJ Smart Start Equipment Incentive ($): $1,425
Net Installation Cost ($): $3,444
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $766
Total Yearly Savings ($/Yr): $766
Estimated ECM Lifetime (Yr): 15
Simple Payback 4.5
Simple Lifetime ROI 233.6%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $11,490
Internal Rate of Return (IRR) 21%
Net Present Value (NPV) $5,700.46
ECM #3 - ENERGY SAVINGS SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 22 of 32
ECM #4: Ultra High Efficiency Gas-Fired Water Heater
Description: The Library has an existing Bradford White Model M240SDS electric hot water heater which is located in the basement. The water heater is just 2 years old but could be replaced with a much more efficient gas-fired hot water heating system. This ECM would replace the electric domestic water heater with a 96% thermal efficient Bradford White gas-fired 40 MBH and 50 gallons of storage domestic water heater. Energy Savings Calculations: Energy Density for Library Building = 1.7 kBtu / SF / year
)(SFFootageSquareBuildingSF
yrkBtuDensityEnergyUsageHeatDHW
UnitFuel
BTUValueHeatFuelEffHeating
BtuConsHeatHWDomUsageTotalDHW
%.
.
UnitFuelCostFuelAveUnitsFuelUsageFuelHeatingCostEnergy
$
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 23 of 32
Maintenance Savings and Project Costs: No maintenance cost savings were estimated for this measure. The installed cost for a gas-fired, high efficiency, condensing domestic water heater is estimated to be $5,800. Project Costs are based off RS Means Unit Cost data.
ECM INPUTS EXISTING PROPOSED SAVINGS
ECM INPUTSExisting Hot Water
HeaterBradford White
Ultra High Efficiency
Building Type Library
Building Square-foot 10,000 10,000
Domestic Water Usage, kBtu 17,000.00 17,000.00
DHW Heating Fuel Type Electric Gas
Heating Efficiency 98% 96% -2%
Total Usage (kBTU) 17,347 17,708 -361
Electric Cost ($/kWh) $ 0.128 $ 0.128
Nat Gas Cost ($/Therm) $ 0.820 $ 0.820
ECM RESULTS EXISTING PROPOSED SAVINGS
Electric Usage (kWh) 5,083 0 5,083
Natural Gas Usage (Therms) 0 177 -177
Energy Cost ($) $651 $145 $505
COMMENTS:
CONDENSING DOM. HOT WATER HEATER CALCULATIONS
Savings are based on Energy Information Administration Commercial Building Energy Consumption Survey 2003 Information
ENERGY SAVINGS CALCULATIONS
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 24 of 32
Energy Savings Summary:
Installation Cost ($): $5,800
NJ Smart Start Equipment Incentive ($): $50
Net Installation Cost ($): $5,750
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $505
Total Yearly Savings ($/Yr): $505
Estimated ECM Lifetime (Yr): 15
Simple Payback 11.4
Simple Lifetime ROI 31.7%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $7,575
Internal Rate of Return (IRR) 4%
Net Present Value (NPV) $278.66
ECM #4 - ENERGY SAVINGS SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 25 of 32
ECM #5: Window AC Unit Replacement
Description: The primary source of cooling for the offices is window air conditioning units. These units vary in size, capacity and efficiency. These window AC units are old and inefficient. It is recommended to utilize the Energy Star ratings as a minimum standard for replacing any window unit that is in need of replacement. Existing units that are old but still working should be considered for replacement if the efficiency is 8.5 EER or less. Window AC units that are over 10 years old are very likely to fall in this efficiency range. This ECM shows the savings and payback for inefficient window air conditioners with new, Energy Star rated units. Qualifying product list can be found at Energy Star website at: www.energystar.gov/products. Although Energy Star rated products provide a valuable benchmark, it is recommended to consider even higher EER ratings for potential AC unit replacements where available. Energy Savings Calculations: Average Electric Cost: $0.128/kWh Typical AC Unit Size: 8,000 BTU/HR or 12,000 BTU/HR Estimated Full Load Hours of Unit: 800/Year
EnergySavings, kWh CoolingCapacity,BTUHr
1EER
1EER
FullLoadHours
1000 WkWh
DemandSavings, kWEnergySavings kWhHoursofCooling
CoolingCostSavings EnergySavings kWh AverageSummerElec. Cost$
kWh
Capacity BTU/H
Amount of Units
Full Load Hrs
Typical Eff. (10 Yrs &
Older) EER
New Eff. EER
Energy Savings
kWh
Demand Savings kW
Cooling Cost
Savings
Net Installed
Cost
Simple Payback
8,000 1 800 8.5 11.3 187 0.23 $24 $280 11.7
12,000 1 800 8.5 11.3 280 0.35 $36 $350 9.8
ENERGY SAVINGS CALCULATIONS
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 26 of 32
Energy Savings Summary:
Installation Cost ($): $630
NJ Smart Start Equipment Incentive ($): $0
Net Installation Cost ($): $630
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $60
Total Yearly Savings ($/Yr): $60
Estimated ECM Lifetime (Yr): 12
Simple Payback 10.5
Simple Lifetime ROI 14.3%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $720
Internal Rate of Return (IRR) 2%
Net Present Value (NPV) ($32.76)
ECM #5 - ENERGY SAVINGS SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 27 of 32
ECM #6: Water Conservation Measures Description: The Library utilizes standard plumbing fixtures in the restrooms. The typical water closet and urinal water consumption only meet the minimum federally required standard for water efficiency. New flush valves are available that use less water than today’s requirements and can add up to significant water reduction over a long period. In addition, the sinks do not have low-flow aerators nor automatic shut offs. This ECM includes the replacement of the existing water closet and urinal flush valves within the restrooms at the facility. In addition, low-flow aerators and automatic shutoffs will be installed at all sinks. The estimated usage of the plumbing fixtures is based on the total population of the facility. The number of valves/faucets to be replaced is based on observation of the facility in combination with federal minimum standards per occupancy load. The proposed retrofit includes installation of low-flow automatic flush valves that utilize 1.0 gallon per flush for the water closets, 0.5 gallon per flush for the urinals, and 0.5 GPM for the sinks. Energy Savings Calculations: For the basis of this calculation the LEED rating system was used to estimate the occupancy usage for employees in the facility. When water consumption information was not available, the GPF values were estimated for the existing fixtures.
