facility energy report - s3. · pdf filetown of dover – public library energy audit...

54
TOWN OF DOVER PUBLIC LIBRARY 32 E. CLINTON STREET DOVER, NJ 07801 FACILITY ENERGY REPORT

Upload: dokhuong

Post on 01-Feb-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

TOWN OF DOVER

PUBLIC LIBRARY

32 E. CLINTON STREET DOVER, NJ 07801

FACILITY ENERGY REPORT

Page 2: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32

TABLE OF CONTENTS

I.  HISTORIC ENERGY CONSUMPTION/COST ................................................................. 2 

II.  FACILITY ENERGY USE INDEX (EUI) .......................................................................... 7 

III.  FACILITY DESCRIPTION ................................................................................................ 9 

IV.  MAJOR EQUIPMENT LIST ............................................................................................ 11 

V.  ENERGY CONSERVATION MEASURES ..................................................................... 12 

VI.  ADDITIONAL RECOMMENDATIONS ......................................................................... 32 

Appendix A – ECM Cost & Savings Breakdown

Appendix B – New Jersey Smart Start® Program Incentives

Appendix C – Portfolio Manager “Statement of Energy Performance”

Appendix D – Major Equipment List

Appendix E – Investment Grade Lighting Audit

Appendix F – Renewable / Distributed Energy Measures Calculations

Page 3: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 2 of 32

I. HISTORIC ENERGY CONSUMPTION/COST The energy usage for the facility has been tabulated and plotted in graph form as depicted within this section. Each energy source has been identified and monthly consumption and cost noted per the information provided by the Owner. Electric Utility Provider: Jersey Central Power & Light Electric Utility Rate Structure: General Service Secondary 3 Phase Third Party Supplier: Hudson Energy Natural Gas Utility Provider: New Jersey Natural Gas Utility Rate Structure: GSL Third Party Supplier: N/A The electric usage profile represents the actual electrical usage for the facility. The electric utility measures consumption in kilowatt-hours (KWH) and maximum demand in kilowatts (KW). One KWH usage is equivalent to 1000 watts running for one hour. One KW of electric demand is equivalent to 1000 watts running at any given time. The basic usage charges are shown as generation service and delivery charges along with several non-utility generation charges. Rates used in this report reflect the historical data received for the facility. The gas usage profile within each facility report shows the actual natural gas energy usage for the facility. The gas utility measures consumption in cubic feet x 100 (CCF), and converts the quantity into Therms of energy. One Therm is equivalent to 100,000 BTUs of energy.

Page 4: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 3 of 32

Table 1 Electricity Billing Data

Utility Provider: Jersey Central Power & LightRate: General Service Secondary 3 Phase

Meter No: G28658189Account No: 100 001 373 784

Third Party Utility Provider: Hudson EnergyTPS Meter / Acct No:

MONTH OF USE CONSUMPTION KWH TOTAL BILL

Jul-14 9,160 $1,022

Aug-14 4,840 $669

Sep-14 7,160 $919

Oct-14 4,960 $645

Nov-14 4,880 $626

Dec-14 4,720 $614

Jan-15 4,120 $536

Feb-15 4,720 $614

Mar-15 5,240 $681

Apr-15 4,880 $634

May-15 5,360 $697

Jun-15 5,960 $775

Totals 66,000 26.1 Max $8,431

AVERAGE DEMAND 22.2 KW average

AVERAGE RATE $0.128 $/kWh

DEMAND KW

25.2

25.2

25.5

26.1

18.6

18.6

22.0

20.6

19.6

23.6

21.2

19.6

ELECTRIC USAGE SUMMARY

Page 5: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 4 of 32

Figure 1 Electricity Usage Profile

Page 6: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 5 of 32

Table 2 Natural Gas Billing Data

Utility Provider: New Jersey Natural GasRate: GSL

Meter No: 00810236Account No: 13-1162-5760-15

Third Party Utility Provider: -TPS Meter No:

MONTH OF USECONSUMPTION

(THERMS)TOTAL BILL

Jun-14 0.00 $104.00

Jul-14 0.00 $104.00

Aug-14 0.00 $104.00

Sep-14 0.00 $109.00

Oct-14 60.00 $136.00

Nov-14 587.00 $356.34

Dec-14 1,012.00 $634.00

Jan-15 1,479.00 $828.00

Feb-15 1,290.00 $722.00

Mar-15 758.00 $682.00

Apr-15 164.00 $498.00

May-15 2.00 $104.00

TOTALS 5,352.00 $4,381.34

AVERAGE RATE: $0.82 $/THERM

-

NATURAL GAS USAGE SUMMARY

Page 7: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 6 of 32

Figure 2 Natural Gas Usage Profile

Page 8: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 7 of 32

II. FACILITY ENERGY USE INDEX (EUI) Energy Use Index (EUI) is a measure of a building’s annual energy utilization per square foot of building. This calculation is completed by converting all utility usage consumed by a building for one year, to British Thermal Units (BTU) and dividing this number by the building square footage. EUI is a good measure of a building’s energy use and is utilized regularly for comparison of energy performance for similar building types. Building Benchmarking data is collected and analyzed within the Commercial Building Energy Consumption Survey (CBECS), performed by the Energy and Information Administration (EIA). Building data is grouped by function types and tabulated, from which a median site and source energy intensity is determined. The national median or PEER Group Comparable in this instance is the middle value of the national population meaning half the buildings use more energy, and half use less. The PEER Group EUI allows us to compare the relative efficiency of the audited building to that of an average building with the same or similar primary function (i.e. group type). Source use differs from site usage when comparing a building’s energy consumption with the national average. Site energy use is the energy consumed by the building at the building site only. Source energy use includes the site energy use as well as all of the losses to create and distribute the energy to the building. Source energy represents the total amount of raw fuel that is required to operate the building. It incorporates all transmission, delivery, and production losses, which allows for a complete assessment of energy efficiency in a building. The type of utility purchased has a substantial impact on the source energy use of a building. The EPA has determined that source energy is the most comparable unit for evaluation purposes and overall global impact. Both the site and source EUI ratings for the building are provided to understand and compare the differences in energy use. The site and source EUI for this facility is calculated as follows:

BuildingSiteEUIElectricUsageinkBtu FuelUsageinkBtu

BuildingSquareFootage

BuildingSourceEUIElectricUsageinkBtu SSRatio FuelUsageinkBtu SSRatio

BuildingSquareFootage

Page 9: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 8 of 32

Table 3 Energy Use Index Summary

kWh Therms Gallons kBtu kBtu

ELECTRIC 66,000.0 225,324 3.140 707,517

NATURAL GAS 5,352.0 535,200 1.050 561,960

TOTAL 760,524 1,269,477

BUILDING TYPE

BUILDING AREA 10,000 SQUARE FEET

BUILDING SITE EUI 76.05 kBtu/SF/YR 91.6 kBtu/SF/YR

BUILDING SOURCE EUI 126.95 kBtu/SF/YR 235.6 kBtu/SF/YR

46%

*Site - Source Ratio data is provided by the Energy Star Performance Rating Methodology for Incorporating Source Energy Use document.

AUDITED BUILDING PEER COMPARISON

Library Library

More Efficient than PEER Comparison

ENERGY USE INTENSITY CALCULATION

ENERGY TYPEBUILDING USE

SITE ENERGY

SITE-SOURCE RATIO

SOURCE ENERGY

Page 10: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 9 of 32

III. FACILITY DESCRIPTION The Town of Dover Public Library located at 32 East Clinton Street in Dover, NJ was originally constructed in 1964. The facility is made up of a large stack area, reference area, a large basement meeting room, child reading area, staff offices, conference room, study rooms, restrooms, mechanical room and other utility/storage rooms. Occupancy Profile The typical hours of operation for the building are:

Monday through Thursday 8:00 am - 9:00 pm Friday 8:00 am - 5:30 pm Saturday 8:00 am - Noon

The facility is occupied approximately 60 hours per week with a staff of 10 employees. Building Envelope

Exterior walls for the building are masonry brick faced with a concrete block construction. The two-story area of the library has single-pane, 1/8 inch glass thermal windows with aluminum frames that are sliders with a small section being operable. The basement has clearstory windows while the front single-story section has large arch windows. The windows in the remainder of the facility are in average condition. Typical windows are double-pane, 1/8 inch glass thermal windows with aluminum frames.

The front section of the roof is pitched with asphalt shingles over a vapor barrier and insulation. The flat roof section is comprised of a built-up roofing system consisting of a rubber membrane, a cover board and 2-inch rigid roof insulation over metal decking. This portion of the roof is in average condition with areas of the roof showing small signs of ponding. HVAC Systems The building heating is generated by a Burnham Model 5007N gas-fired, flexible water tube steam boiler rated at 468 MBH input, 374 MBH output and with an efficiency of 79% (present age). The boiler is fired by a natural gas 878 CFH (max input) cyclonic burner. The boiler has associated hi/low combustion air dampers that open on a call for heat. Steam is then sent to various steam radiators, steam coils and steam fin-tube radiators throughout the facility. The majority of the library is cooled by two (2) Carrier Model ZS-05C packaged rooftop units that are rated at 5 tons of cooling capacity each and have a cooling efficiency of 10.8 EER. Several smaller offices are cooled by thru-the-wall air conditioning units.

Page 11: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 10 of 32

Exhaust System There is a rooftop exhaust fan that serves the restrooms and an exhaust fan that serves the lobby and large meeting room. A smaller exhaust fan serves the mechanical room. Domestic Hot Water Domestic hot water is generated by a Bradford White Model M240S6DS electric water heater with a 40-gallon capacity. The water heater is rated for 7,000 watts maximum. The domestic hot water is circulated by a 1/25-HP cartridge circulator pump. Plumbing System The sink faucets are rated at 1.0 gallon per minute. The water closets and urinals located in the restroom and locker room areas have a rating of 2.6 and 2.0 gallons per flush, respectively. HVAC System Controls

The boiler operates on an outdoor air lockout/reset through Honeywell control devices. The packaged rooftop units are controlled by stand-alone systems located in the spaces that they serve. There is no front-end BAS computer. The HVAC systems within the building utilize “stand alone” controls. The units are configured to operate in “occupied” mode during the day and “unoccupied” mode at night.

Lighting

Refer to the Investment Grade Lighting Audit Appendix for a detailed list of the lighting throughout the facility and estimated operating hours per space.

Page 12: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 11 of 32

IV. MAJOR EQUIPMENT LIST

The equipment list contains major energy consuming equipment that through implementation of energy conservation measures could yield substantial energy savings. The list shows the major equipment in the facility and all pertinent information utilized in energy savings calculations. An approximate age was assigned to the equipment in some cases if a manufactures date was not shown on the equipment’s nameplate. The ASHRAE service life for the equipment along with the remaining useful life is also shown in the Appendix.

Refer to the Major Equipment List Appendix for this facility.

Page 13: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 12 of 32

V. ENERGY CONSERVATION MEASURES Energy Conservation Measures are developed specifically for this facility. The energy savings and calculations are highly dependent on the information received from the site survey and interviews with operations personnel. The assumptions and calculations should be reviewed by the owner to ensure accurate representation of this facility. The following ECMs were analyzed:

Table 1 ECM Financial Summary

ECM #1 Interior Lighting Upgrade $16,757 $2,624 6.4 134.9%

ECM #2 Interior Lighting Controls $1,400 $35 40.0 -62.5%

ECM #3 Exterior Lighting Upgrade $3,444 $766 4.5 233.6%

ECM #4Domestic Water Heater

Upgrade$5,750 $505 11.4 31.7%

ECM #5 Window AC Unit $630 $60 10.5 14.3%

ECM #6 Water Conservation $7,871 $547 14.4 -30.5%

REM #1 4 kW Solar Array $22,000 $1,451 15.2 -1.1%

Notes:

NET INSTALLATION

COSTA

RENEWABLE ENERGY MEASURES (REM's)

ECM NO.

DESCRIPTIONNET

INSTALLATION COST

ANNUAL

SAVINGSB

ANNUAL SAVINGS

SIMPLE PAYBACK

(Yrs)

SIMPLE LIFETIME

ROI

A. Cost takes into consideration applicable NJ Smart StartTM incentives.B. Savings takes into consideration applicable maintenance savings.

ECM NO.

DESCRIPTIONSIMPLE

PAYBACK (Yrs)

SIMPLE LIFETIME

ROI

ENERGY CONSERVATION MEASURES (ECM's)

Page 14: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 13 of 32

Table 2 ECM Energy Summary

ECM #1 Interior Lighting Upgrade 7.2 20,504 0

ECM #2 Interior Lighting Controls 0.0 277 0

ECM #3 Exterior Lighting Upgrade 2.3 5,983 0

ECM #4Domestic Water Heater

Upgrade0.0 5,083 -177

ECM #5 Window AC Unit 0.6 466 0

ECM #6 Water Conservation 0.0 2,747 0

REM #1 4 kW Solar Array 3.9 5,191 0

ECM NO.

DESCRIPTION

ANNUAL UTILITY REDUCTION

ECM NO.

DESCRIPTION

ANNUAL UTILITY REDUCTION

RENEWABLE ENERGY MEASURES (REM's)

NATURAL GAS (THERMS)

ELECTRIC DEMAND

(KW)

NATURAL GAS (THERMS)

ELECTRIC CONSUMPTION

(KWH)

ENERGY CONSERVATION MEASURES (ECM's)

ELECTRIC DEMAND

(KW)

ELECTRIC CONSUMPTION

(KWH)

Page 15: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 14 of 32

Table 3 ECM Emissions Summary

ECM #1 Interior Lighting Upgrade 31,166 57 133

ECM #2 Interior Lighting Controls 421 1 2

ECM #3 Exterior Lighting Upgrade 9,094 17 39

ECM #4Domestic Water Heater

Upgrade5,655 13 33

ECM #5 Window AC Unit 708 1 3

ECM #6 Water Conservation 4,175 8 18

Total Emissions Savings 51,220 97 228

ENERGY CONSERVATION MEASURES (ECM's)

ECM NO.

DESCRIPTION

GREENHOUSE GAS EMISSIONS REDUCTION

CO2

EMISSIONS (LBS)

NOX

EMISSIONS (LBS)

SO2

EMISSIONS (LBS)

Page 16: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 15 of 32

Table 4 Facility Project Summary

Note that the measure totals in this table do not take into account interactive effects of measures; see Method of Analysis Section III in Executive Report for further explanation. This project does not qualify for additional incentives through the Pay for Performance Program; please see the Installation Funding Options section for additional program options.

Interior Lighting Upgrade $2,624 $18,622 $1,865 $16,757 6.4

Interior Lighting Controls $35 $1,600 $200 $1,400 40.0

Exterior Lighting Upgrade $766 $4,869 $1,425 $3,444 4.5

Domestic Water Heater Upgrade

$505 $5,800 $50 $5,750 11.4

Window AC Unit $60 $630 $0 $630 10.5

Water Conservation $547 $7,871 $0 $7,871 14.4

Total Project $4,537 $39,392 $3,540 $35,852 7.9

FACILITY PROJECT SUMMARY TABLE

ENERGY CONSERVATION

MEASURES

ANNUAL ENERGY

SAVINGS ($)

PROJECT COST ($)

CUSTOMER COST

SIMPLE PAYBACK

SMART START

INCENTIVES

Page 17: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 16 of 32

ECM #1: Interior Lighting Upgrade Description: Approximately half of the interior lighting in the Library is provided with fluorescent fixtures with T12 lamps and magnetic ballasts. The other half of the lighting is provided by older generation, 700 series and 741/ECO 32W T8 lamps and electronic ballasts. Considerable energy savings can be achieved by replacing the existing T12 lighting fixtures with equivalent LED lighting fixtures with the appropriate wattage. The fixtures with T8 lamps can be retro-fitted with Light Emitting Diode (LED) direct replacement T8 ballast compatible lamps without compromising light output. Any older T12 fixtures with magnetic ballasts (reading area, restrooms, basement workroom, basement storage, etc.) would be replaced with the appropriate new LED lighting fixtures. This ECM also includes replacement of any incandescent lamps with Phillips Endura LED lamps which can be retrofit into existing incandescent A-lamp fixtures. All exit signs throughout the building are currently high efficiency LED exit signs. Energy Savings Calculations:

The Investment Grade Lighting Audit Appendix outlines the hours of operation, proposed retrofits, costs, savings, and payback periods for each set of fixtures in the each building.