A. Water Closets and Urinals:
Flush
GalFixture
DayperPerson
FlushUse
Yr
DaysOccupancynConsumptioWater
Gal1000
Gal1000
$CostAveGallonsn ConsumptioWater
CostWater
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 28 of 32
B. Automatic Sink Faucets with Low-Flow Aerators
WaterUsage Quantity OperationDaysyr
UsageMinDay
FixtureGalMin
ElectricUsage
FaucetWaterUsage Gal 8.33lbsGal
SpecificHeat 1 ∆T 70
3,413Btu
1HWHEfficiency
50%
ECM INPUTS EXISTING PROPOSED SAVINGS
ECM INPUTS Existing FixturesLow Flow / Auto
Flow Fixtures-
Total Number of Occupants 10 10 -
% Male to Female 50% 50% -
Occupied Days Per Year 300 300 -
Lavatory Uses per Day per Person (Female) 3 3 -
Lavatory Uses per Day per Person (Male) 2 2
WC Uses per Day per Person 2.0 2.0 -
Urinal Uses per Day per Person 2.0 2.0 -
Total Urinal Flushes Per Day 10 10 -
Total WC Flushes Per Day 25 25 -
Urinal Gallons Per Flush (GPF) 2.200 0.500 1.700
WC Gallons Per Flush (GPF) 1.6 1.28 0.32
** Water Cost ($/1000 Gal) $5.00 $5.00 -
ECM RESULTS EXISTING PROPOSED SAVINGSWater Consumption, Water Closets (Gal) 18,600 11,100 7,500
Water Cost ($) $93 $56 $38
COMMENTS:
WATER CONSERVATION CALCULATIONS
ENERGY SAVINGS CALCULATIONS
*Savings are based on LEED Reference Guide for Green Building Design and Construction - 2009 Edition for WC and Urinal water usage.
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 29 of 32
Project Cost and Incentive Estimates: The cost for installation and materials for six (6) water closet automatic flush valves, four (4) urinal automatic flush valves, and six (6) automatic sink shutoffs with low-flow sink aerators is approximately $7,870. Project costs were obtained from vendor pricing and a local Plumbing Contractor. There are no Smart Start rebates for installation of low flow or automatic plumbing fixtures.
ECM INPUTS EXISTING PROPOSED SAVINGS
Quantity of Sinks 6 6
Flow Rate (GPM) 2.2 0.5 1.7
Device Usage (min per day) 10 9
Facility Operation (days / year) 300 300
Heat Content of Water (Btu/gal/°F) 8.33 8.33
Temperature Rise (°F) 70.0 70.0
Water Heater Type Electric Electric
Efficiency of Heating System (%) 98% 98%
Conversion Factor for Electric 3412 3412
Conversion Factor for Gas 100000 100000
Electric Rate ($/kWh) $0.128 $0.128
Natural Gas Rate ($/therm) $0.820 $0.820
Water Rate ($/1000gal) $5.000 $5.000
Electric Usage (kWh) 3,453 706 2,747Natural Gas Usage (Therm) 0 0 0Water Usage (gallons) 39,600 8,100 31,500Energy Cost ($) $640 $131 $509COMMENTS:
LOW FLOW WATER SAVING DEVICES
ENERGY SAVINGS CALCULATIONS
Heating Savings based on 50% Hot Cold Mix. Assume a 10% reduction based on timed faucet controls
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 30 of 32
Energy Savings Summary:
Installation Cost ($): $7,871
NJ Smart Start Equipment Incentive ($): $0
Net Installation Cost ($): $7,871
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $547
Total Yearly Savings ($/Yr): $547
Estimated ECM Lifetime (Yr): 10
Simple Payback 14.4
Simple Lifetime ROI -30.5%
Simple Lifetime Maintenance Savings 0
Simple Lifetime Savings $5,470
Internal Rate of Return (IRR) -6%
Net Present Value (NPV) ($3,204.98)
ECM #6 - ENERGY SAVINGS SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 31 of 32
REM #1: 4 kW Solar System Description: The Public Library Building has available roof space that could accommodate solar arrays. Based on the available area a 4 kilowatt solar array could be installed. The array will produce approximately 5,191 kilowatt-hours annually that will reduce the overall electric usage of the facility by 8%. The owner should consult a structural engineer prior to installing any solar array to insure the roof can accommodate the additional weight. Energy Savings Calculations: See Renewable / Distributed Energy Measures Calculations Appendix for detailed financial summary and proposed solar layout areas. Financial results in table below are based on 100% financing of the system over a fifteen year period. Energy Savings Summary:
Installation Cost ($): $22,000
NJ Smart Start Equipment Incentive ($): $0
Net Installation Cost ($): $22,000
SREC Revenue ($/Yr): $786
Energy Savings ($/Yr): $664
Total Yearly Savings ($/Yr): $1,451
Estimated ECM Lifetime (Yr): 15
Simple Payback 15.2
Simple Lifetime ROI -1.1%
Simple Lifetime Maintenance Savings $11,796
Simple Lifetime Savings $21,762
Internal Rate of Return (IRR) -0.1%
Net Present Value (NPV) ($4,680.81)
REM #1 - ENERGY SAVINGS SUMMARY
Town of Dover – Public Library Energy Audit
Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 32 of 32
VI. ADDITIONAL RECOMMENDATIONS The following recommendations include no cost/low cost measures, Operation & Maintenance (O&M) items, and water conservation measures with attractive paybacks. These measures are not eligible for the Smart Start Buildings incentives from the office of Clean Energy but save energy none the less.
A. Chemically clean the condenser and evaporator coils periodically to optimize efficiency. Poorly maintained heat transfer surfaces can reduce efficiency 5-10%.
B. Maintain all weather stripping on windows and doors.
C. Clean all light fixtures to maximize light output.
D. Provide more frequent air filter changes to decrease overall system power usage and maintain better IAQ.
E. Turn off computers when not in use. Ensure computers are not running in screen saver mode.
F. Replace any old CRT Monitors with LED/LCD Type Monitors, which can draw as much as a quarter the power of an equivalent CRT monitor.
G. Ensure outside air dampers are functioning properly and only open during occupied mode.
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX A
APPENDIX A1 of 1
LIFETIME ENERGY SAVINGS
LIFETIME MAINTENANCE
SAVINGSLIFETIME ROI SIMPLE PAYBACK
INTERNAL RATE OF RETURN (IRR)
NET PRESENT VALUE (NPV)
MATERIAL LABORREBATES,
INCENTIVES
NET INSTALLATION
COSTENERGY MAINT. / SREC TOTAL (Yearly Saving * ECM Lifetime)
(Yearly Maint Svaing * ECM Lifetime)
(Lifetime Savings - Net Cost) / (Net Cost)
(Net cost / Yearly Savings)
($) ($) ($) ($) ($/Yr) ($/Yr) ($/Yr) (Yr) ($) ($) (%) (Yr) ($) ($)
ECM #1 Interior Lighting Upgrade $9,716 $8,906 $1,865 $16,757 $2,624 $0 $2,624 15 $39,360 $0 134.9% 6.4 13.23% $14,568.14
ECM #2 Interior Lighting Controls $1,250 $350 $200 $1,400 $35 $0 $35 15 $525 $0 -62.5% 40.0 -10.33% ($982.17)
ECM #3 Exterior Lighting Upgrade $3,420 $1,449 $1,425 $3,444 $766 $0 $766 15 $11,490 $0 233.6% 4.5 20.96% $5,700.46
ECM #4 Domestic Water Heater Upgrade $2,900 $2,900 $50 $5,750 $505 $0 $505 15 $7,575 $0 31.7% 11.4 3.66% $278.66
ECM #5 Window AC Unit $630 $0 $0 $630 $60 $0 $60 12 $720 $0 14.3% 10.5 2.12% ($32.76)
ECM #6 Water Conservation $3,500 $4,371 $0 $7,871 $547 $0 $547 10 $5,470 $0 -30.5% 14.4 -6.12% ($3,204.98)
REM #1 4 kW Solar Array $14,000 $8,000 $0 $22,000 $664 $786 $1,451 15 $21,762 $11,796 -1.1% 15.2 -0.14% ($4,680.81)
Notes: 1) The variable Cn in the formulas for Internal Rate of Return and Net Present Value stands for the cash flow during each period.2) The variable DR in the NPV equation stands for Discount Rate3) For NPV and IRR calculations: From n=0 to N periods where N is the lifetime of ECM and Cn is the cash flow during each period .
REM RENEWABLE ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY
ECM COST & SAVINGS BREAKDOWN
CONCORD ENGINEERING
Town of Dover - Public Library
INSTALLATION COST YEARLY SAVINGS
ECM LIFETIMEDESCRIPTIONECM NO.