DESCRIPTION SAVINGSElectric Demand Savings (kW) 7.2Electric Usage Savings (kWh) 20,504

Electric Cost Savings ($) $2,624

LIGHTING UPGRADE SAVINGS SUMMARY

Page 18: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 17 of 32

Energy Savings Summary:

Installation Cost ($): $18,622

NJ Smart Start Equipment Incentive ($): $1,865

Net Installation Cost ($): $16,757

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $2,624

Total Yearly Savings ($/Yr): $2,624

Estimated ECM Lifetime (Yr): 15

Simple Payback 6.4

Simple Lifetime ROI 134.9%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $39,360

Internal Rate of Return (IRR) 13%

Net Present Value (NPV) $14,568.14

ECM #1 - ENERGY SAVINGS SUMMARY

Page 19: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 18 of 32

ECM #2: Interior Lighting Controls Upgrade – Occupancy Sensors Description: Some of the lights in the Library are left on unnecessarily. In many cases the lights are left on because of the inconvenience to manually switch lights off when a room is left or on when a room is first occupied. This is common in rooms that are occupied for only short periods and only a few times per day. In some instances lights are left on due to the misconception that it is better to keep the lights on rather than to continuously switch lights on and off. Although increased switching reduces lamp life, the energy savings outweigh the lamp replacement costs. The payback timeframe for when to turn the lights off is approximately two minutes. If the lights are expected to be off for at least a two minute interval, then it pays to shut them off.

Lighting controls come in many forms. Sometimes an additional switch is adequate to provide reduced lighting levels when full light output is not needed. Occupancy sensors detect motion and will switch the lights on when the room is occupied. Occupancy sensors can either be mounted in place of a current wall switch, or on the ceiling to cover large areas. The U.S. Department of Energy sponsored a study to analyze energy savings achieved through various types of building system controls. The referenced savings is based on the “Advanced Sensors and Controls for Building Applications: Market Assessment and Potential R&D Pathways,” document posted for public use April 2005. The study has found that commercial buildings have the potential to achieve significant energy savings through the use of building controls. The average energy savings are as follows based on the report:

Occupancy Sensors for Lighting Control 20% - 28% energy savings.

Savings resulting from the implementation of this ECM for energy management controls are estimated to be 20% of the total light energy controlled by occupancy sensors (The majority of the savings is expected to be after hours when rooms are left with lights on) This ECM includes installation of ceiling or switch mount sensors for offices, large storage rooms, and restrooms. The larger rooms/spaces will have multiple sensors that will automatically turn off lights when the spaces are unoccupied. These new sensors will contain the latest dual-sensor technology (passive infrared and ultrasonic activated). The Investment Grade Lighting Audit Appendix of this report includes the summary of lighting controls implemented in this ECM and outlines the proposed controls, costs, savings, and payback periods. The calculations adjust the lighting power usage by the applicable percent savings for each area that includes lighting controls. Energy Savings Calculations:

kWh/YrEnergyLightControlledSavings%SavingsEnergy

Page 20: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 19 of 32

kWh

$CostElecAvekWhSavingsEnergySavings.

Rebates and Incentives:

From the NJ Smart Start® Program Incentives Appendix, the installation of a lighting control device warrants the following incentive: SmartStartIncentive

#Wallmountsensors $20persensor#Ceilingmountsensors $35persensor

Energy Savings Summary:

DESCRIPTION SAVINGSElectric Demand Savings (kW) 0.0Electric Usage Savings (kWh) 277

Electric Cost Savings ($) $35

LIGHTING CONTROLS SAVINGS SUMMARY

Installation Cost ($): $1,600

NJ Smart Start Equipment Incentive ($): $200

Net Installation Cost ($): $1,400

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $35

Total Yearly Savings ($/Yr): $35

Estimated ECM Lifetime (Yr): 15

Simple Payback 40.0

Simple Lifetime ROI -62.5%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $525

Internal Rate of Return (IRR) -10%

Net Present Value (NPV) ($982.17)

ECM #2 - ENERGY SAVINGS SUMMARY

Page 21: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 20 of 32

ECM #3: Exterior Lighting Upgrade Description: Exterior lighting throughout the Library is provided by various types, sizes and wattages of metal halide wall-mounted fixtures and canopy 60-watt incandescent lamp fixtures. This ECM includes the replacement of existing fixtures with new high-efficiency LED lighting fixtures that require a lower energy use for the same light output. LED bulbs and diodes have an outstanding operational life time expectancy of 100,000 hours which equates to 22 years at 50% operation. This results in substantial savings in bulb replacement. Exterior lighting is controlled via time clock and typically operates from dusk to dawn or less. Energy Savings Calculations:

The Investment Grade Lighting Audit Appendix outlines the hours of operation, proposed retrofits, costs, savings, and payback periods for each set of exterior fixtures on the building. Maintenance Savings and Project Costs: Maintenance savings have not been included in the energy savings summary. Project Costs were obtained from lighting vendor quotes and a local lighting contractor.

DESCRIPTION SAVINGSElectric Demand Savings (kW) 2.3Electric Usage Savings (kWh) 5,983

Electric Cost Savings ($) $766

LIGHTING UPGRADE SAVINGS SUMMARY

Page 22: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 21 of 32

Energy Savings Summary:

Installation Cost ($): $4,869

NJ Smart Start Equipment Incentive ($): $1,425

Net Installation Cost ($): $3,444

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $766

Total Yearly Savings ($/Yr): $766

Estimated ECM Lifetime (Yr): 15

Simple Payback 4.5

Simple Lifetime ROI 233.6%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $11,490

Internal Rate of Return (IRR) 21%

Net Present Value (NPV) $5,700.46

ECM #3 - ENERGY SAVINGS SUMMARY

Page 23: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 22 of 32

ECM #4: Ultra High Efficiency Gas-Fired Water Heater

Description: The Library has an existing Bradford White Model M240SDS electric hot water heater which is located in the basement. The water heater is just 2 years old but could be replaced with a much more efficient gas-fired hot water heating system. This ECM would replace the electric domestic water heater with a 96% thermal efficient Bradford White gas-fired 40 MBH and 50 gallons of storage domestic water heater. Energy Savings Calculations: Energy Density for Library Building = 1.7 kBtu / SF / year

)(SFFootageSquareBuildingSF

yrkBtuDensityEnergyUsageHeatDHW

UnitFuel

BTUValueHeatFuelEffHeating

BtuConsHeatHWDomUsageTotalDHW

%.

.

UnitFuelCostFuelAveUnitsFuelUsageFuelHeatingCostEnergy

$

Page 24: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 23 of 32

Maintenance Savings and Project Costs: No maintenance cost savings were estimated for this measure. The installed cost for a gas-fired, high efficiency, condensing domestic water heater is estimated to be $5,800. Project Costs are based off RS Means Unit Cost data.