ECM ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX B
Appendix B Page 1 of 6
Concord Engineering Group, Inc. 520 BURNT MILL ROAD VOORHEES, NEW JERSEY 08043 PHONE: (856) 427-0200 FAX: (856) 427-6508
SmartStart Building Incentives The NJ SmartStart Buildings Program offers financial incentives on a wide variety of building system equipment. The incentives were developed to help offset the initial cost of energy-efficient equipment. The following tables show the current available incentives from July 1, 2015 to June 30, 2016, further details including how to apply, forms, and calculated incentive values can be found the Clean Energy Website. (www.njcleanenergy.com)
Electric Chillers
Water-Cooled Chillers
Constant Speed: Base: $8 - $30 per ton
Performance Add: $2 - $2.25 per ton Variable Speed:
Base: $12 - $44 per ton Performance Add: $2 - $4.00 per ton
Air-Cooled Chillers
Constant Speed: Base: $20 per ton
Performance Add: $3.50 per ton Variable Speed:
Base: $90 - $92 per ton Performance Add: $4.00 per ton
Energy Efficiency must comply with ASHRAE 90.1-2013
Gas Cooling Gas Absorption Chillers (Indirect & Direct-Fired)
$185 - $450 per ton
Desiccant Systems
$1.00 per cfm – gas or electric
Electric Unitary HVAC
Unitary AC and Split Systems $73 - $92 per ton Air-to-Air Heat Pumps $73 - $92 per ton
Water-Source Heat Pumps $81 per ton Packaged Terminal AC & HP $65 per ton
Central DX AC Systems $40- $72 per ton Dual Enthalpy Economizer Controls $250 Occupancy Controlled Thermostat
(Hospitality & Institutional Facility) $75 per thermostat
A/C Economizing Controls < 5 tons $85/unit; >5 tons $170/unit Energy Efficiency must comply with ASHRAE 90.1-2007
Appendix B Page 2 of 6
Gas Heating
Hot Water Gas Fired Boilers < 300 MBH
Non-Condensing: $0.95 per MBH,
Minimum $400 per unit Condensing:
$2.00 per MBH, Minimum $1000 per unit
Hot Water Gas Fired Boilers ≥ 300 - 1500 MBH
Non-Condensing: $1.75 per MBH
Condensing: $2.20 per MBH
Minimum $1000 per unit
Hot Water Gas Fired Boilers >1500 - ≤ 2500 MBH
Non-Condensing: $1.50 per MBH
Condensing: $2.20 per MBH
Hot Water Gas Fired Boilers >2500 - ≤ 4000 MBH
Non-Condensing: $1.30 per MBH
Condensing: $2.00 per MBH
Steam, Except Natural Draft, Gas fired Boilers < 300 MBH
$1.40 per MBH, Minimum $400 per unit
Steam, Except Natural Draft, Gas fired Boilers ≥ 300 – 1500 MBH
$1.20 per MBH
Steam, Except Natural Draft, Gas fired Boilers > 1500 – 2500 MBH
$1.20 per MBH
Steam, Except Natural Draft, Gas fired Boilers > 2500 – 4000 MBH
$1.00 per MBH
Steam, Natural Draft < 300 MBH
$1.40 per MBH, Minimum $300 per unit
Steam, Natural Draft ≥ 300 - 1500 MBH
$1.00 per MBH
Steam, Natural Draft >1500 - ≤ 2500 MBH
$0.90 per MBH
Steam, Natural Draft >2500 - ≤ 4000 MBH
$0.70 per MBH
All Types Gas Fired Boilers > 4000 MBH
(Calculated through Custom Measure Path)
Gas Furnaces $400 per unit, AFUE ≥ 95%
Boiler Economizing Controls $1,200 - $2,700
Low Intensity Infrared Heating $300 - $500 per unit
Natural Gas Water Heating Gas Water Heaters ≤ 50 gallons, 0.67
energy factor or better $50 per unit
Gas-Fired Water Heaters > 50 gallons $1.00 - $2.00 per MBH
Gas-Fired Booster Water Heaters $17 - $35 per MBH
Gas Fired Tankless Water Heaters $300 per unit
Appendix B Page 3 of 6
Ground Source Heat Pumps
Closed Loop $450 per ton, EER ≥ 16 $600 per ton, EER ≥ 18 $750 per ton, EER ≥ 20
Energy Efficiency must comply with ASHRAE 90.1-2007
Variable Frequency Drives Variable Air Volume $65 - $155 per hp
Chilled-Water Pumps ≥ 20 hp $60 per VFD rated hp
Rotary Screw Air Compressors ≥ 25 hp $5,250 to $12,500 per drive Centrifugal Fan Applications on
Constant Volume HVAC Systems $80 per VFD rated hp, maximum
$6,000 per drive Cooling Towers ≥ 10 hp $60 per VFD rated hp
Boiler Fans > 5 HP $65 to $155 per hp
Boiler Feed Water Pumps > 5 HP $60 to $155 per hp
Commercial Kitchen Hood up to 50 HP Retrofit $55 – $300 per hp
New Hood $55 - $250 per hp
Prescriptive Lighting
T-8 reduced Wattage (28w/25w 4’, 1-4 lamps)
Lamp & ballast replacement $10 per fixture
For retrofit of T-8 fixtures by permanent de-lamping & new reflectors
(Electronic ballast replacement required)
$5 per fixture
T-5 and T-8 High Bay Fixtures $25 - $150 per fixture
HID ≥ 100w Replace with new induction fixture.
(must be 30% less watts/fixture than HID system)
$70 per fixture
HID ≥ 100w Retrofit with induction lamp, power coupler and generator
(must be 30% less watts/fixture than HID system)
$50 per fixture
Appendix B Page 4 of 6
Prescriptive Lighting - LED
LED Architectural Floor and Spot Luminaires
$50 per fixture
LED Bollard Fixtures $50 per fixture
LED Display Case Lighting $30 per display case
LED Fuel Pump Canopy $100 per fixture
LED High-Bay and Low-Bay Fixtures for Commercial & Industrial Bldgs.
$150 per fixture
LED High-Bay-Aisle Lighting $150 per fixture
LED Linear Ambient Luminaires (Indirect, Indirect/Direct, Direct/Indirect, Direct)
2’ Fixtures - $20/fixture 3’ Fixtures - $30/fixture 4’ Fixtures - $45/fixture 6’ Fixtures - $60/fixture 8’ Fixtures - $75/fixture
LED Linear Replacement Lamps (2’ & 4’ only)
$5 per lamp
Luminaires for Ambient Lighting of Interior Commercial Spaces
(1x4, 2x2, 2x4 New Fixtures and Retrofit Kits)
1x4 LED - $15 per fixture 2x2 LED - $15 per fixture 2x4 LED - $25 per fixture
LED Outdoor Pole/Arm-Mounted Area and Roadway Luminaries
$100 per fixture
LED Outdoor Pole/Arm-Mounted Decorative Luminaries
$50 per fixture
LED Outdoor Wall-Mounted Area Luminaries
$100 per fixture
LED Parking Garage Luminaries $100 per fixture
LED Retrofit Kits for Large Outdoor Pole / Arm-Mounted Area and
Roadway Luminaires $150 per fixture
LED Refrigerator/Freezer case lighting replacement of fluorescent in medium
and low temperature display case
$30 per 4 foot $42 per 5 foot $65 per 6 foot
LED Shelf-Mtd. Display & Task Lights $15 per linear foot
Appendix B Page 5 of 6
LED Stairwell and Passageway Luminaires
$40 per fixture
LED Track or Mono-Point Directional Lighting Fixtures
$30 per fixture
LED Wall-Wash Lights $30 per fixture
EnergyStar Commercial Lighting Fixtures
$5 to $10 per fixture
EnergyStar Screw and Pine-Based Bulbs
$5 to $10 per lamp
Lighting Controls – Occupancy Sensors
Wall Mounted (Existing Facilities Only)
$20 per control
Remote Mounted (Existing Facilities Only)
$35 per control
Daylight Dimming Controls $45 per fixture controlled
Occupancy Based hi-low Dimming Control
$35 per fixture controlled
Occupancy Sensor Remote Mounted High-Bay (Existing Facilities Only)
$35 per control
Refrigeration Doors/Covers
Energy-Efficient Doors/Covers for Installation on Open Refrigerated Cases
$100 per door
Aluminum Night Curtains for Installation on Open Refrigerated Cases
$3.50 per linear foot
Refrigeration Controls
Door Heater Controls $50 per control Electric Defrost Controls $50 per control Evaporator Fan Controls $75 per control Novelty Cooler Shutoff $50 per control
Refrigerator / Freezer Case Premium Efficiency Motors
Fraction ECM Motor < 1 HP $40 per ECM for replacement of
existing shaded-pole motor
Appendix B Page 6 of 6
Food Service Equipment
Combination Oven/Steamer (Electric) $1,000/oven
Combination Oven/Steamer (Natural Gas)
$750/oven
Convection Oven (Electric) $350/oven
Convection Oven (Natural Gas) $500/oven
Rack Oven (Natural Gas) $1,000/single oven, $2,000/double oven
Conveyor Oven (Natural Gas) $500/small deck $750/large deck
Fryer (Electric) $200/vat
Fryer (Natural Gas) $749/vat
Large Vat Fryer (Electric) $200/vat
Large Vat Fryer (Natural Gas) $500/vat
Griddle (Electric) $300/griddle
Griddle (Natural Gas) $125/griddle
Steam Cooker (Electric) $1,250/steamer
Steam Cooker (Natural Gas) $2,000/steamer
Insulated Holding Cabinets $200 to $300/unit
Glass Door Refrigerators $75 to $150/unit
Solid Door Refrigerators $50 to $200/unit
Glass Door Freezers $200 to $1,000/unit
Solid Door Freezers $100 to $600/unit
Ice Machines $50 to $500/unit
Dishwashers $400 to $1,500/unit
Other Equipment Incentives
Performance Lighting
$1.00 per watt per SF below program incentive threshold, currently 5% more energy efficient than ASHRAE 90.1-
2007 for New Construction and Complete Renovation
Custom Electric and Gas Equipment Incentives
not prescriptive
Custom Measures
$0.16 KWh and $1.60/Therm of 1st year savings, or a buy down to a 1 year
payback on estimated savings. Minimum required savings of 75,000
KWh or 1,500 Therms and an IRR of at least 10%.
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX C
ENERGY STAR® Statement of EnergyPerformance
N/AENERGY STAR®
Score1
Public Library
Primary Property Type: LibraryGross Floor Area (ft²): 10,000Built: 1964
For Year Ending: May 31, 2015Date Generated: February 24, 2016
1. The ENERGY STAR score is a 1-100 assessment of a building’s energy efficiency as compared with similar buildings nationwide, adjusting forclimate and business activity.
Property & Contact Information
Property AddressPublic Library32 E. Clinton StreetDover, New Jersey 07801
Property OwnerTown of Dover37 N. Sussex StreetDover, NJ 07801(____)____-______
Primary ContactDonald Travisano37 N. Sussex StreetDover, NJ [email protected]
Property ID: 4778526
Energy Consumption and Energy Use Intensity (EUI)
Site EUI75.4 kBtu/ft²
Annual Energy by FuelElectric - Grid (kBtu) 218,414 (29%)Natural Gas (kBtu) 535,155 (71%)
National Median ComparisonNational Median Site EUI (kBtu/ft²) 142.3National Median Source EUI (kBtu/ft²) 235.6% Diff from National Median Source EUI -47%
Source EUI124.8 kBtu/ft²
Annual EmissionsGreenhouse Gas Emissions (Metric TonsCO2e/year)
58
Signature & Stamp of Verifying Professional
I ___________________ (Name) verify that the above information is true and correct to the best of my knowledge.