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTSExisting Hot Water

HeaterBradford White

Ultra High Efficiency

Building Type Library

Building Square-foot 10,000 10,000

Domestic Water Usage, kBtu 17,000.00 17,000.00

DHW Heating Fuel Type Electric Gas

Heating Efficiency 98% 96% -2%

Total Usage (kBTU) 17,347 17,708 -361

Electric Cost ($/kWh) $ 0.128 $ 0.128

Nat Gas Cost ($/Therm) $ 0.820 $ 0.820

ECM RESULTS EXISTING PROPOSED SAVINGS

Electric Usage (kWh) 5,083 0 5,083

Natural Gas Usage (Therms) 0 177 -177

Energy Cost ($) $651 $145 $505

COMMENTS:

CONDENSING DOM. HOT WATER HEATER CALCULATIONS

Savings are based on Energy Information Administration Commercial Building Energy Consumption Survey 2003 Information

ENERGY SAVINGS CALCULATIONS

Page 25: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 24 of 32

Energy Savings Summary:

Installation Cost ($): $5,800

NJ Smart Start Equipment Incentive ($): $50

Net Installation Cost ($): $5,750

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $505

Total Yearly Savings ($/Yr): $505

Estimated ECM Lifetime (Yr): 15

Simple Payback 11.4

Simple Lifetime ROI 31.7%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $7,575

Internal Rate of Return (IRR) 4%

Net Present Value (NPV) $278.66

ECM #4 - ENERGY SAVINGS SUMMARY

Page 26: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 25 of 32

ECM #5: Window AC Unit Replacement

Description: The primary source of cooling for the offices is window air conditioning units. These units vary in size, capacity and efficiency. These window AC units are old and inefficient. It is recommended to utilize the Energy Star ratings as a minimum standard for replacing any window unit that is in need of replacement. Existing units that are old but still working should be considered for replacement if the efficiency is 8.5 EER or less. Window AC units that are over 10 years old are very likely to fall in this efficiency range. This ECM shows the savings and payback for inefficient window air conditioners with new, Energy Star rated units. Qualifying product list can be found at Energy Star website at: www.energystar.gov/products. Although Energy Star rated products provide a valuable benchmark, it is recommended to consider even higher EER ratings for potential AC unit replacements where available. Energy Savings Calculations: Average Electric Cost: $0.128/kWh Typical AC Unit Size: 8,000 BTU/HR or 12,000 BTU/HR Estimated Full Load Hours of Unit: 800/Year

EnergySavings, kWh CoolingCapacity,BTUHr

1EER

1EER

FullLoadHours

1000 WkWh

DemandSavings, kWEnergySavings kWhHoursofCooling

CoolingCostSavings EnergySavings kWh AverageSummerElec. Cost$

kWh

Capacity BTU/H

Amount of Units

Full Load Hrs

Typical Eff. (10 Yrs &

Older) EER

New Eff. EER

Energy Savings

kWh

Demand Savings kW

Cooling Cost

Savings

Net Installed

Cost

Simple Payback

8,000 1 800 8.5 11.3 187 0.23 $24 $280 11.7

12,000 1 800 8.5 11.3 280 0.35 $36 $350 9.8

ENERGY SAVINGS CALCULATIONS

Page 27: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 26 of 32

Energy Savings Summary:

Installation Cost ($): $630

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $630

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $60

Total Yearly Savings ($/Yr): $60

Estimated ECM Lifetime (Yr): 12

Simple Payback 10.5

Simple Lifetime ROI 14.3%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $720

Internal Rate of Return (IRR) 2%

Net Present Value (NPV) ($32.76)

ECM #5 - ENERGY SAVINGS SUMMARY

Page 28: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 27 of 32

ECM #6: Water Conservation Measures Description: The Library utilizes standard plumbing fixtures in the restrooms. The typical water closet and urinal water consumption only meet the minimum federally required standard for water efficiency. New flush valves are available that use less water than today’s requirements and can add up to significant water reduction over a long period. In addition, the sinks do not have low-flow aerators nor automatic shut offs. This ECM includes the replacement of the existing water closet and urinal flush valves within the restrooms at the facility. In addition, low-flow aerators and automatic shutoffs will be installed at all sinks. The estimated usage of the plumbing fixtures is based on the total population of the facility. The number of valves/faucets to be replaced is based on observation of the facility in combination with federal minimum standards per occupancy load. The proposed retrofit includes installation of low-flow automatic flush valves that utilize 1.0 gallon per flush for the water closets, 0.5 gallon per flush for the urinals, and 0.5 GPM for the sinks. Energy Savings Calculations: For the basis of this calculation the LEED rating system was used to estimate the occupancy usage for employees in the facility. When water consumption information was not available, the GPF values were estimated for the existing fixtures.

A. Water Closets and Urinals:

Flush

GalFixture

DayperPerson

FlushUse

Yr

DaysOccupancynConsumptioWater

Gal1000

Gal1000

$CostAveGallonsn ConsumptioWater

CostWater

Page 29: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 28 of 32

B. Automatic Sink Faucets with Low-Flow Aerators

WaterUsage Quantity OperationDaysyr

UsageMinDay

FixtureGalMin

ElectricUsage

FaucetWaterUsage Gal 8.33lbsGal

SpecificHeat 1 ∆T 70

3,413Btu

1HWHEfficiency

50%

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTS Existing FixturesLow Flow / Auto

Flow Fixtures-

Total Number of Occupants 10 10 -

% Male to Female 50% 50% -

Occupied Days Per Year 300 300 -

Lavatory Uses per Day per Person (Female) 3 3 -

Lavatory Uses per Day per Person (Male) 2 2

WC Uses per Day per Person 2.0 2.0 -

Urinal Uses per Day per Person 2.0 2.0 -

Total Urinal Flushes Per Day 10 10 -

Total WC Flushes Per Day 25 25 -

Urinal Gallons Per Flush (GPF) 2.200 0.500 1.700

WC Gallons Per Flush (GPF) 1.6 1.28 0.32

** Water Cost ($/1000 Gal) $5.00 $5.00 -

ECM RESULTS EXISTING PROPOSED SAVINGSWater Consumption, Water Closets (Gal) 18,600 11,100 7,500

Water Cost ($) $93 $56 $38

COMMENTS:

WATER CONSERVATION CALCULATIONS

ENERGY SAVINGS CALCULATIONS

*Savings are based on LEED Reference Guide for Green Building Design and Construction - 2009 Edition for WC and Urinal water usage.

Page 30: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 29 of 32

Project Cost and Incentive Estimates: The cost for installation and materials for six (6) water closet automatic flush valves, four (4) urinal automatic flush valves, and six (6) automatic sink shutoffs with low-flow sink aerators is approximately $7,870. Project costs were obtained from vendor pricing and a local Plumbing Contractor. There are no Smart Start rebates for installation of low flow or automatic plumbing fixtures.

ECM INPUTS EXISTING PROPOSED SAVINGS

Quantity of Sinks 6 6

Flow Rate (GPM) 2.2 0.5 1.7

Device Usage (min per day) 10 9

Facility Operation (days / year) 300 300

Heat Content of Water (Btu/gal/°F) 8.33 8.33

Temperature Rise (°F) 70.0 70.0

Water Heater Type Electric Electric

Efficiency of Heating System (%) 98% 98%

Conversion Factor for Electric 3412 3412

Conversion Factor for Gas 100000 100000

Electric Rate ($/kWh) $0.128 $0.128

Natural Gas Rate ($/therm) $0.820 $0.820

Water Rate ($/1000gal) $5.000 $5.000

Electric Usage (kWh) 3,453 706 2,747Natural Gas Usage (Therm) 0 0 0Water Usage (gallons) 39,600 8,100 31,500Energy Cost ($) $640 $131 $509COMMENTS:

LOW FLOW WATER SAVING DEVICES

ENERGY SAVINGS CALCULATIONS

Heating Savings based on 50% Hot Cold Mix. Assume a 10% reduction based on timed faucet controls

Page 31: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 30 of 32

Energy Savings Summary:

Installation Cost ($): $7,871

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $7,871

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $547

Total Yearly Savings ($/Yr): $547

Estimated ECM Lifetime (Yr): 10

Simple Payback 14.4

Simple Lifetime ROI -30.5%

Simple Lifetime Maintenance Savings 0

Simple Lifetime Savings $5,470

Internal Rate of Return (IRR) -6%

Net Present Value (NPV) ($3,204.98)

ECM #6 - ENERGY SAVINGS SUMMARY

Page 32: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 31 of 32

REM #1: 4 kW Solar System Description: The Public Library Building has available roof space that could accommodate solar arrays. Based on the available area a 4 kilowatt solar array could be installed. The array will produce approximately 5,191 kilowatt-hours annually that will reduce the overall electric usage of the facility by 8%. The owner should consult a structural engineer prior to installing any solar array to insure the roof can accommodate the additional weight. Energy Savings Calculations: See Renewable / Distributed Energy Measures Calculations Appendix for detailed financial summary and proposed solar layout areas. Financial results in table below are based on 100% financing of the system over a fifteen year period. Energy Savings Summary:

Installation Cost ($): $22,000

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $22,000

SREC Revenue ($/Yr): $786

Energy Savings ($/Yr): $664

Total Yearly Savings ($/Yr): $1,451

Estimated ECM Lifetime (Yr): 15

Simple Payback 15.2

Simple Lifetime ROI -1.1%

Simple Lifetime Maintenance Savings $11,796

Simple Lifetime Savings $21,762

Internal Rate of Return (IRR) -0.1%

Net Present Value (NPV) ($4,680.81)

REM #1 - ENERGY SAVINGS SUMMARY

Page 33: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Town of Dover – Public Library Energy Audit

Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 32 of 32

VI. ADDITIONAL RECOMMENDATIONS The following recommendations include no cost/low cost measures, Operation & Maintenance (O&M) items, and water conservation measures with attractive paybacks. These measures are not eligible for the Smart Start Buildings incentives from the office of Clean Energy but save energy none the less.