Signature: _______________________Date: ___________
Licensed Professional
Donald Travisano37 N. Sussex StreetDover, NJ [email protected]
Professional Engineer Stamp(if applicable)
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX D
MAJOR EQUIPMENT LISTConcord Engineering
Rooftops
Rooftop UnitsTag RTU-1 RTU-2
Unit Type Packaged Packaged
Qty 1 1
Location Rooftop Rooftop
Area Served Entire facility Entire facility
Manufacturer Carrier Carrier
Model No. ZS-05C00AFAA… ZS-05C00AFAA…
Serial No. N1K0338977 N1K0338976
Cooling Type Packaged DX Packaged DX
Cooling Capacity (Tons) 5-tons 5-tons
Cooling Efficiency (SEER/EER)
10.8 EER 10.8 EER
Heating Type No Heating No Heating
Heating Input (MBH) N/A N/A
Efficiency N/A N/A
Supply Fan (HP) 1 1
Supply Fan VFD
Return/Exhaust Fan (HP) N/A N/A
Return/Exhaust Fan VFD
Approx Age 5 5
ASHRAE Service Life 15 15
Remaining Life 10 10
Comments
Note:
"N/A" = Not Applicable. "-" = Info Not Available
Yes No N/A
Yes No N/A
Yes No N/A
Yes No N/A
Appendix D - Major Equipment List - Public Library Page 1 of 3
MAJOR EQUIPMENT LISTConcord Engineering
Boilers
BoilersTag B-1
Unit Type Cast-Iron Sectional (Steam)
Qty 1
Location Boiler Room
Manufacturer Burnham
Model No. 5007N
Serial No. 64868589
Input Capacity 468 MBH
Output Capacity 374 MBH
Approx. Efficiency % (Present Age)
79.0%
Fuel Type Natural Gas
Approx Age 5
ASHRAE Service Life 30
Remaining Life 25
CommentsCondensate Pump/Receiver with
1/2 HP Pump
Note:
"N/A" = Not Applicable. "-" = Info Not Available
Appendix D - Major Equipment List - Public Library Page 2 of 3
MAJOR EQUIPMENT LISTConcord Engineering
Dom HWH
Domestic Water HeatersTag DHW-1
Unit Type Automatic Storage Water Heater
Qty 1
Location Boiler Room
Area Served Entire Facility
Manufacturer Bradford White
Model # M240S6DS
Serial # EK11163489
Storage Size (Gal) 40
Input Capacity (MBH/KW) 3,500 Watts per element
Recovery (Gal/Hr) -
Efficiency % 97%
Fuel Electric
Approx Age 2
ASHRAE Service Life 15
Remaining Life 13
Comments
Note:
"N/A" = Not Applicable. "-" = Info Not Available
Appendix D - Major Equipment List - Public Library Page 3 of 3
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX E
CEG Project #:
Facility Name:
Address:
City, State, Zip
Fixture Reference #
LocationAverage
Burn Hours
DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Work Description Equipment DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Energy Savings,
kW
Energy Savings,
kWh
Energy Savings, $
Control Ref #
Controls DescriptionQty of
Controls
Hour Reduction
%
Energy Savings,
kWh
Energy Savings, $
Material Total Labor Total AllRebate
EstimateSimple
PaybackTotal
MaterialsTotal Labor Total All
Simple Payback
1 Reading Area 30002-Lamp 1x8 F96T12 60W
Pendant-Mounted Egg Crate Lens
2 108.7 12 1.30 3,913 New FixtureInstall New 1x4 Ceiling
Mounted LED Wrap4 58 12 0.70 2,088 0.61 1,825 $234 0 No New Controls 0 0.0% 0 $0 $1,800.00 $1,140.00 $2,940.00 $120.00 12.07 $0.00 $0.00 $0.00 YES -
13 Reading Area 3000Arch. Pendant with 42 Watt
CFL3 126 3 0.38 1,134 Existing to Remain No Change 3 126 0 0.38 1,134 0.00 0 $0 0 No New Controls 0 0.0% 0 $0 $0.00 $0.00 $0.00 $0.00 - $0.00 $0.00 $0.00 FALSE -
3 Book Racks 30003-Lamp 2x4 F32T8 32W Recessed Prismatic Lens
3 86.2 28 2.41 7,241 Re-LampPhilips LED T8 InstaFit Lamp
(12W)3 36 28 1.01 3,024 1.41 4,217 $540 0 No New Controls 0 0.0% 0 $0 $1,848.00 $1,330.00 $3,178.00 $420.00 5.11 $0.00 $0.00 $0.00 FALSE -
4 Men's Restroom 30001-Lamp 6"x24" Vanity
Fixture F34T121 31 1 0.03 93 Re-Lamp
Seesmart 2-foot 9W SP SEP LED Tube
1 9 1 0.01 27 0.02 66 $8 4
Dual Tech. Occupancy Sensor w/2 Pole Powerpack
- Remote Mnt.1 20.0% 5 $1 $22.00 $23.75 $45.75 $5.00 4.82 $300.00 $50.00 $350.00 $35.00 455.73
5 Men's Restroom 3000Ceiling Globe 60 Watt
Incandescent1 60 1 0.06 180 Replace TCP 13W LED A21 LED 1 13 1 0.01 39 0.05 141 $18 0 No New Controls 0 0.0% 0 $0 $12.00 $23.75 $35.75 $5.00 1.70 $0.00 $0.00 $0.00 FALSE -
4 Women's Restroom 30001-Lamp 6"x24" Vanity
Fixture F34T121 31 1 0.03 93 Re-Lamp
Seesmart 2-foot 9W SP SEP LED Tube
1 9 1 0.01 27 0.02 66 $8 4
Dual Tech. Occupancy Sensor w/2 Pole Powerpack
- Remote Mnt.1 20.0% 5 $1 $22.00 $23.75 $45.75 $5.00 4.82 $300.00 $50.00 $350.00 $35.00 455.73
5 Women's Restroom 3000Ceiling Globe 60 Watt
Incandescent1 60 1 0.06 180 Replace TCP 13W LED A21 LED 1 13 1 0.01 39 0.05 141 $18 0 No New Controls 0 0.0% 0 $0 $12.00 $23.75 $35.75 $5.00 1.70 $0.00 $0.00 $0.00 FALSE -
6 Office 30002-Lamp 1x4 F32T8 Surface
Wrap2 62 7 0.43 1,302 Re-Lamp
Philips LED T8 InstaFit Lamp (12W)
2 24 7 0.17 504 0.27 798 $102 5Dual Technology
Occupancy Sensor - Remote Mnt.