A. Chemically clean the condenser and evaporator coils periodically to optimize efficiency. Poorly maintained heat transfer surfaces can reduce efficiency 5-10%.

B. Maintain all weather stripping on windows and doors.

C. Clean all light fixtures to maximize light output.

D. Provide more frequent air filter changes to decrease overall system power usage and maintain better IAQ.

E. Turn off computers when not in use. Ensure computers are not running in screen saver mode.

F. Replace any old CRT Monitors with LED/LCD Type Monitors, which can draw as much as a quarter the power of an equivalent CRT monitor.

G. Ensure outside air dampers are functioning properly and only open during occupied mode.

Page 34: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX A

Page 35: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

APPENDIX A1 of 1

LIFETIME ENERGY SAVINGS

LIFETIME MAINTENANCE

SAVINGSLIFETIME ROI SIMPLE PAYBACK

INTERNAL RATE OF RETURN (IRR)

NET PRESENT VALUE (NPV)

MATERIAL LABORREBATES,

INCENTIVES

NET INSTALLATION

COSTENERGY MAINT. / SREC TOTAL (Yearly Saving * ECM Lifetime)

(Yearly Maint Svaing * ECM Lifetime)

(Lifetime Savings - Net Cost) / (Net Cost)

(Net cost / Yearly Savings)

($) ($) ($) ($) ($/Yr) ($/Yr) ($/Yr) (Yr) ($) ($) (%) (Yr) ($) ($)

ECM #1 Interior Lighting Upgrade $9,716 $8,906 $1,865 $16,757 $2,624 $0 $2,624 15 $39,360 $0 134.9% 6.4 13.23% $14,568.14

ECM #2 Interior Lighting Controls $1,250 $350 $200 $1,400 $35 $0 $35 15 $525 $0 -62.5% 40.0 -10.33% ($982.17)

ECM #3 Exterior Lighting Upgrade $3,420 $1,449 $1,425 $3,444 $766 $0 $766 15 $11,490 $0 233.6% 4.5 20.96% $5,700.46

ECM #4 Domestic Water Heater Upgrade $2,900 $2,900 $50 $5,750 $505 $0 $505 15 $7,575 $0 31.7% 11.4 3.66% $278.66

ECM #5 Window AC Unit $630 $0 $0 $630 $60 $0 $60 12 $720 $0 14.3% 10.5 2.12% ($32.76)

ECM #6 Water Conservation $3,500 $4,371 $0 $7,871 $547 $0 $547 10 $5,470 $0 -30.5% 14.4 -6.12% ($3,204.98)

REM #1 4 kW Solar Array $14,000 $8,000 $0 $22,000 $664 $786 $1,451 15 $21,762 $11,796 -1.1% 15.2 -0.14% ($4,680.81)

Notes: 1) The variable Cn in the formulas for Internal Rate of Return and Net Present Value stands for the cash flow during each period.2) The variable DR in the NPV equation stands for Discount Rate3) For NPV and IRR calculations: From n=0 to N periods where N is the lifetime of ECM and Cn is the cash flow during each period .

REM RENEWABLE ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY

ECM COST & SAVINGS BREAKDOWN

CONCORD ENGINEERING

Town of Dover - Public Library

INSTALLATION COST YEARLY SAVINGS

ECM LIFETIMEDESCRIPTIONECM NO.

ECM ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY

Page 36: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX B

Page 37: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix B Page 1 of 6

Concord Engineering Group, Inc. 520 BURNT MILL ROAD VOORHEES, NEW JERSEY 08043 PHONE: (856) 427-0200 FAX: (856) 427-6508

SmartStart Building Incentives The NJ SmartStart Buildings Program offers financial incentives on a wide variety of building system equipment. The incentives were developed to help offset the initial cost of energy-efficient equipment. The following tables show the current available incentives from July 1, 2015 to June 30, 2016, further details including how to apply, forms, and calculated incentive values can be found the Clean Energy Website. (www.njcleanenergy.com)

Electric Chillers

Water-Cooled Chillers

Constant Speed: Base: $8 - $30 per ton

Performance Add: $2 - $2.25 per ton Variable Speed:

Base: $12 - $44 per ton Performance Add: $2 - $4.00 per ton

Air-Cooled Chillers

Constant Speed: Base: $20 per ton

Performance Add: $3.50 per ton Variable Speed:

Base: $90 - $92 per ton Performance Add: $4.00 per ton

Energy Efficiency must comply with ASHRAE 90.1-2013

Gas Cooling Gas Absorption Chillers (Indirect & Direct-Fired)

$185 - $450 per ton

Desiccant Systems

$1.00 per cfm – gas or electric

Electric Unitary HVAC

Unitary AC and Split Systems $73 - $92 per ton Air-to-Air Heat Pumps $73 - $92 per ton

Water-Source Heat Pumps $81 per ton Packaged Terminal AC & HP $65 per ton

Central DX AC Systems $40- $72 per ton Dual Enthalpy Economizer Controls $250 Occupancy Controlled Thermostat

(Hospitality & Institutional Facility) $75 per thermostat

A/C Economizing Controls < 5 tons $85/unit; >5 tons $170/unit Energy Efficiency must comply with ASHRAE 90.1-2007

Page 38: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix B Page 2 of 6

Gas Heating

Hot Water Gas Fired Boilers < 300 MBH

Non-Condensing: $0.95 per MBH,

Minimum $400 per unit Condensing:

$2.00 per MBH, Minimum $1000 per unit

Hot Water Gas Fired Boilers ≥ 300 - 1500 MBH

Non-Condensing: $1.75 per MBH

Condensing: $2.20 per MBH

Minimum $1000 per unit

Hot Water Gas Fired Boilers >1500 - ≤ 2500 MBH

Non-Condensing: $1.50 per MBH

Condensing: $2.20 per MBH

Hot Water Gas Fired Boilers >2500 - ≤ 4000 MBH

Non-Condensing: $1.30 per MBH

Condensing: $2.00 per MBH

Steam, Except Natural Draft, Gas fired Boilers < 300 MBH

$1.40 per MBH, Minimum $400 per unit

Steam, Except Natural Draft, Gas fired Boilers ≥ 300 – 1500 MBH

$1.20 per MBH

Steam, Except Natural Draft, Gas fired Boilers > 1500 – 2500 MBH

$1.20 per MBH

Steam, Except Natural Draft, Gas fired Boilers > 2500 – 4000 MBH

$1.00 per MBH

Steam, Natural Draft < 300 MBH

$1.40 per MBH, Minimum $300 per unit

Steam, Natural Draft ≥ 300 - 1500 MBH

$1.00 per MBH

Steam, Natural Draft >1500 - ≤ 2500 MBH

$0.90 per MBH

Steam, Natural Draft >2500 - ≤ 4000 MBH

$0.70 per MBH

All Types Gas Fired Boilers > 4000 MBH

(Calculated through Custom Measure Path)

Gas Furnaces $400 per unit, AFUE ≥ 95%

Boiler Economizing Controls $1,200 - $2,700

Low Intensity Infrared Heating $300 - $500 per unit

Natural Gas Water Heating Gas Water Heaters ≤ 50 gallons, 0.67

energy factor or better $50 per unit

Gas-Fired Water Heaters > 50 gallons $1.00 - $2.00 per MBH

Gas-Fired Booster Water Heaters $17 - $35 per MBH

Gas Fired Tankless Water Heaters $300 per unit

Page 39: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix B Page 3 of 6

Ground Source Heat Pumps

Closed Loop $450 per ton, EER ≥ 16 $600 per ton, EER ≥ 18 $750 per ton, EER ≥ 20

Energy Efficiency must comply with ASHRAE 90.1-2007

Variable Frequency Drives Variable Air Volume $65 - $155 per hp

Chilled-Water Pumps ≥ 20 hp $60 per VFD rated hp

Rotary Screw Air Compressors ≥ 25 hp $5,250 to $12,500 per drive Centrifugal Fan Applications on