1 20.0% 101 $13 $308.00 $332.50 $640.50 $70.00 5.59 $200.00 $50.00 $250.00 $35.00 16.66
5 Basement Restrooms 3000Ceiling Globe 60 Watt
Incandescent1 60 1 0.06 180 Replace TCP 13W LED A21 LED 1 13 1 0.01 39 0.05 141 $18 4
Dual Tech. Occupancy Sensor w/2 Pole Powerpack
- Remote Mnt.1 20.0% 8 $1 $12.00 $23.75 $35.75 $5.00 1.70 $300.00 $50.00 $350.00 $35.00 315.50
4 Basement Restrooms 30001-Lamp 6"x24" Vanity
Fixture F34T121 31 1 0.03 93 Re-Lamp
Seesmart 2-foot 9W SP SEP LED Tube
1 9 1 0.01 27 0.02 66 $8 0 No New Controls 0 0.0% 0 $0 $22.00 $23.75 $45.75 $5.00 4.82 $0.00 $0.00 $0.00 FALSE -
8 Basement Work Room 30002-Lamp 1x4 F34T12
Surface Wrap2 62 2 0.12 372 Re-Lamp
Philips LED T8 InstaFit Lamp (12W)
2 24 2 0.05 144 0.08 228 $29 6Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 29 $4 $88.00 $95.00 $183.00 $20.00 5.59 $50.00 $50.00 $100.00 $20.00 21.70
7Basement
Storage/Meeting Room
30004-Lamp 2x4 F40T12 34W Recessed Prismatic Lens
4 119 30 3.57 10,710 Re-LampPhilips LED T8 InstaFit Lamp
(12W)4 48 30 1.44 4,320 2.13 6,390 $818 0 No New Controls 0 0.0% 0 $0 $2,640.00 $2,850.00 $5,490.00 $600.00 5.98 $0.00 $0.00 $0.00 FALSE -
8 Storage Room 30002-Lamp 1x4 F34T12
Surface Wrap2 62 8 0.50 1,488 Re-Lamp
Philips LED T8 InstaFit Lamp (12W)
2 24 8 0.19 576 0.30 912 $117 6Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 115 $15 $352.00 $380.00 $732.00 $80.00 5.59 $50.00 $50.00 $100.00 $20.00 5.43
8 Children's Book Area 30002-Lamp 1x4 F34T12
Surface Wrap2 62 47 2.91 8,742 Re-Lamp
Philips LED T8 InstaFit Lamp (12W)
2 24 47 1.13 3,384 1.79 5,358 $686 0 No New Controls 0 0.0% 0 $0 $2,068.00 $2,232.50 $4,300.50 $470.00 5.59 $0.00 $0.00 $0.00 FALSE -
1 Storage Room 4002-Lamp 1x8 F96T12 60W
Pendant-Mounted Egg Crate Lens
2 108.7 3 0.33 130 New FixtureInstall New 1x4 Ceiling
Mounted LED Wrap4 58 3 0.17 70 0.15 61 $8 6
Dual Technology Occupancy Sensor - Switch
Mnt.1 20.0% 14 $2 $450.00 $285.00 $735.00 $30.00 90.53 $50.00 $50.00 $100.00 $20.00 44.90
11 Mechanical Room 40060 Watt Incandescent Industrial Shade Open
1 60 5 0.30 120 Re-Lamp TCP 13W LED A21 LED 1 13 5 0.07 26 0.24 94 $12 0 No New Controls 0 0.0% 0 $0 $60.00 $118.75 $178.75 $25.00 12.78 $0.00 $0.00 $0.00 FALSE -
10 Exterior Building 2600 Wall-Mounted 150 MH 1 185 14 2.59 6,734 Replace RAB 40 Watt LED Wall Pack 1 40 14 0.56 1,456 2.03 5,278 $676 0 No New Controls 0 0.0% 0 $0 $3,360.00 $1,330.00 $4,690.00 $1,400.00 4.87 $0.00 $0.00 $0.00 FALSE -
12 Exterior Building 300060 Watt Exterior Lamp Post
Fixture1 60 5 0.30 900 Re-Lamp TCP 13W LED A21 LED 1 13 5 0.07 195 0.24 705 $90 0 No New Controls 0 0.0% 0 $0 $60.00 $118.75 $178.75 $25.00 1.70 $0.00 $0.00 $0.00 FALSE -
TOTAL 170 15.42 43,605 167 5.99 17,119 9.44 26,487 $3,390 7 277 $35 $13,136 $10,355 $23,491 $3,290 5.96 $1,250 $350 $1,600 $200.00 39.44
Dover, NJ 07801
32 E. Clinton Street
1C15676
Public Library
LIGHTING CONTROLS COSTRETROFIT ENERGY SAVINGSEXISTING FIXTURES PROPOSED FIXTURE RETROFIT PROPOSED LIGHTING CONTROLS LIGHTING RETROFIT COSTS
Smart Start Incentive
Appendix E - Lighting Audit - Public Library Page 1 of 1
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX F
Appendix FPage 1 of 3
Location Description
Area (Sq FT) Panel Qty
Panel Sq Ft
Panel Total Sq
FtTotal KWDC
Total Annual kWh
Total KWAC
Panel Weight
(41.9 lbs) W/SQFT
Library 1125SHARP
ND-240QCJ18 17.5 316 4.32 5,191 3.9 754 13.68
= Proposed PV Roof Layout = Proposed PV Parking Layout
Notes:
1. Estimated kWH based on the National Renewable Energy Laboratory PVWatts Version 1 Calculator Program.
Appendix FPage 2 of 3
Project Name: LGEA Solar PV Project - Library
Location: Dover, NJDescription: Photovoltaic System 100% Financing - 15 year
Simple Payback Analysis
Total Construction Cost $22,000Annual kWh Production 5,191
Annual Energy Cost Reduction $664Average Annual SREC Revenue $786
Simple Payback: Years
Life Cycle Cost AnalysisAnalysis Period (years): 15 Financing %: 100%
Discount Rate: 3% Maintenance Escalation Rate: 3.0%Average Energy Cost ($/kWh) $0.128 Energy Cost Escalation Rate: 3.0%
Financing Rate: 6.00% Average SREC Value ($/kWh) $0.152Period Additional Energy kWh Energy Cost Additional SREC Interest Loan Net Cash Cumulative
Cash Outlay Production Savings Maint Costs Revenue Expense Principal Flow Cash Flow0 $0 0 0 0 $0 0 0 0 01 $0 5,191 $664 $0 $1,298 $1,295 $933 ($266) ($266)2 $0 5,165 $684 $0 $1,291 $1,237 $991 ($252) ($518)3 $0 5,139 $705 $0 $1,285 $1,176 $1,052 ($238) ($756)4 $0 5,113 $726 $0 $1,023 $1,111 $1,117 ($479) ($1,236)5 $0 5,087 $748 $52 $1,017 $1,042 $1,186 ($515) ($1,750)6 $0 5,062 $770 $52 $1,012 $969 $1,259 ($497) ($2,248)7 $0 5,037 $793 $52 $756 $891 $1,336 ($731) ($2,979)8 $0 5,012 $817 $52 $752 $809 $1,419 ($711) ($3,689)9 $0 4,986 $842 $51 $748 $722 $1,506 ($690) ($4,379)10 $0 4,962 $867 $51 $496 $629 $1,599 ($916) ($5,295)11 $0 4,937 $893 $51 $494 $530 $1,698 ($892) ($6,187)12 $0 4,912 $920 $51 $491 $425 $1,803 ($868) ($7,054)13 $0 4,888 $947 $50 $244 $314 $1,914 ($1,086) ($8,141)14 $0 4,863 $976 $50 $243 $196 $2,032 ($1,059) ($9,200)15 $0 4,839 $1,005 $50 $242 $71 $2,157 ($1,031) ($10,230)
Totals: 75,191 $12,357 $562 $11,392 $11,417 $22,000 ($10,230) ($63,926)Net Present Value (NPV)
Photovoltaic System 100% Financing - 15 year
15.16
($7,262)
Appendix FPage 3 of 3
PVWatts: Monthly PV Performance Data Rooftop ArrayRequested Location: 32 E Clinton St, Dover, NJ 07801Location: NEWARK, NJLat (deg N): 40.7Long (deg W): 74.17Elev (m): 9DC System Size (kW): 4.32Module Type: StandardArray Type: Fixed (roof mount)Array Tilt (deg): 10Array Azimuth (deg): 175System Losses: 14Invert Efficiency: 96DC to AC Size Ratio: 1.1Average Cost of Electricity No utility data availableInitial Cost No initial cost definedCost of Electricity Generatenot determined
MonthAC System
Output(kWh)
Solar Radiation
(kWh/m^2/day)
Plane of Array Irradiance (W/m^2)
DC array Output (kWh) Value ($)
1 275 2.39 74.05 289 02 327 3.16 88.61 343 03 455 4.07 126.22 477 0.004 505 4.83 144.96 529 0.005 597 5.70 176.63 624 0.006 586 5.94 178.22 614 0.007 581 5.76 178.70 609 0.008 538 5.38 166.76 563 0.009 463 4.65 139.52 485 0.00
10 384 3.61 112.02 402 011 252 2.35 70.60 265 012 227 2.01 62.36 240 0
Total 5,191 49.87 1518.63 5,441 0