Constant Volume HVAC Systems $80 per VFD rated hp, maximum

$6,000 per drive Cooling Towers ≥ 10 hp $60 per VFD rated hp

Boiler Fans > 5 HP $65 to $155 per hp

Boiler Feed Water Pumps > 5 HP $60 to $155 per hp

Commercial Kitchen Hood up to 50 HP Retrofit $55 – $300 per hp

New Hood $55 - $250 per hp

Prescriptive Lighting

T-8 reduced Wattage (28w/25w 4’, 1-4 lamps)

Lamp & ballast replacement $10 per fixture

For retrofit of T-8 fixtures by permanent de-lamping & new reflectors

(Electronic ballast replacement required)

$5 per fixture

T-5 and T-8 High Bay Fixtures $25 - $150 per fixture

HID ≥ 100w Replace with new induction fixture.

(must be 30% less watts/fixture than HID system)

$70 per fixture

HID ≥ 100w Retrofit with induction lamp, power coupler and generator

(must be 30% less watts/fixture than HID system)

$50 per fixture

Page 40: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix B Page 4 of 6

Prescriptive Lighting - LED

LED Architectural Floor and Spot Luminaires

$50 per fixture

LED Bollard Fixtures $50 per fixture

LED Display Case Lighting $30 per display case

LED Fuel Pump Canopy $100 per fixture

LED High-Bay and Low-Bay Fixtures for Commercial & Industrial Bldgs.

$150 per fixture

LED High-Bay-Aisle Lighting $150 per fixture

LED Linear Ambient Luminaires (Indirect, Indirect/Direct, Direct/Indirect, Direct)

2’ Fixtures - $20/fixture 3’ Fixtures - $30/fixture 4’ Fixtures - $45/fixture 6’ Fixtures - $60/fixture 8’ Fixtures - $75/fixture

LED Linear Replacement Lamps (2’ & 4’ only)

$5 per lamp

Luminaires for Ambient Lighting of Interior Commercial Spaces

(1x4, 2x2, 2x4 New Fixtures and Retrofit Kits)

1x4 LED - $15 per fixture 2x2 LED - $15 per fixture 2x4 LED - $25 per fixture

LED Outdoor Pole/Arm-Mounted Area and Roadway Luminaries

$100 per fixture

LED Outdoor Pole/Arm-Mounted Decorative Luminaries

$50 per fixture

LED Outdoor Wall-Mounted Area Luminaries

$100 per fixture

LED Parking Garage Luminaries $100 per fixture

LED Retrofit Kits for Large Outdoor Pole / Arm-Mounted Area and

Roadway Luminaires $150 per fixture

LED Refrigerator/Freezer case lighting replacement of fluorescent in medium

and low temperature display case

$30 per 4 foot $42 per 5 foot $65 per 6 foot

LED Shelf-Mtd. Display & Task Lights $15 per linear foot

Page 41: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix B Page 5 of 6

LED Stairwell and Passageway Luminaires

$40 per fixture

LED Track or Mono-Point Directional Lighting Fixtures

$30 per fixture

LED Wall-Wash Lights $30 per fixture

EnergyStar Commercial Lighting Fixtures

$5 to $10 per fixture

EnergyStar Screw and Pine-Based Bulbs

$5 to $10 per lamp

Lighting Controls – Occupancy Sensors

Wall Mounted (Existing Facilities Only)

$20 per control

Remote Mounted (Existing Facilities Only)

$35 per control

Daylight Dimming Controls $45 per fixture controlled

Occupancy Based hi-low Dimming Control

$35 per fixture controlled

Occupancy Sensor Remote Mounted High-Bay (Existing Facilities Only)

$35 per control

Refrigeration Doors/Covers

Energy-Efficient Doors/Covers for Installation on Open Refrigerated Cases

$100 per door

Aluminum Night Curtains for Installation on Open Refrigerated Cases

$3.50 per linear foot

Refrigeration Controls

Door Heater Controls $50 per control Electric Defrost Controls $50 per control Evaporator Fan Controls $75 per control Novelty Cooler Shutoff $50 per control

Refrigerator / Freezer Case Premium Efficiency Motors

Fraction ECM Motor < 1 HP $40 per ECM for replacement of

existing shaded-pole motor

Page 42: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix B Page 6 of 6

Food Service Equipment

Combination Oven/Steamer (Electric) $1,000/oven

Combination Oven/Steamer (Natural Gas)

$750/oven

Convection Oven (Electric) $350/oven

Convection Oven (Natural Gas) $500/oven

Rack Oven (Natural Gas) $1,000/single oven, $2,000/double oven

Conveyor Oven (Natural Gas) $500/small deck $750/large deck

Fryer (Electric) $200/vat

Fryer (Natural Gas) $749/vat

Large Vat Fryer (Electric) $200/vat

Large Vat Fryer (Natural Gas) $500/vat

Griddle (Electric) $300/griddle

Griddle (Natural Gas) $125/griddle

Steam Cooker (Electric) $1,250/steamer

Steam Cooker (Natural Gas) $2,000/steamer

Insulated Holding Cabinets $200 to $300/unit

Glass Door Refrigerators $75 to $150/unit

Solid Door Refrigerators $50 to $200/unit

Glass Door Freezers $200 to $1,000/unit

Solid Door Freezers $100 to $600/unit

Ice Machines $50 to $500/unit

Dishwashers $400 to $1,500/unit

Other Equipment Incentives

Performance Lighting

$1.00 per watt per SF below program incentive threshold, currently 5% more energy efficient than ASHRAE 90.1-

2007 for New Construction and Complete Renovation

Custom Electric and Gas Equipment Incentives

not prescriptive

Custom Measures

$0.16 KWh and $1.60/Therm of 1st year savings, or a buy down to a 1 year

payback on estimated savings. Minimum required savings of 75,000

KWh or 1,500 Therms and an IRR of at least 10%.

Page 43: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX C

Page 44: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

ENERGY STAR® Statement of EnergyPerformance

N/AENERGY STAR®

Score1

Public Library

Primary Property Type: LibraryGross Floor Area (ft²): 10,000Built: 1964

For Year Ending: May 31, 2015Date Generated: February 24, 2016

1. The ENERGY STAR score is a 1-100 assessment of a building’s energy efficiency as compared with similar buildings nationwide, adjusting forclimate and business activity.

Property & Contact Information

Property AddressPublic Library32 E. Clinton StreetDover, New Jersey 07801

Property OwnerTown of Dover37 N. Sussex StreetDover, NJ 07801(____)____-______

Primary ContactDonald Travisano37 N. Sussex StreetDover, NJ [email protected]

Property ID: 4778526

Energy Consumption and Energy Use Intensity (EUI)

Site EUI75.4 kBtu/ft²

Annual Energy by FuelElectric - Grid (kBtu) 218,414 (29%)Natural Gas (kBtu) 535,155 (71%)

National Median ComparisonNational Median Site EUI (kBtu/ft²) 142.3National Median Source EUI (kBtu/ft²) 235.6% Diff from National Median Source EUI -47%

Source EUI124.8 kBtu/ft²

Annual EmissionsGreenhouse Gas Emissions (Metric TonsCO2e/year)

58

Signature & Stamp of Verifying Professional

I ___________________ (Name) verify that the above information is true and correct to the best of my knowledge.

Signature: _______________________Date: ___________

Licensed Professional

Donald Travisano37 N. Sussex StreetDover, NJ [email protected]

Professional Engineer Stamp(if applicable)

Page 45: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX D

Page 46: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

MAJOR EQUIPMENT LISTConcord Engineering

Rooftops

Rooftop UnitsTag RTU-1 RTU-2

Unit Type Packaged Packaged

Qty 1 1

Location Rooftop Rooftop

Area Served Entire facility Entire facility

Manufacturer Carrier Carrier

Model No. ZS-05C00AFAA… ZS-05C00AFAA…

Serial No. N1K0338977 N1K0338976

Cooling Type Packaged DX Packaged DX

Cooling Capacity (Tons) 5-tons 5-tons

Cooling Efficiency (SEER/EER)

10.8 EER 10.8 EER

Heating Type No Heating No Heating

Heating Input (MBH) N/A N/A

Efficiency N/A N/A

Supply Fan (HP) 1 1

Supply Fan VFD

Return/Exhaust Fan (HP) N/A N/A

Return/Exhaust Fan VFD

Approx Age 5 5

ASHRAE Service Life 15 15

Remaining Life 10 10

Comments

Note:

"N/A" = Not Applicable. "-" = Info Not Available

Yes No N/A

Yes No N/A

Yes No N/A

Yes No N/A

Appendix D - Major Equipment List - Public Library Page 1 of 3

Page 47: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

MAJOR EQUIPMENT LISTConcord Engineering

Boilers

BoilersTag B-1

Unit Type Cast-Iron Sectional (Steam)

Qty 1

Location Boiler Room

Manufacturer Burnham

Model No. 5007N

Serial No. 64868589

Input Capacity 468 MBH

Output Capacity 374 MBH

Approx. Efficiency % (Present Age)

79.0%

Fuel Type Natural Gas

Approx Age 5

ASHRAE Service Life 30

Remaining Life 25

CommentsCondensate Pump/Receiver with

1/2 HP Pump

Note:

"N/A" = Not Applicable. "-" = Info Not Available

Appendix D - Major Equipment List - Public Library Page 2 of 3

Page 48: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

MAJOR EQUIPMENT LISTConcord Engineering

Dom HWH

Domestic Water HeatersTag DHW-1

Unit Type Automatic Storage Water Heater

Qty 1

Location Boiler Room

Area Served Entire Facility

Manufacturer Bradford White

Model # M240S6DS

Serial # EK11163489

Storage Size (Gal) 40

Input Capacity (MBH/KW) 3,500 Watts per element

Recovery (Gal/Hr) -

Efficiency % 97%

Fuel Electric

Approx Age 2

ASHRAE Service Life 15

Remaining Life 13

Comments

Note:

"N/A" = Not Applicable. "-" = Info Not Available

Appendix D - Major Equipment List - Public Library Page 3 of 3

Page 49: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX E

Page 50: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

CEG Project #:

Facility Name:

Address:

City, State, Zip

Fixture Reference #

LocationAverage

Burn Hours

DescriptionLamps per

FixtureWatts per

FixtureQty of

FixturesTotal kW

Usage kWh/Yr

Work Description Equipment DescriptionLamps per

FixtureWatts per

FixtureQty of

FixturesTotal kW

Usage kWh/Yr

Energy Savings,

kW

Energy Savings,

kWh

Energy Savings, $

Control Ref #

Controls DescriptionQty of

Controls

Hour Reduction

%

Energy Savings,

kWh

Energy Savings, $

Material Total Labor Total AllRebate

EstimateSimple

PaybackTotal

MaterialsTotal Labor Total All

Simple Payback

1 Reading Area 30002-Lamp 1x8 F96T12 60W

Pendant-Mounted Egg Crate Lens

2 108.7 12 1.30 3,913 New FixtureInstall New 1x4 Ceiling

Mounted LED Wrap4 58 12 0.70 2,088 0.61 1,825 $234 0 No New Controls 0 0.0% 0 $0 $1,800.00 $1,140.00 $2,940.00 $120.00 12.07 $0.00 $0.00 $0.00 YES -

13 Reading Area 3000Arch. Pendant with 42 Watt

CFL3 126 3 0.38 1,134 Existing to Remain No Change 3 126 0 0.38 1,134 0.00 0 $0 0 No New Controls 0 0.0% 0 $0 $0.00 $0.00 $0.00 $0.00 - $0.00 $0.00 $0.00 FALSE -

3 Book Racks 30003-Lamp 2x4 F32T8 32W Recessed Prismatic Lens

3 86.2 28 2.41 7,241 Re-LampPhilips LED T8 InstaFit Lamp

(12W)3 36 28 1.01 3,024 1.41 4,217 $540 0 No New Controls 0 0.0% 0 $0 $1,848.00 $1,330.00 $3,178.00 $420.00 5.11 $0.00 $0.00 $0.00 FALSE -

4 Men's Restroom 30001-Lamp 6"x24" Vanity

Fixture F34T121 31 1 0.03 93 Re-Lamp

Seesmart 2-foot 9W SP SEP LED Tube

1 9 1 0.01 27 0.02 66 $8 4

Dual Tech. Occupancy Sensor w/2 Pole Powerpack

- Remote Mnt.1 20.0% 5 $1 $22.00 $23.75 $45.75 $5.00 4.82 $300.00 $50.00 $350.00 $35.00 455.73

5 Men's Restroom 3000Ceiling Globe 60 Watt

Incandescent1 60 1 0.06 180 Replace TCP 13W LED A21 LED 1 13 1 0.01 39 0.05 141 $18 0 No New Controls 0 0.0% 0 $0 $12.00 $23.75 $35.75 $5.00 1.70 $0.00 $0.00 $0.00 FALSE -

4 Women's Restroom 30001-Lamp 6"x24" Vanity

Fixture F34T121 31 1 0.03 93 Re-Lamp

Seesmart 2-foot 9W SP SEP LED Tube

1 9 1 0.01 27 0.02 66 $8 4

Dual Tech. Occupancy Sensor w/2 Pole Powerpack

- Remote Mnt.1 20.0% 5 $1 $22.00 $23.75 $45.75 $5.00 4.82 $300.00 $50.00 $350.00 $35.00 455.73

5 Women's Restroom 3000Ceiling Globe 60 Watt

Incandescent1 60 1 0.06 180 Replace TCP 13W LED A21 LED 1 13 1 0.01 39 0.05 141 $18 0 No New Controls 0 0.0% 0 $0 $12.00 $23.75 $35.75 $5.00 1.70 $0.00 $0.00 $0.00 FALSE -

6 Office 30002-Lamp 1x4 F32T8 Surface

Wrap2 62 7 0.43 1,302 Re-Lamp

Philips LED T8 InstaFit Lamp (12W)

2 24 7 0.17 504 0.27 798 $102 5Dual Technology

Occupancy Sensor - Remote Mnt.

1 20.0% 101 $13 $308.00 $332.50 $640.50 $70.00 5.59 $200.00 $50.00 $250.00 $35.00 16.66

5 Basement Restrooms 3000Ceiling Globe 60 Watt

Incandescent1 60 1 0.06 180 Replace TCP 13W LED A21 LED 1 13 1 0.01 39 0.05 141 $18 4

Dual Tech. Occupancy Sensor w/2 Pole Powerpack

- Remote Mnt.1 20.0% 8 $1 $12.00 $23.75 $35.75 $5.00 1.70 $300.00 $50.00 $350.00 $35.00 315.50

4 Basement Restrooms 30001-Lamp 6"x24" Vanity

Fixture F34T121 31 1 0.03 93 Re-Lamp

Seesmart 2-foot 9W SP SEP LED Tube

1 9 1 0.01 27 0.02 66 $8 0 No New Controls 0 0.0% 0 $0 $22.00 $23.75 $45.75 $5.00 4.82 $0.00 $0.00 $0.00 FALSE -

8 Basement Work Room 30002-Lamp 1x4 F34T12

Surface Wrap2 62 2 0.12 372 Re-Lamp

Philips LED T8 InstaFit Lamp (12W)

2 24 2 0.05 144 0.08 228 $29 6Dual Technology

Occupancy Sensor - Switch Mnt.

1 20.0% 29 $4 $88.00 $95.00 $183.00 $20.00 5.59 $50.00 $50.00 $100.00 $20.00 21.70

7Basement

Storage/Meeting Room

30004-Lamp 2x4 F40T12 34W Recessed Prismatic Lens

4 119 30 3.57 10,710 Re-LampPhilips LED T8 InstaFit Lamp

(12W)4 48 30 1.44 4,320 2.13 6,390 $818 0 No New Controls 0 0.0% 0 $0 $2,640.00 $2,850.00 $5,490.00 $600.00 5.98 $0.00 $0.00 $0.00 FALSE -

8 Storage Room 30002-Lamp 1x4 F34T12

Surface Wrap2 62 8 0.50 1,488 Re-Lamp

Philips LED T8 InstaFit Lamp (12W)

2 24 8 0.19 576 0.30 912 $117 6Dual Technology

Occupancy Sensor - Switch Mnt.

1 20.0% 115 $15 $352.00 $380.00 $732.00 $80.00 5.59 $50.00 $50.00 $100.00 $20.00 5.43

8 Children's Book Area 30002-Lamp 1x4 F34T12

Surface Wrap2 62 47 2.91 8,742 Re-Lamp

Philips LED T8 InstaFit Lamp (12W)

2 24 47 1.13 3,384 1.79 5,358 $686 0 No New Controls 0 0.0% 0 $0 $2,068.00 $2,232.50 $4,300.50 $470.00 5.59 $0.00 $0.00 $0.00 FALSE -

1 Storage Room 4002-Lamp 1x8 F96T12 60W

Pendant-Mounted Egg Crate Lens

2 108.7 3 0.33 130 New FixtureInstall New 1x4 Ceiling

Mounted LED Wrap4 58 3 0.17 70 0.15 61 $8 6

Dual Technology Occupancy Sensor - Switch

Mnt.1 20.0% 14 $2 $450.00 $285.00 $735.00 $30.00 90.53 $50.00 $50.00 $100.00 $20.00 44.90

11 Mechanical Room 40060 Watt Incandescent Industrial Shade Open

1 60 5 0.30 120 Re-Lamp TCP 13W LED A21 LED 1 13 5 0.07 26 0.24 94 $12 0 No New Controls 0 0.0% 0 $0 $60.00 $118.75 $178.75 $25.00 12.78 $0.00 $0.00 $0.00 FALSE -

10 Exterior Building 2600 Wall-Mounted 150 MH 1 185 14 2.59 6,734 Replace RAB 40 Watt LED Wall Pack 1 40 14 0.56 1,456 2.03 5,278 $676 0 No New Controls 0 0.0% 0 $0 $3,360.00 $1,330.00 $4,690.00 $1,400.00 4.87 $0.00 $0.00 $0.00 FALSE -

12 Exterior Building 300060 Watt Exterior Lamp Post

Fixture1 60 5 0.30 900 Re-Lamp TCP 13W LED A21 LED 1 13 5 0.07 195 0.24 705 $90 0 No New Controls 0 0.0% 0 $0 $60.00 $118.75 $178.75 $25.00 1.70 $0.00 $0.00 $0.00 FALSE -

TOTAL 170 15.42 43,605 167 5.99 17,119 9.44 26,487 $3,390 7 277 $35 $13,136 $10,355 $23,491 $3,290 5.96 $1,250 $350 $1,600 $200.00 39.44

Dover, NJ 07801

32 E. Clinton Street

1C15676

Public Library

LIGHTING CONTROLS COSTRETROFIT ENERGY SAVINGSEXISTING FIXTURES PROPOSED FIXTURE RETROFIT PROPOSED LIGHTING CONTROLS LIGHTING RETROFIT COSTS

Smart Start Incentive

Appendix E - Lighting Audit - Public Library Page 1 of 1

Page 51: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix Energy Audit

Concord Engineering Group, Inc.

APPENDIX F

Page 52: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix FPage 1 of 3

Location Description

Area (Sq FT) Panel Qty

Panel Sq Ft

Panel Total Sq

FtTotal KWDC

Total Annual kWh

Total KWAC

Panel Weight

(41.9 lbs) W/SQFT

Library 1125SHARP

ND-240QCJ18 17.5 316 4.32 5,191 3.9 754 13.68

= Proposed PV Roof Layout = Proposed PV Parking Layout

Notes:

1. Estimated kWH based on the National Renewable Energy Laboratory PVWatts Version 1 Calculator Program.

Page 53: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix FPage 2 of 3

Project Name: LGEA Solar PV Project - Library

Location: Dover, NJDescription: Photovoltaic System 100% Financing - 15 year

Simple Payback Analysis

Total Construction Cost $22,000Annual kWh Production 5,191

Annual Energy Cost Reduction $664Average Annual SREC Revenue $786

Simple Payback: Years

Life Cycle Cost AnalysisAnalysis Period (years): 15 Financing %: 100%

Discount Rate: 3% Maintenance Escalation Rate: 3.0%Average Energy Cost ($/kWh) $0.128 Energy Cost Escalation Rate: 3.0%

Financing Rate: 6.00% Average SREC Value ($/kWh) $0.152Period Additional Energy kWh Energy Cost Additional SREC Interest Loan Net Cash Cumulative

Cash Outlay Production Savings Maint Costs Revenue Expense Principal Flow Cash Flow0 $0 0 0 0 $0 0 0 0 01 $0 5,191 $664 $0 $1,298 $1,295 $933 ($266) ($266)2 $0 5,165 $684 $0 $1,291 $1,237 $991 ($252) ($518)3 $0 5,139 $705 $0 $1,285 $1,176 $1,052 ($238) ($756)4 $0 5,113 $726 $0 $1,023 $1,111 $1,117 ($479) ($1,236)5 $0 5,087 $748 $52 $1,017 $1,042 $1,186 ($515) ($1,750)6 $0 5,062 $770 $52 $1,012 $969 $1,259 ($497) ($2,248)7 $0 5,037 $793 $52 $756 $891 $1,336 ($731) ($2,979)8 $0 5,012 $817 $52 $752 $809 $1,419 ($711) ($3,689)9 $0 4,986 $842 $51 $748 $722 $1,506 ($690) ($4,379)10 $0 4,962 $867 $51 $496 $629 $1,599 ($916) ($5,295)11 $0 4,937 $893 $51 $494 $530 $1,698 ($892) ($6,187)12 $0 4,912 $920 $51 $491 $425 $1,803 ($868) ($7,054)13 $0 4,888 $947 $50 $244 $314 $1,914 ($1,086) ($8,141)14 $0 4,863 $976 $50 $243 $196 $2,032 ($1,059) ($9,200)15 $0 4,839 $1,005 $50 $242 $71 $2,157 ($1,031) ($10,230)

Totals: 75,191 $12,357 $562 $11,392 $11,417 $22,000 ($10,230) ($63,926)Net Present Value (NPV)

Photovoltaic System 100% Financing - 15 year

15.16

($7,262)

Page 54: FACILITY ENERGY REPORT - s3. · PDF fileTown of Dover – Public Library Energy Audit Concord Engineering Group, Inc. 1C15676 March 30, 2016 – FINAL Page 1 of 32 TABLE OF CONTENTS

Appendix FPage 3 of 3

PVWatts: Monthly PV Performance Data Rooftop ArrayRequested Location: 32 E Clinton St, Dover, NJ 07801Location: NEWARK, NJLat (deg N): 40.7Long (deg W): 74.17Elev (m): 9DC System Size (kW): 4.32Module Type: StandardArray Type: Fixed (roof mount)Array Tilt (deg): 10Array Azimuth (deg): 175System Losses: 14Invert Efficiency: 96DC to AC Size Ratio: 1.1Average Cost of Electricity No utility data availableInitial Cost No initial cost definedCost of Electricity Generatenot determined

MonthAC System

Output(kWh)

Solar Radiation

(kWh/m^2/day)

Plane of Array Irradiance (W/m^2)

DC array Output (kWh) Value ($)

1 275 2.39 74.05 289 02 327 3.16 88.61 343 03 455 4.07 126.22 477 0.004 505 4.83 144.96 529 0.005 597 5.70 176.63 624 0.006 586 5.94 178.22 614 0.007 581 5.76 178.70 609 0.008 538 5.38 166.76 563 0.009 463 4.65 139.52 485 0.00

10 384 3.61 112.02 402 011 252 2.35 70.60 265 012 227 2.01 62.36 240 0

Total 5,191 49.87 1518.63 5,441 0